Codename One Developer Guide
version DEV-SNAPSHOT, 2026-08-20
- Preface
- 1. Maven Project Workflow
- 1.1. Introduction
- 1.2. Getting started
- 1.3. Updating Codename One
- 1.4. Creating project templates
- 1.5. Codename One libraries
- 2. Introduction
- 3. Basics: Themes, styles, components, and layouts
- 4. Advanced theming
- 4.1. Working with UIIDs
- 4.2. Theme layering
- 4.3. Override resources in platform
- 4.4. Theme constants
- 4.5. Native theming
- 4.6. Under the hood of the theme engine
- 4.7. Understanding images and Multi-Images
- 4.8. Use millimeters for Padding/Margin and font sizes
- 4.9. Creating a great looking side menu
- 4.10. Converting a PSD to a theme
- 5. Native modern themes
- 5.1. Selecting a theme
- 5.2. Light and dark mode
- 5.3. Material 3 color palette (Android)
- 5.4. iOS modern color palette
- 5.5. Accent palette override
- 5.6. Platform-specific UIIDs
- 5.7. Switching CheckBox / RadioButton glyphs
- 5.8. Component-specific tuning constants
- 5.9. iOS 26 Liquid Glass tab selection morph
- 5.10. Customizing in your own theme
- 5.11. Inheriting from a native UIID
- 5.12. Translucency, glass effects, and the test harness
- 6. CSS
- 7. The components of Codename One
- 7.1. Container
- 7.2. Form
- 7.3. Dialog
- 7.4. InteractionDialog
- 7.5. Label
- 7.6. TextField and TextArea
- 7.7. TextComponent
- 7.8. Button
- 7.9. CheckBox/RadioButton
- 7.10. ComponentGroup
- 7.11. MultiButton
- 7.12. SpanButton
- 7.13. SpanLabel
- 7.14. OnOffSwitch
- 7.15. InfiniteProgress
- 7.16. InfiniteScrollAdapter and InfiniteContainer
- 7.17. List, MultiList, renderers & models
- 7.17.1. InfiniteContainer/InfiniteScrollAdapter vs. List/ContainerList
- 7.17.2. Why isn’t list deprecated
- 7.17.3. MVC in lists
- 7.17.4. Understanding MVC
- 7.17.5. Important - lists and Layout managers
- 7.17.6. MultiList & DefaultListModel
- 7.17.7. List cell renderer
- 7.17.8. Generic list cell renderer
- 7.17.9. ComboBox
- 7.18. Slider
- 7.19. Table
- 7.20. Tree
- 7.21. ShareButton
- 7.22. iOS Share Extension Authoring Helper
- 7.23. Tabs
- 7.24. MediaManager & MediaPlayer
- 7.25. ImageViewer
- 7.26. ScaleImageLabel & ScaleImageButton
- 7.27. Toolbar
- 7.28. BrowserComponent & WebBrowser
- 7.29. Text editors
- 7.30. AutoCompleteTextField
- 7.31. Picker
- 7.32. SwipeableContainer
- 7.33. EmbeddedContainer
- 7.34. MapComponent
- 7.35. Chart Component
- 7.36. Calendar
- 7.37. ToastBar
- 7.38. SignatureComponent
- 7.39. Accordion
- 7.40. Floating hint
- 7.41. Floating Button
- 7.42. SplitPane
- 8. Rich Text and Code Editing
- 8.1. Editor architecture and backend selection
- 8.2. Focus, change events, and editability
- 8.3. Platform text input and input methods
- 8.4. Lightweight fields with EditField
- 8.5. Selection, bidirectional text, and scrolling
- 8.6. RichTextArea
- 8.7. Read-only rich text with RichTextComponent
- 8.8. CodeEditor
- 8.9. Port integration checklist
- Accessibility Semantics
- 9. Built-in semantics
- 10. Roles, names, values, and state
- 11. Ranges and editable values
- 12. Custom accessibility actions
- 13. Grouping and virtual descendants
- 14. Traversal order
- 15. Live regions and screen changes
- 16. User accessibility preferences
- 17. Collections
- 18. Inspecting and testing semantics
- 19. Diagnosing and correcting an inaccessible screen
- 20. Platform mappings
- MCP Headless API
- Media and Audio
- 29. MediaManager and MediaPlayer
- 30. PCM Audio Buffers, Mixing, and Effects
- 31. Animations
- 32. The EDT - Event Dispatch Thread
- 33. Graphics, drawing, images, and fonts
- 34. 3D Graphics and Shaders
- 35. Augmented Reality
- 36. Virtual Reality and 360 Media
- 37. Game Development
- 37.1. Sample games
- 37.2. The game loop:
GameView - 37.3. Input:
GameInput - 37.4. On-screen touch controls
- 37.5. Sprites
- 37.6. Case study: The card game (flat 2D)
- 37.7. Case study: Faux-3D checkers (isometric projection)
- 37.8. 3D and perspective
- 37.9. Low latency audio:
SoundPool - 37.10. Physics
- 37.11. Putting it together: Anatomy of a game
- 37.12. Performance notes
- 38. The Game Builder
- 39. Game Assets
- 40. Events
- 41. Device Input and Form Factors
- 42. File system, storage, network, and parsing
- 42.1. JAR resources
- 42.2. Storage
- 42.3. File system
- 42.4. SQL
- 42.5. Network manager & connection request
- 42.6. Debugging network connections
- 42.7. Rest API
- 42.8. Webservice wizard
- 42.9. Connection request caching
- 42.10. Cached data service
- 42.11. Externalizable objects
- 42.12. UI bindings & utilities
- 42.13. Logging & crash protection
- 42.14. Sockets
- 42.15. Properties
- 43. Push notifications
- 43.1. Create and configure an application
- 43.2. Bind the client
- 43.3. Build a message
- 43.4. Send from a server
- 43.5. Build audiences in the Console
- 43.6. Send a message from the Console
- 43.7. Event automations
- 43.8. Widgets and live surfaces
- 43.9. Use an application-owned push server
- 43.10. Testing delivery behavior
- 44. Notifications and Background Execution
- 45. Calendar integration
- 46. External Surfaces: Widgets and Live Activities
- 47. Maps
- 48. In-Car Experiences (CarPlay & Android Auto)
- 49. Motion Sensors
- 50. Miscellaneous features
- 50.1. Phone functions
- 50.2. Larger text accessibility
- 50.3. Contacts API
- 50.4. Localization & internationalization (L10N & I18N)
- 50.5. Location - GPS
- 50.6. Background music playback
- 50.7. Capture - photos, video, audio
- 50.8. Gallery
- 50.9. Analytics integration
- 50.10. Social sign-in (Facebook, Google, …)
- 50.11. Lead Component
- 50.12. Pull to refresh
- 50.13. Running 3rd party apps using display’s execute
- 50.14. Automatic build hint configuration
- 50.15. Easy thread
- 50.16. Mouse cursor
- 50.17. Working with GIT
- 51. Video encoding & decoding (VideoIO)
- 52. Performance, size & debugging
- 52.1. Reducing resource file size
- 52.2. Improving performance
- 52.3. SIMD: Data-Parallel primitives
- 52.3.1. When to use SIMD
- 52.3.2. Getting an instance
- 52.3.3. Allocation: Alignment and provenance
- 52.3.4. A minimal End-to-End example
- 52.3.5. Scratch allocations:
alloca* - 52.3.6. Rules for
alloca*scratch arrays - 52.3.7. Build-Time verification
- 52.3.8. Simulator tracking of aligned arrays
- 52.3.9. Built-In SIMD paths
- 52.4. Performance monitor
- 52.5. Network speed
- 52.6. Debugging Codename One sources
- 52.7. Device testing Framework/Unit testing
- 52.8. EDT error handler and sendlog
- 52.9. Kitchen sink case study
- 53. Testing with JUnit 5
- 53.1. When to use JUnit versus AbstractTest
- 53.2. Dependencies
- 53.3. A minimal JUnit test
- 53.4.
@CodenameOneTest - 53.5.
@RunOnEdt - 53.6.
@SimulatorProperty/@SimulatorProperties - 53.7.
@Theme - 53.8.
@DarkMode - 53.9.
@LargerText - 53.10.
@Orientation - 53.11.
@RTL - 53.12. Annotation resolution
- 53.13. EDT semantics
- 53.14. Headless behavior
- 53.15. Coexistence with
cn1:test - 53.16. Side-by-side example
- 53.17. Cross-reference
- 54. Advertising
- 55. Crash Protection
- 56. Analytics
- 57. Commerce
- 58. Monetization
- 58.1. In-app purchase
- 58.1.1. The SKU
- 58.1.2. Types of products
- 58.1.3. The "hello world" of in-app purchase
- 58.1.4. Making it consumable
- 58.1.5. Non-Renewable subscriptions
- 58.1.6. Promotional offers (iOS)
- 58.1.7. Restoring purchases and managing subscriptions
- 58.1.8. The Server-Side
- 58.1.9. The "hello world" of Non-Renewable subscriptions
- 58.1.10. Subscribe() vs purchase()
- 58.1.11. Screenshots
- 58.1.12. Summary
- 58.1.13. Auto-Renewable subscriptions
- 58.1.14. Auto-Renewable vs Non-Renewable: Choosing between them
- 58.1.15. Learning by example
- 58.1.16. Building the IAP demo project
- 58.1.17. Looking at the source of the app
- 58.1.18. The CN1-IAP-Validator library
- 58.1.19. The
validateAndSaveReceipt()method - 58.1.20. Google play setup
- 58.1.21. iTunes connect setup
- 58.1. In-app purchase
- 59. App Review & Feedback
- 60. Apple Wallet Extension
- 61. Advanced topics/under the hood
- 61.1. Sending arguments to the build server
- 61.2. Versioned builds
- 61.3. Android permissions
- 61.4. On device debugging
- 61.5. Native interfaces
- 61.6. Libraries - cn1lib
- 61.7. Integrating Android 3rd party libraries & JNI
- 61.8. Drag & drop
- 61.9. Android Lollipop ActionBar customization
- 61.10. Intercepting URLs on iOS & Android
- 61.11. Native peer components
- 61.12. Integrating 3rd party native SDKs
- 61.12.1. Step 1 : Review the FreshDesk SDKs
- 61.12.2. Step 2: Designing the Codename One public API
- 61.12.3. Step 3: The architecture and internal APIs
- 61.12.4. Step 4: Implement the public API and native interface
- 61.12.5. Step 5: Implementing the native interface in Android
- 61.12.6. Step 6: Bundling the native SDKs
- 61.12.7. Step 7: Injecting Android manifest and proguard config
- 61.13. Part 2: Implementing the iOS native code
- 61.14. Part 3 : Packaging as a cn1lib
- 61.15. Building your own Layout manager
- 61.16. Port a language to Codename One
- 61.17. Update framework
- 62. Security
- 62.1. Constant obfuscation
- 62.2. Storage encryption
- 62.3. Secure storage and secrets
- 62.4. Disabling screenshots
- 62.5. Blocking copy & paste
- 62.6. Blocking jailbreak
- 62.7. Device integrity, RASP & attestation
- 62.8. Strong Android certificates
- 62.9. Certificate pinning
- 62.10. Cryptographic primitives
- 62.10.1. Hashing
- 62.10.2. Message authentication (HMAC)
- 62.10.3. Secure random numbers
- 62.10.4. Symmetric encryption (AES)
- 62.10.5. Asymmetric encryption and digital signatures (RSA, ECDSA)
- 62.10.6. JSON Web Tokens
- 62.10.7. HOTP / TOTP one-time passwords
- 62.10.8. Walkthrough: Adding two-factor authentication to a sign-in flow
- 62.10.9. OTP input widget
- 62.10.10. Algorithm identifier reference
- 62.10.11. Key sizes and recommended defaults
- 63. App Shield
- 63.1. How it fits together
- 63.2. Turning it on
- 63.3. Protecting hosts
- 63.4. What happens to a request
- 63.5. Status, and what to do about it
- 63.6. Getting a token yourself
- 63.7. Certificate pinning
- 63.8. Runtime signals
- 63.9. Transports the guard doesn’t cover
- 63.10. Composing with your own network guard
- 63.11. Verifying the token in your backend
- 63.12. iOS App Attest specifics
- 63.13. Testing it in the simulator
- 63.14. When there is no engine
- 64. App Hardening
- 65. Biometric Authentication
- 66. Authentication and Identity
- 67. Deep-Link Routing
- 68. JSON / XML Object Mapping
- 69. Component Binding
- 70. SQLite ORM
- 71. AI, Chat UI, and Speech
- 71.1. The
com.codename1.aipackage- 71.1.1. A first chat
- 71.1.2. Streaming tokens
- 71.1.3. Tool calling
- 71.1.4. Structured output
- 71.1.5. Multi-modal messages
- 71.1.6. Embeddings
- 71.1.7. Image generation
- 71.1.8. Conversation persistence
- 71.1.9. Prompt templates
- 71.1.10. Retry policy
- 71.1.11. Simulator redirect for offline development
- 71.1.12. Storing the API key
- 71.2. The
ChatViewcomponent - 71.3. Speech recognition and TextToSpeech
- 71.4. On-device vision
- 71.5. Portable LiteRT inference
- 71.6. On-device language services
- 71.7. Platform availability
- 71.8. Migrating from the AI cn1libs
- 71.1. The
- 72. Near-Field Communication (NFC)
- 73. Bluetooth
- 74. Health
- 74.1. Quick start
- 74.2. Permissions, and the one thing that will surprise you
- 74.3. Reading samples
- 74.4. Aggregates and time buckets
- 74.5. Writing samples
- 74.6. Background delivery
- 74.7. Workouts
- 74.8. Bluetooth health sensors
- 74.9. Nutrition
- 74.10. Build configuration
- 74.11. Privacy and store policy
- 74.12. Simulating health
- 74.13. Troubleshooting
- 75. Smart Home
- 75.1. The model
- 75.2. Quick start
- 75.3. Android’s default answer isn’t "available"
- 75.4. Reading and writing
- 75.5. Values and units
- 75.6. Watching for change
- 75.7. Scenes
- 75.8. Adding an accessory
- 75.9. Build hints
- 75.10. Previewing in the simulator
- 75.11. Not claimed in this release
- 75.12. Commissioning onto your own fabric
- 76. Printing
- 77. Deeper Network Connectivity
- 78. Signing, certificates & provisioning
- 78.1. Common terms in signing & distribution
- 78.2. Certificate Wizard
- 78.2.1. Creating the App Store Connect API key
- 78.2.2. Recommended fast path: Auto Setup
- 78.2.3. Mac signing and notarization
- 78.2.4. Android signing
- 78.2.5. Windows signing
- 78.2.6. Clearing cached signing data
- 78.2.7. Manual asset management
- 78.2.8. Selecting devices
- 78.2.9. Decisions & edge cases
- 78.2.10. App IDs and provisioning profiles
- 78.2.11. Installing files locally
- 78.2.12. Building your app
- 78.3. Advanced iOS signing
- 78.4. Provisioning profile & certificates visual guide
- 78.5. Android
- 79. Working with iOS
- 79.1. Troubleshooting iOS debug build installs
- 79.2. Launch screen storyboard best practices
- 79.3. Local notifications on iOS and Android
- 79.4. iOS beta testing (testflight)
- 79.5. Metal renderer
- 79.6. Choosing a color space for the Metal renderer
- 79.7. Accessing insecure URLs
- 79.8. Using Cocoapods
- 79.9. Using Swift package manager
- 79.10. Including dynamic frameworks
- 80. On-Device Debugging (iOS)
- 80.1. When to use it
- 80.2. Quick start (IntelliJ IDEA)
- 80.3. Quick start (NetBeans)
- 80.4. Quick start (Maven from the command line)
- 80.5. What works today
- 80.6. Pointing the IDE at the Codename One sources
- 80.7. Known limitations
- 80.8. Performance
- 80.9. Debugging the generated Xcode project natively
- 80.10. Troubleshooting
- 80.10.1. The proxy reports "device disconnected" before the breakpoint fires
- 80.10.2. "Connection refused" when the device tries to reach the proxy
- 80.10.3. jdb reports "Internal exception: Unexpected JDWP Error: 100"
- 80.10.4. The app launches but the breakpoint never fires
- 80.10.5. Make the app wait while the proxy and IDE attach
- 81. On-Device Debugging (Android)
- 81.1. When to use it
- 81.2. Quick start (IntelliJ IDEA)
- 81.3. Wireless debugging
- 81.4. Quick start (Maven from the command line)
- 81.5. Useful command-line flags
- 81.6. What you can step through
- 81.7. Pointing the IDE at the Codename One sources
- 81.8. Debugging the generated Gradle project from Android Studio
- 81.9. Troubleshooting
- 82. Working with JavaScript
- 82.1. Choosing the JavaScript compiler
- 82.2. Troubleshooting build errors
- 82.3. ZIP, WAR, or preview: What’s the difference
- 82.4. Setting up a proxy for network requests
- 82.5. Using the CORS proxy for same origin requests
- 82.6. Customizing the splash screen
- 82.7. Debugging
- 82.8. Including Third-Party JavaScript libraries
- 82.9. Browser environment variables
- 82.10. Changing the native theme
- 82.11. Disabling the 'OnBeforeUnload' handler
- 82.12. Deploying as a progressive web app
- 82.13. Playing media and opening links
- 82.14. BrowserComponent lifecycle
- 83. Working with macOS
- 84. App Store Submission and Deployment
- 85. Desktop Integration
- 86. Working with the native Windows port
- 86.1. How it works (the technology stack)
- 86.2. Building a native Windows app
- 86.3. Cloud builds (the
win32target) - 86.4. Build hints
- 86.5. Optimized, with debug info in a separate file
- 86.6. Code signing
- 86.7. Native Windows vs. the desktop (JVM) app vs. the jar
- 86.8. How it works (the technology stack)
- 86.9. Runs on essentially any Linux desktop
- 86.10. Building a native Linux app
- 86.11. Build hints
- 86.12. Optimized and stripped by default
- 86.13. Native Linux vs. the executable jar
- 86.14. Blocking native calls and the concurrent GC
- 87. Wearables (Apple Watch and Wear OS)
- 87.1. One Project, Two Apps
- 87.2. Companion or Standalone
- 87.3. Running the Pair While You Develop
- 87.4. Detecting the Watch Form Factor
- 87.5. Designing for the Watch
- 87.6. Sharing Data Between the Phone and the Watch
- 87.7. Complications and Tiles
- 87.8. Apple Watch (watchOS)
- 87.9. Android (Wear OS)
- 87.10. Summary
- 88. Television (Apple TV and Android TV)
- 89. Working with Codename One sources
- 90. Skin Designer
- Appendix A: Project archetypes
- Appendix B: Maven goals
- B.1. Codename One build (
build) - B.2. Generate legacy cn1lib (
cn1lib) - B.3. Compliance check (
compliance-check) - B.4. Compile CSS (
css) - B.5. Generate app project (
generate-app-project) - B.6. Clone project (
clone) - B.7. Create GUI Form (
create-gui-form) - B.8. Generate cn1lib project (
generate-cn1lib-project) - B.9. Generate desktop app wrapper (
generate-desktop-app-wrapper) - B.10. Generate GUI sources (
generate-gui-sources) - B.11. Generate native interfaces (
generate-native-interfaces) - B.12. Generate OpenAPI client (
generate-openapi) - B.13. Generate gRPC client (
generate-grpc) - B.14. Generate GraphQL client (
generate-graphql) - B.15. GUIBuilder goal (
guibuilder) - B.16. Generate archetype (
generate-archetype) - B.17. Install Codename One (
install-codenameone) - B.18. Install legacy Cn1lib (
install-cn1lib) - B.19. Open Designer (
designer) - B.20. Prepare simulator classpath (
prepare-simulator-classpath) - B.21. Open settings (
settings) - B.22. Run tests (
test) - B.23. Update Codename One (
update)
- B.1. Codename One build (
- Appendix C: API
- Appendix D: Codename One Settings
- Appendix E: Rich properties file (rpf) format
- Historical reference
Preface
This developer guide comes directly from the docs directory of the Codename One Git repository. The documentation is written in AsciiDoc, reviewed through pull requests, and published from the main branch to several targets.
How to contribute updates
To contribute updates, clone the repository, create a feature branch, and edit the AsciiDoc files in docs/developer-guide. Follow the steps in the CONTRIBUTING guidelines to open a GitHub pull request (PR) instead of using the deprecated community wiki. Continuous integration lints and builds each PR automatically. A maintainer then reviews the PR before merging it. After the merge, the content appears in the web manual at https://www.codenameone.com/manual/ and in the downloadable PDF at https://www.codenameone.com/files/developer-guide.pdf. From time to time, major revisions are collected for print-on-demand distribution.
This guide focuses on tutorial and conceptual material. The complete API reference is available in the Codename One Javadoc. The framework source code and this manual live side by side in Git, so documentation and code improvements follow the same contribution workflow.
Authors
This document includes content from contributors and community wiki edits. If you edit pages in the guide, add your name here in alphabetical order by surname:
Rights & Licensing
You may copy, redistribute, or print this document without prior permission from Codename One. You may not charge for the document itself, but charging for printing costs remains permitted.
If you print or reproduce sections and make changes, state that the result is a modified copy. Also link to the original source at https://www.codenameone.com/developer-guide/.
Conventions
This guide uses several notations for tips and further guidance.
When additional information breaks from the current tutorial flow, use a sidebar like this:
Here are common conventions for highlighting notes:
| This is an important note |
| This is a helpful tip |
| This is a general informational note. It may be interesting, but it isn’t crucial. |
| This is a warning. Pay attention to it. |
This convention is used when referring to a button or widget to press in the UI. For example, press the button labeled Press Here.
Quotes appear as follows:
This is a quote
Bold provides light emphasis for a specific word or two within a sentence.
1. Maven Project Workflow
Codename One uses Maven as the standard way to create, run, and maintain applications. This chapter consolidates the workflow guidance that used to live in the standalone Maven manual so the developer guide provides a single source of truth for building apps, updating projects, and managing add-ons.
1.1. Introduction
Codename One uses Maven as its primary build tool. This guide aims to be the definitive source of information for this project structure.
1.1.1. Conventions
The instructions throughout this chapter provide parallel guidance for the supported development environments. Each subsection heading identifies the target tooling so you can follow the directions that match your workflow:
Command Line (CLI): Focused on running Maven from a terminal. The commands use a Unix-style shell syntax; adapt the examples for Windows when necessary.
IntelliJ IDEA: Step-by-step directions for working inside IntelliJ.
NetBeans: Equivalent instructions tailored to NetBeans.
Eclipse: Maven-based guidance for Eclipse users.
When you reach environment-specific sections later in the guide, follow the subsection corresponding to your preferred tools.
1.2. Getting started
1.2.1. Prerequisites
Codename One supports JDK 11 through 25 for running the simulator and the "Run as desktop app" target. Eclipse Temurin is the easiest source of a supported JDK on macOS, Windows, and Linux.
After installing the JDK, point JAVA_HOME at it and confirm with:
java -version
mvn -vBoth should report Java 11 or newer. The Codename One Maven plugin checks the
runtime JDK version when you invoke mvn cn1:run or mvn cn1:debug and fails
fast with a friendly message if it’s older than 11. Build-only goals (such as
-Pexecutable-jar) still work on older JDKs.
1.2.2. Creating a new project
Codename One initializr
The easiest way to create a new project is to use the Codename One initializr.

This tool will allow you to choose from a growing selection of project templates, and download a starter project that you can open in your preferred IDE (IntelliJ IDEA, NetBeans, etc.), or build directly on the command-line using Maven.
The starter projects are based on the Section A.1, “Codename One application project archetype (cn1app-archetype)”.
The following tutorials provide step-by-step instructions for getting started with bare-bones app templates. Those tutorials are a better starting place for Codename One development than this manual, as they’re written in tutorial form. Java Getting Started Tutorial: Kotlin Getting Started Tutorial: |
Generating a new project from the command-line
Bare-bones Java project
If you prefer to generate your projects directly on the command-line, you can use the Section A.1, “Codename One application project archetype (cn1app-archetype)” to generate the project directly on the command-line:
mvn archetype:generate \
-DarchetypeGroupId=com.codenameone \
-DarchetypeArtifactId=cn1app-archetype \
-DarchetypeVersion=LATEST \
-DgroupId=YOUR_GROUP_ID \
-DartifactId=YOUR_ARTIFACT_ID \
-Dversion=1.0-SNAPSHOT \
-DmainName=YOUR_MAIN_NAME \
-DinteractiveMode=falseThis will generate a project in the current directory. The project’s directory will have the same name as the artifact ID you specified here. For example, If your command had -DartifactId=myapp, then the project will be located in a newly created directory named "myapp."
| If you haven’t used Maven archetypes before, this snippet may be confusing. See Introduction to Maven Archetypes to get up to speed. |
This command uses the Section A.1, “Codename One application project archetype (cn1app-archetype)” which has the following Maven coordinates:
<dependency>
<groupId>com.codenameone</groupId>
<artifactId>cn1app-archetype</artifactId>
<version>LATEST</version>
<type>maven-archetype</type>
</dependency>This archetype generates a bare-bones Java project (the same one described in Getting Started with the Bare-bones Java App Template).
| View the source of the cn1app-archetype project here. |
You can learn more about using the archetype in the appendix.
Project templates
The bare-bones Kotlin App project template is an alternative starter project that uses Kotlin as the primary language instead of Java. It’s built on the cn1app-archetype at its core, but it includes some more configuration settings and sources to change the template. You can use such templates as starter projects by using the generate-app-project goal of the Codename One Maven plugin.
Here is an example which generates a project based on the bare-bones Kotlin template:
mvn com.codenameone:codenameone-maven-plugin:{cn1-plugin-release-version}:generate-app-project \
-DarchetypeGroupId=$archetypeGroupId \
-DarchetypeArtifactId=$archetypeArtifactId \
-DarchetypeVersion=$archetypeVersion \
-DartifactId=$artifactId \
-DgroupId=$groupId \
-Dversion=$version \
-DmainName=$mainName \
-DinteractiveMode=false \
-DsourceProject=/path/to/kotlin-example-app| This command is formatted for the bash prompt (for example, Linux or Mac). It will work on Windows also if you use bash. If you’re on Windows and are using PowerShell or the regular command prompt, then you’ll need to modify the command slightly. In particular, the entire command would need to be on a single line. (Remove the '\' at the end of each line, and merge lines together, with space between the command-line flags) |
Like the archetype:generate goal, this will create the project in a directory named after your specified artifact ID. For example, If your command included -DartifactId=myapp, then the project would be in a newly created directory named "myapp."
Some notes here:
The
com.codenameone:codenameone-maven-plugin:7.0.210:generate-app-projectargument is the fully qualified goal name for thegenerate-app-project. This is necessary since you aren’t running this goal in the context of any existing project. You should adjust the version number (7.0.210) to reflect the latest available Codename One version on Maven Central.The
archetypeGroupId,archetypeArtifactId, andarchetypeVersionparameters are the same as when using thearchetype:generategoal, and they will (almost) always refer to the Section A.1, “Codename One application project archetype (cn1app-archetype)”.The
groupId,artifactId, andversionwork the same as for thearchetype:generategoal. That’s, that they specify the coordinates for your newly created project.The
mainNamespecifies the Main class name for your app. This is the class name, and shouldn’t include the full package. For example,MyApp, not "com.example.MyApp"The
sourceProjectproperty is the path to the "template" project. In this case, you will assume that you’ve cloned the bare-bones Kotlin project template repository at /path/to/kotlin-example-app.
A project template isn’t much different than a regular project. The template can be either a legacy Ant project, or a new Maven project. In fact, this goal is the same one you would use to migrate a legacy Ant project to use the new Maven project structure. See Section 1.4, “Creating project templates” for instructions on building your own project templates. |
1.2.3. Migrating an existing project
If you have an existing Codename One application project that uses the old Ant project structure, you can use the generate-app-project goal to migrate the project over to maven. This goal doesn’t make any changes to the Ant project. It creates a new Maven project and copies over all the project sources and libraries, reorganized to fit the new project structure.
A minimal invocation of this goal would look like:
# Specify your the version of the codenameone-maven-plugin.
# Find the latest version at
# https://search.maven.org/search?q=a:codenameone-maven-plugin
CN1VERSION={cn1-plugin-release-version}
mvn com.codenameone:codenameone-maven-plugin:$CN1VERSION:generate-app-project \
-DgroupId=YOUR_GROUP_ID \
-DartifactId=YOUR_ARTIFACT_ID \
-DsourceProject=/path/to/your/project \
-Dcn1Version=$CN1VERSION| This command is formatted for the bash prompt (for example, Linux or Mac). It will work on Windows also if you use bash. If you’re on Windows and are using PowerShell or the regular command prompt, then you’ll need to modify the command slightly. In particular, the entire command would need to be on a single line. (Remove the '\' at the end of each line, and merge lines together, with space between the command-line flags) |
This will generate the new project in the current directory inside a folder named after the artifactId parameter.
After building the project, try running it to make sure that the migration worked. For example, Assuming that your artifactId was myapp:
Command line
cd myapp
./run.shOn Windows it would be run.bat instead of run.sh. |
If All goes well, your app should open in the Codename One simulator.
IntelliJ IDEA
Open the myapp folder in IntelliJ. Then press the "Run"
button in the upper right of the toolbar.
If All goes well, your app should open in the Codename One simulator.
NetBeans
| Before opening the project in NetBeans, be sure to copy the files in the tools/netbeans directory into the root directory. These are necessary for NetBeans to run, build, and debug the project. |
Open the myapp folder as a project in NetBeans. Then press the "Run"
button on the toolbar.
If all goes well it should open in the Codename One simulator.
Eclipse IDE
Open Eclipse, and select "File" > "Import…"

In the Import dialog, expand Maven, select Existing Maven Projects, and press Next.

In the next panel, press the Browse button, and, in the file dialog, select the "myapp" directory, and press Next.

The next panel should look like the one below. Make sure all the projects are "checked," and press Finish.

Almost there, but not quite…
Next you need to import the Eclipse launch configurations located inside the tools/eclipse directory.
Select File > Import… again, but this time, in the Import dialog, select Run/Debug > Launch Configurations and click Next.

In the next panel, press Browse… then select the tools/eclipse directory.

Then check the eclipse option, and press Finish

The "Run" button menu should now include options for all the major build targets. You can see them by pressing on the Run button in the toolbar:

Select the MyApp - Run Simulator option from this menu.
If all goes well it should open in the Codename One simulator.
Example: Migrating kitchen sink app
Consider a concrete example, now. Download the KitchenSink Ant project from here and extract it.
The following is a bash script that uses curl to download this project as a zip file, and then converts it to a fully functional Maven project:
CN1_VERSION={cn1-plugin-release-version}
curl -L https://github.com/codenameone/KitchenSink/archive/v1.0-cn7.0.11.zip > master.zip
unzip master.zip
rm master.zip
mvn com.codenameone:codenameone-maven-plugin:${CN1_VERSION}:generate-app-project \
-DarchetypeGroupId=com.codename1 \
-DarchetypeArtifactId=cn1app-archetype \
-DarchetypeVersion=${CN1_VERSION} \
-DartifactId=kitchensink \
-DgroupId=com.example \
-Dversion=1.0-SNAPSHOT \
-DinteractiveMode=false \
-DsourceProject=KitchenSink-1.0-cn7.0.11| This command is formatted for the bash prompt (for example, Linux or Mac). It will work on Windows also if you use bash. If you’re on Windows and are using PowerShell or the regular command prompt, then you’ll need to modify the command slightly. In particular, the entire command would need to be on a single line. (Remove the '\' at the end of each line, and merge lines together, with space between the command-line flags) |
This will generate the maven project in a directory named "kitchensink" in the current working directory because of the -DartifactId=kitchensink directory.
1.2.4. Adding project dependencies
| For the easiest and recommended approach to adding dependencies to your project, skip to Section 1.2.4.5, “Managing add-ons in Codename One Settings”. |
One of the reasons to use Maven as the build tool is because it makes the management of project dependencies almost trivial. If the library you want to add is on Maven central, then you can copy and paste its <dependency> snippet into your pom.xml file and you’re good to go. Maven does the rest.
| See Introduction to the Dependency Mechanism on the Maven website for a gentle, but comprehensive introduction to Maven dependencies. |
With Codename One projects, there are a few caveats (see Section 1.2.4.4, “The compliance check”), and a few added niceties that make it easier to find and install add-on libraries in your project (see Section 1.2.4.5, “Managing add-ons in Codename One Settings”).
Which pom.xml to add the <dependency> snippet to
Suppose you have a Maven <dependency> snippet that you’ve copied from Maven central, and it’s burning a hole in your clipboard while you’re trying to figure out where to paste it into your project.
Codename One application projects, being multi-module projects, have more than one pom.xml file; One per module.
Question: Which pom.xml file should you paste the snippet into?
Answer: common/pom.xml (almost always).
The "common" module is where all your Codename One application resides. It houses your Java and Kotlin files, your CSS files, your GUI builder files, your Codename One configuration files (that is, codenameone_settings.properties). Pretty much everything. The things you’d place in the other modules (for example, Java SE, ios, etc.) are your platform-specific native interface implementations; And in many applications you won’t need any of that.
When adding dependencies into your app, you’ll therefore almost always place them inside the pom.xml file for the "common" module.
You can add dependencies without editing XML by launching Codename One Settings with mvn cn1:settings. See Section 1.2.4.5, “Managing add-ons in Codename One Settings”. |
Example: Adding Google Maps dependency via Maven central
Add the GoogleMaps library to your app as a maven dependency.
As described in the GoogleMaps cn1lib README, the dependency snippet is:
<dependency>
<groupId>com.codenameone</groupId>
<artifactId>googlemaps-lib</artifactId>
<version>1.0.1</version>
<type>pom</type>
</dependency>You should, but, look on Maven central to see what the latest version number is, and substitute that version into the <version> tag of the snippet.
Copy and paste this snippet into the <dependencies> section of your common/pom.xml file. And save it.
The common/pom.xml file has a lot of existing configuration in it, and it may not be clear, on first glance, where the The correct This is a special marker that’s used by some Codename One tooling to help it locate the optimal place to inject dependencies. Don’t REMOVE THIS COMMENT. Just add your dependency snippet somewhere before or after it. |
Compatibility with Codename One
You can paste any Maven dependency snippet you like into your project, but libraries that haven’t been specifically developed for Codename One might not be compatible. See Appendix C, API. If you’re unsure whether a library is compatible, you could add the dependency and try to use it in your app. If it isn’t compatible, it will fail when you try to build the app, during the compliance check.
The easiest way to find Codename One libraries is to use the Extensions view in Codename One Settings. These libraries were built specifically for Codename One. Settings warns before installing catalog entries known to target older Codename One releases.
The compliance check
All application code in the common module of your Codename One project must be compatible with Codename One. This includes all dependencies. When you build your project, it will perform a compliance check to ensure that no code uses unsupported APIs. (See Appendix C, API).
If the compliance check fails (that is, the app uses unsupported APIs), the build will fail. The error log should provide some clues about where the offending code resides.
Managing add-ons in Codename One Settings
Launch Codename One Settings from the project root, then select Extensions in the left navigation rail:
mvn cn1:settings
As an example, install the "Google Maps" library.
Type Maps in the search field and locate Codename One Google Native, the Google Maps library.
Click Install or Download, depending on how the catalog entry is distributed.
Settings shows progress while it installs the extension. For an installed extension, click the same action area and confirm Uninstall to remove it.
If the Settings window opens blank
Settings is a Codename One app hosted in a native window, so a window that opens but shows nothing can come from the window layer, the display scale, the theme, or font loading. Capture the render state and attach it to a bug report rather than guessing:
mvn cn1:settings -Dsettings.diagnostics=cn1-settings-diagnostics.txtThe file records the OS and JDK, the HiDPI scale the JVM reports, the window and canvas geometry, the size Codename One laid the form out at, and the colours and font metrics resolved for the theme. Add -Dsettings.screenshot=shot.png to also write the window contents; a second shot.onscreen.png captures the pixels actually on screen, which can differ from the offscreen paint. The launch log is at ~/.codenameoneSettings/settings.log.
Installing legacy cn1libs
The recommended approach for installing add-ons is to use Codename One Settings or add the Maven dependency to common/pom.xml. In some situations neither method is available. For example, you might have a legacy cn1lib file that isn’t listed in the extension catalog or deployed to Maven Central.
In cases like this you can use the install-cn1lib Maven goal to install it as follows:
mvn cn1:install-cn1lib -Dfile=/path/to/yourlibrary.cn1lib1.3. Updating Codename One
Codename One releases new versions weekly on Maven central. It’s recommended that you stay up to date with the latest version as much as possible to ensure compatibility with the Codename One build server, which is always running the latest version.
You can use the update goal to update both the Codename One libraries, and the Codename One dependencies in your project.
For example:
mvn cn:updateCLI
Or you can use the run.sh/run.bat script to run this goal as follows:
./run.sh updateUse run.bat update instead on Windows |
IntelliJ
Or you can click on the "Configuration" menu, and select "Tools" > "Update Codename One" as shown here:

Then press the
button.
NetBeans
Or you can right-click on the project in the project inspector, and select "Run Maven" > "Update Codename One" as shown here:

Then press the
button.
Manually updating the pom.xml file
You can also update your Codename One dependencies manually by modifying the cn1.version and cn1.plugin.version properties defined in your project’s pom.xml file.
For example, Open the pom.xml file, and look for the following:
<cn1.plugin.version>7.0.210</cn1.plugin.version>
<cn1.version>7.0.210</cn1.version>Change these values to reflect the latest version of the codenameone-maven-plugin found here.
Updating the cn1.plugin.version and cn1.version properties manually will update the Maven dependencies for your project but it won’t update the other Codename One tools such as the GUI builder, and the Build Server Client, which are managed outside of Maven. You should use the Section B.23, “Update Codename One (update)” as described at the beginning of this section to perform a "full" update. |
1.4. Creating project templates
A project template is a Codename One application project that can be used as a starting point for building a Codename One application. Codename One initializr uses project templates to generate starter projects for Codename One applications. You can also use the Section B.5, “Generate app project (generate-app-project)” goal to generate starter projects from templates directly in Maven.
Any Codename One project can be converted into a project template.
1.4.1. Converting a Codename One application project into a project template
If you have an existing maven Codename One application project, you can convert it into a project template by adding a file named generate-app-project.rpf in the root directory of the project.
The contents of this file should look like:
template.mainName=$YOUR_PROJECT_MAIN_NAME
template.packageName=$YOUR_PROJECT_PACKAGE_NAME
[dependencies]
====
... YOUR PROJECT MAVEN DEPENDENCIES ...
====
[parentDependencies]
====
... YOUR PARENT PROJECT MAVEN DEPENDENCIES ...
====Where you make the following substitutions:
- $YOUR_PROJECT_MAIN_NAME
This should be the value of the
codename1.mainNameproperty in the project’scodenameone_settings.propertiesfile.- $YOUR_PROJECT_PACKAGE_NAME
This should be the value of the
codename1.packageNameproperty in the project’scodenameone_settings.propertiesfile.- … YOUR PROJECT MAVEN DEPENDENCIES…
Paste any maven dependencies that the project requires into this section. These will be injected into the
<dependencies>section of the common/pom.xml file.- … YOUR PARENT PROJECT MAVEN DEPENDENCIES…
Paste any maven dependencies that the parent project requires into this section. These will be injected into the
<dependencies>section of the pom.xml file.
See Section B.5.4.2, “Sample generate-app-project.rpf file” for a more concrete example of the generate-app-project.rpf.
1.4.2. Test your project template
You can test your project template by using it as the sourceProject parameter for the generate-app-project goal. See Section B.5, “Generate app project (generate-app-project)”.
1.4.3. Add your template to Codename One intializr
If you have a project template that you want to share with the community, please file an issue in the Codename One issue tracker with a link to a GitHub Repository of your project template, and request to have it added Codename One initializr.
1.5. Codename One libraries
A Codename One Library (cn1lib) is a module that can be distributed and added to Codename One applications to add functionality. It can be distributed as a self-contained bundle (a file with the.cn1lib extension), or deployed on Maven central to be included in application projects as a pom dependency.
A cn1lib may contain any of the following:
Cross-platform Java classes.
Native code that targets specific platforms.
Build hints, which will affect how projects will be built that include this library. These can contain things like Gradle dependencies on Android, Cocoapods dependencies on iOS, and other hints to affect the build-server process.
CSS files.
1.5.1. Creating a library project
Use the cn1lib-archetype for generating a new Codename One library project as follows:
Command line
mvn archetype:generate \
-DarchetypeArtifactId=cn1lib-archetype \
-DarchetypeGroupId=com.codenameone \
-DarchetypeVersion=LATEST \
-DgroupId=com.example.mylib \
-DartifactId=mylib \
-Dversion=1.0-SNAPSHOT \
-DinteractiveMode=false| This command is formatted for the bash prompt (for example, Linux or Mac). It will work on Windows also if you use bash. If you’re on Windows and are using PowerShell or the regular command prompt, then you’ll need to modify the command slightly. In particular, the entire command would need to be on a single line. (Remove the '\' at the end of each line, and merge lines together, with space between the command-line flags) |
In the above snippet you would change the groupId, artifactId, and version properties to reflect your project settings.
You can run the And then follow the prompts. Or you could enter:
And follow the prompts. This will, result in fewer prompts because you’ve already specified the archetype to use. |
This will create a new project for you in the current directory, in a newly created directory named after the artifactId that you entered.
IntelliJ IDEA
Select "File" > "New Project"…

Select "Maven" in the left menu.

Check the "Create from Archetype" checkbox.
. This should allow you to choose from of archetypes that are already known to IntelliJ.If you don’t see an option for
com.codenameone:cn1lib-archetype, then IntelliJ doesn’t know about it yet. If, but you do see this option, you can skip to the next step. Press the "Add Archetype…" button. This will display a dialog for you to enter the details of the archetype.
Fill in this dialog as shown in the above image. Specifically
groupId=com.codenameone,artifactId="cn1lib-archetype," andversion="LATEST"Then press
OK.Select the option that says "com.codenameone:cn1lib-archetype"

Then press "Next"
This will display a form where you can enter the details of your project such as its location (where you want to create the project folder), the name, the artifact ID, and the groupID. Fill in this form as you see fit.

Then click "Next"
The final form in this wizard summarizes the project details and gives you an opportunity to add more properties to pass to the
archetype:generategoal. In your case you don’t need to add any more properties. If the information looks correct, you can pressNext.
At this point you will be prompted to open the project.
NetBeans
Select "File" > "New Project…"

In the "New Project" dialog, select "Java with Maven" in the left panel, and "Project from Archetype" in the right panel, as shown below.

Then press "Next"
This will bring you to the "Maven Archetype" dialog as shown below:

Enter "com.codenameone" or "cn1lib-archetype" into the search field. Then select "cn1lib-archetype" in the "Known archetypes:" panel. This will prefill the Group ID, Artifact ID and Version fields for you. You may want to change Version to LATEST to ensure that it tries to use the latest available version of the archetype.
Then click "Next"
This will bring you to the "Name and Location" panel of the wizard.

Enter in the project name (which you’ll be forced to use as the artifact ID also), project location, groupId, version, and package. The "Package" is unimportant here as it isn’t used anywhere in the project.
Once you’ve entered the information to your liking press the "Finish" button.
This will create a new library project for you at the location you specified.
Eclipse IDE
Select "File" > "New Project…"
In the New Project dialog, expand the Maven item, and select Maven Project

Then press "Next"
The next panel will look like the below image. The default settings on this panel should be fine. Press Next

In the next panel, enter "cn1lib" in the Filter field. After a moment the cn1lib-archetype should appear in the area below as shown here:

Select that option, and press Next
The next panel, allows you to enter your project details, such as group ID, and artifact ID. Your project information here and then press Finish.

This will create a new library project for you at the location you specified.
Project structure
Take a look at the project that was created. It’s a multi-module Maven project with the following modules:
- common
The module where you’ll add all your cross-platform code and CSS, and build hint configuration. This module is in the "common" directory of the main project.
- Java SE
The module where you can implement native interfaces for the Java SE platform. This module is in the "Java SE" directory of the main project.
- ios
The module where you can implement native interfaces for the iOS platform. This module is in the "ios" directory of the main project.
- android
The module where you can implement native interfaces for the Android platform. This module is in the "android" directory of the main project.
- JavaScript
The module where you can implement native interfaces for the JavaScript platform. This module is in the "JavaScript" directory of the main project.
- lib
The library module which includes all the other modules as dependencies, and can be used as a pom dependency in Codename One application projects that wish to use this library. This module is in the "lib" directory of the main project.
- tests
An application project for writing unit tests against your library. This module is in the "tests" directory of the main project.
IntelliJ IDEA
The project inspector will look like:

This top-level view of the module structure may seem daunting. Most of your development will occur inside the "common" module. If you expand that module it will look more familiar to developers who have used the old Ant project structure:

Your cross-platform Java source would go in the common/src/main/java directory. Your CSS files go in the common/src/main/css directory.
NetBeans
The project inspector will look like:

This top-level view of the modules doesn’t provide a clear view of the project landscape, but, since 99% of your development will occur inside the common submodule. Open that "common" sub-module project as well and take a peek.
Right-click on the "Common" sub-module, and select "Open Project" as shown below:

With the common subproject open, the project inspector will look like:

In this screenshot, "Source Packages" and "Other Sources/css" are expanded to highlight where your Java source files and CSS source files will be located.
The project inspector hides a few important files, but, so here is a screenshot of the File inspector for the common project:

Eclipse IDE
The package explorer will look like:

In this screenshot, the common/src/main/css and common/src/main/java directories are expanded since this is where most of your module source will go.
Command line
If you do a file listing on the project directory, it shows the following:
Steves-Mac-Pro:MyFirstLibrary shannah$ find .
.
./tests
./tests/pom.xml
./tests/javase
./tests/javase/pom.xml
./tests/common
./tests/common/codenameone_settings.properties
./tests/common/pom.xml
./tests/common/nbactions.xml
./tests/common/src
./tests/common/src/test
./tests/common/src/test/java
./tests/common/src/test/java/com
./tests/common/src/test/java/com/example
./tests/common/src/test/java/com/example/myfirstlib
./tests/common/src/test/java/com/example/myfirstlib/MyFirstTest.java
./tests/common/src/main
./tests/common/src/main/css
./tests/common/src/main/css/theme.css
./tests/common/src/main/java
./tests/common/src/main/java/com
./tests/common/src/main/java/com/example
./tests/common/src/main/java/com/example/myfirstlib
./tests/common/src/main/java/com/example/myfirstlib/LibraryTests.java
./tests/cn1libs
./tests/.mvn
./tests/.mvn/jvm.config
./pom.xml
./javase
./javase/pom.xml
./javase/src
./javase/src/main
./javase/src/main/java
./javase/src/main/java/com
./javase/src/main/java/com/example
./javase/src/main/java/com/example/myfirstlib
./ios
./ios/pom.xml
./ios/src
./ios/src/main
./ios/src/main/objectivec
./common
./common/codenameone_library_required.properties
./common/pom.xml
./common/codenameone_library_appended.properties
./common/src
./common/src/test
./common/src/test/java
./common/src/test/java/com
./common/src/test/java/com/example
./common/src/test/java/com/example/myfirstlib
./common/src/test/java/com/example/myfirstlib/MyLibraryTest.java
./common/src/main
./common/src/main/css
./common/src/main/css/theme.css
./common/src/main/java
./common/src/main/java/com
./common/src/main/java/com/example
./common/src/main/java/com/example/myfirstlib
./common/src/main/java/com/example/myfirstlib/MyLibrary.java
./android
./android/pom.xml
./android/src
./android/src/main
./android/src/main/java
./android/src/main/java/com
./android/src/main/java/com/example
./android/src/main/java/com/example/myfirstlib
./lib
./lib/pom.xml
./MyFirstLibrary.iml
./javascript
./javascript/pom.xml
./javascript/src
./javascript/src/main
./javascript/src/main/javascript
./.idea
./.idea/encodings.xml
./.idea/jarRepositories.xml
./.idea/.gitignore
./.idea/workspace.xml
./.idea/misc.xml
./.idea/compiler.xmlThis may seem daunting at first, but it’s important to realize that 99% of the time, you’ll be working in the "common" module - most of the other stuff is boilerplate.
Important files
A few key files in this project that you’ll be using more than the others.
- pom.xml
The maven configuration file of the root module is where you will set project-wide properties such as the
cn1.versionproperty, which specifies the version of the Codename One libraries that the module should be compiled against. Periodically, you’ll want to update thecn1.versionproperty to point to the latest version.When/if you decide to deploy your module to Maven central, you’ll need to add more deployment-related settings in this file.
- common/pom.xml
The maven configuration file for the "common" module, which will contain most of your cn1lib’s source code, CSS files, and properties files. If your library depends on other libraries or jar files, you’ll be adding them as dependencies in this file, and not the root pom.xml file.
- common/codenameone_library_appended.properties
This file is where you can specify properties that should be merged with the codenameone_settings.properties of application projects that include this library as a dependency. This is where you would add, for example, Gradle dependencies required for the Android builds, or CocoaPods dependencies that are required for iOS builds.
- common/codenameone_library_required.properties
This file allows you to specific build hints that must be present in application projects that include this library. If this library requires a particular android build tools version, or a specific Java version, then those requirements should be specified in this file.
Important directories
As mentioned earlier, 99% of all your development will likely occur inside the "common" module. The other modules are for native implementations of Native interfaces.
- common/src/main/java
This is where your cross-platform Java source files will be placed.
- common/src/main/css
If your library uses CSS, this is where all CSS-related files will be placed.
- common/src/main/resources
Other non-java resources that you want to have included in the classpath.
Building the library
Command line
To build the library, run the "install" goal on the root module as follows:
mvn installIntelliJ IDEA
Press the "build"
button on the toolbar.
NetBeans
Right-click on the "root" module in the project explorer and select Build.

| You must build the root module and not one of the submodules. |
Or you could have selected the "root" module in the project explorer and pressed the "build"
button on the toolbar.
Eclipse IDE
Right-click on the "root" module in the project explorer and select Run as > Maven Install

If the build fails for any reason, check to make sure that your project is using the latest version of the Codename One plugin. You can do this by opening the pom.xml file, and changing the cn1.version and cn1.plugin.version properties to reference the latest version. Check for the latest version here. |
Building the Legacy.cnlib file
When using the Maven build tool, you no longer require the.cn1lib file at all. Your library projects can be handled entirely via Maven’s dependency mechanism. The preferred way to distribute your libraries is on Maven central, and the preferred way to add a library to an application is via a Maven "pom" dependency.
That being said, you may still want to distribute your library as a.cn1lib file for the sake of users who are still using Ant as their build tool. For that reason, when you build a library project, the cn1lib is automatically built as well. After running a build, you can look in the common/target directory and find your.cn1lib file ready to be distributed.
Editing Java Code
To get acquainted with your project, add a "Hello World" Java class that you want to make available as part of your cn1lib.
Add a new class inside the "common/src/main/java" directory with package com.example, and name HelloWorld. Enter the following contents into the class:
public class HelloWorld {
public static void helloWorld() {
System.out.println("Hello world");
}
}Now build the library again. (See Section 1.5.1.6, “Building the library”).
Using the library in an application project
Now that you’ve built your library and added a Java class, try adding it as a dependency in an application project. If you haven’t yet created an application project, do that now. See Section 1.2.2, “Creating a new project” for instructions on creating a new application project.
Open the common/pom.xml file of your application project.
| Make sure you’re editing the common/pom.xml file of the application project and not the library project. |
This file may look a little hairy as there is a lot of configuration in there. You will be looking for the <dependencies> section.
The common/pom.xml file will have more than one <dependencies> tag, as it includes some profiles handling things like Kotlin support. There will be one particular <dependencies> tag that includes a comment like
<!-- INJECT DEPENDENCIES -->You should add your dependencies before this comment.
For the sake of this example, suppose your library was set up with the following coordinates:
groupId: |
|
artifactId: |
|
version: |
|
In this case you would add the following XML snippet to the <dependencies> section of your application’s common/pom.xml file:
<dependency>
<groupId>com.example</groupId>
<artifactId>mylib-lib</artifactId>
<version>1.0-SNAPSHOT</version>
<type>pom</type>
</dependency>Notice that you appended "-lib" to the artifactId. This is because you’re including the "lib" module of your library project as the dependency, and not the root module. Also the <type>pom</type> is important as it indicates that this is a pom dependency - not a regular jar dependency. |
Now try it out. Try adding the following code to your application project’s main class (or anywhere in the application project, for that matter):
And build the project. The project should build OK, and if you run it, you should see that the helloWorld() method works as designed.
1.5.2. Adding menus to the simulator
A cn1lib can contribute menu items to the Codename One simulator’s menu bar. This is the same affordance the framework itself uses for the Skins / Native Theme / Simulate menus — opened up so library authors can expose backend-specific actions (for example, "Add a simulated peripheral," "Inject a push notification," or "Switch backend") without users having to write any Swing code or instrument their app.
Every menu item is also reachable from CN1 UnitTests (or any app code) through CN.execute("namespace:itemN") — the JavaSE port’s URL execute is overloaded to recognize a registered hook url and dispatch it on the EDT instead of opening it as a browser URL. On Android, iOS, JavaScript and other production targets no hooks are registered, so a hook-style URL falls through to the normal native execute and (almost always) becomes a no-op; tests should pair CN.execute with CN.canExecute for that reason. Hooks can also be declared with no menu label, which makes them callable from tests but invisible in the menu — useful for state-priming actions a human wouldn’t click.
The contract
Each cn1lib ships a properties file at a well-known classpath location. The simulator scans every jar on its classpath for this resource and merges the results, so multiple cn1libs coexist cleanly:
# META-INF/codenameone/simulator-hooks.properties
name=Bluetooth
namespace=bluetooth # optional; defaults to slugified `name`
# Each itemN is the action; the matching labelN is the menu text.
# Items are positional — the loader reads item1, item2, item3, ... and
# stops at the first missing index. Don't skip numbers.
item1=com.example.bt.simulator.Hooks#toggleAdapter
label1=Toggle adapter on/off
item2=com.example.bt.simulator.Hooks#addDemoPeripheral
label2=Add demo peripheral
# Label omitted → API-only hook. Callable from tests, invisible in menu.
item3=com.example.bt.simulator.Hooks#primeReadFailureRequired keys:
nameMenu title shown in the simulator’s menu bar. One menu per properties file.
itemNA
fully.qualified.ClassName#staticMethodNamereference for the Nth menu item. The method must bepublic static voidand take no arguments. Items are numbered from 1 upward; the loader stops at the first missingitemN, so don’t leave gaps.
Optional keys:
namespaceIdentifier used for the
CN.executelookup (for example,bluetoothfor a URL likebluetooth:item1). Defaults to lowercased, ASCII-slugifiedname(Push Notifications!→push-notifications). Set this explicitly when you want a different identifier from the display name.labelNDisplay text for the matching
itemN. Omit entirely to make the hook API-only — registered withCN.executebut hidden from the menu.
No groups, no submenus, no priority — flat by design. If you need ordering relative to another cn1lib, you can’t have it: discovery order wins, and that’s intentional so the contract stays small and the future simulator UX can re-render this metadata however it likes.
The action method
The simulator dispatches every action on the Codename One EDT through Display.callSerially, so your method can call Display.getInstance(), Form.show(), Dialog.show(), ToastBar.showInfoMessage() and any other CN1 API. Reflection uses the same classloader that loaded Display, so cn1lib internals (including package-private classes) resolve normally:
The Display.isInitialized() guard is a useful pattern when the same static methods are also called from JUnit tests that don’t run inside a live CN1 simulator — the state mutation runs in both contexts, only the UI feedback is skipped.
Worked example using cn1-bluetooth
The cn1-bluetooth cn1lib ships a JavaSE port with two backends: a scriptable in-memory simulator and a real-hardware backend that talks to a native helper (CoreBluetooth on macOS, BlueZ on Linux, WinRT on Windows). Both are useful in different stages of development, and the menu lets the user choose between them and exercise the simulator without writing any test scaffolding.
Its simulator-hooks.properties looks like this:
name=Bluetooth
namespace=bluetooth
item1=com.codename1.bluetoothle.BluetoothSimulatorHooks#toggleAdapter
label1=Toggle adapter on/off
item2=com.codename1.bluetoothle.BluetoothSimulatorHooks#addDemoPeripheral
label2=Add demo peripheral
item3=com.codename1.bluetoothle.BluetoothSimulatorHooks#switchToNativeBle
label3=Switch backend → native BLE (real hardware)
# API-only: used by the test suite but never displayed in the menu
item4=com.codename1.bluetoothle.BluetoothSimulatorHooks#primeReadFailureWhen the user runs an app that depends on cn1-bluetooth, the simulator’s menu bar gets a Bluetooth menu with the three labeled items. Clicking Add demo peripheral drops a peripheral into the in-memory simulator that the running app can then scan for, connect to, and exchange data with — without any real hardware. item4 is callable from tests via CN.execute("bluetooth:item4") but never shows up in the menu.
Calling hooks from CN1 unit tests
CN1 unit tests (AbstractTest subclasses run via mvn cn1:test) compile under the same restrictions as the rest of the app — no reflection, no JavaSE-only imports. Drive a hook the same way you’d execute any URL — CN.execute recognizes registered hook urls and dispatches them on the EDT:
public class BluetoothDemoTest extends AbstractTest {
@Override
public boolean runTest() throws Exception {
// Skip cleanly off-simulator: a real device has no hook registered
// and CN.canExecute will not return TRUE.
if (!Boolean.TRUE.equals(CN.canExecute("bluetooth:item2"))) {
return true;
}
// Seed the simulator — same effect as clicking "Add demo peripheral".
CN.execute("bluetooth:item2");
// nullnow drive the public Bluetooth API as usual.
return true;
}
}A common pattern: ship label-bearing hooks for actions a developer might want to fire manually (toggle adapter, inject notification), and ship label-less hooks for test-only state setup (primeReadFailure, seedFixture) that would just clutter the menu.
What’s intentionally not exposed
Swing types.
JMenu,JMenuItem,KeyStrokeand friends don’t appear in the contract. The simulator UX may change shape (toolbar, command palette, sidebar) and cn1libs shouldn’t have to follow.Submenus, separators, priority. The metadata is a flat list with no hierarchy. If you want grouping, ship multiple
simulator-hooks.propertiesfiles in separate jars — each becomes its own menu.Long-running work on the EDT. Hook methods run on the CN1 EDT; if you need to do I/O, fire-and-forget a
new Thread(…)from the method or useCN.invokeAndBlockso you don’t block the UI.
1.5.3. Distributing your library
The recommended way to distribute your library is on Maven central. That way users will be able to install your library by copying and pasting a familiar <dependency> snippet into their pom.xml file.
2. Introduction
Codename One is a Write Once Run Anywhere mobile development platform for Java/Kotlin developers. It fits into modern Maven-capable IDEs such as IntelliJ IDEA, NetBeans, VS Code, and Eclipse, and you can also drive it entirely from the command line.
Codename One’s mission statement is:
Unify the complex and fragmented task of mobile device programming into a single set of tools, APIs and services. As a result create a more manageable approach to mobile application development without sacrificing the power/control given to developers.
This brings that old "Write Once Run Anywhere" (WORA) Java mantra to mobile devices without dumbing it down to the lowest common denominator.
The things that make Codename One stand out from other tools in this field are:
Write Once Run Anywhere support with no special hardware requirements and 100% code reuse
Compiles Java/Kotlin into native code for iOS, Android and even JavaScript/PWA
Open Source and Free with commercial backing/support
Easy to use with 100% portable Drag GUI builder
Full access to underlying native OS capabilities using the native OS programming language (for example: Objective-C) without compromising portability
Provides full control over every pixel on the screen
Lets you use native widgets (views) and mix them with Codename One components within the same hierarchy (heavyweight/lightweight mixing)
Supports seamless Continuous Integration out of the box
Codename One can trace its roots to the open source LWUIT project started at Sun Microsystem in 2007 by Chen Fishbein (co-founder of Codename One). It has been under constant development for over a decade.
2.1. Build cloud
The build cloud approach to mobile development is one of the things that makes Codename One stand out. iOS native development requires a Mac with Xcode. Windows native development requires a Windows machine. To make matters worse, Apple, Google, and Microsoft change their tools.
That makes it hard to keep up.
When you develop an app in Codename One, use the built-in simulator for running and debugging. When you want to build a native app, use the build cloud, where Macs build the native iOS apps and Windows machines build the native Windows apps. This works seamlessly and makes Codename One apps native because the native platform compiles them. For example, iOS builds use Macs running Xcode, the native Apple tool, to build the app.
| Codename One doesn’t send source code to the build cloud, compiled bytecode! |
2.1.1. Why build servers
The build servers can build native iOS apps without a Mac and native Windows apps without a Windows machine. They remove the need to install and update complex toolchains and simplify the process of building a native app to a right click.
Even though the build servers streamline delivery, Codename One also supports fully local builds. You can install the toolchain on your own hardware and follow the workflows in Chapter 1, Maven Project Workflow and Chapter 89, Working with Codename One sources to compile, package, and test apps without leaving your desktop environment.
For example, because native iOS applications require a Mac with a recent version of Xcode, Codename One maintains such machines in the cloud. When developers send an iOS build, that Mac generates C source code using ParparVM, then compiles the C source code using Xcode and signs the resulting binary using Xcode. You can install the binary on your device or build a distribution binary for the App Store. Since C code is generated, your app is also future-proof against changes from Apple. You can also inject Objective-C native code into the app while keeping it 100% portable thanks to Codename One’s native interfaces capability.
Subscribers can receive the C source code back using the include-sources feature of Codename One and use those sources for benchmarking and debugging on devices.
The same is true for most other platforms. On Android and Java SE, Codename One runs the standard Java code, unchanged.
2.1.2. How does Codename One work
Codename One uses a SaaS-based approach so the information in this appendix might (and probably will) change in the future to accommodate improved architectures. This appendix includes this information for reference, you don’t need to understand this to follow the content of the book…
Since Android is already based on Java, Codename One is already native to Android and works with the Android VM (ART/Dalvik).
On iOS, Codename One built and open-sourced ParparVM, which is a conservative VM. ParparVM features a concurrent, non-blocking GC and is written entirely in Java/C. ParparVM is a transpiler that generates C source code matching the given Java bytecode. This means that an Xcode project is generated and compiled on the build servers. It’s as if you hand-coded a native app and is thus future-proof against changes that Apple introduces. For example, Apple migrated to 64-bit and later introduced bitcode support to iOS. ParparVM needed no modifications to meet those changes.
| Codename One translates the bytecode to C, which is faster than Swift/Objective-C. The port code that invokes iOS APIs is hand coded in Objective-C |
Codename One earlier offered a UWP (Universal Windows Platform) target based on iKVM. That target was discontinued in release 7.0.229 and is preserved as historical context in older documentation and blog posts.
JavaScript build targets use TeaVM to do the translation statically. TeaVM supports threading using JavaScript by breaking the app down in a rather elaborate way. To support the complex UI Codename One uses the HTML5 Canvas API which allows absolute flexibility for building applications.
For desktop builds Codename One uses javapackager, since both Macs and Windows machines are available in the cloud, the platform-specific nature of javapackager isn’t a problem.
Lightweight architecture
What makes Codename One stand out is the approach it takes to UI: “lightweight architecture.”
Lightweight architecture is the “not so secrete sauce” to Codename One’s portability. Essentially it means all the components/widgets in Codename One are written in Java. Thus their behavior is consistent across all platforms and they’re fully customizable from the developer code as they don’t rely on OS internal semantics. This allows developers to preview the application accurately in the simulators and GUI builders.
One of the big accomplishments in Codename One is its unique ability to embed “heavyweight” widgets into place among the “lightweights.” This is crucial for apps such as Uber where the cars and widgets on top are implemented as Codename One components yet below them, you have the native map component.
Codename One achieves fast performance by drawing using the native gaming APIs of most platforms for example: OpenGL ES on iOS. The core technologies behind Codename One are all open source including most of the stuff developed by Codename One itself, for example: ParparVM but also the full library, platform ports, designer tool, device skins etc.
Why ParparVM
On iOS, Codename One uses ParparVM which translates Java bytecode to C code and boasts a non-blocking GC as well as 64 bit/bitcode support. This VM is fully open source in the Codename One git repository. In the past Codename One used XMLVM to generate native code similarly, but the XMLVM solution was too generic for the needs of Codename One. ParparVM boasts a unique architecture of translating code to C (similarly to XMLVM), because of that Codename One is the only solution of its kind that can guarantee future iOS compatibility since the officially supported iOS toolchain is always used instead of undocumented behaviors.
| XMLVM could guarantee that as well, but it’s no longer maintained and lacked the API layer support |
The key advantages of ParparVM over other approaches are:
Truly Native: since code is translated to C rather than directly to ARM or LLVM code, the app is "more native." It uses the official tools and approaches from Apple and can gain from their advancements. For example: bitcode changes or profiling toolchain.
Smaller Class Library: ParparVM includes a small segment of the full JavaAPI’s resulting in final binaries that are smaller than the alternatives by orders of size. This maps directly to performance and memory overhead.
Simple and Extensible: to work with ParparVM you need a basic understanding of C. Unlike other tools that require deep understanding of ARM assembly and LLVM bitcode. This is crucial for the fast-moving world of mobile development, as Apple changes things left and right, you need a more agile VM.
Historical windows ports
Codename One experimented with many Windows ports over the years, including the legacy Windows Phone target and a later UWP (Universal Windows Platform) target based on iKVM.
| The UWP target was discontinued in release 7.0.229 and is no longer part of the supported build targets. Older references to it in historical material are retained for archival context. |
JavaScript port
The JavaScript port of Codename One uses ParparVM to translate Java bytecode into JavaScript. Cloud builds retain the original TeaVM-based builder as a compatibility fallback, selected with the public javascript.port=teavm build hint.
The JavaScript port allows unmodified Codename One applications to run within a desktop or mobile browser. The port itself is based on the HTML5 Canvas API, which provides a pixel-perfect implementation of the Codename One API.
| The JavaScript port is available to all Codename One users. |
Desktop and Android
The other ports of Codename One use the VMs available on the host machines and environments to execute the runtime. Historically, Retrolambda was used to provide Java 8 language features portably.
The Android port uses the native Android tools, including the Gradle build environment, in the latest versions.
The desktop port creates a standard Java SE application, which is packaged with the JRE and an installer.
| The Desktop port is available to pro grade subscribers of Codename One |
2.2. History

Codename One was started by Chen Fishbein and Shai Almog who authored the Open Source LWUIT project at Sun Microsystems (circa 2007). The LWUIT project aimed to solve the fragmentation within J2ME/Blackberry devices by creating a higher standard of user interface than the common baseline at the time. LWUIT received critical acclaim and traction within many industries but was limited by the declining feature phone market. It was forked by many companies including Nokia. It was used as the base standard for DTV in Brazil. Another fork has brought a LWUIT into high-end cars from Toyota and other companies. This fork later adapted Codename One as well.
In 2012 Shai and Chen formed Codename One as they left Oracle. The project has taken many of the basic concepts developed within the LWUIT project and adapted them to the smartphone world which is still experiencing similar issues to the device fragmentation of the old J2ME phones.
2.3. Core concepts of mobile programming
Before you proceed, this section explains some universal core concepts of mobile programming that might not be intuitive. These are universal concepts that apply to mobile programming regardless of the tools you’re using.
You can skip this section if you feel you’re familiar enough with the core problems/issues in mobile app development.
2.3.1. Density
Density is also known as DPI (Dots Per Inch) or PPI (pixels or points per inch). Density is confusing, unintuitive and might collide with common sense. For example, an iPhone 7 plus has a resolution of 1080x1920 pixels and a PPI of 401 for a 5-inch screen. But, an iPad 4 has 1536x2048 pixels with a PPI of 264 on a 9.7 inch screen… Smaller devices can have higher resolutions!
As the following figure shows, if a Pixel 2 XL had pixels the size of an iPad, it would have been twice the size of that iPad. While in reality, it’s half the height of the iPad!

Differences in density can be extreme. A second generation iPad has 132 PPI, where modern phones have PPI that’s over 600 dpi.
Low resolution images on high PPI devices will look either small or pixelated. High resolution images on low PPI devices will look huge, overscaled (artifacts) and will consume too much memory.

The exact same image will look different on each device, sometimes to a comical effect. One of the solutions for this problem is multi-images. All OS’s support the ability to define different images for various densities. Chapter 2 discusses multi-images later in detail.
This also highlights the need for working with measurements other than pixels. Codename One supports millimeters (or dips) as a unit of measurement. This is highly convenient and is a better representation of size when dealing with mobile devices.
However, there is a bigger conceptual issue involved. You need to build a UI that adapts to the wide differences in form factors. You might have fewer pixels on an iPad, but because of its physical size, you would expect the app to cram more information into that space so the app won’t feel like a blown-up phone application. Many strategies to address that, but one of the first steps is in the layout managers.
Chapter 2 discusses the layout managers in depth, but the core concept is that they decide where a UI element is placed based on generic logic. That way, the user interface can adapt automatically to the huge variance in display size and density.
2.3.2. Touch interface
The fact that mobile devices use a touch interface today isn’t news… However, the implications of that aren’t obvious to some developers.
UI elements need to be finger sized and spaced. Otherwise, you risk the “fat finger” effect. That means spacing should be in millimeters and not in pixels due to device density.
Scrolling poses another challenge in touch-based interfaces. In desktop applications, it’s common to nest scrollable items. For example, in touch interfaces, the scrolling gesture doesn’t allow such a nuance. Furthermore, scrolling on both the horizontal and vertical axis (side scrolling) can be inconvenient in touch-based interfaces.
2.3.3. Device fragmentation
Some developers single out this wide range of resolutions and densities as “device fragmentation.” While it does contribute to development complexity, it isn’t a challenging problem to overcome.
Densities aren’t the cause of device fragmentation. Device fragmentation is caused by many OS versions with different behaviors. This is clear on Android and relates to the slow rollout of Android vendor versions compared to Google rollout. For example, 7 months after the Android 8 (Oreo) release in 2018, it was still available on 1.1% of the devices. The damning statistic is that 12% of the devices in mid 2018 run Android 4.4 Kitkat released in 2013!
This makes QA difficult as the disparity between these versions is pretty big. These numbers will be out of date by the time you read this, but the core problem remains. It’s hard to get all device manufacturers aligned, so this problem will probably remain in the foreseeable future despite everything.
2.3.4. Performance
Besides the obvious need for performance and smooth animation within a mobile app, there are a couple of performance related issues that might not be intuitive to new developers: size and power.
App size
Apps are installed and managed through stores. This poses some restrictions about what an app can do. However, it also creates a huge opportunity. Stores manage automatic update and to some degree the marketing/monetization of the app.
A good mobile app is updated once a month and sometimes even once a week. Since the app downloads automatically from the store, this can be a huge benefit:
Existing users are reminded of the app and get new features instantly
New users notice the app featured on a “what’s new” list
If an app is big, it might not update over a cellular network connection. Google and Apple have restrictions on automatic updates over cellular networks to preserve battery life and data plans. A large app might negatively impact users perception of the app and trigger uninstalls for example, when a phone is low on available space.
Power drain
Desktop developers think about power usage within their apps. In mobile development, this is a crucial concept. Modern device OSes have tools that highlight misbehaving applications, and this can lead to bad reviews.
Code that loops forever while waiting for input will block the CPU from sleeping and drain the battery.
Worse. Mobile OSes kill applications that drain the battery. If the app is draining the battery and is minimized, (for example, during an incoming call) the app could be killed. This will impact app performance and usability.
2.3.5. Sandbox and permissions
Apps installed on the device are "sandboxed" to a specific area so they won’t harm the device or its functionality. The filesystem of mobile applications is restricted so one application can’t access the files of another application. Things that most developers take for granted on the desktop such as a "file picker" or accessing the image folder don’t work on devices!
This means that when your application works on a file, it belongs to your application. To share the file with a different application, you need to ask the operating system to do that for you.
Furthermore, some features require a "permission" prompt and sometimes require special flags in system files. Apps need to request permission to use sensitive capabilities, for example, Camera, Contacts etc.
Historically, Android developers declared required permissions for an app and the user was prompted with permissions during installation. Android 6 adopted the approach used by iOS of prompting the user for permission when accessing a feature.
This means that in runtime a user might revoke a permission. A good example for an Uber app is the location permission. If a user revokes that permission, the app might lose its location.
2.4. Installing Codename One
| Codename One supports JDK 11 through 25 for running the simulator and the desktop ("Run as desktop app") target. Eclipse Temurin (https://adoptium.net) is the easiest way to install a supported JDK. |
Codename One projects are built with Maven. Typical Maven targets such as package, clean and install work out of the box, but the Codename One integrations that ship with each IDE provide dedicated Run and Build actions for a smoother workflow.
To create a new Codename One project visit https://www.codenameone.com/initializr/ and generate a starter project, or run the Codename One Application Project Archetype (cn1app-archetype) directly on the command line:
mvn archetype:generate \
-DarchetypeGroupId=com.codenameone \
-DarchetypeArtifactId=cn1app-archetype \
-DarchetypeVersion=LATEST \
-DgroupId=YOUR_GROUP_ID \
-DartifactId=YOUR_ARTIFACT_ID \
-Dversion=1.0-SNAPSHOT \
-DmainName=YOUR_MAIN_NAME \
-DinteractiveMode=falseThis command generates a project in the current directory. The folder name matches the artifactId value. For example, specifying -DartifactId=myapp produces a project inside a new myapp directory.
Import the generated Maven project into your preferred IDE and use the Codename One Run in Simulator task from the IDE toolbar or Run/Debug buttons:
IntelliJ IDEA: use File > Open on the project directory, then choose the Codename One Run in Simulator action from the toolbar or standard Run/Debug controls.
NetBeans: use File > Open Project, select the generated Maven project, and rely on the Codename One toolbar actions to run and debug the simulator.
VS Code: install the Java and Codename One extensions, open the folder, and trigger the Run in Simulator task from the command palette or the Run/Debug buttons.
Eclipse: use File > Import > Existing Maven Projects, then use the Codename One launch shortcuts provided by the plugin for simulator and build tasks.
Command line: invoke Maven goals directly whenever you need to integrate with CI/CD pipelines or scripting.
For deeper coverage of the Maven goals, project structure, and automation tasks, continue with Chapter 1, Maven Project Workflow.
| Arbitrary Maven dependencies probably won’t work for Codename One. Many dependencies assume a full JDK which Codename One can’t provide and they often assume functionality that might not be available for example: reflection, Spring, etc. |
2.4.1. Important notes for new projects
Before you get to the code there are few important things you need to understand about Codename One applications.
App Name - This is the name of the app and the main class, it’s important to get this right as it’s hard to change this value later
Package Name - it’s crucial you get this value right. Besides the difficulty of changing this after the fact, once an app is submitted to iTunes/Google Play with a specific package name this can’t be changed! See the sidebar
Picking a Package Name.Theme - Codename One ships with various built-in themes; for simplicity recommend
Nativeas it’s a minimal starting point
2.4.2. Runtime
Once Maven is set up you can run the HelloWorld application by selecting the Codename One Run in Simulator task from the IDE run menu. The Codename One simulator launches and you can use its menus to control and inspect details related to the device. You can rotate it, determine its location in the world, monitor networking calls etc.
With the Skins menu you can download device skins to see how your app will look on different devices.
Some skins are bigger than the screen size, uncheck the Scrollable flag in the Simulator menu to handle them more effectively |
Use your IDEs Debug button with the Run in Simulator task to launch the simulator under the debugger.
2.4.3. The source code of the hello world app
After clicking finish in the new project wizard you have a HelloWorld project with a few default settings. The following sections break the class down to small pieces and explain each piece starting with the enclosing class:
public class HelloWorld { (1)
private Form current; (2)
private Resources theme; (3)
// null class methods null
}| 1 | This is the main class, it’s the entry point to the app, notice it doesn’t have a main method but rather callback which this guide covers soon |
| 2 | Forms are the “top level” UI element in Codename One. Only one Form is shown at a time and everything you see on the screen is a child of that Form |
| 3 | Every app has a theme, it determines how everything within the application looks for example: colors, fonts etc. |
Next consider the first lifecycle method init(Object). The Application Lifecycle Sidebar discusses the lifecycle in depth:
init(Object) works as a constructor to some degree. Recommend avoiding the constructor for the main class and placing logic in the init method instead. This isn’t crucial but recommend it since the constructor might happen too early in the application lifecycle.
In a cold start init(Object) is invoked followed by the start() method. For example, start() can be invoked more than once if an app is minimized and restored, see the sidebar Application Lifecycle:

Some complex ideas appear within this short snippet that this chapter addresses later when talking about layout. The gist of it’s that you create and show a Form. Form is the top level UI element, it takes over the whole screen. You can add UI elements to that Form object, in this case the Label. You use the BoxLayout to arrange the elements within the Form from top to the bottom vertically.
Now that you have a general sense of the lifecycle lets look at the last two lifecycle methods:
That’s it. You should now have a general sense of the code. It’s time to run on the device.
2.4.4. Building and deploying on devices

Use the standalone Codename One Settings editor to configure the application title, version, package, icon, build hints, and extensions. Launch it from the Maven project root:
mvn cn1:settingsUse the standalone Certificate Wizard for signing assets. Monitor Codename One Cloud builds and subscription information on the Codename One website.
Signing/Certificates
All the modern mobile platforms require signed applications but they all take radically different approaches when implementing it.
Signing is a process that marks your final application for the device with a special value. This value (signature) is a value that you can generate based on the content of the application and your certificate. Effectively it guarantees the app came from you. This blocks a 3rd party from signing their apps and posing as you to the App Store or to the user. It’s a crucial security layer.
A certificate is the tool you use for signing. Think of it as a mathematical rubber stamp that generates a different value each time. Unlike a rubber stamp a signature can’t be forged!
Signing on Android
Backup your Android certificate and save its password! If you lose your Android certificate you won’t be able to update your app |
Android uses a self-signed certificate approach. You can generate a certificate by describing who you’re and picking a password!
Anyone can do that. For example, once a certificate is published it can’t be replaced…
If this wasn’t the case someone else could push an “upgrade” to your app. Once an app is submitted with a certificate to Google Play this app can’t be updated with any other certificate.
With that in mind generating an Android certificate is trivial.
| The following chart illustrates a process that’s identical on all IDEs |

Your certificate will generate into the file Make sure to back that up and the password as losing these can have dire consequencesKeychain.ks in your home directory |
Signing and provisioning iOS
Code signing for iOS relies on Apple as the certificate authority. This is something that doesn’t exist on Android. iOS also requires provisioning as part of the certificate process and separates the process for development/release.
First, the good news:
Losing an iOS certificate is no big deal - in fact you revoke them often with no impact on shipping apps
Codename One has a wizard that hides most of the pain related to iOS signing
In iOS Apple issues the certificates for your applications. That way the certificate is trusted by Apple and is assigned to your Apple iOS developer account. One important caveat applies: You need an iOS Developer Account and Apple charges a 99USD Annual fee for that.
| The 99USD price and need have been around since the introduction of the iOS developer program for 10 years at the time of this writing. It might change at some point though |
Apple also requires a “provisioning profile” which is a special file bound to your certificate and app. This file describes some details about the app to the iOS installation process. One of the details it includes during development is the list of permitted devices.

You need 4 files for signing. Two certificates and two provisioning profiles:
Production: The production certificate/provisioning pair is used for builds that are uploaded to iTunes
Development: The development certificate/provisioning is used to install on your development devices
The standalone Certificate Wizard can automatically create these files and configure the current Maven project.
Run the wizard from the project directory:
mvn cn1:certificatewizardAfter storing an App Store Connect API key, click Auto Setup in the toolbar. The wizard reads the project package and display name, creates or reuses the Bundle ID with push enabled, creates/reuses development and App Store signing assets, and writes the debug/release signing settings back into codenameone_settings.properties.
If you have more than one project you should use the same iOS P12 certificate files in all the projects and regenerate the provisioning. In this situation the Certificate Wizard asks you if you want to revoke the existing certificate which you shouldn’t revoke in such a case. You can update the provisioning profile in Apple’s iOS developer website. |
One important aspect of provisioning on iOS is the device list in the provisioning step. Apple allows you to install the app on 100 devices during development. This blocks developers from skipping the App Store altogether. It’s important you list the correct UDID for the device in the list otherwise install will fail.
| Many apps and tools offer the UDID of the device, but they aren’t necessarily reliable and might give a fake number! |

| You can right-click the UDID and select copy to copy it |
The simplest and most reliable process for getting a UDID is through iTunes. Other approaches have worked in the past but this approach is guaranteed.
| Ad hoc provisioning allows 1000 beta testers for your application but it’s a more complex process that you won’t discuss here although it’s supported by Codename One |
Build and install
Before you continue with the build you should sign up at https://www.codenameone.com/build-server.html where you can soon follow the progress of your builds. You need a Codename One account to build for the device.
Now that you have certificates, the process of device builds is a right click away for both OSes. You can right-click the project and select Codename One → Send iOS Debug Build or Codename One → Send Android Build.

| The first time you send a build you will be prompted for the email and password you provided when signing up for Codename One |
Once you send a build you should see the results in the build server page:

| On iOS make sure you use Safari when installing, as 3rd party browsers might have issues |
Once you go through those steps you should have the HelloWorld app running on your device. This process is non-trivial when starting so if you run into difficulties don’t despair and seek help at the discussion forum (https://www.codenameone.com/discussion-forum.html) or stack overflow (https://stackoverflow/tags/codenameone/). Once you go through signing and installation, it becomes easier.
| You can also install the application either by emailing the installation link to your account (using the e-mail Link button) |
You can also download the binaries to upload them to the appstores.
2.5. Kotlin
Codename One started before Kotlin became public. Kotlin has since shown itself as an interesting option for developers within the Android community. With that in mind, Codename One added support for Kotlin.
To use Kotlin with Codename One you can create a kotlin directory next to the java directory under the common/src/main directory. Kotlin code that resides there can work as usual and interact with the Java code.
Please notice the following:
Don’t use the project conversion tools or accept the warning that the project isn’t a Kotlin project. You do your own build process
Warnings and errors aren’t listed and builds that claim to have errors might pass
2.5.1. Hello Kotlin
Due to the way Kotlin works you can create a regular Java project and convert sources to Kotlin. You can mix Java and Kotlin code without a problem and Codename One would "work."
The hello world Java source file looks like this (removed some comments and whitespace):
When you select that file and select the menu option Code → Convert Java file to Kotlin File you should get a familiar structure. The problem is that there are two bugs in the automatic conversion… That’s the code for Kotlin behaves differently from standard Java.
The first problem is that Kotlin classes are final unless declared otherwise so you need to add the open keyword before the class declaration.
This is essential as the build server will fail with weird errors related to instanceof.
This applies to the main class of the project, other classes in Codename One can remain final |
The second problem is that arguments are non-null by default. The init method might have a null argument. This fails with an exception. The solution is to add a question mark to the end of the call: fun init(context: Any?).
Once all that’s in place Kotlin should work. This should be possible for more JVM languages in the future.
3. Basics: Themes, styles, components, and layouts
Start with a brief overview of the core ideas in Codename One. This chapter revisits them in more detail as it goes on.
3.1. Components
Every button, label, or other element on the screen in a Codename One application is a Component. This is a simplified version of the class hierarchy:

The Form is a special Component. It’s the root component shown to the user. Container is a Component type that can hold other components. That lets you create elaborate hierarchies by nesting Container instances.

A Codename One application is effectively a series of forms, but one Form can be visible at a time. The form contains everything on the screen. Under the hood, the Form has a few separate parts:

Content Pane - this is the body of the
Form. When you add aComponentto theForm, it goes into the content pane. The content pane scrolls vertically by default.Title Area - you can’t add directly to this area. The title area is managed by the
Toolbarclass.Toolbarsits at the top of the form and handles the title design. The title area has two parts:Title of the
Formand its commands (the buttons on the right and left of the title)Status Bar - on iOS, the top area leaves room for the notch, battery, clock, and similar indicators. Without that space, those elements would overlap the title.
Now that the structure is clear, open the Java file TodoApp.java in the project you created. You should see the lines that set up the UI in the start() method:
3.1.1. Layout managers
A layout manager decides the size and location of components within a Container. Every Container has a layout manager. The default layout manager is FlowLayout.
To understand layouts, first understand a basic concept about Component: each component has a “preferred size.” That’s the size a component wants to occupy. For example, a Label uses the exact size needed to fit the label text, icon, and padding.
A layout manager places a component based on its own logic and the preferred size, sometimes called the “natural size.” A FlowLayout walks the components in the order they were added and sizes them one after another. When it reaches the end of the row, it moves to the next row.
Use FlowLayout for simple thingsFlowLayout is great for simple cases, but it has issues when components change size dynamically, such as a text field. In those cases, it can choose bad line breaks and take up too much space. |


Scrolling doesn’t work well for all layout types because the positioning algorithm within a layout can break. Scrolling on the Y axis works well for BoxLayout Y, which is why it was picked for the TodoForm:
| Layout | Scrollable |
|---|---|
Flow Layout | Possible on Y axis only |
Border Layout | Scrolling is blocked |
Box Layout Y | Scrollable only on the Y axis |
Box Layout X | Scrollable only on the X axis |
Grid Layout | Scrollable |
LayeredLayout | Not scrollable (usually) |
Layouts can be divided into two distinct groups:
Constraint Based -
BorderLayout(and a few others such asGridBagLayout,MigLayout, andTableLayout)Regular - All the other layout managers
When you add a Component to a Container with a regular layout you do so with a simple add method:
Container cnt = new Container(BoxLayout.y());
cnt.add(new Label("Just Added"));This works great for regular layouts but might not for constraint based layouts. A constraint based layout accepts another argument. For example: BorderLayout needs a location for the Component:
This line assumes you have an import static com.codename1.ui.CN.*; in the top of the file. In BorderLayout (which is a constraint based layout) placing an item in the NORTH places it in the top of the Container.
The CN class is a class that contains many static helper methods and functions. It’s specifically designed for static import in this way to help keep your code terse |
Terse syntax
Almost every layout allows you to add a component using many variants of the add method:
Container cnt = new Container(BoxLayout.y());
cnt.add(new Label("Just Added")); (1)
cnt.addAll(new Label("Adding Multiple"), (2)
new Label("Second One"));
cnt.add(new Label("Chaining")). (3)
add(new Label("Value"));| 1 | Regular add |
| 2 | addAll accepts many components and adds them in a batch |
| 3 | add returns the parent Container instance so you can chain calls like that |
In the race to make code “tighter” you can make this even shorter. Most layout managers have their own custom terse syntax style for example:
To sum this up, you can use layout managers and nesting to create elaborate UI’s that implicitly adapt to different screen sizes and device orientation.
Flow Layout

Flow layout lets the components "flow" horizontally and break a line when reaching the edge of the container. It’s the default layout manager for containers. Because it’s so flexible it’s also problematic as it can result in wrong preferred size values for the parent Container. This can create a reflow issue, as a result recommend using flow layout for trivial cases. Avoid it for things such as text input etc. As the size of the text input can vary in runtime:
Form hi = new Form("Flow Layout", new FlowLayout());
hi.add(new Label("First")).
add(new Label("Second")).
add(new Label("Third")).
add(new Label("Fourth")).
add(new Label("Fifth"));
hi.show();Flow layout also supports terse syntax shorthand such as:
Container flowLayout = FlowLayout.encloseIn(
new Label("First"),
new Label("Second"),
new Label("Third"),
new Label("Fourth"),
new Label("Fifth"));Flow layout can be aligned to the left (the default), to the center, or to the right. It can also be vertically aligned to the top (the default), middle (center), or bottom.



Components within the flow layout get their natural preferred size by default and aren’t stretched in any axis.
The natural sizing behavior is often used to prevent other layout managers from stretching components. For example: if you have a border layout element in the south and you want it to keep its natural size instead of adding the element to the south directly you can wrap it using parent.add(BorderLayout.SOUTH, FlowLayout.encloseCenter(dontGrowThisComponent)). |
Box Layout
BoxLayout places elements in a row (X_AXIS) or column (Y_AXIS) according to box orientation. Box is a simple and predictable layout that serves as the "workhorse" of component lists in Codename One.
You can create a box layout Y using something like this:
Form hi = new Form("Box Y Layout", new BoxLayout(BoxLayout.Y_AXIS));
hi.add(new Label("First")).
add(new Label("Second")).
add(new Label("Third")).
add(new Label("Fourth")).
add(new Label("Fifth"));Which results in this

Box layout also supports a shorter terse notation which you use here to show the X axis box:
Container box = BoxLayout.encloseX(new Label("First"),
new Label("Second"),
new Label("Third"),
new Label("Fourth"),
new Label("Fifth"));
The box layout keeps the preferred size of its destination orientation and scales elements on the other axis. Specifically X_AXIS will keep the preferred width of the component while growing all the components vertically to match in size. Its Y_AXIS counterpart keeps the preferred height
while growing the components horizontally.
This behavior is useful since it allows elements to align as they would all have the same size.
Sometimes the growing behavior in the X axis is undesired, for these cases you can use the X_AXIS_NO_GROW variant.

FlowLayout vs. BoxLayout.X_AXISBoxLayout over FlowLayout as it acts more consistently in all situations. Another advantage of BoxLayout is the fact that it grows and thus aligns the components in a consistent column or row |
Border Layout

Border layout is unique. BorderLayout is a constraint-based layout that can place up to five components in one of the five positions: NORTH, SOUTH,
EAST, WEST or CENTER:
Form hi = new Form("Border Layout", new BorderLayout());
hi.add(BorderLayout.CENTER, new Label("Center")).
add(BorderLayout.SOUTH, new Label("South")).
add(BorderLayout.NORTH, new Label("North")).
add(BorderLayout.EAST, new Label("East")).
add(BorderLayout.WEST, new Label("West"));
hi.show();The Constraints are Included in the You can use the static import of the CN classCN class and then the syntax can be add(SOUTH, new Label("South")) |
The layout always stretches the NORTH/SOUTH components on the X-axis to fill the container and the EAST/WEST components on the Y-axis. The center component is stretched to fill the remaining area by default. For example, the setCenterBehavior allows you to manipulate the behavior of the center component so it’s placed in the center without stretching.
For example:
Form hi = new Form("Border Layout", new BorderLayout());
((BorderLayout)hi.getLayout()).setCenterBehavior(BorderLayout.CENTER_BEHAVIOR_CENTER);
hi.add(BorderLayout.CENTER, new Label("Center")).
add(BorderLayout.SOUTH, new Label("South")).
add(BorderLayout.NORTH, new Label("North")).
add(BorderLayout.EAST, new Label("East")).
add(BorderLayout.WEST, new Label("West"));
hi.show();Results in:

Scrolling is Disabled in Border Layout Because of its scaling behavior scrolling a border
layout makes no sense. Container implicitly blocks scrolling on a border layout, but it can scroll its parents/children |
For RTL the EAST and WEST values are implicitly reversed as shown in this image:

Preferred Size Still Matters The preferred size of the center component doesn’t matter in border layout but the preferred size of the sides is. For example: If you place a large component in the SOUTH it will take up the entire screen and won’t leave room for anything |
Grid Layout
GridLayout accepts a predefined grid (rows/columns) and grants all components within it equal size based on the dimensions of the largest components.
| The main use case for this layout is a grid of icons for example: like one would see in the iPhone home screen |
If the number of rows * columns is smaller than the number of components added a new row is implicitly added to the grid.
For example, if the number of components is smaller than available cells (won’t fill the last row) blank spaces will
be left in place.
In this example you can see that a 2×2 grid is used to add 5 elements, this results in an additional row that’s implicitly added turning the grid to a 3×2 grid implicitly and leaving one blank cell:
Form hi = new Form("Grid Layout 2×2", new GridLayout(2, 2));
hi.add(new Label("First")).
add(new Label("Second")).
add(new Label("Third")).
add(new Label("Fourth")).
add(new Label("Fifth"));
When you use a 2×4 size ratio you would see elements getting cropped as you do here. The grid layout uses the grid size first and doesn’t pay too much attention to the preferred size of the components it holds.

Grid also has an autoFit attribute that can be used to automatically calculate the column count based on available space and preferred width. This is useful for working with UI’s where the device orientation might change.
A terse syntax for working with a grid also exists in two versions, one that uses the "auto-fit" option and another that accepts the number of columns. Here’s a sample of the terse syntax coupled with auto-fit followed by screenshots of the same code in two orientations:
GridLayout.encloseIn(new Label("First"),
new Label("Second"),
new Label("Third"),
new Label("Fourth"),
new Label("Fifth"));

3.1.2. Table Layout
The TableLayout is an elaborate constraint based layout manager that can arrange elements in rows/columns while defining constraints to control complex behavior such as spanning, alignment/weight etc.
Note the Different Package for The TableLayoutTableLayout is in the com.codename1.ui.table package and not in the layouts package.This is because TableLayout was originally designed for the Table class. |
Despite being constraint based the TableLayout isn’t strict about constraints and will implicitly add a constraint when one is missing. This is unlike the BorderLayout which will throw an exception in this case.
Unlike GridLayout TableLayout won’t implicitly add a row if the row/column count is wrong |
Form hi = new Form("TableLayout", new TableLayout(2, 2));
hi.add(new Label("First"));
hi.add(new Label("Second"));
hi.add(new Label("Third"));
hi.add(new Label("Fourth"));
hi.add(new Label("Fifth"));
hi.show();
TableLayout supports the ability to grow the last column which can be enabled using the setGrowHorizontally method. You can also use a shortened terse syntax to construct a TableLayout but since the TableLayout is a constraint based layout you won’t be able to use its full power with this syntax.
The default usage of the encloseIn method below uses the setGrowHorizontally flag:
Container table = TableLayout.encloseIn(2,
new Label("First"),
new Label("Second"),
new Label("Third"),
new Label("Fourth"),
new Label("Fifth"));
Form hi = new Form("TableLayout Enclose 2", new BorderLayout());
hi.add(BorderLayout.CENTER, table);
hi.show();
TableLayout.encloseIn() with default behavior of growing the last columnThe full potential
TableLayout is a beast, to truly appreciate it you need to use the constraint syntax which allows you to span, align and set width/height for the rows and columns.
TableLayout works with a Constraint instance that can communicate your intentions into the layout manager. Such constraints can include more than one attribute for example: span and height.
TableLayout constraints can’t be reused for more than one component |
The constraint class supports the following attributes
| The column for the table cell. This defaults to -1 which will place the component in the next available cell |
| Like column, defaults to -1 as well |
| The column width in percentages, -1 will use the preferred size. -2 for width will take up the rest of the available space |
| Like width but doesn’t support the -2 value |
| The cells that should be occupied horizontally defaults to 1 and can’t exceed the column count - current offset. |
| Like spanHorizontal with the same limitations |
| The horizontal alignment of the content within the cell, defaults to the special case -1 value to take up all the cell space can be either |
| Like horizontalAlign can be one of |
You need to set width/height to one cell in a column/row |
The table layout constraint sample tries to show some unique things you can do with constraints.
The constraint sample below spans the title across all three columns and spans the notes row across two columns:
TableLayout layout = new TableLayout(4, 3);
layout.setGrowHorizontally(true);
Form hi = new Form("Table Layout", layout);
TableLayout.Constraint title = layout.createConstraint();
title.setHorizontalSpan(3);
title.setHorizontalAlign(Component.CENTER);
hi.add(title, new Label("Invoice"));
hi.add(new Label("Item"));
hi.add(new Label("Qty"));
hi.add(new Label("Total"));
hi.add(new Label("Design"));
hi.add(new Label("2"));
hi.add(new Label("$120"));
TableLayout.Constraint notes = layout.createConstraint();
notes.setHorizontalSpan(2);
notes.setHeightPercentage(40);
hi.add(notes, new SpanLabel("Notes span two columns"));
hi.add(new Button("Pay"));
hi.show();
TextMode Layout
TextModeLayout is a unique layout manager. It acts like TableLayout on Android and like BoxLayout.Y_AXIS in other platforms. Internally it delegates to one of these two layout managers so in a sense it doesn’t have as much functionality of its own.
For example: this is a sample usage of TextModeLayout:
TextModeLayout tl = new TextModeLayout(3, 2);
Form f = new Form("Pixel Perfect", tl);
TextComponent title = new TextComponent().label("Title");
TextComponent price = new TextComponent().label("Price");
TextComponent location = new TextComponent().label("Location");
TextComponent description = new TextComponent().label("Description").multiline(true);
f.add(tl.createConstraint().horizontalSpan(2), title);
f.add(tl.createConstraint().widthPercentage(30), price);
f.add(tl.createConstraint().widthPercentage(70), location);
f.add(tl.createConstraint().horizontalSpan(2), description);
f.setEditOnShow(title.getField());
f.show();As you can see from the code and samples above there is a lot going on under the hood. On Android you want a layout that’s like TableLayout so you can “pack” the entries. On iOS you want a box layout Y kind of layout but you also want the labels/text to align…
The TextModeLayout isn’t a layout as much as it’s a delegate. When running in the Android mode (which you refer to as the “on top” mode) the layout is almost an exact synonym of TableLayout and in fact delegates to an underlying TableLayout. In fact there is a public final table instance within the layout that you can refer to directly…
One small difference exists between the TextModeLayout and the underlying TableLayout: your choice to default to align entries to TOP with this mode.
Aligning to TOP is important for error handling for TextComponent in Android otherwise the entries “jump” |
When working in the non-android environment you use a BoxLayout on the Y axis as the delegate. One thing you do here differs from a default box layout: grouping. Grouping allows the labels to align by setting them to the same width, internally it invokes Component.setSameWidth(). Since text components hide the labels there is a special group method there that can be used. For example, this is implicit with the TextModeLayout which is pretty cool.
TextModeLayout was created specifically for the TextComponent and InputComponent so check out the section about them in the components chapter.
3.1.3. Layered Layout
When used without constraints, the LayeredLayout places the components in order one on top of the other and sizes them all to the size of the largest component. This is useful when trying to create an overlay on top of an existing component. For example: an "x" button to allow removing the component.

The code to generate this UI is slightly complex and contains few relevant pieces. The truly relevant piece is this block:
hi.add(LayeredLayout.encloseIn(settingsLabel,
FlowLayout.encloseRight(close)));You’re doing three distinct things here:
You’re adding a layered layout to the form
You’re creating a layered layout and placing two components within. This would be the equivalent of creating a
LayeredLayoutContainerand invokingaddtwiceYou use
FlowLayoutto position theXclose button in the right position
| When used without constraints, the layered layout sizes all components to the exact same size one on top of the other. It requires that you use another container within; to position the components correctly |
This is the full source of the example for completeness:
Form hi = new Form("Layered Layout");
int w = Math.min(Display.getInstance().getDisplayWidth(), Display.getInstance().getDisplayHeight());
Button settingsLabel = new Button("");
Style settingsStyle = settingsLabel.getAllStyles();
settingsStyle.setFgColor(0xff);
settingsStyle.setBorder(null);
settingsStyle.setBgColor(0xff00);
settingsStyle.setBgTransparency(255);
settingsStyle.setFont(settingsLabel.getUnselectedStyle().getFont().derive(w / 3, Font.STYLE_PLAIN));
FontImage.setMaterialIcon(settingsLabel, FontImage.MATERIAL_SETTINGS);
Button close = new Button("");
close.setUIID("Container");
close.getAllStyles().setFgColor(0xff0000);
FontImage.setMaterialIcon(close, FontImage.MATERIAL_CLOSE);
hi.add(LayeredLayout.encloseIn(settingsLabel,
FlowLayout.encloseRight(close)));Forms have a built in layered layout that you can access through getLayeredPane(), this allows you to overlay elements on top of the content pane.
The layered pane is used internally by components such as InteractionDialog, AutoComplete etc.
| Codename One also includes a GlassPane that resides on top of the layered pane. Its useful if you want to "draw" on top of elements but is harder to use than layered pane |
Insets and reference components
LayeredLayout supports insets for its children. This effectively allows you to position child components precisely where you want them, relative to their container or siblings. This functionality forms the under-pinnings of the GUI Builder’s Auto layout mode.
As an example, suppose you wanted to position a button in the lower right corner of its container. This can be achieved with LayeredLayout as follows:
Container cnt = new Container(new LayeredLayout());
Button btn = new Button("Submit");
LayeredLayout ll = (LayeredLayout)cnt.getLayout();
cnt.add(btn);
ll.setInsets(btn, "auto 0 0 auto");The result is:

The thing new here is this line:
ll.setInsets(btn, "auto 0 0 auto");This is called after btn has already been added to the container. It says that you want its insets to be "auto" on the top and left, and 0 on the right and bottom. This insets string follows the CSS notation of top right bottom left (that’s: start on top and go clockwise), and the values of each inset may be provided in pixels (px), millimetres (mm), percent (%), or the special "auto" value. Like CSS, you can also specify the insets using a 1, 2, or 3 values. For example:
"1mm"- Sets 1mm insets on all sides."1mm 2mm"- Sets 1mm insets on top and bottom; 2mm on left and right."1mm 10% 2mm"- Sets 1mm on top, 10% on left and right, and 2mm on bottom."1mm 2mm 1px 50%"- Sets 1mm on top, 2mm on right, 1px on bottom, and 50% on left.
auto insets
The special "auto" inset indicates that it’s a flexible inset. If all insets are set to "auto," then the component will be centered both horizontally and vertically inside its "bounding box."
| The "inset bounding box" is the containing box from which a component’s insets are measured. If the component’s insets aren’t linked to any other components, then its inset bounding box will be the inner bounds (that’s: taking padding into account) of the component’s parent container. |
If one inset is fixed (that’s: defined in px, mm, or %), and the opposite inset is "auto," then the "auto" inset will allow the component to be its preferred size. If you want to position a component to be centered vertically, and 5mm from the left edge, you could do:
ll.setInsets(btn, "auto auto auto 5mm");Resulting in:

Move it to the right edge with:
ll.setInsets(btn, "auto 5mm auto auto");% insets
Percent (%) insets are calculated about the inset bounding box. A 50% inset is measured as 50% of the length of the bounding box on the inset’s axis. For example: A 50% inset on top would be 50% of the height of the inset bounding box. A 50% inset on the right would be 50% of the width of the inset bounding box.
Insets, margin, and padding
A component’s position in a layered layout is determined as follows: (Assume that cmp is the component that you’re positioning, and cnt is the container (In pseudo-code):
x = cnt.paddingLeft + cmp.calculatedInsetLeft + cmp.marginLeft
y = cnt.paddingTop + cmp.calculatedInsetTop + cmp.marginTop
w = cnt.width - cnt.verticalScroll.width - cnt.paddingRight - cmp.calculatedInsetRight - cmp.marginRight - x
h = cnt.height - cnt.horizontalScroll.height - cnt.paddingBottom - cmp.calculatedInsetBottom - cmp.marginBottom - yThe calculatedInsetXXX values here will be the same as the corresponding provided inset if the inset has no reference component. If it does have a reference component, then the calculated inset will depend on the position of the reference component. |
If no inset is specified, then it’s assumed to be 0. This ensures compatibility with designs that were created before layered layout supported insets.
Component references: Linking components together
If all you need to do is position a component relative to its parent container’s bounds, then mere insets provide you with enough vocabulary to achieve this. But most UIs are more complex than this and require another concept: reference components. Often you will want to position a component relative to another child of the same container. This is also supported.
For example, suppose you want to place a text field in the center of the form (both horizontally and vertically), and have a button placed beside it to the right. Positioning the text field is trivial (setInset(textField, "auto")), but there is no inset that you can provide that would position the button to the right of the text field. To do your goal, you need to set the text field as a reference component of the button’s left inset, which "links" the button’s left inset to the text field. Here is the syntax:
Container cnt = new Container(new LayeredLayout());
LayeredLayout ll = (LayeredLayout)cnt.getLayout();
Button btn = new Button("Submit");
TextField tf = new TextField();
cnt.add(tf).add(btn);
ll.setInsets(tf, "auto")
.setInsets(btn, "auto auto auto 0")
.setReferenceComponentLeft(btn, tf, 1f);This would result in:

The two active lines here are the last two:
ll.setInsets(tf, "auto")
.setInsets(btn, "auto auto auto 0")
.setReferenceComponentLeft(btn, tf, 1f);| The reference position is defined as the distance, expressed as a fraction of the reference component’s length on the inset’s axis, between the reference component’s leading (outer) edge and the point from which the inset is measured. A reference position of 0 means that the inset is measured from the leading edge of the reference component. A value of 1.0 means that the inset is measured from the trailing edge of the reference component. A value of 0.5 means that the inset is measured from the center of the reference component. Etc. Any floating point value can be used, though the most common values are 0 and 1. |
The definition above may make reference components and reference position seem more complex than they are. Some examples:
For a top inset:
referencePosition == 0 ⇒ the inset is measured from the top edge of the reference component.
referencePosition == 1 ⇒ the inset is measured from the bottom edge of the reference component.
For a bottom inset:
referencePosition == 0 ⇒ the inset is measured from the bottom edge of the reference component.
referencePosition == 1 ⇒ the inset is measured from the top edge of the reference component.
For a left inset:
referencePosition == 0 ⇒ the inset is measured from the left edge of the reference component.
referencePosition == 1 ⇒ the inset is measured from the right edge of the reference component.
For a right inset:
referencePosition == 0 ⇒ the inset is measured from the right edge of the reference component.
referencePosition == 1 ⇒ the inset is measured from the left edge of the reference component.

3.1.4. GridBag Layout
GridBagLayout was introduced to simplify the process of porting existing Swing/AWT code with a more familiar API. The API for this layout is problematic as it was designed for AWT/Swing where styles were unavailable. As a result it has its own insets API instead of using elements such as padding/margin.
Your recommendation is to use Table which is as powerful but has better Codename One integration.
To show GridBagLayout you ported http://docs.oracle.com/Java SE/tutorial/uiswing/layout/gridbag.html[the sample from the Java tutorial] to Codename One:
private static Button gridButton(String text) {
Button button = new Button(text);
button.setCapsText(false);
Style style = button.getAllStyles();
style.setBgColor(0xf4f8ff);
style.setBgTransparency(255);
style.setFgColor(0x0d47a1);
style.setBorder(Border.createLineBorder(1, 0x2b5c9e));
style.setPaddingUnit(Style.UNIT_TYPE_DIPS);
style.setPadding(2, 2, 2, 2);
return button;
}
public static Form createForm() {
Form hi = new Form("GridBagLayout", new BorderLayout());
Container grid = new Container(new GridBagLayout());
Style gridStyle = grid.getAllStyles();
gridStyle.setPaddingUnit(Style.UNIT_TYPE_DIPS);
gridStyle.setPadding(4, 4, 4, 4);
Button button;
GridBagConstraints c = new GridBagConstraints();
//natural height, maximum width
c.fill = GridBagConstraints.HORIZONTAL;
button = gridButton("One");
c.weightx = 0.5;
c.fill = GridBagConstraints.HORIZONTAL;
c.gridx = 0;
c.gridy = 0;
grid.addComponent(c, button);
button = gridButton("Two");
c.fill = GridBagConstraints.HORIZONTAL;
c.weightx = 0.5;
c.gridx = 1;
c.gridy = 0;
grid.addComponent(c, button);
button = gridButton("Three");
c.fill = GridBagConstraints.HORIZONTAL;
c.weightx = 0.5;
c.gridx = 2;
c.gridy = 0;
grid.addComponent(c, button);
button = gridButton("Long-Named Button 4");
c.fill = GridBagConstraints.HORIZONTAL;
c.ipady = 40; //make this component tall
c.weightx = 0.0;
c.gridwidth = 3;
c.gridx = 0;
c.gridy = 1;
grid.addComponent(c, button);
button = gridButton("5");
c.fill = GridBagConstraints.HORIZONTAL;
c.ipady = 0; //reset to default
c.weighty = 1.0; //request any extra vertical space
c.anchor = GridBagConstraints.PAGE_END; //bottom of space
c.insets = new Insets(10,0,0,0); //top padding
c.gridx = 1; //aligned with button 2
c.gridwidth = 2; //2 columns wide
c.gridy = 2; //third row
grid.addComponent(c, button);
hi.add(BorderLayout.NORTH, grid);
return hi;
}Notice that because of the way gridbag works you didn’t provide any terse syntax API for it although it should be possible.

3.1.5. Group Layout
GroupLayout is a layout that would be familiar to the users of the NetBeans GUI builder (Matisse). Its a layout manager that’s hard to use for manual coding but is powerful for some elaborate use cases. Although MiGLayout and LayeredLayout might be superior options.
It was originally added during the LWUIT days as part of an internal try to port Matisse to LWUIT. It’s still useful to this day as developers copy and paste Matisse code into Codename One and produce elaborate layouts with drag.
Since the layout is based on an older version of GroupLayout some things need to be adapted in the code or you should use the special "compatibility" library for Matisse to get better interaction. You also recommend tweaking Matisse to use import statements instead of full package names, that way if you use Label changing the awt import to a Codename One import will make it use work for Codename One’s Label.
Unlike any other layout manager GroupLayout adds the components into the container instead of the standard API. This works for GUI builder code but as you can see from this sample it doesn’t make the code readable:
public static Form createForm() {
Form hi = new Form("GroupLayout");
Label label1 = new Label();
Label label2 = new Label();
Label label3 = new Label();
Label label4 = new Label();
Label label5 = new Label();
Label label6 = new Label();
Label label7 = new Label();
label1.setText("label1");
label2.setText("label2");
label3.setText("label3");
label4.setText("label4");
label5.setText("label5");
label6.setText("label6");
label7.setText("label7");
GroupLayout layout = new GroupLayout(hi.getContentPane());
hi.setLayout(layout);
layout.setHorizontalGroup(
layout.createParallelGroup(GroupLayout.LEADING)
.add(layout.createSequentialGroup()
.addContainerGap()
.add(layout.createParallelGroup(GroupLayout.LEADING)
.add(layout.createSequentialGroup()
.add(label1, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.addPreferredGap(LayoutStyle.RELATED)
.add(layout.createParallelGroup(GroupLayout.LEADING)
.add(label4, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.add(label3, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.add(label2, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)))
.add(label5, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.add(layout.createSequentialGroup()
.add(label6, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.addPreferredGap(LayoutStyle.RELATED)
.add(label7, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)))
.addContainerGap(296, Short.MAX_VALUE))
);
layout.setVerticalGroup(
layout.createParallelGroup(GroupLayout.LEADING)
.add(layout.createSequentialGroup()
.addContainerGap()
.add(layout.createParallelGroup(GroupLayout.TRAILING)
.add(label2, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.add(label1, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE))
.addPreferredGap(LayoutStyle.RELATED)
.add(label3, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.addPreferredGap(LayoutStyle.RELATED)
.add(label4, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.addPreferredGap(LayoutStyle.RELATED)
.add(label5, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.addPreferredGap(LayoutStyle.RELATED)
.add(layout.createParallelGroup(GroupLayout.LEADING)
.add(label6, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE)
.add(label7, GroupLayout.PREFERRED_SIZE, GroupLayout.DEFAULT_SIZE, GroupLayout.PREFERRED_SIZE))
.addContainerGap(150, Short.MAX_VALUE))
);
return hi;
}
If you’re porting newer Matisse code there are simple changes you can do:
Change
addComponenttoaddChange
addGrouptoaddRemove references to
ComponentPlacementand referenceLayoutStyledirectly
3.1.6. Mig Layout
MigLayout is a popular cross-platform layout manager that was ported to Codename One from Swing.
| MiG is still considered experimental so proceed with caution! The API was deprecated to serve as a warning of its experimental status. |
The best reference for MiG would probably be its quick start guide (PDF link). As a reference you ported one of the samples from that PDF to Codename One:
public static Form createForm() {
Form hi = new Form("MigLayout",
new MigLayout("wrap 2, insets 4mm", "[right]3mm[32mm]", "[]12[]12[]12[]"));
hi.add(new Label("First name"));
hi.add("growx, w 32mm", new TextField("", "First name"));
hi.add(new Label("Last name"));
hi.add("growx, w 32mm", new TextField("", "Last name"));
hi.add(new Label("Phone"));
hi.add("growx, w 32mm", new TextField("", "Phone"));
Button ok = new Button("OK");
ok.setCapsText(false);
Style okStyle = ok.getAllStyles();
okStyle.setBgColor(0xf4f8ff);
okStyle.setBgTransparency(255);
okStyle.setFgColor(0x0d47a1);
okStyle.setBorder(Border.createLineBorder(1, 0x2b5c9e));
okStyle.setPaddingUnit(Style.UNIT_TYPE_DIPS);
okStyle.setPadding(2, 2, 2, 2);
hi.add("span 2, growx", FlowLayout.encloseCenter(ok));
return hi;
}
It should be reasonably easy to port MiG code but you should notice the following:
MiG handles a lot of the spacing/padding/margin issues that are missing in Swing/AWT. With Codename One styles you have the padding and margin which are probably a better way to do a lot of the things that MiG does
The
addmethod in Codename One can be changed as shown in the sample above.The constraint argument for Codename One
addcalls appears before theComponentinstance.
3.2. Themes and styles
Next you need to introduce you to 3 important terms in Codename One: Theme, Style, and UIID.
Themes are similar conceptually to CSS, in fact they can be created with CSS syntax as this guide covers soon. The various Codename One ports ship with a native theme representing the appearance of the native OS UI elements. Every Codename One application has its own theme that derives the native theme and overrides behavior within it.
If the native theme has a button defined, you can override properties of that button in your theme. This allows you to customize the look while retaining some native appearances. This works by merging the themes to one big theme where your application theme overrides the definitions of the native theme. This is pretty like the cascading aspect of CSS if you’re familiar with that.
Themes consist of a set of UIID definitions. Every component in Codename One has a UIID associated with it. UIID stands for User Interface Identifier. This UIID connects the theme to a specific component. A UIID maps to CSS classes if you’re familiar with that concept. For example, Codename One doesn’t support the complex CSS selector syntax options as those can impact runtime performance.
For example: see this code where:
This is a text field component (user input field) but it will look like a Label.
Effectively you told the text field that it should use the UIID of Label when it’s drawing itself. It’s common to do tricks like that in Codename One. For example: button.setUIID("Label") would make a button appear like a label and allow you to track clicks on a Label.
The UIID’s translate the theme elements into a set of Style objects. These Style objects get their initial values from the theme but can be further manipulated after the fact. To make the text field’s foreground color red you could use this code:
The color is in hexadecimal RRGGBB format so 0xff00 would be green and 0xff0000 would be red.
getAllStyles() returns a Style object but why do you need “all” styles?
Each component can have one of 4 states and each state has a Style object. This means you can have 4 style objects per Component:
Unselected: used when a component isn’t touched and doesn’t have focus. You can get that object with
getUnselectedStyle().Selected: used when a component is touched or if focus is drawn for non-touch devices. You can get that object with
getSelectedStyle().Pressed: used when a component is pressed. Notice it’s applicable to buttons and button subclasses. You can get that object with
getPressedStyle().Disabled: used when a component is disabled. You can get that object with
getDisabledStyle().
The getAllStyles() method returns a special case Style object that lets you set the values of all 4 styles from one class so the code before would be equivalent to invoking all 4 setFgColor methods. For example, getAllStyles() works for setting properties not for getting them!
don’t use getStyle() for manipulationgetStyle() returns the current Style object which means it will behave inconsistently. The paint method uses getStyle() as it draws the current state of the Component but other code should avoid that method. Use the specific methods instead: getUnselectedStyle(), getSelectedStyle(), getPressedStyle(), getDisabledStyle() and getAllStyles() |
As you can see, it’s a bit of a hassle to change styles from code which is why the theme is so appealing.
3.2.1. Theme
A theme allows you to define the styles externally through a set of UIID’s (User Interface ID’s). Themes can be authored directly in CSS and then compiled into the Codename One resource file, which keeps styling concerns separate from application logic.
The theme is stored in the theme.res file in the project.
You load the theme file using this line of code in the init(Object) method in the main class of the application:
theme = UIManager.initFirstTheme("/theme");In a CSS project this file is generated automatically from the stylesheet. Legacy applications that still edit the resource file by hand can continue to do so, but new projects should prefer the CSS workflow described below.
This code is shorthand for resource file loading and for the installation of theme. You could technically have more than one theme in a resource file at which point you could use initNamedTheme() instead. The resource file is a special file format that includes inside it many features:
Themes
Images
Localization Bundles
Data files
3.2.2. Working with CSS themes
Modern Codename One projects ship with a src/main/css/theme.css file (or an equivalent stylesheet). Editing this file allows you to define UIIDs using standard CSS syntax together with Codename One–specific extensions such as cn1-derive for inheritance and the #Constants block for theme constants. Each time you build or run the project, the build tool compiles the CSS into the theme.res resource file automatically. Saving the CSS while the simulator is running will also trigger a refresh so you can iterate on styling.
Because the CSS compiler produces the final resource file, you should treat the generated theme.res as an output artifact and keep your changes in the CSS source. Images referenced from CSS rules (for example: background images or multi-images) should be placed alongside the stylesheet so that they’re picked up by the compiler. More details about the supported selectors and properties are covered in the dedicated CSS chapter later in this guide.
3.3. GUI builder
The GUI builder arranges components visually: you drag them onto a canvas, position them, and edit their properties in an inspector, without writing the layout code by hand. It’s a desktop application that the Codename One Maven plugin launches, so it works the same way whichever IDE you use for the surrounding Java code. Forms designed in the builder use auto layout mode by default, which positions and resizes components on the canvas using LayeredLayout behind the scenes.
3.3.1. Hello world
Two goals do the work:
cn1:create-gui-formgenerates a new GUI form: the.guiXML file plus the matching Java source.cn1:guibuilderopens the GUI builder on the project.
Both goals accept a className parameter that points at the fully qualified class name of the form. From the root of a multi-module Codename One project, create a new form like this:
mvn cn1:create-gui-form -DclassName=com.example.MyFormThis generates two files inside the common module:
common/src/main/guibuilder/com/example/MyForm.guicommon/src/main/java/com/example/MyForm.java
If you run the goal from inside the common submodule the files are written directly under that module’s src/main/… directory. By default the goal creates a Form; pass -DguiType=Dialog or -DguiType=Container to generate one of the other types, and pass -DautoLayout=false to opt out of auto layout mode. |
To open the form in the GUI builder:
mvn cn1:guibuilder -DclassName=com.example.MyFormProjects generated from the archetype also carry a ready-made shortcut for this: a CN1 GUI Builder run configuration in IntelliJ IDEA, an Open in GUI Builder action in NetBeans, a GUI Builder launch configuration in Eclipse, and a Tools > GUI Builder entry in the Visual Studio Code Maven favorites. They all run the same goal.
The full goal reference, including every parameter, lives in Section B.7, “Create GUI Form (create-gui-form)” and Section B.15, “GUIBuilder goal (guibuilder)” in the Maven goals appendix.
| The GUI builder is a Java 8 artifact, so it runs on whichever JDK already builds your project. |
3.3.2. The workspace

cn1:create-gui-formThe window has three columns:
Project forms and palette — on the left. The upper half lists every
.guifile in the project under the Forms tab, and the component tree of the form you are editing under the Hierarchy tab. Picking a component from the tree is often easier than hitting it on the canvas, particularly when it’s behind something else. The lower half is the component palette, with a search field for finding a component by name.Design canvas — in the middle. This is a live Codename One rendering of your form, styled by the project’s own
theme.css, so what you see is what the application draws. The buttons above the canvas switch it between phone portrait, phone landscape, tablet, and a full-width desktop canvas.Inspector — on the right. It shows the selected component under three tabs: Properties, Layout, and Events.
The toolbar carries Save, Undo, Redo and Refresh on the left, and CSS and Code on the right. Changes are written to the .gui file when you press Save.
The two dividers between the columns can be dragged, so you can give the canvas more room while positioning components and give the inspector more room while filling in properties.
3.3.3. Designing a form
Drag a component from the palette onto the canvas to add it. As you drag, the builder highlights where the component would land: the container that would receive it, and, in auto layout mode, guides showing the edges it would line up with. Dropping outside a valid target leaves the form unchanged.
Select a component by clicking it on the canvas or by picking it in the Hierarchy tab. A selected component shows resize handles; drag its body to move it, or a handle to resize it. Hold Shift while clicking to select several components at once, which is what the alignment actions in the top-left corner of the canvas operate on: they align edges, centers or baselines, match widths or heights, or disconnect a component from the relationships it has picked up.
Double-click a component that displays text — or long-press it — to edit that text in place, without going to the inspector.
The Properties tab holds what the component is: its name, its text, the UIID that connects it to a CSS selector, and the settings that belong to its type, such as the input constraint of a text field or the range of a slider. The Layout tab holds where it sits: its position in its parent, the layout manager of a container, and, for auto layout, its alignment reference and its horizontal and vertical size policies. The Events tab binds an event, such as a button press, to a method in the companion Java source.
3.3.4. Auto layout mode
New forms use auto layout mode. In this mode you place components where you want them rather than accepting the positions a layout manager dictates.
All forms designed in auto layout mode use Auto layout mode is built on the inset support in LayeredLayoutLayeredLayout. Component positioning uses insets and reference components, not absolute coordinates. |
An inset can be fixed (stated in millimetres, pixels or a percentage) or flexible, and it can be measured from the parent or from a sibling component. That’s what makes a form designed on one canvas size still work on another: a component pinned to the bottom of the form stays there on a taller screen, and a component pinned below its neighbor follows that neighbor when it moves.
The builder chooses insets for you as you drag, and it prefers a relationship with a nearby component over a distance from the edge of the form. The Layout tab shows the choice it made and lets you change it:
Alignment reference — the component this one is positioned against, or the nearest component if you haven’t chosen one.
Horizontal size policy and Vertical size policy — whether the component keeps its preferred size, keeps a fixed size, fills its parent, or matches the size of its reference component.
Resize the canvas with the device buttons above it after every few changes. A form that looks right on one canvas can fall apart on another, and switching between phone portrait and desktop is the quickest way to find out before a device does.
3.3.5. Nested containers and other layouts
A form doesn’t have to be one flat surface. Drag a Container from the palette to group components together, then use the Container layout picker in the Layout tab to give it whichever layout manager suits that part of the form: box, border, flow, grid, table, or layered again. Components dragged into that container are then arranged by it, and the drop guides change to match — a box layout shows where in the sequence the component would go, a border layout shows which region would receive it, and a table layout shows the cell.
Containers can be nested as far as you need, and a component can be dragged out of one container and into another; the builder rewrites its constraints for the layout it lands in.
3.3.6. The theme and the companion source
The CSS button opens the project stylesheet inside the builder.

The stylesheet is compiled and applied to the canvas as you edit it, so a color or a font change is visible immediately on the form you are designing. This is the same src/main/css/theme.css the application builds with, described in Working with CSS themes.
The Code button opens the companion Java source.

Everything between the // <gui-builder-generated> and // </gui-builder-generated> markers is written by the builder from the .gui file and is replaced whenever the form is saved. The region between the // <gui-builder-user-code> markers is yours: event handlers and anything else you add there is preserved across saves. The editor makes the distinction visible, and the status line reminds you which region takes your changes.
Forms scaffolded by older versions of cn1:create-gui-form used a different marker style. Opening such a form in the builder converts the file to the format above and keeps the methods you had written.
3.3.7. What’s stored on disk
A form is two files that belong together:
common/src/main/guibuilder/<package>/<Name>.gui— the XML description of the component tree. This is the file the builder reads and writes, and the one to keep under version control.common/src/main/java/<package>/<Name>.java— the companion Java source.
| The two files are connected by name. If you rename or move one, rename or move the other to match, or the builder can no longer pair them. |
The .gui file is plain XML and readable enough to review in a diff:
<?xml version="1.0" encoding="UTF-8"?>
<component type="Form" name="SignInForm" title="Sign in" layout="LayeredLayout" autoLayout="true">
<component type="Label" name="heading" text="Welcome back" layeredInsets="12% auto auto 8%" />
<component type="TextField" name="email" hint="Email" layeredInsets="26% 8% auto 8%"
guidedReferences="heading|-|-|-" />
<component type="Button" name="signIn" text="Sign in" actionEvent="onSignIn"
layeredInsets="62% 8% auto 8%" guidedReferences="email|-|-|-" />
</component>You can edit it by hand, but reopen the form afterward: the builder doesn’t watch the file while it’s running.
4. Advanced theming
Before getting into CSS, this section introduces a few advanced theme concepts. Those ideas also apply to CSS because CSS uses features such as theme constants.
4.1. Working with UIIDs
A UIID (User Interface Identifier) uniquely identifies a group of theme definitions for UI components. For example, a Button UIID can be linked to a component, and the theme can then define that component’s appearance.
A major advantage of UIIDs is the ability to change a component’s UIID. For example, to create a multiline label, use code like this:
TextArea t = new TextArea(); // ...
t.setUIID("Label");
t.setEditable(false);| Components such as SpanLabel use this approach internally. |
UIIDs can be customized in the GUI builder and support per-component styling.
| The component class name often matches the UIID, but the two remain separate entities. |
4.2. Theme layering
Theme layering helps in two common cases:
A platform needs a slightly different theme.
A specific use case needs theme customization. For example, a user might select larger fonts.
Theme layering is straightforward and doesn’t require rebuilding the entire theme. A theme can be applied on top of another theme, like CSS cascading. To create a layer, add a new theme with the Add Theme button.
Remove the includeNativeBool constant from the new theme. |
In the new theme, define the changes you need. For example, to use a larger default font, define that property for the relevant UIIDs and leave the other properties unchanged.
In a non-GUI-builder app, the theme loading code looks like this by default:
Resources theme = UIManager.initFirstTheme("/theme");Update it to look like this:
Resources theme = UIManager.initNamedTheme("/theme", "Theme");This example assumes that the main theme is named Theme, not the layer theme that was added. |
The original code relies on the theme being at position 0 in the theme name array. That might not always be true.
To add the theme layer, use:
UIManager.getInstance().addThemeProps(theme.getTheme("NameOfLayerTheme"));The addThemeProps call places the secondary theme on top of the primary "Theme" and keeps the original UIIDs in "Theme" intact.
To apply theme changes to a running application, call Form’s `refreshTheme(). This updates the UI and provides visual feedback for the theme changes.
4.3. Override resources in platform
When you adapt an application to different OS conventions, one common need is to use different icons. Sometimes you also need to change behavior based on device type, for example to use a different UI structure for a tablet.
Codename One lets you override a resource for a specific platform. You can redefine a resource for that platform and add platform-specific resources.

Overridden resources take precedence over embedded resources, which lets you change the look or even behavior for a specific platform or OS.
| Overriding the theme is dangerous because a theme has external dependencies, such as image borders. The solution is to use theme layering and override the layer. |
To override a resource, select the platform where the override applies.

You can then click the green checkbox to mark that resource as specific to this platform. All resources added while that platform is selected apply to that platform. If you change your mind, delete the override in override mode and it will stop applying.
4.4. Theme constants
The Codename One Designer has a tab for creating constants. These constants can add global values and behavior hints to Codename One and its components. Constants are always strings. Some conventions let the UI adapt to input types. For example, a constant that ends with Bool is treated as a boolean value and displays as a checkbox. An Int suffix displays a numeric picker, and an Image suffix shows a combo box for picking an image.
| The combo box in the designer for adding a theme constant is editable, so you can type any value you want. |
To use a constant, call the appropriate UIManager methods:
getThemeConstantisThemeConstantgetThemeImageConstant
Internally, Codename One has many built-in constants, and the list keeps growing. As features are added, the list is updated, but theme constants are inherently ad hoc and some may not appear here.
| Constant | Description/Argument |
|---|---|
alwaysTensileBool | Enables tensile drag even when there is no scrolling in the container (only for scrollable containers) |
backGestureThresholdInt | The threshold for the back gesture in the SwipeBackSupport class, defaults to 5 |
backUsesTitleBool | Indicates to the GUI builder that the back command should use the title of the previous form and not just the word "Back" |
buttonRippleBool |
|
capsButtonTextBool |
|
capsButtonUiids | A list of the UIID’s that should be capitalized by default (in supported platforms) other than the |
defaultCommandImage | Image to give a command with no icon |
dialogButtonCommandsBool | Place commands in the dialogs as buttons |
dialogBlurRadiusInt | Sets the default Gaussian blur radius for the background of the dialogs. The default value is -1 indicating no blur |
dialogPosition | Place the dialog in an arbitrary border layout position (for example, North, South, Center, etc.) |
centeredPopupBool | Popup of the combo box will appear in the center of the screen |
changeTabOnFocusBool | Useful for feature phones, allows changing the tab when the focus changes, without pressing a key |
checkBoxCheckDisImage | CheckBox image to use instead of Codename One drawing it on its own |
checkBoxCheckedImage | CheckBox image to use instead of Codename One drawing it on its own |
checkBoxOppositeSideBool | Indicates the check box should be drawn on the opposite side to the text and not next to the text |
checkBoxUncheckDisImage | CheckBox image to use instead of Codename One drawing it on its own |
checkBoxUncheckedImage | CheckBox image to use instead of Codename One drawing it on its own |
comboImage | Combo image to use instead of Codename One drawing it on its own |
commandBehavior | Deprecated: don’t use this constant as it conflicts with the |
ComponentGroupBool | Enables component group, which allows components to be logically grouped together, so the UIID’s of components would be modified based on their group placement. This allows for some unique styling effects where the first/last elements have different styles from the rest of the elements. It’s disabled by default, thus leaving its usage up to the designer |
dialogTransitionIn | Default transition for dialog |
dialogTransitionInImage | Default transition Image for dialog, causes a Timeline transition effect |
dialogTransitionOut | Default transition for dialog |
defaultCommandImage | An image to place on a command if none is defined, only applies to touch commands |
defaultEmblemImage | The emblem painted on the side of the multibutton, by default this is an arrow on some platforms |
emblemUiid | Overrides the UIID applied to emblem labels rendered by composite buttons such as |
iconUiid | Allows theming the icon component used by |
iosScrollMotionBool | Enables iOS-style scroll physics (nonlinear rubber-band during drag and critically damped tensile snap-back). When unset it defaults to |
imageviewerNavigationArrowsBool | Enables side navigation arrows by default for |
imageviewerThumbnailBarHeightMM | Sets the default thumbnail strip height (in millimeters) for |
imageviewerThumbnailsBool | Enables the bottom thumbnail strip by default for |
textUiid | Overrides the text component UIID for |
useLargerTextScaleBool | When |
dialogTransitionOutImage | Default transition Image for dialog, causes a Timeline transition effect |
DecayMotionScaleFactorInt | Velocity-to-distance multiplier for the exponential-decay scroll motion (see Section 4.4.1, “Scroll motion tuning”). Default is |
disabledColor | Color to use when disabling entries by default |
dlgButtonCommandUIID | The UIID used for dialog button commands |
dlgCommandButtonSizeInt | Minimum size to give to command buttons in the dialog |
dlgCommandGridBool | Places the dialog commands in a grid for uniform sizes |
dlgInvisibleButtons | Includes an RRGGBB color for the line separating dialog buttons, as is the case with Android 4 and iOS 7 buttons in dialogs |
dlgSlideDirection | Slide hints |
dlgSlideInDirBool | Slide hints |
dlgSlideOutDirBool | Slide hints |
drawMapPointerBool | Indicates whether a pointer should appear in the center of the map component |
fadeScrollBarBool | Boolean indicating if the scrollbar should fade when there is inactivity |
setFadeScrollBarSpeed(int) (API) | Sets the per-frame opacity decrement for scrollbar fading (not milliseconds). Approximate fade duration is |
fadeScrollEdgeBool | Places a fade effect at the edges of the screen to show that it’s possible to scroll until you reach the edge (common on Android) |
fadeScrollEdgeInt | Amount of pixels to fade out at the edge |
firstCharRTLBool | Indicates to the GenericListCellRenderer that it should determine RTL status based on the first character in the sentence |
noTextModeBool | Indicates that the on/off switch in iOS shouldn’t draw text on top of the switch, which is the case for iOS 7+ but not for prior versions |
fixedSelectionInt | Number corresponding to the fixed selection constants in List |
formTransitionIn | Default transition for form |
formTransitionInImage | Default transition Image for form, causes a Timeline transition effect |
formTransitionOut | Default transition for form |
formTransitionOutImage | Default transition Image for form, causes a Timeline transition effect |
globalToobarBool | Indicates that the Toolbar API should be on/off by default for all forms |
hasRaisedButtonBool | Is true in platforms where the theme has the |
hideBackCommandBool | Hides the back command from the side menu when possible |
hideEmptyTitleBool | Indicates that a title with no content should be hidden even if the border for the title occupies space |
hideLeftSideMenuBool | Hides the side menu icon that appears on the left side of the UI |
hideRightSideMenuBool | Hides the toolbar menu icon that appears on the right side of the title area |
ignorListFocusBool | Hide the focus component of the list when the list doesn’t have focus |
infiniteImage | The image used by the infinite progress component, the component will rotate it as needed |
infiniteMaterialDesignSize | Size (in millimeters) of the generated material design spinner when |
infiniteMaterialImageSize | Size (in millimeters) of the generated spinner image when no custom |
infiniteDefaultColor | Hex RGB color used for the autogenerated material spinner when |
interactionDialogSpeedInt | Controls the duration in milliseconds that |
includeNativeBool | True to derive from the platform native theme, false to create a blank theme that only uses the basic defaults |
labelGap | Positive floating point value representing the default gap value between the label text and the icon in millimeters |
listItemGapInt | Built-in item gap in the list, this defaults to 2, which predated padding/margin in Codename One |
listLongPressBool | Indicates whether a list should handle long press events, defaults to true |
mapTileLoadingImage | An image to preview while loading the MapComponent tile |
mapTileLoadingText | The text of the tiles in the MapComponent during loading, defaults to "Loading…" |
mapZoomButtonsBool | Indicates whether buttons should be drawn on the map component |
mediaBackImage | Media icon used by the media player class |
mediaFwdImage | Media icon used by the media player class |
mediaPauseImage | Media icon used by the media player class |
mediaPlayImage | Media icon used by the media player class |
menuButtonBottomBool | When set to true this flag aligns the menu button to the bottom portion of the title. Defaults to false |
menuButtonTopBool | When set to true this flag aligns the menu button to the top portion of the title. Defaults to false |
landscapeTitleUiidBool | When true the toolbar swaps to landscape-specific UIIDs (such as |
menuHeightPercent | Allows positioning and sizing the menu |
menuImage | The three dot menu image used in Android and the Toolbar to show more command entries |
menuImageSize | The size in millimeters (floating point value) of the generated side menu image, this is only used if you don’t supply a custom image. The default value is 4.5. |
menuPrefSizeBool | Allows positioning and sizing the menu |
menuSlideDirection | Defines menu entrance effect |
menuSlideInDirBool | Defines menu entrance effect |
menuSlideOutDirBool | Defines menu entrance effect |
menuTransitionIn | Defines menu entrance effect |
menuTransitionInImage | Defines menu entrance effect |
menuTransitionOut | Defines menu exit effect |
menuTransitionOutImage | Defines menu entrance effect |
menuWidthPercent | Allows positioning and sizing the menu |
iosStyleBackArrowBool | Renders the back command using the iOS-style chevron arrow (with a small icon gap) when the toolbar shows back text |
minimizeOnBackBool | Indicates whether the form should minimize the entire application when the physical back button is pressed (if available) and no command is defined as the back command. Defaults to true |
onOffIOSModeBool | Indicates whether the on/off switch should use the iOS or Android mode |
otherPopupRendererBool | Indicates that a separate renderer UIID/instance should be used to the list within the combo box popup |
PackTouchMenuBool | Enables preferred sized packing of the touch menu (true by default), when set to false this allows manually determining the touch menu size using percentages |
paintsTitleBarBool | Indicates that the StatusBar UIID should be added to the top of the form to space down the title area, as is the case on iOS 7+ where the status bar is painted on top of the UI |
rightSideMenuImage | Overrides the default icon used for the right-side toolbar menu button |
rightSideMenuPressImage | Optional pressed-state icon for the right-side toolbar menu button |
popupCancelBodyBool | Indicates that a cancel button should appear within the combo box popup |
PopupDialogArrowBool | Indicates whether the popup dialog has an arrow, notice that this constant will change if you change UIID of the popup dialog |
PopupDialogArrowBottomImage | Image of the popup dialog arrow, notice that this constant will change if you change UIID of the popup dialog |
PopupDialogArrowTopImage | Image of the popup dialog arrow, notice that this constant will change if you change UIID of the popup dialog |
PopupDialogArrowLeftImage | Image of the popup dialog arrow, notice that this constant will change if you change UIID of the popup dialog |
PopupDialogArrowRightImage | Image of the popup dialog arrow, notice that this constant will change if you change UIID of the popup dialog |
popupNoTitleAddPaddingInt | Adds padding to a popup when no title is present |
popupTitleBool | Indicates that a title should appear within the combo box popup |
pullToRefreshImage | The arrow image used to draw the |
pureTouchBool | Indicates the pure touch mode |
radioOppositeSideBool | Indicates the radio button should be drawn on the opposite side to the text and not next to the text |
radioSelectedDisImage | Radio button image |
radioSelectedImage | Radio button image |
radioUnselectedDisImage | Radio button image |
radioUnselectedImage | Radio button image |
radioSelectedDisFocusImage | Radio button image |
radioSelectedFocusImage | Radio button image |
radioUnselectedDisFocusImage | Radio button image |
radioUnselectedFocusImage | Radio button image |
releaseRadiusInt | Indicates the distance from the button with dragging, in which the button should be released, defaults to 0 |
rendererShowsNumbersBool | Indicates whether renderers should render the entry number |
reverseSoftButtonsBool | Swaps the softbutton positions |
rightSideMenuImage | Same as sideMenuImage only for the right side, optional and defaults to sideMenuImage |
rightSideMenuPressImage | Same as sideMenuPressImage only for the right side, optional and defaults to sideMenuPressImage |
rubberBandCoefficientInt | Resistance coefficient for the iOS-style rubber-band compression used while the finger drags past a scroll edge. Value is interpreted as hundredths, so |
ScrollMotion | Selects the post-release flick model. |
ScrollMotionTimeConstantInt | Time constant in milliseconds for the exponential-decay flick model (active when |
scrollVisibleBool |
|
showBackCommandOnTitleBool | Used by the Toolbar API to show whether the back button should appear on the title |
shrinkPopupTitleBool | Indicates the title of the popup should be set to 0 if it’s missing |
sideMenuAnimSpeedInt | The speed at which a sidemenu moves defaults to 300 milliseconds |
sideMenuFoldedSwipeBool | Indicates the side menu could be opened via swiping |
sideMenuImage | The image representing the side menu, three lines (Hamburger menu) |
sideMenuPressImage | Optional pressed version of the sideMenuImage |
sideMenuScrollVisibleBool | Indicates whether the scroll bar on the side menu should be visible or not, defaults to hidden |
sideMenuShadowBool | Indicates whether the shadow for the side menu should be drawn |
sideMenuShadowImage | The image used when drawing the shadow (a default is used if this isn’t supplied) |
sideMenuSizeTabPortraitInt | The size of the side menu when expanded in a tablet in portrait mode |
sideMenuSizePortraitInt | The size of the side menu when expanded in a phone in portrait mode |
sideMenuSizeTabLandscapeInt | The size of the side menu when expanded in a tablet in landscape mode |
sideMenuSizeLandscapeInt | The size of the side menu when expanded in a phone in landscape mode |
sideMenuTensileDragBool | Enables/disables the tensile drag behavior within the opened side menu |
sideSwipeActivationInt | Indicates the threshold in the side menu bar at which a swipe should trigger activation, defaults to 15 (percent) |
sideSwipeSensitiveInt | Indicates the region of the screen that’s sensitive to side swipe in the side menu bar, defaults to 10 (percent) |
sigButtonOKUIID | Defines the UIID applied to the confirmation button in the signature capture dialog (defaults to |
sigButtonResetUIID | Defines the UIID applied to the reset/clear button in the signature capture dialog (defaults to |
sigButtonCancelUIID | Defines the UIID applied to the cancel button in the signature capture dialog (defaults to |
slideDirection | Default slide transition settings |
slideInDirBool | Default slide transition settings |
slideOutDirBool | Default slide transition settings |
sliderThumbImage | The thumb image that can appear on the sliders |
snapGridBool | Snap to grid toggle |
statusBarScrollsUpBool | Indicates that a tap on the status bar should scroll up the UI, only relevant in OSes where paintsTitleBarBool is true |
switchButtonPadInt | Indicates the padding in the on/off switch, defaults to 16 |
switchMaskImage | Indicates the mask image used in iOS mode to draw on top of the switch |
switchOnImage | Indicates the on image used in iOS mode to draw the on/off switch |
switchOffImage | Indicates the off image used in iOS mode to draw the on/off switch |
TabEnableAutoImageBool | Indicates images should be filled by default for tabs |
TabSelectedImage | Default selected image for tabs (if TabEnableAutoImageBool=true) |
TabUnselectedImage | Default unselected image for tabs (if TabEnableAutoImageBool=true) |
tabPlacementInt | The placement of the tabs in the Tabs component: TOP = 0, LEFT = 1, BOTTOM = 2, RIGHT = 3 |
tabsSlideSpeedInt | The time of the animation that occurs (in milliseconds) between releasing a swiped tab and reaching the next tab. Defaults to 200 |
tabsFillRowsBool | Indicates if the tabs should fill the row using flow layout |
tabsGridBool | Indicates whether tabs should use a grid layout thus forcing all tabs to have identical sizes |
tabsOnTopBool | Indicates the tabs should be drawn on top of their content in a layered UI, this allows a tab to intrude into the content of the tabs |
textCmpVAlignInt | The vertical alignment of the text component: TOP = 0, CENTER = 4, BOTTOM = 2 |
textComponentErrorColor | A hex RGB color which defaults to null in which case this has no effect. When defined this will change the color of the border and label to the given color to match the material design styling. This implements the red border underline in cases of error and the label text color change |
textComponentOnTopBool | Toggles the on top mode which makes things look like they do on Android. This defaults to true on Android and false on other OSes. This can also be manipulated via the |
textComponentAnimBool | toggles the animation mode which again can be manipulated by a method in |
textComponentFieldUIID | sets the UIID of the text field to something other than |
textFieldCursorColorInt | The color of the cursor as an integer (not hex) |
tickerSpeedInt | The speed of label/button etc. (in milliseconds) |
tintColor | The aarrggbb hex color to tint the screen when a dialog is shown |
topMenuSizeTabPortraitInt | The size of the side menu when expanded and attached to the top in a tablet in portrait mode |
topMenuSizePortraitInt | The size of the side menu when expanded and attached to the top in a phone in portrait mode |
topMenuSizeTabLandscapeInt | The size of the side menu when expanded and attached to the top in a tablet in landscape mode |
topMenuSizeLandscapeInt | The size of the side menu when expanded and attached to the top in a phone in landscape mode |
touchCommandFillBool | Indicates how the touch menu should lay out the commands within |
touchCommandFlowBool | Indicates how the touch menu should lay out the commands within |
transitionSpeedInt | Indicates the default speed for transitions |
treeFolderImage | Picture of a folder for the Tree class |
treeFolderOpenImage | Picture of a folder expanded for the |
treeNodeImage | Picture of a file node for the |
tensileDragBool | Indicates that tensile drag should be enabled/disabled. This is set by platform themes |
tensileSnapMinDurationInt | Minimum duration in milliseconds for the tensile snap-back animation when the finger is released past a scroll edge. Defaults to |
tensileSnapMotion | Motion curve used for the tensile snap-back. |
4.4.1. Scroll motion tuning
Scroll feel is controlled by three stages, each tunable via theme constants:
While the finger is dragging past an edge--when
iosScrollMotionBoolistrue, the over-edge distance is compressed by the iOS UIScrollView rubber-band functionc * d * dim / (c * d + dim), wheredis the raw finger displacement past the edge,dimis the viewport dimension, andcisrubberBandCoefficientInt / 100(default0.55). The result is that the content feels heavier the farther you pull it, asymptotically approachingdim. WheniosScrollMotionBoolisfalse, the legacy behavior is used: a linear 1:1 follow clamped totensileLength.After the finger is lifted, while there is still velocity--the
ScrollMotionconstant selects the model.DECAY(default) uses exponential velocity decay with a time constant ofScrollMotionTimeConstantIntmilliseconds and a distance scale ofDecayMotionScaleFactorInt. Any other value (for example,FRICTION) falls back to linear friction.When the scroll comes to rest past an edge--a tensile snap-back animates the content back to the edge.
tensileSnapMotionpicks the curve:SPRINGis a critically damped envelope (iOS-like soft settle) andDECELERATIONis the legacy quadratic ease-out. The duration scales with distance but never falls belowtensileSnapMinDurationIntmilliseconds.iosScrollMotionBoolis the single switch that flips stage 1 and the default of stage 3 to the iOS-matching behavior. It defaults totrueon the iOS platform only. Every individual constant can still be overridden regardless of this switch, so you can, for example, enable the nonlinear rubber-band globally (iosScrollMotionBool=true) while keeping the legacy quadratic snap-back (tensileSnapMotion=DECELERATION).
To make scrolling feel stiffer on iOS (less pull), reduce
rubberBandCoefficientIntfrom55toward35.To make flicks stop sooner, reduce
ScrollMotionTimeConstantInt(default500) orDecayMotionScaleFactorInt(default950).To enable iOS-style physics on Android or desktop for consistency, set
iosScrollMotionBool=trueexplicitly.To disable iOS physics on the simulator while debugging, set
iosScrollMotionBool=falsein your development theme.
4.5. Native theming
Codename One uses a theme constant called includeNativeBool, when that constant is set to true Codename One starts by loading the native theme first and then applying all the theme settings. This means your theme "derives" the style of the native theme first, like the cascading effect of CSS. Internally this is what the theme layering section covered.
By avoiding this flag you can create themes that look EXACTLY the same on all platforms.
| If you avoid the native theming you might be on your own. A few small device oddities such as the iOS status bar are abstracted by native theming. Without it you will need to do everything from scratch |
You can simulate different OS platforms by using the native theme menu option

Developers can pick the platform of their liking and see how the theme will appear in that particular platform by selecting it and having the preview update on the fly.
4.6. Under the hood of the theme engine
To truly understand a theme you need to understand what it is. Internally a theme is a Hashtable key/value pair between UIID based keys and their respective values. For example: the key:
return "Button.fgColor=ffffff";Will set the foreground color of the Button UIID to white.
When a Codename One Component is instantiated it requests a Style object from the UIManager class. The Style object is based on the settings within the theme and can be modified through code or by using the theme.
You can replace the theme dynamically in runtime and refresh the styles assigned to the various components using the refreshTheme() method.
It’s a common mistake to invoke refreshTheme() without actually changing the theme. You see developers doing it when all they need is a repaint() or revalidate(). Since refreshTheme() is ** expensive recommend that you don’t use it unless you need to… |
A theme Hashtable key comprises:
[UIID.][type#]attribute
The UIID, corresponds to the component’s UIID for example: Button, CheckBox etc. It’s optional and may be omitted to address the global default style.
The type is omitted for the default unselected type, and may be one of sel (selected type), dis (disabled type) or press (pressed type). The attribute should be one of:
derive- the value for this attribute should be a string representing the base component.bgColor- represents the background color for the component, if applicable, in a web hex string format RRGGBB for example: ff0000 for red.fgColor- represents the foreground color, if applicable.border- an instance of the border class, used to display the border for the component.bgImage- an Image object used in the background of a component.transparency- aStringcontaining a number between 0-255 representing the alpha value for the background. This applies to the bgColor.margin- the margin of the component as aStringcontaining 4 comma separated numbers for top, bottom, left, right.padding- the padding of the component, it has an identical format to the margin attribute.font- A Font object instance.alignment- anIntegerobject containing the LEFT/RIGHT/CENTER constant values defined in Component.textDecoration- anIntegervalue containing one of the TEXT_DECORATION_* constant values defined in Style.backgroundType- aByteobject containing one of the constants for the background type defined in Style under BACKGROUND_*.backgroundGradient- contains anObjectarray containing 2 integers for the colors of the gradient. If the gradient is radial it contains 3 floating points defining the x, y & size of the gradient.
To set the foreground color of a selected button to red, a theme will define a property like:
Button.sel#fgColor=ff0000
This information is useful for understanding how things work within Codename One, but it can also be useful in runtime.
For example: to increase the size of all fonts in the application, you can do something like:
Hashtable h = new Hashtable();
h.put("font", largeFont);
UIManager.getInstance().addThemeProps(h);
Display.getInstance().getCurrent().refreshTheme();4.7. Understanding images and Multi-Images
| This section provides a high-level overview of images. You dive deeper into the various types of images in the graphics section. |
When working with a theme, you often use images for borders or backgrounds. You also use images within the GUI for various purposes and most such images will be extracted from the resource file.
Adding a standard JPEG/PNG image to the resource file is straight forward, and the resulting image can be viewed within the images section. For example, due to the wide difference between device types, an image that would be appropriate in size for an iPhone 3gs would not be appropriate in size for a Nexus device or an iPhone 4 (but perhaps, it will be right for iPad 1 and iPad 2).
The density of the devices varies and Codename One tries to simplify the process by unifying everything into one set of values to show density. For simplicity’s sake, density is sometimes expressed in pixels, but it’s mapped internally to actual screen measurements where possible.
A multi-image is an image that has many varieties for different densities, and thus looks sharp in all the densities. Since scaling on the device can’t interpolate the data (due to performance considerations), significant scaling on the device becomes impractical. For example, a multi-image will provide the "right" resolution image for the given device type.
From the programming perspective this is seamless, a developer accesses one image and has no ability to access the images in the different resolutions. Within the designer, but, you can explicitly define images for many resolutions and perform high quality scaling so the "right" image is available.
You can use two basic methods to add a multi-image: quick add and standard add.
Both methods rely on understanding the source resolution of the image, for example: if you have an icon that you expect to be 128×128 pixels on iPhone 4, 102×102 on nexus one and 64×64 on iPhone 3gs. You can provide the source image as the 128 pixel image and perform a quick add option while picking the # High# density option.
This will show to the algorithm that your source image is designed for the " high" density and it will scale for the rest of the densities accordingly.
| This relies on the common use case of asking your designer to design for one high end device (for example: iPhone X) then you can take the resources and add them as "HD" resources. They will automatically adapt to the lower resolutions |
Or, you can use the standard add multi-image dialog and set it like this:

Notice that you selected the square image option, essentially eliminating the height option. Setting values to 0 prevents the system from generating a multi-image entry for that resolution, which will mean a device in that category will fall on the closest alternative.
The percentage value will change the entire column, and it means the percentage of the screen. For example: You know the icon is 128 for the high resolution, you can move the percentage until you reach something close to 128 in the " High" row and the other rows will represent a size that should be pretty close in physical size to the 128 figure.
At runtime, you can always find the host device’s approximate pixel density using the Display.getDeviceDensity()
method. This will return one of:
Constant | Density | Example Device |
| ~ 88 ppi | |
| ~ 120 ppi | Android ldpi devices |
| ~ 160 ppi | iPhone 3GS, iPad, Android mdpi devices |
| ~ 240 ppi | Android hdpi devices |
| ~ 320 ppi | iPhone 4, iPad Air 2, Android xhdpi devices |
| ~ 540 ppi | iPhone 6+, Android xxhdpi devices |
| ~ 750 ppi | Android xxxhdpi devices |
| ~ 1000 ppi | |
| ~ 1250ppi |
4.8. Use millimeters for Padding/Margin and font sizes
When configuring your styles, you should rarely use "Pixels" as the unit for padding, margins, font size, and border thickness because the results will be inconsistent on different densities. Instead, you should use millimeters for all non-zero units of measurement.
As you now understand the complexities of DPI it should be clear why this is important.
4.8.1. Fractions of millimeters
Sometimes millimeters don’t give you enough precision for what you want to do. The designer allows you to specify integer values for most units. For example, you can achieve more precise results when working directly in Java. The Display.convertToPixels() method will allow you to convert millimeters (or DIPS) to pixels. It also takes an integer input, but you can use it to get a multiplier that you can then use to convert any millimeter value you want into pixels.
For example:
double pixelsPerMM = ((double) Display.getInstance().convertToPixels(10, true)) / 10.0;And now you can set the padding on an element to 1.5mm. For example:
myButton.getAllStyles().setPaddingUnit(Style.UNIT_TYPE_PIXELS);
int pixels = (int) (1.5 * pixelsPerMM);
myButton.getAllStyles().setPadding(pixels, pixels, pixels, pixels);4.9. Creating a great looking side menu

A side menu is a crucial piece of an elegant application. You will explain how one creates a simple side menu that’s elegant, portable and easy to build. This is a good "starting point" side menu from which you can build more elaborate designs.
To get this result you will start from a native theme and a bare-bones application to keep things simple.
The code for the side menu is this:
Form hi = new Form("Hi World");
Toolbar tb = hi.getToolbar();
Image icon = theme.getImage("icon.png"); (1)
Container topBar = BorderLayout.east(new Label(icon));
topBar.add(BorderLayout.SOUTH, new Label("Cool App Tagline...", "SidemenuTagline")); (2)
topBar.setUIID("SideCommand");
tb.addComponentToSideMenu(topBar);
tb.addMaterialCommandToSideMenu("Home", FontImage.MATERIAL_HOME, e -> {}); (3)
tb.addMaterialCommandToSideMenu("Website", FontImage.MATERIAL_WEB, e -> {});
tb.addMaterialCommandToSideMenu("Settings", FontImage.MATERIAL_SETTINGS, e -> {});
tb.addMaterialCommandToSideMenu("About", FontImage.MATERIAL_INFO, e -> {});
hi.addComponent(new Label("Hi World"));
hi.show();| 1 | This is the icon which was used instead of a logo it appears in the top right of the side menu |
| 2 | This is the top bar containing the tagline and the icon it’s styled as if it’s a command but you can put anything here for example: an image etc. |
| 3 | The commands are added as usual to the side menu with no styling or functionality, the entire look is determined by the theme |
Next you will open the designer tool to style the UI

Now when you press Add the side menu entries will appear in the combo box (you can type them but this is more convenient). You will start with the SideNavigationPanel style:

The SideCommand style is a bit more elaborate, you start with a white foreground and an opaque bluish/purple color:

You will set padding to 3 millimeters which provides everything a good feel and spacing. This is important for finger touch sensitivity.

You will set margin to 0 except for the bottom one pixel which will leave a nice white line by showing off the background. This means the commands will have a space between them and the white style you gave to the SideNavigationPanel will appear through that space.

Setting the border to empty is crucial!
The iOS version of the side command inherits a border style so you must "remove" it by defining a different border in this case an empty border. Since borders take precedence over color this would have prevented the color changes you made from appearing.

Next you need to pick a good looking font and make sure it’s large enough. You use millimeters size it for all OS’s and override the derived text decoration which has a value in the iOS native theme so it can impact the final look.

Next you need to move to the selected tab and add a new side command entry that derives from the unselected version. You will pick a new color that’s slightly deeper and will make the selected style appear selected. You will also copy and paste this selected style to the pressed style.


The SidemenuTagline is a SideCommand style that was slightly adapted. You will remove the padding and margin because the whole section is wrapped in a side command and you don’t want double padding. You will leave 1mm padding at the top for a bit of spacing from the logo.

You will also update the font to a smaller size and italic styling so it will feel like a tagline.

The last change for the theme is for the StatusBarSideMenu UIID which is a spacing on the top of the sidemenu. This spacing is there for iOS devices which render the clock/battery/reception symbols on top of the app. You will set the padding to 0.

Finally, you will add the icon image (or a logo if you have it) into the theme as a multi image so you can use it within the side menu as a good looking logo. A large icon image works as a 2HD multi-image but you can use many strategies to get a fitting image for this spot.
| Rounded images work well here, you can round images dynamically using masking |
These steps produce the UI above as a side menu, they might seem like a long set of steps but each step is pretty simple as you walk through each one. This does show off the versatility and power of Codename One as a change to one step can create a radically different UI design.
4.10. Converting a PSD to a theme
Codename One provides extensive support for designing beautiful user interfaces, but it isn’t necessarily obvious to new developers how to achieve their desired results. A common workflow for app design includes a PSD file with mock-ups of the UI, created by a professional designer.
| PSD is the Adobe Photoshop file format, it’s the most common format for UI designs in the industry |
For this tutorial you adapt a slick looking sign-up form found online and convert it to a Codename One component that can be used inside an application.
The process you followed was:
Find the PSD design you want to use: this PSD file created by Adrian Chiran (you mirrored it here in case it goes offline):
Figure 64. Sign Up form DesignRe-create the general structure and layout of the design in a Codename One
Formusing nested components and layout managers. Here is a break-down of how you structured the component hierarchy in theForm:
Figure 65. Component hierarchy and layoutsExtract the images you needed using Photoshop - this process is often referred to as "cutting"
Extract the fonts, colors, and styles you needed to reproduce the design in Codename One
Import images into the Codename one project, and define theme styles so that your components match the look of the original design
Here is a screenshot of the resulting component running inside the Codename One simulator:

4.10.1. Breaking down the PSD
Open the PSD you’re interested in using Photoshop.
| You might be missing fonts in your system so you can either install them or ignore that. Keep in mind that some fonts might not be redistributable with your application |
In this PSD you want one of the screen designs so initially you want to remove everything that isn’t related so you can get your bearings more effectively:
Select the drag tool (the top left tool)
In the toolbar for the tool (top bar area) check the Auto Select mode
Select the Layer Mode for auto selection (sometimes group would actually be better so feel free to experiment)
Click on the portion in the PSD that you’re interested in
You should end up with something like this where a layer is selected in the layers window:

Scroll up the hierarchy a bit and uncheck/recheck the eye icon on the left until you locate the right element layer.

Right-click the layer and select Convert To Smart Object.
| The right click menu will present different options when you click different areas of the layer, clicking on the left area of the layer works |

Once the layer hierarchy is a smart object you can double-click it which will open the sub hierarchy in a new tab and you now have the pieces of the image you care about.

Removing the noise
The first thing you need to do is remove from the image all the things that you don’t need. The status bar area on the top is redundant as if is a part of the phones UI. You can select it using the select tool and click the eye icon next to the layer to hide it.
You’d want to have the back arrow but thanks to the material design icons that are a part of Codename One you don’t need that icon so you can hide that too.
You don’t need the "Sign Up" or "Done" strings in the title either but before removing them you’d like to know the font that’s used.
To discover that, click them to select the layer then switch to the text tool:

Then double-click the text area layer to find out the font in the top of the UI like this:

| Notice that you don’t actually need to have the font installed; in this case the font isn’t installed (hence the square brackets) |
Also notice that the color of the font is accessible in that toolbar, by clicking the color element you get this dialog which shows the color value to be f73267, this is something you will use later

You can now hide both text layers so they won’t pose a problem later.
The camera Button
The camera button includes an icon and the button background itself. You can use that as a single image and be done with it, but for this tutorial you will take the harder route of separating this into a button background and a foreground image.
When you click on the camera icon you will notice that the camera icon comprises two separate layers: the camera and the "x" symbol above it. You can select both layers using ctrl-click (command click on the Mac) and convert both to a smart object together using the same method as before:

Since the image is used as an icon you want it to be square which isn’t the situation here!
This is important as a non-square image can trigger misalignment when dealing with icons and the background. You need to use the Image → Canvas Size menu and set the values to be the same (the higher value of the two).

You can now use File → Export and save the first image resource you will need into a temporary directory. Make sure to save a PNG file to preserve quality and transparency!
| Use File → Export and never use File → Save As. The latter can produce a huge size difference as it retains image meta-data |
For convenience you will refer to the file as camera.png when you need it later.

You can follow the exact same procedure with the parent button layer (the white portion) which you can convert to a smart object and export camera-button.png.
Now you can hide both of these elements and proceed to get the background image for the title.
Here the "smart object trick" won’t work… An effects layer is in place and the smart object will provide you with the real underlying image instead of the look you actually want. For example, solving this is trivial now that you hid all the elements on top of the image!
You need to switch to the rectangular select tool:

Now drag the select tool to select the image don’t cross into the white pixels below the image. You can use the zoom value and set it to a high value to get the selection right.
When the selection is right click Edit → Copy Merged. Copy would copy a specific layer but in this case you want to copy what you see on the screen!
Now click File → New it should have the Presets set to Clipboard which means the newly created image is based on what you copied (great UX). Just accept that dialog and paste (Ctrl-V or Command-V).
You can now save the image, since it’s a background using JPEG is totally acceptable in this case. You named it background.jpg.

The last thing you need is the colors used in the UI. You can use the "eye drop" tool in a high zoom level to discover the colors of various elements for example: the text color is 4d606f and the separator color is f5f5f5:

4.10.2. The Code
While that was verbose it was simple. You will create a simple barebones manual application with the native theme.
| The reason for this is to avoid "noise," if you use a more elaborate theme it would have some existing settings. This can make the tutorial harder to follow |

Once the project is created double-click the theme.res file and within the designer select Images → Quick Add Multi Images. Select the 3 images you created above: background.jpg, camera.png & camera-button.png. Leave the default setting on # High# and press OK.
Then save the resource file so you can use these images from code.
Here is the source code you used to work with the UI above there are comments within the code explaining some logic:
private Label createSeparator() {
Label sep = new Label();
sep.setUIID("Separator");
// the separator line is implemented in the theme using padding and background color, by default labels
// are hidden when they have no content, this method disables that behavior
sep.setShowEvenIfBlank(true);
return sep;
}if (current != null) {
current.show();
return;
}
// The toolbar uses the layered mode so it resides on top of the background image, the theme makes
// it transparent so we will see the image below it, we use border layout to place the background image on
// top and the "Get started" button in the south
Form psdTutorial = new Form("Signup", new BorderLayout());
Toolbar tb = new Toolbar(true);
psdTutorial.setToolbar(tb);
// we create 4mm material arrow images for the back button and the Get started button
Style iconStyle = psdTutorial.getUIManager().getComponentStyle("Title");
FontImage leftArrow = FontImage.createMaterial(FontImage.MATERIAL_ARROW_BACK, iconStyle, 4);
FontImage rightArrow = FontImage.createMaterial(FontImage.MATERIAL_ARROW_FORWARD, iconStyle, 4);
// we place the back and done commands in the toolbar, we need to change UIID of the "Done" command
// so we can color it in Red
tb.addCommandToLeftBar("", leftArrow, (e) -> Log.p("Back pressed"));
Command doneCommand = tb.addCommandToRightBar("Done", null, (e) -> Log.p("Done pressed"));
tb.findCommandComponent(doneCommand).setUIID("RedCommand");
// The camera button is comprised of 3 pieces. A label containing the image and the transparent button
// with the camera icon on top. This is all wrapped in the title container where the title background image
// is placed using the theme. We chose to use a Label rather than a background using the cameraLayer so
// the label will preserve the original size of the image without scaling it and take up the space it needs
Button cameraButton = new Button(theme.getImage("camera.png"));
Container cameraLayer = LayeredLayout.encloseIn(
new Label(theme.getImage("camera-button.png")),
cameraButton);
cameraButton.setUIID("CameraButton");
Container titleContainer = Container.encloseIn(
new BorderLayout(BorderLayout.CENTER_BEHAVIOR_CENTER),
cameraLayer, BorderLayout.CENTER);
titleContainer.setUIID("TitleContainer");
TextField firstName = new TextField("", "First Name");
TextField lastName = new TextField("", "Last Name");
TextField email = new TextField("", "Email Address", 20, TextField.EMAILADDR);
TextField password = new TextField("", "Choose a Password", 20, TextField.PASSWORD);
TextField phone = new TextField("", "Phone Number", 20, TextField.PHONENUMBER);
Label phonePrefix = new Label("+1");
phonePrefix.setUIID("TextField");
// The phone and full name have vertical separators, we use two table layouts to arrange them correctly
// so the vertical separator will be in the right place
TableLayout fullNameLayout = new TableLayout(1, 3);
Container fullName = new Container(fullNameLayout);
fullName.add(fullNameLayout.createConstraint().widthPercentage(49), firstName).
add(fullNameLayout.createConstraint().widthPercentage(1), createSeparator()).
add(fullNameLayout.createConstraint().widthPercentage(50), lastName);
Container fullPhone = TableLayout.encloseIn(3, phonePrefix, createSeparator(), phone);
// The button in the south portion needs the arrow icon to be on the right side so we place the text on the left
Button southButton = new Button("Get started", rightArrow);
southButton.setTextPosition(Component.LEFT);
southButton.setUIID("SouthButton");
// we add the components and the separators the center portion contains all of the elements in a box
// Y container which we allow to scroll. BorderLayout Containers implicitly disable scrolling
Container by = BoxLayout.encloseY(
fullName,
createSeparator(),
email,
createSeparator(),
password,
createSeparator(),
fullPhone,
createSeparator()
);
by.setScrollableY(true);
psdTutorial.add(BorderLayout.NORTH, titleContainer).
add(BorderLayout.SOUTH, southButton).
add(BorderLayout.CENTER, by);
psdTutorial.show();4.10.3. Styling the UI
The code above is most of the work but you still need to put everything together using the theme. This is what you’ve so far:


This looks like a major set of changes but it requires 10 UIID definitions to get to this look!
Open the designer and select the theme. Press the Add button and type in TitleContainer. Uncheck derive for the background and select IMAGE_SCALED_FILL for the Type and the background.jpg image.
Define the padding as:
Left - 3 millimeters
Right - 3 millimeters
Top - 8 millimeters
Bottom - 2 millimeters
This will allow enough space for the title. Define margin as 0 on all sides. Then press OK.
Add the "Title" UIID. In the Color tab define the foreground as ffffff define transparency as 0 (fully transparent so you will see the TitleContainer). Define padding as 1 millimeter on all sides and margin as 0 on all sides.
In the Border tab press the … button and select [Empty].
In the Font tab select the True Type as native:MainThin. Select the True Type Size as millimeters and set the value to 3.5.
Press OK to save the changes.
Copy the Title UIID and paste it, change the name to "TitleCommand" and press OK to save the changes.
Copy the Title UIID again and paste it, change the name to RedCommand. In the Color tab set the foreground color to f73267. In the Font tab set the True Type to native:MainLight and set the size to 3. Press OK to save the changes.
Add the "TitleArea" UIID. In the Color tab define transparency as 0 (fully transparent so you will see the TitleContainer). Define padding and margin as 0 on all sides.
In the Border tab press the … button and select [Empty].
Press OK to save the changes.
Add the "TextField" UIID. In the Color tab define transparency as 255 (fully opaque) and the background as ffffff (white). Define padding as 2 millimeters on all sides and margin as 0 on all sides.
In the Border tab press the … button and select [Empty].
In the Font tab set the True Type to native:MainLight and set the size to 2. Press OK to save the changes.
Copy the TextField UIID again and paste it, change the name to TextHint. In the Color tab set the foreground color to 4d606f. Press OK to save the changes.
Add the "SouthButton" UIID. In the Color tab define transparency as 255 (fully opaque) and the background as f73267 (red) and the foreground as ffffff (white). Define Alignment as Center.
Define padding as:
Left - 1 millimeter
right - 1 millimeter
top - 2 millimeters
bottom - 2 millimeters
Define margin as 0 on all sides. In the Font tab set the True Type to native:MainThin and set the size to 3. Press OK to save the changes.
Add the "CameraButton" UIID. In the Color tab define transparency as 0 (fully transparent). Define Alignment as Center.
Define padding as:
Left - 1 millimeter
right - 1 millimeter
top - 3 millimeters
bottom - 1 millimeter
| This helps spacing away from the title |
Define margin as 1 millimeter on all sides. Press OK to save the changes.
You can now save the theme and the app should look like the final result!
Not quite there yet
One last piece would become apparent if you actually try to run this code. When pressing the buttons/text fields you would see their look change due to the different styles for focus/press behavior.
You can derive the regular styles from the selected/pressed styles but one of the simplest ways is to copy & paste the styles to the pressed/selected tabs. You can copy CameraButton, RedCommand, SouthButton & TextField to the selected state. Then copy CameraButton, RedCommand & SouthButton to the pressed state to get the complete app running!
5. Native modern themes
Codename One ships an iOS Modern (liquid-glass) theme and an Android
Material 3 theme that you can opt your app into with a single build
hint. Both are fully overridable - their color palettes, type
ramps, and state-specific styles are all reachable from your own
theme.css and from runtime API.
The legacy iOS 7 (iOS) and Holo Light (Android) themes remain the default so existing apps see no behavior change.
5.1. Selecting a theme
Three build hints control the platform native theme. None of them are required; with all three unset every app continues to load the legacy theme it always did.
| Hint | Values | Description |
|---|---|---|
|
|
|
|
|
|
|
| Cross-platform shortcut that sets both |
The legacy and.hololight=true hint still works and maps to
and.themeMode=hololight.
5.2. Light and dark mode
Both modern themes ship a dark variant via a
@media (prefers-color-scheme: dark) block in their CSS. The CSS
compiler rewrites each rule inside that block into a $Dark<UIID>
style entry; UIManager picks them up whenever
CN.isDarkMode() == true.
Display.getInstance().setDarkMode(Boolean) controls the active
appearance:
null(the default) - follow the device. iOS readsUITraitCollection, Android readsConfiguration.uiMode. When the user toggles light / dark in system settings the app reflects the change.true/false- force the app into one mode regardless of system setting (useful for theme-preview screens or accessibility toggles).
5.3. Material 3 color palette (Android)
The Android Material 3 theme is built around the Material Design 3 "baseline" palette. Each color is referenced from one or more UIIDs; if you change a color the change ripples to every UIID that inherits from it.
| Role | Light | Dark | Used by |
|---|---|---|---|
primary |
|
| Default |
on-primary |
|
| Text printed on top of the primary fill. |
primary-container |
|
|
|
surface |
|
|
|
on-surface |
|
| Body text on surfaces ( |
surface-variant |
|
| Track of the off-state |
on-surface-variant |
|
| Secondary text ( |
surface-container |
|
|
|
surface-container-highest |
|
|
|
outline / outline-variant |
|
|
|
state-pressed |
|
| All |
state-disabled / on-disabled |
|
| All |
To rebrand the app, override the color at the role level rather
than touching every UIID. The example below layers a teal palette
on top from your app’s own theme.css; if you want the same
rebrand to apply at runtime (for in-app accent toggles, branded
flavours, A/B tests) without recompiling the theme, see
Runtime accent palette override further down - a single
addThemeProps({"@accent-color": …}) call retunes every
accent-bearing UIID at once:
#Constants {
includeNativeBool: true;
darkModeBool: true;
}
/* Touch the four UIIDs that paint with primary / primary-container.
The role-as-rule pattern keeps brand changes localised. */
Button { background-color: #00796b; }
Button.pressed { background-color: #4db6ac; color: #00251a; }
RaisedButton { background-color: #b2dfdb; color: #00251a; }
RaisedButton.pressed { background-color: #80cbc4; }
SelectedTab { color: #00796b; }
BackCommand { color: #00796b; }
TitleCommand { color: #00796b; }5.4. iOS modern color palette
The iOS modern theme follows Apple’s system palette.
| Role | Light | Dark | Used by |
|---|---|---|---|
accent |
|
|
|
accent-pressed |
|
| All |
accent-disabled |
|
| All |
surface |
|
| Pure surface used by |
surface-grouped |
|
| Form / ContentPane (the iOS "grouped" form bg). |
surface-tertiary |
|
|
|
text-primary |
|
|
|
text-secondary |
|
|
|
text-tertiary / text-disabled |
|
|
|
separator |
|
|
|
success |
|
|
|
To layer a brand color on top, override RaisedButton and
accent-driven UIIDs the same way as Android above. The color names
match Apple’s UIColor.systemBlue etc. So you can mirror the SF
Symbols semantics if you want.
5.5. Accent palette override
Both shipped native themes expose their accent palette as named
constants you can retune from your app’s own theme.css (or, for
dynamic theming, at runtime). The CSS source uses
var(--accent-color, fallback) references so the fallback ships as
the baked-in default (the .res file loads fine with no override)
and the compiler additionally emits a
@cn1-bind:<UIID>.<key>=accent-color constant alongside each
affected style key. When the resolved theme constants pick up a new
@accent-color value (whether from your CSS or via runtime
UIManager.addThemeProps), the framework fans the override out to
every bound UIID at once - no per-UIID rule duplication, no theme
recompile.
| Constant | Light default | Dark default | Drives |
|---|---|---|---|
|
| (see |
|
| n/a |
|
|
|
|
| All |
|
|
| All |
|
| (same) | Text color painted on top of the accent fill. |
| Constant | Light default | Dark default | Material 3 token |
|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5.5.1. Override from your app’s theme.css (recommended)
Redeclare the accent variable inside the #Constants block of your
app’s theme.css. The framework’s CSS compiler exports any
--name declaration in #Constants as a @name theme constant,
so the value flows through the same binding pass that handles
runtime overrides:
#Constants {
includeNativeBool: true;
darkModeBool: true;
/* Override the native theme's accent palette. The compiler picks
up these declarations from #Constants and exports them as
@accent-color / @accent-color-dark theme constants so every
UIID bound to var(--accent-color) in the parent native theme
picks them up at app launch - no per-UIID rule edit needed. */
--accent-color: #ff2d95;
--accent-color-dark: #ff2d95;
--accent-pressed-color: #c71a75;
--accent-pressed-color-dark: #c71a75;
--accent-on-color: #ffffff;
/* Material 3 RaisedButton uses a separate "container" tonal
pair; iOS ignores these (no bindings reference them) so it's
safe to set them unconditionally. */
--accent-container-color: #ff2d95;
--accent-container-color-dark: #ff2d95;
--accent-on-container-color: #ffffff;
--accent-on-container-color-dark: #ffffff;
}Bindings that reference a constant you didn’t override stay at
their baked-in default, so a partial override (for example, just
--accent-color) is fine.
5.5.2. Runtime override
For dynamic theming - in-app accent toggles, branded flavours,
A/B tests - push the same constants through
UIManager.addThemeProps after the theme has been installed:
Values can be passed with or without the leading # and in any
case; the runtime accepts "ff2d95", "#FF2D95", and the 3-digit
shorthand "#f0a" interchangeably.
PaletteOverrideThemeScreenshotTest in the hellocodenameone test
suite exercises this path against both native themes, light + dark.
5.5.3. When the override path doesn’t apply
The binding mechanism handles every accent UIID the shipped themes
expose. For other widgets - or when you want to override a color
the native CSS hard-codes (for example, the iOS success green on
Switch.selected) - either:
Layer a per-UIID redeclaration in your app’s
theme.css(seeCustomizing in your own themebelow). Right when you want to tweak a UIID the binding vocabulary doesn’t already cover.Or pass the specific UIID/state key directly into
UIManager.addThemeProps(Switch.sel#bgColoretc.). Runtime, bypasses the binding system. Right when you need a one-off color tweak you can’t anchor in CSS.
5.6. Platform-specific UIIDs
A handful of UIIDs exist only because one platform draws them differently from the other. They’re still safe to override; you just want to know which platform’s screen the override is going to land on.
iOS-only behavior:
Toolbar,TitleArea,Titlepaint over the status-bar area. iOS reserves room above for the notch / status bar; in your capture this reads as a colored strip at the top of the Form. In production the device fills it with system content (signal, battery, time).MultiButtonis styled as an iOS Settings row (multi-line text ramp + chevron). Compare against Material 3’s denser list-item pattern.
Android-only behavior:
Toolbardoesn’t paint over the system status bar; the native Android status bar handles that.Tabsuse Material 3 top tabs (flat, underline-by-color). iOS modern renders Tabs as a bottom-anchored pill group via thetabPlacementIntconstant - that constant is intentionally only set in the iOS theme so behavior stays consistent on each platform.
5.7. Switching CheckBox / RadioButton glyphs
The default check / radio glyphs are Material icons drawn by
DefaultLookAndFeel. The theme can swap them via four optional
constants (Material codepoints):
| Constant | Default | Notes |
|---|---|---|
|
| Override to for example, |
|
| Match the empty version of whatever you chose above. |
|
| Filled circle with dot. |
|
| Empty circle. |
Set these in your #Constants { … } block; the icons rebuild on
the next style refresh.
5.8. Component-specific tuning constants
| Constant | Effect |
|---|---|
| Stretches the Switch track. Larger X = longer pill, larger Y = thicker. iOS uses 2.5 / 1.5; Material uses 3.0 / 0.9. |
| Scales the Switch thumb relative to the track. iOS 1.4, Material 1.5. |
| Pixels of breathing room between thumb and track. |
| iOS draws a faint ring around the off-state track; Material does not. |
|
|
| Distribute tabs evenly across the bar. |
|
|
| Duration of the indicator tween in milliseconds (default |
| Indicator underline thickness in millimetres (default |
|
|
| Outer diameter of the modern arc spinner in millimetres (default |
| Stroke thickness of the modern arc spinner in millimetres (default
|
|
|
5.9. iOS 26 Liquid Glass tab selection morph
When the iOS modern theme renders Tabs as a bottom bar
(tabPlacementInt: 2) the selected tab is marked by a Liquid Glass
drop — a frosted, magnifying glass capsule painted over the (dark)
icons rather than a flat highlight. On a selection change the drop springs
across to the new tab, elongating while it travels and settling with a
small overshoot. The selected blue is supplied by the drop itself (a
luminance-keyed dark→accent tint of the glyph beneath it), so the color
travels with the drop instead of snapping between tabs.

On iOS the drop is rendered live by a Metal fragment shader that samples
the bar beneath it on the GPU, so the morph runs at frame rate with no
screen read-back; other platforms and the simulator use the equivalent CPU
lens. The effect is opt-in: the iOS modern theme sets
tabsSelectionCapsuleBool: true and glassMaterialBool: true. Without the
glass flag the capsule degrades to a plain translucent pill.
The morph is developed against the real OS control: the frame-by-frame comparison below shows the native iOS 26 tab bar (left) and the Codename One render (right) at matching moments of the selection travel.

The animation is controlled by a named motion preset plus a handful of
high-level knobs. The detailed envelopes (stretch, squash, lift, lens
magnification, aberration, tint timing) live inside the preset in the
motion model (TabSelectionMorph), where they’re pinned by unit test and
validated frame-by-frame by the fidelity suite — a theme picks a preset
and scales it rather than tuning a dozen loose constants:
| Constant | iOS modern | Effect |
|---|---|---|
|
| Master switch for the selection drop. Off falls back to the legacy
colored underline indicator ( |
|
| The named motion preset: |
|
| Morph duration in milliseconds. Lower is snappier. |
|
| Scales the drop’s optics (magnification, chromatic aberration, accent
tint) around the preset: |
|
| Scales the settle overshoot: |
|
| The accent the dark glyph is tinted to inside the drop. |
Similarly, the Liquid Glass backdrop materials themselves are typed,
named recipes (GlassRecipe): a theme assigns chrome (edge-anchored
bars), pill (the floating tab bar) or panel (buttons, dialogs, panels — the default) per UIID with <UIID>GlassRecipe constants, e.g.
ToolbarGlassRecipe: "chrome". Each recipe bundles the measured
saturation/scale/offset color transform and edge optics of one native
material, so similar glass surfaces can’t drift apart one constant at a
time.
The drop’s glass cues (rim shrink, refraction, glare, edge shadow)
fade out as it settles, so a resting selection reads as a calm frosted
pill rather than a distorting lens. Every motion preset is validated
deterministically: the fidelity suite freezes the morph at the fixed
progress points 0, 10, 25, 50, 75, 90 and 100 percent, regression-compares
each frame, and pins the same points numerically against the motion model
in unit tests. The Switch thumb uses the same discipline for its liquid
droplet morph (switchLiquidGlassBool, stretch/squash while sliding,
frame-validated): |

5.10. Customizing in your own theme
Your app’s theme.css inherits from the installed native theme:
#Constants {
includeNativeBool: true;
darkModeBool: true;
}
/* Tweak only what's different. Everything you do not redeclare
keeps coming from the native theme. */
RaisedButton { background-color: #d81b60; }
RaisedButton.pressed { background-color: #b71c5c; }
RaisedButton.disabled { background-color: #ffd6e2; color: #ffffff; }
@media (prefers-color-scheme: dark) {
RaisedButton { background-color: #ff80ab; color: #4a0026; }
RaisedButton.pressed { background-color: #f06292; }
}The user’s CSS is layered on top of the native theme at app launch, so refresh / restart picks the override up.
For a wholesale accent rebrand prefer redeclaring the
--accent-color (etc.) variables in your #Constants block - see
Override from your app’s theme.css above. That single declaration
fans out through every UIID bound to the variable in the native
theme, no per-UIID rules required. Per-UIID redeclaration here
remains the right choice for tweaking non-accent properties
(typography, spacing, surface fills) the binding vocabulary doesn’t
cover.
5.11. Inheriting from a native UIID
cn1-derive lets a custom UIID start from one of the native
theme’s UIIDs and refine it:
DangerButton {
cn1-derive: RaisedButton;
background-color: #d32f2f;
}
DangerButton.pressed {
cn1-derive: RaisedButton;
background-color: #b71c1c;
}cn1-derive works best when the relationship is child refines
parent. Avoid deriving across unrelated UIIDs (for example, a TitleArea
that derives from Toolbar) - inline the properties instead.
5.12. Translucency, glass effects, and the test harness
The iOS modern Dialog and Tabs use translucent surfaces (rgba with
alpha < 1) so any backdrop reads through the widget. To exercise
this in screenshot tests, the hellocodenameone fidelity tests
opt-in to a diagonal-stripe textured backdrop on the form
(useTexturedBackdrop() in DualAppearanceBaseTest). Translucent
widgets show their see-through tint against the stripes; opaque
widgets cover the stripes entirely.
CSS backdrop-filter: blur(<length>) and filter: blur(<length>) are
now recognized by the compiler and persisted in the theme as the
backdropFilterBlur and filterBlur Style properties (also reachable
programmatically via Style#getBackdropFilterBlurRadius() /
Style#getFilterBlurRadius()). Image-level blur is hardware-accelerated
(CIGaussianBlur on iOS, RenderScript / RenderEffect on Android,
JHLabs GaussianFilter in the simulator). Painting the blur into the
component framebuffer is still being wired up; until that lands, the
rgba approximation above remains useful for translucent surfaces.
6. CSS
In this chapter this guide covers theming with CSS in Codename One.
CSS Changes don’t Require a Recompile You can change the CSS values while the simulator is running and the changes will reflect in the simulator within a few seconds |
6.1. Activating CSS
Codename One applications always use the resource file. The CSS support compiles a file in CSS syntax to a Codename One resource file and adds it to the application. In runtime the CSS no longer exists and the file acts like a regular theme file.
New Maven projects enable CSS by default with codename1.cssTheme=true in common/codenameone_settings.properties. Add that property manually if you are migrating an older project where CSS support is disabled.
Once enabled your theme.res file will regenerate from a CSS file that resides under the css directory. Changes you make to the CSS file will instantly update the simulator as you save. But, there are some limits to this live update so sometimes a simulator restart would be necessary.
6.2. Supported CSS selectors
Since Codename One stylesheets are meant to be used with Codename One component hierarchies instead of XML/HTML documents, selectors work a little differently.
All selectors (with some specific exceptions discussed below) are interpreted as UIIDs.
Only 4 predefined CSS classes are supported:
.pressed: Targets the component when in "Pressed" state..selected: Targets the component when in "Selected" state..unselected: Targets the component when in "Unselected" state..disabled: Targets the component when in "Disabled" state.If no class is specified, then the selector targets "all" states of the given component.
The following are a few possible selectors you can include in your stylesheet.
Button: Defines styles for the "Button" UIID.Button.pressed: Defines styles for the "Button" UIID’s "pressed" state.Button, TextField, Form: Defines styles for theButton,TextField, and "Form" UIIDs.
The following example creates a simple button with a border, and text aligned center. By default the button will have a transparent background, but when it’s pressed, it will have a gray background:
Button {
text-align: center;
border: 1pt solid gray;
background-color: transparent;
}
Button.pressed {
background-color: gray;
}6.2.1. Inheriting properties using cn1-derive
The following example defines a custom Button style named "MyButton" that inherits all the styles of Button but changes the background color to blue:
MyButton {
cn1-derive: Button;
background-color: blue;
}6.3. Special selectors
6.3.1. #device
The #Device selector allows you to define which device resolutions this CSS file should target. Mutli-images generated from this style-sheet will be included variants for device resolutions in the range (min-resolution, max-resolution) as defined in this section. By default all resolutions are generated:
#Device {
min-resolution: 120dpi;
max-resolution: 480dpi;
resolution: 480dpi;
}6.3.2. #constants
The #Constants selector allows you to specify theme constants.
For example:
#Constants {
includeNativeBool: true;
commandBehavior: "Side";
defaultFontSizeInt: 18;
defaultDesktopFontSizeInt: 14;
defaultSourceDPIInt: "0";
menuImage: "menu.png";
}
MenuIcon {
background-image: url(images/menu.png);
}In the above example, the constants referring to an image name as a string requires that the image exists in one of the following locations:
res/<cssfilename>/<imageName>../res/<cssfilename>/<imageName>../../res/<cssfilename>/<imageName>
It must also have been defined as a background image in some selector in this CSS file.
6.3.3. Default
The Default selector is special in that it will set properties on the theme’s "default" element. The default element is a special UIID in Codename One from which all other UIIDs in the same theme are derived. This is a good place to set things like default fonts or background-colors.
6.4. Standard CSS properties
padding(and variants)margin(and variants)border(and variants)border-radiusbackground(Usage below)background-colorbackground-repeatbackground-imageborder-imageborder-image-slicefont(Usage is covered in the following font section)font-family(Usage is covered in the following font section)font-style(Usage is covered in the following font section)font-size(Usage is covered in the following font section)@font-face(Usage is covered in the following font section)colortext-aligntext-decoration(Usage below)opacitybox-shadowwidth( used for generating background-images and borders)height( used for generating background-images and borders)
6.5. Custom properties
cn1-source-dpiUsed to specify source DPI for multi-image generation of background images. Accepted values:
0(Not multi-image),120(Low res),160(Medium Res),320(Very High Res),480(HD), Higher than480(2HD). If not specified, the default value will be the value of thedefaultSourceDPIInttheme constant, if specified, or480, if not specified.cn1-background-typeUsed to explicitly specify the background-type that should be used for the class.
cn1-9patchUsed to explicitly specify the slices used when generating 9-piece borders. Deprecated - Use
border-imageandborder-image-slicefor 9-piece borders.cn1-deriveUsed to specify that this UIID should derive from an existing UIID.
6.6. CSS variables
As of CodenameOne 7.0, you can use variables in your CSS file via the var() CSS function. For example:
#Constants {
--header-color: blue;
}
Header {
color: var(--header-color, blue);
}The var() function can be used inside property values. That is, You can’t use it in property names or selectors.
The var() grammar follows the browser CSS form:
#Constants {
--custom-property-name: #0066cc;
}
ExampleSelector {
color: var(--custom-property-name, #0066cc);
}The <custom-property-name> must begin with two dashes (--).
The <declaration-value> is the fallback value that will be used if the variable hasn’t been defined in the CSS file. The fallback value may include commas.
Examples
#Constants {
--main-bg-color: red;
}
MyContainer {
background-color: var(--main-bg-color);
}#Constants {
--main-bg-color: red;
}
MyContainer {
background-color: var(--main-bg-color, blue);
}See the MDN docs for more details about the CSS variable spec.
6.7. CSS properties
This section isn’t as comprehensive as it should be due to the breadth of CSS.
6.7.1. Text-decoration
underline | Underlines text. For example, |
overline | Overlines text. For example, |
line-through | Strikes through text. For example, |
none | No text decoration. For example, |
cn1-3d | 3D text. For example, |
cn1-3d-lowered | 3D lowered text. For example, |
cn1-3d-shadow-north | 3D text with north shadow. For example, |
For other CSS font settings see the Fonts section
6.7.2. Border
This library supports the border property and most of its variants (for example, border-width, border-style, and border-color. It will try to use native Codename One styles for generating borders if possible. If the border definition is too complex, it will fall-back to generating a 9-piece image border at compile-time. This has the effect of making the resulting resource file larger, but will produce good runtime performance, and a look that’s faithful to the provided CSS.
The algorithm used to determine whether to use a native border or to generate a 9-piece image, is complex, but the following guidelines may help you if you wish to design borders that can be rendered natively in CN1:
Non-pixel units
border-width. (Except with thecn1-round-borderandcn1-pill-borderstyles)Using the
border-radiusdirective.Using
box-shadow(Unless usingcn1-round-borderorcn1-pill-borderstyles)Using a background gradient in combination with a border or any kind
Using a different
border-width,border-style, orborder-colorfor different sides of the borderUsing a
filter
| You can open the resulting theme file in the designer and inspect it to see if an image was generated |
Generating the image triggers slower CSS compilation and a larger binary, so tune the CSS so it avoids this fallback.
Round borders
Rounded borders can be achieved in a few different ways. The easiest methods are:
The
cn1-round-borderstyle. This will render a circular round border in the background natively. That is, this doesn’t require generation of an image borderThe
cn1-pill-borderstyle. This will render a pill-shaped border in the background natively. This also doesn’t require generation of an image borderThe
border-radiusproperty. This will round the corners of the border. If the style can be achieved using theRoundRectBorderin CodenameOne, then it will use that border. If not, this will cause the style to be generated as an image border
A border generated from border-radius follows the CSS box model, so the radius rounds the component without changing its size. A radius larger than the component scales down to fit it. This differs from a RoundRectBorder you create in Java, which grows the component to twice the radius so the corners are always drawn in full. Use cn1-pill-border when a shape has to stay a pill at any height.
Examples using cn1-round-border
RoundBorder {
border: 1px #3399ff cn1-round-border;
text-align: center;
margin: 2mm;
padding: 3mm;
}
RoundBorderFilled {
background: cn1-round-border;
background-color: #cccccc;
text-align: center;
margin: 2mm;
padding: 3mm;
}Examples using cn1-pill-border
PillBorder {
border: 1pt #3399ff cn1-pill-border;
text-align: center;
}
PillBorderFilled {
background: cn1-pill-border;
background-color: #3399ff;
color: white;
text-align: center;
}Examples using border-radius
RoundRectLabel {
background-color: red;
border-radius: 2mm;
}cn1-pill-border and cn1-round-border don’t support the standard CSS box-shadow property. This is because the box-shadow property parameters don’t map onto the shadow parameters for the Codename One RoundBorder class. To get shadows on the cn1-pill-border, you should use one or more of the following CSS properties:
cn1-box-shadow-spread: Accepts values in any scalar unit (for example, px, mm, cm, etc.). This maps directly to the border’s shadowSpread property.cn1-box-shadow-h: Accepts values in real values or integers (not a scalar unit). This maps directly to the border’s shadowX property.cn1-box-shadow-v: Accepts values in real values or integers (not a scalar unit). This maps directly to the border’s shadowY property.cn1-box-shadow-blur: Scalar value. Maps to the border’s shadowBlur property.cn1-box-shadow-color: The shadow colorcn1-box-shadow-inset: Set toinsetto render an inner shadow instead of the default outer shadow spread.
Using the regular CSS box-shadow in conjunction with border-radius will cause a 9-piece border to be generated rather than mapping to the RoundRectBorder. If, but, you use the cn1-box-* properties for the shadow instead, it will use the RoundRectBorder—assuming that no other styles are specified that trigger an image border to be generated.
Codename One also exposes per-corner elliptical radius controls that map to the RoundBorder’s X/Y radii. You can set them directly with `cn1-border-top-left-radius-x / cn1-border-top-left-radius-y (and the equivalent top-right, bottom-left, and bottom-right pairs) to fine tune horizontal and vertical curvature independently. The CSS parser automatically populates these properties when you use standard border-radius syntax, including the longhand declarations and the border-radius: <x-radii> / <y-radii> shorthand:
EllipticalBorder {
border-radius: 2mm 4mm 6mm 1mm / 1mm 3mm 5mm 7mm;
cn1-box-shadow-spread: 1.5mm;
cn1-box-shadow-inset: inset;
}In the example above, the four horizontal radii (2mm 4mm 6mm 1mm) populate the cn1-border--radius-x properties clockwise from the top-left corner. The four values after the slash fill the matching cn1-border--radius-y entries. Setting cn1-box-shadow-inset: inset; converts the shadow into an inset glow that follows the same elliptical curvature.
6.7.3. Background
The background property supports most standard CSS values for setting the background color, or background image.
9-piece Image borders always take precedence over background settings in Codename One. If your background directive seems to have no effect, it’s likely because the theme has specified a 9-piece image border for the UIID. You can disable the image border using a directive like border: none |
Background images
See Images
Gradients
The full CSS gradient range is natively supported: linear-gradient, radial-gradient, conic-gradient, repeating-linear-gradient, and repeating-radial-gradient — all with arbitrary angles, unlimited multi-stop colors (with optional position hints), and full radial shape/extent control. The compiled theme resource file carries a compact descriptor and the gradient is rendered at runtime by the platform-native graphics API (Java2D on JavaSE, LinearGradient/RadialGradient/SweepGradient on Android, Core Graphics / Core Image on iOS).

to <side>, linear with mismatched alphas, radial farthest-corner, radial ellipse, conic, repeating-linear, repeating-radial).linear-gradient
Any angle in degrees, radians, or turn, or the canonical to <side> / to <side1> <side2> directions. Two or more stops, each with optional position percentage; positions left blank between fixed anchors are autodistributed:
LinearGradientA { background: linear-gradient(0deg, #cccccc, #666666); }
LinearGradientB { background: linear-gradient(to top, #cccccc, #666666); }
LinearGradientC { background: linear-gradient(45deg, #eaeaea, #666666); }
LinearGradientD { background: linear-gradient(135deg, #ff0080 0%, #ff8c00 50%, #40e0d0 100%); }
LinearGradientE { background: linear-gradient(to bottom right, #ff0066, #000033); }
LinearGradientF { background: linear-gradient(90deg, rgba(255, 0, 0, 0.6), blue); }radial-gradient
Full CSS radial syntax: circle or ellipse, any of the four extent keywords (closest-side / closest-corner / farthest-side / farthest-corner, defaulting to farthest-corner), explicit radii as percentages, an optional at <position> clause with side keywords or percentages, and two or more multi-stop colors:
RadialGradientA { background: radial-gradient(circle, gray, white); }
RadialGradientB { background: radial-gradient(ellipse closest-side at 25% 75%, #ffffff, #000000); }
RadialGradientC { background: radial-gradient(circle farthest-corner at right, #ffffee, #006666 60%, #000011 100%); }conic-gradient
Sweep / pie-style gradient. Optional from <angle> (CSS convention: 0° points up, sweep is clockwise) and at <position> prefix, followed by the stop list:
ConicGradientA { background: conic-gradient(red, yellow, green, blue, red); }
ConicGradientB { background: conic-gradient(from 45deg at 50% 50%, #ff0066 0%, #ffcc00 25%, #00cc66 50%, #0066ff 75%, #ff0066 100%); }repeating-linear-gradient / repeating-radial-gradient
Identical syntax to their non-repeating counterparts. The stop pattern tiles outward to fill the bounding box, ideal for stripes and rings:
MyStripe { background: repeating-linear-gradient(45deg, #eeeeee 0%, #eeeeee 10%, #cccccc 10%, #cccccc 20%); }
MyTarget { background: repeating-radial-gradient(circle at center, #ffffff 0%, #ffffff 20%, #cc3333 20%, #cc3333 40%); }filter and backdrop-filter
CSS filter and backdrop-filter accept a chain of functions. Two storage forms land on the corresponding Style:
blur(<length>)→filterBlurRadius/backdropFilterBlurRadius(a single pixel value).brightness,contrast,grayscale,hue-rotate,invert,opacity,saturate,sepia→filterColorMatrix/backdropFilterColorMatrix(a 4×5 color matrix; a multi-function chain composes into a single matrix in CSS order):
MyOverlay {
background: rgba(0, 0, 0, 0.4);
backdrop-filter: blur(12px);
}
MyBlurredImage {
filter: blur(4px);
}
MyFaded {
filter: brightness(0.7) contrast(1.15);
}
MyGrayscale {
filter: grayscale(1);
}
MySepia {
filter: sepia(0.8) saturate(1.1);
}
filter: blur() applied at a graphics primitive level — the framework’s screenshot test renders RGB stripes and a gradient, then blurs both via Graphics.gaussianBlur(…). Component-level paint-time integration of filter: declarations is in progress; until it lands, set the radius / matrix on a Style and consume them via the corresponding Graphics primitives manually.filter applies to the component’s own painted content; backdrop-filter applies to whatever is painted behind. The radii / matrices are also exposed on Style (getFilterBlurRadius(), getFilterColorMatrix(), getBackdropFilterBlurRadius(), getBackdropFilterColorMatrix()) so they can be set programmatically. Hardware blur is used where available (Core Image on iOS, RenderScript/RenderEffect on Android, JHLabs GaussianFilter on JavaSE simulator); ports without a fast path fall back to a software Gaussian.
6.7.4. cn1-background-type
It also supports some special Codename One values, which are identifiers with a "cn1-" prefix. The following special values are available. They map to the standard Codename One values you discussed in the theming chapter:
cn1-image-scaledcn1-image-scaled-fillcn1-image-scaled-fitcn1-image-tile-bothcn1-image-tile-valign-leftcn1-image-tile-valign-centercn1-image-tile-valign-rightcn1-image-tile-halign-topcn1-image-tile-halign-centercn1-image-tile-halign-bottomcn1-image-align-bottomcn1-image-align-leftcn1-image-align-rightcn1-image-align-centercn1-image-align-top-leftcn1-image-align-top-rightcn1-image-align-bottom-leftcn1-image-align-bottom-rightcn1-image-bordercn1-nonecn1-round-bordercn1-pill-border
6.8. Images
Images are supported as both "inputs" of the stylesheet, and as outputs to the compiled resource file. "Input" images are specified via the background-image property in a selector. "Output" images are always saved as multi-images inside the resource file.
6.8.1. Image DPI and device densities
To appropriately size the image, the CSS compiler needs to know what the source density of the image is. For example, if an image is 160×160 pixels with a source density of 160dpi (that is, medium density - or the same as an iPhone 3G), then the resulting multi-image will be sized at 160×160 for medium density devices and 320×320 on high density devices (for example, iPhone 4S Retina) - which will result in the same perceived size to the user of 1×1 inch.
However, if the image has a source density of 320dpi, then the resulting multi-image would be 80×80 pixels on medium density devices and 160×160 pixels on high density devices.
Some images have this density information embedded in the image itself so that the CSS processor will know how to resize the image. But, it’s better to explicitly document your intentions by including the cn1-source-dpi property as follows:
SomeStyle {
background-image: url(images/my-image.png);
cn1-source-dpi: 160;
}cn1-source-dpi values are meant to fall into threshold ranges. Values less than or equal to 120, are interpreted as low density. 121 - 160 are medium density (iPhone 3GS). 161 - 320, high density (iPhone 4S). 321 - 480 == HD. 481 and higher == 2HD. In general, you should try to use images that are one of these DPIs exactly: 160, 320, or 480, then images will be scaled up or down to the other densities accordingly. |
6.8.2. Multi-Images vs regular images
By default all images are imported as multi-images (unless you define the defaultSourceDPIInt theme constant). If you want to import an image as a "regular" image, you can set cn1-source-dpi to 0. For example:
SomeStyle {
background-image: url(images/my-image.png);
cn1-source-dpi: 0;
}You can change the default source DPI for the whole stylesheet by adding Most application templates in Codename One Initializr include this constant by default. |
6.8.3. Multi-Images as inputs
If you’ve already generated images in all the appropriate sizes for all densities, you can provide them in the same file structure used by the Codename One XML resource files: The image path is a directory that contains images named after the density that they’re intended to be used for. The possible names include:
verylow.pnglow.pngmedium.pnghigh.pngveryhigh.png560.pnghd.png2hd.png4k.png
For example, Given the CSS directives:
MyStyle {
background-image: url(images/mymultiimage.png);
}The files would look like:
css/
+--- mycssfile.css
+--- images/
+--- mymultiimage.png/
+--- verylow.png
+--- low.png
+--- medium.png
... etc.Multi-image inputs are supported for local URLs. You can’t use remote (for example, http://) urls with multi-image inputs |
6.8.4. Image constants
Theme constants can be images. The convention is to suffix the constant name with "Image" so that it will be treated as an image. Also to the standard url() notation for specifying a constant image, you can provide a simple string name of the image, and the CSS processor will try to find an image by that name specified as a background image for one of the styles. If it can’t find one, it will look inside a special directory named "res" (located in the same directory as the CSS stylesheet), inside which it will look for a directory named the same as the stylesheet, inside which it will look for a directory with the specified multi-image. This directory structure is the same as used for Codename One’s XML resources directory.
For example, In the CSS file "mycssfile.css":
radioSelectedFocusImage: "Radio_btn_Press.png";
Will look for a directory located at res/mycssfile.css/Radio_btn_Press.png/ with the following images:
verylow.pnglow.pngmedium.pnghigh.pngveryhigh.png560.pnghd.png2hd.png4k.png
It will then create a multi-image from these images and include them in the resource file.
6.9. Image recipes
6.9.1. Import multiple images in single selector
It’s quite useful to be able to embed images inside the resource file that’s generated from the CSS stylesheet so that you can access the images using the Resources.getImage() method in your app and set it as an icon on a button or label. In this case, it’s easier to create a dummy style that you don’t intend to use and include multiple images in the background-image property like so:
Images {
background-image: url(images/NowLogo.png),
url(images/Username-icon.png),
url(images/Password-icon.png),
url(images/Name-icon.png),
url(images/Email-icon.png),
url(images/SeaIce.png),
url(images/Back-icon.png),
url(images/Source-icon.png),
url(images/Date-icon.png),
url(images/Arrow-right.png),
url(images/Share-icon.png),
url(images/Text-icon.png),
url(images/Comments-icon.png),
url(images/RedPlanet.png),
url(images/News-icon.png),
url(images/Channels-icon.png),
url(images/Bookmarks-icon.png),
url(images/Overview-icon.png),
url(images/Calendar-icon.png),
url(images/Timeline-icon.png),
url(images/Profile-icon.png),
url(images/Widgets-icon.png),
url(images/Settings-icon.png),
url(images/Bookmark-icon.png);
}Then in Java, you might do something like:
Resources theme = Resources.openLayered("/theme");
Label bookmark = new Label(theme.getImage("Bookmark-icon.png"));6.9.2. Loading images from URLs
You can also load images from remote URLs. The compiled guide fixture uses a local asset so the build is deterministic and doesn’t depend on network access; application CSS can use the same url(…) syntax with an HTTPS URL:
ImagesRemote {
background-image: url(images/remote-logo.png);
}6.9.3. Generating 9-Piece Image borders

9-Piece image borders can be created using the image-border and image-border-slice properties.
For example:
NinePiece {
border-image: url(images/dashbg_landscape.png);
}In the above example you omitted the border-image-slice property, so it defaults to "40%," which means that the image is sliced 40% from the top, 40% from the bottom, 40% from the left, and 40% from the right.
If you want more specific "slice" points, you can add the border-image-slice property. For example:
NinePiece {
border-image: url(images/dashbg_landscape.png);
border-image-slice: 10% 49%;
}
NinePiece2 {
border-image: url(images/dashbg_landscape.png);
border-image-slice: 10% 49% 20%;
}
NinePiece3 {
border-image: url(images/dashbg_landscape.png);
border-image-slice: 10% 30% 40% 20%;
}
NinePiece4 {
border-image: url(images/dashbg_landscape.png);
border-image-slice: 10%;
}6.9.4. Image backgrounds
Component backgrounds in Codename One are a common source of confusion for newcomers because there are 3 different properties that can be used to define what a component’s background looks like, and they have priorities:
Background Color - You can specify an RGB color to be used as the background for a component.
Background Image - You can specify an image to be used as the background for a component. Codename One includes settings to define how the image is treated, for example, scale/fill, tile, etc. If a background image is specified, it will override the background color setting - unless the image has transparent regions.
Image Border - You can define a 9-piece image border which will effectively cover the entire background of the component. If an image border is specified, it will override the background image of the component.
A common scenario you may run into is trying to set the background color of a component and seeing no change when you preview the form, because the style had an image background defined - which overrides the background color change.
The potential for confusion is mitigated somewhat, but still exists when using CSS. You can make your intentions explicit by adding the cn1-background-type property to your style. Possible values include:
cn1-image-scaledcn1-image-scaled-fillcn1-image-scaled-fitcn1-image-tile-bothcn1-image-tile-valign-leftcn1-image-tile-valign-centercn1-image-tile-valign-rightcn1-image-tile-halign-topcn1-image-tile-halign-centercn1-image-tile-halign-bottomcn1-image-align-bottomcn1-image-align-leftcn1-image-align-rightcn1-image-align-centercn1-image-align-top-leftcn1-image-align-top-rightcn1-image-align-bottom-leftcn1-image-align-bottom-rightcn1-image-bordercn1-nonenone
Example setting background Image to scale fill
MyContainer {
background-image: url(images/myimage.png);
cn1-background-type: cn1-image-scaled-fill;
}6.10. Image compression
CN1 resource files support both PNG and JPEG images, but PNG is the default. Multi-images that are generated by the CSS compiler will be PNG if they include alpha transparency, and JPEG otherwise. This is to try to reduce the file size as much as possible while not sacrificing quality.
6.11. Fonts
This library supports the font, font-size, font-family, font-style, font-weight, and text-decoration properties, as well as the @font-face CSS "at" rule for including TrueType and OpenType fonts.
6.11.1. font-family
By default, CN1’s native fonts are used. The appropriate native font is selected for the provided font-weight and font-style properties. You can also explicitly specify the native font you wish to use in the font-family property. For example:
SideCommand {
font-family: "native:MainThin";
}If you omit the font-family directive altogether, it will use native:MainRegular. The following native fonts are available:
native:MainThinnative:MainLightnative:MainRegularnative:MainBoldnative:MainBlacknative:ItalicThinnative:ItalicLightnative:ItalicRegularnative:ItalicBoldnative:ItalicBlack
Using bundled fonts
If you want to use a font other than the built-in fonts, you’ll need to define the font using the @font-face rule. For example:
@font-face {
font-family: "GuideDemoFont";
src: url(res/GuideDemoFont-Regular.ttf);
}Both TrueType (.ttf) and OpenType (.otf) files work, upper-case or lower-case. Every platform loads both formats through its own font API, so an OpenType font needs no conversion before you bundle it. Web-only formats such as .woff aren’t supported, and the CSS compiler fails the build on one rather than letting it reach the device.
| The compiler reads each font at build time, so a file it can’t parse, or one with no PostScript name, fails the build. That second case is worth knowing about: iOS resolves fonts by their PostScript name, so a font without one renders everywhere except on an iOS device. |
Then you’ll be able to reference the font using the specified font-family in any CSS element. For example:
MyLabel {
font-family: "GuideDemoFont";
}Where to put the font file
A relative src URL is resolved against the directory that holds the CSS file. You can keep font files directly beside theme.css, or in any subdirectory of it, whichever you prefer:
@font-face {
font-family: "GuideRootFont";
src: url(GuideRootFont.ttf);
}
@font-face {
font-family: "GuideDemoFont Bold";
src: url(res/GuideDemoFont-Bold.ttf);
}The font does have to live somewhere under that directory, because only that directory is copied into the build. A font reached through ../, or one that doesn’t exist, fails the build rather than producing an app whose text falls back to the system font. Two @font-face rules naming different files that share a file name also fail, since fonts are deployed by file name alone and one would overwrite the other. Pointing two families at the same file is fine.
Family names, weights and styles
A font-family name that contains spaces must be quoted, both in the @font-face rule and wherever you reference it. An unquoted name is parsed as a list of separate identifiers, so font-family: GuideDemoFont Bold registers the family as GuideDemoFont and collides with your regular weight.
font-weight and font-style select between the built-in native: fonts, but they have no effect once font-family resolves to a @font-face rule. Declare one @font-face per weight and style you need, each with its own family name, as in the example above, then reference the right family from each UIID.
To change the base font of an entire theme, set font-family on the special Default selector, then override the UIIDs that need a bold or italic face:
Default {
font-family: "GuideRootFont";
}
Title {
font-family: "GuideDemoFont Bold";
}Remote and GitHub-hosted fonts
The @font-face directive’s src property will accept both local and remote URLs. The guide fixture below uses a local font so the demo build remains offline and repeatable; application CSS can replace the URL with an HTTPS font URL:
@font-face {
font-family: "GuideDownloadedFont";
src: url(res/GuideDemoFont-Regular.ttf);
}In this case, it will download the myfont.ttf file into the build directory alongside the merged CSS file, and reuse that copy on later builds so that it doesn’t have to make a network request every time. A mvn clean discards the cache and the next build downloads the font again.
Fonts are automatically copied next to the compiled theme.res when the CSS file is compiled, so that they’re distributed with the app and available at runtime. The copy uses the font’s file name only, which means two @font-face rules that point at identically named files in different directories will collide. The copy is also skipped when a file of that name is already there, so run mvn clean after you replace a font file with a different one of the same name.
GitHub URLs
Fonts hosted on GitHub are accessible using a special github: protocol to make it easier to reference such fonts. The compiled guide fixture uses a bundled icon font for offline validation; application CSS can use the same rule shape with a github: URL.
@font-face {
font-family: "GuideIconFont";
src: url(res/GuideIconFont.ttf);
}| If a third-party font repository moves or changes licensing, vendor the font into your project and reference it locally so builds stay reproducible. |
6.11.2. font-size
It’s best practice to size your fonts using millimetres (rem) (or another "real-world" measurement unit such as inches (in), centimetres (cm), millimetres (mm). This will allow the font to be sized appropriate for all display densities. If you specify size in pixels (px), it will treat it the same as if you sized it in points (pt), where 1pt == 1/72 inches (one seventy-second of an inch).
If you size your font in percentage units (for example, 150%) it will set the font size relative to the medium font size of the platform. This is different than the standard behaviour of a web browser, which would size it relative to the parent element’s font size.
font-size: 150% is the same as font-size: 1.5rem. |
You can use system fonts, true type fonts, and native fonts in your CSS stylesheet. True Type fonts need to be defined in a @font-face directive before they can be referenced. True-type fonts and native fonts have the advantage that you can specify their sizes in generic terms (for example, small, medium, large) and in more specific units such as millimeters (mm) or pixels (px).
6.11.3. text-decoration
See the text-decoration section in the "Supported Properties" page.
6.11.4. Some sample CSS directives
@font-face {
font-family: "GuideDemoFont";
src: url(res/GuideDemoFont-Regular.ttf);
}
@font-face {
font-family: "GuideDemoFont-Bold";
src: url(res/GuideDemoFont-Bold.ttf);
}
PlainText0p5mm { font-size: 0.5mm; }
PlainText1mm { font-size: 1mm; }
PlainText2mm { font-size: 2mm; }
PlainText5mm { font-size: 5mm; }
PlainText10mm { font-size: 10mm; }
PlainText50mm { font-size: 50mm; }
PlainTextSmall { font-size: small; }
PlainTextMedium { font-size: medium; }
PlainTextLarge { font-size: large; }
PlainText3pt { font-size: 3pt; }
PlainText6pt { font-size: 6pt; }
PlainText12pt { font-size: 12pt; }
PlainText20pt { font-size: 20pt; }
PlainText36pt { font-size: 36pt; }
BoldText { font-weight: bold; }
BoldText1mm { font-weight: bold; font-size: 1mm; }
BoldText2mm { font-weight: bold; font-size: 2mm; }
BoldText3mm { font-weight: bold; font-size: 3mm; }
BoldText5mm { font-weight: bold; font-size: 5mm; }
ItalicText { font-style: italic; }
ItalicText3mm { font-style: italic; font-size: 3mm; }
ItalicBoldText { font-style: italic; font-weight: bold; }
PlainTextUnderline { text-decoration: underline; }
BoldTextUnderline { text-decoration: underline; font-weight: bold; }
ItalicTextUnderline { text-decoration: underline; font-style: italic; }
PlainText3d {
text-decoration: cn1-3d;
color: white;
background-color: #3399ff;
}
BoldText3d {
text-decoration: cn1-3d;
font-weight: bold;
color: white;
background-color: #3399ff;
}
ItalicText3d {
text-decoration: cn1-3d;
font-style: italic;
color: white;
background-color: #3399ff;
}
PlainText3dLowered {
text-decoration: cn1-3d-lowered;
color: black;
background-color: #3399ff;
}
BoldText3dLowered {
text-decoration: cn1-3d-lowered;
font-weight: bold;
color: black;
background-color: #3399ff;
}
ItalicText3dLowered {
text-decoration: cn1-3d-lowered;
font-style: italic;
color: black;
background-color: #3399ff;
}
PlainText3dShadow {
text-decoration: cn1-3d-shadow-north;
color: white;
background-color: #3399ff;
}
BoldText3dShadow {
text-decoration: cn1-3d-shadow-north;
font-weight: bold;
color: white;
background-color: #3399ff;
}
ItalicText3dShadow {
text-decoration: cn1-3d-shadow-north;
font-style: italic;
color: white;
background-color: #3399ff;
}
MainThin {
font-size: 200%;
background: radial-gradient(circle at top left, yellow, blue 100%);
}
MainRegular0001 {
font-family: "native:MainRegular";
color: blue;
border: 1px cn1-pill-border blue;
padding: 2mm;
}
MainRegular0001.pressed {
font-family: "native:MainRegular";
background: cn1-pill-border blue;
color: white;
border: 1px solid white;
padding: 2mm;
}
Heading {
font-size: 4mm;
font-family: "GuideDemoFont-Bold";
color: black;
padding: 2mm;
text-align: center;
}6.12. Media queries
You can use media queries to target styles to specific platforms, devices, and device densities. The following media queries are supported:
platform-xxx- Target a specific platform. For example,platform-and,platform-ios,platform-mac,platform-win.density-xxx- Target a specific device density. For example,density—low,density-low,density-medium,density-high,density—high,density-hd,density-2hd, anddensity-560.device-xxx- Target a specific device type. For example,device-desktop,device-tablet,device-phone,device-tv(Apple TV / Android TV), anddevice-watch(Apple Watch / Wear OS). Thedevice-tvanddevice-watchvariants are selected at runtime whenDisplay.isTV()/Display.isWatch()returnstrue, letting you adapt styling for the 10-foot TV UI or the small wearable screen.
Also to the Codename One specific media tokens above, the CSS compilers also recognize standard dark-mode media queries using prefers-color-scheme: dark. Rules inside these blocks are compiled into $Dark UIIDs automatically (for example, Button becomes $DarkButton, Button.selected becomes $DarkButton.selected).
Button {
color: #222222;
}
@media (prefers-color-scheme: dark) {
Button {
color: #f0f0f0;
background-color: #000000;
}
Button.selected {
color: #ff0000;
}
}Label {
color: black;
}
@media platform-and {
Label {
color: green;
}
}
@media platform-ios {
Label {
color: red;
}
}Label {
color: black;
}
@media density-very-low, density-low, density-medium, density-high {
Label {
color: green;
}
}
@media density-very-high, density-h2, density-2hd, density-560 {
Label {
color: red;
}
}Label {
color: black;
}
@media device-desktop {
Label {
color: green;
}
}
@media device-tablet, device-phone {
Label {
color: red;
}
}When deploying your app using the JavaScript port, it will use a platform name derived from the "UserAgent" string in the browser, rather than the result of Display.getPlatformName(), which is used for other ports. When running on Android, then, the platform will be "and." When running on iOS, the platform will be "ios." Etc. |
6.12.1. Compound media queries
You can combine multiple media queries together, separated by a comma. Queries of the same type are "OR"ed together. Queries of different types are "AND"ed together. For example if you have a media query that specifies two different device densities (for example, density-low and density-high) the query will match both devices with low density and high density. But, if the query specifies a device density and a platform (for example, density-low and platform-and), then it will match a device if it matches the platform and the density.
@media platform-and, density-high {
Label {
color: green;
}
}@media platform-ios, density-high, density-low {
Label {
color: red;
}
}@media device-desktop, platform-mac {
Label {
color: blue;
}
}6.12.2. Order or precedence
The order of precedence when applying styles differs slightly from the way styles would be applied in standard CSS. The order of precedence is as follows:
Styles defined inside
@mediablocks will always take precedence over styles defined outside of@mediablocks.@mediablocks with more query matches will take precedence over blocks with fewer query matches. For example, A media block matching density, platform, and device will take precedence over a block that only matches the density and platform.If the same style is defined in two media blocks which contain the same number of query matches, then the order precedence is
platform,device,densityin decreasing order. That is, the block that matches on platform will take precedence over the block that matches on density.If the same style is defined in two media blocks with identical query matches, then the order of precedence is undefined.
6.12.3. Font scaling constants
Sometimes you may find that fonts are coming out too large or too small across the board on certain types of devices. You can use standard media queries to customize font sizes, but you can also use font-scaling constants to scale font sizes for the entire stylesheet based on platform, device, and/or density. Sometimes you may find this approach easier.
For example, consider the following simple stylesheet that defines a font size of 2mm on labels:
Label {
font-size: 3mm;
}During testing, perhaps you find that, on desktop, the fonts are a little bit too small. In this case, you can apply a font-scale constant that only applies to the desktop:
#Constants {
device-desktop-font-scale: "1.5";
}
Label {
font-size: 3mm;
}Now, on most devices the Label style will have 3mm fonts. However, on desktop, it will have 4.5mm fonts.
The above would be equivalent to:
Label {
font-size: 3mm;
}
@media device-desktop {
Label {
font-size: 4.5mm;
}
}#Constants {
device-phone-font-scale: "1.5";
device-tablet-font-scale: "1.2";
device-desktop-font-scale: "1.4";
platform-ios-font-scale: "0.9";
density-low-font-scale: "1.2";
platform-ios-density-low-font-scale: "1.3";
}All matching font-scale constants will be applied to the styles. If you define 3 font-scale constants that all match the current runtime environment, they will all be applied. For example, If there are 3 matching font-scale constants with 2.0, 3.0, and 4.0, then fonts will be scaled by 2*3*4=24! |
7. The components of Codename One
This chapter covers the components of Codename One. It doesn’t cover every component, but it goes deeper than the Javadocs.
7.1. Container
The Codename One container is a base class for many high-level components. A container can hold other components.
Every component has a parent container. That parent can be null when the component isn’t inside another container or when it’s a top-level container. A container can have many children.

Components are arranged in containers with layout managers. A layout manager decides how to arrange components inside the container.
You can read more about layout managers in the basics section.
7.1.1. Composite components
Codename One components share a generic inheritance hierarchy. For example, Button derives from Label and thus receives all its abilities.
Some components are composites and derive from the Container class. For example, the MultiButton is a composite button that derives from Container but behaves like a Button. Most of the time this feels seamless, but a few details matter.
Don’t use the
Container-derived methods on such a composite component (for example,addandremove).You can’t cast it to the type it relates to. For example, you can’t cast
MultiButtontoButton.Events can be more nuanced. For example, if you rely on ActionEvent.getSource() or ActionEvent.getComponent(), they may not behave as expected. For a
MultiButton, they return the underlyingButton. To work around that, use ActionEvent.getActualComponent().
7.2. Form
Form is the top-level container in Codename One. Form derives from Container and is the element the app shows. Only one form can be visible at any given time. You can get the visible Form with the code:
Form currentForm = Display.getInstance().getCurrent();A form is a container with a title, a content area, and an optional menu or menu-bar area. When you call methods such as add or remove on a form, you’re invoking something that maps to this:
Form is effectively a Container with a border layout. The north section holds the title area, the south section holds the optional menu bar, and the center stretches as the content pane. Place all components in the content pane.

You can see that every Form has space allocated for the title area. If you don’t set the title, it won’t show up, but it will still be there. The same isn’t always true for the menu bar, which can vary. Effectively, the section that matters is the content pane, so the form tries to do the right thing by pretending to be the content pane. For example, this isn’t always seamless, and sometimes code needs to invoke getContentPane() to work directly with the container.
A good example for such a case is layout animations. Animating the form might not produce the right results. When in doubt, it’s easier to use getContentPane() instead of working with the Form directly. |
As you can see from the graphic, Form has two layers that live on top of the content pane/title. The first is the layered pane, which allows you to place "always on top" components. The layered pane is added implicitly when you invoke getLayeredPane().
| You still need to place components using layout managers to get them to appear in the right place when using the layered pane. |
7.2.1. Safe areas
Modern phones often include display cut-outs, rounded corners, or persistent gesture/navigation indicators that overlap the physical screen edges. These intrusions are no longer limited to iOS—many recent Android devices behave the same way—so Codename One provides a "safe area" API to ensure your UI remains visible regardless of the device. The safe area is the portion of the display that’s guaranteed to be unobstructed.


Automatic Safe-Area handling
Form calculates the safe region automatically, and core UI components that anchor themselves to the screen edges apply that information without more work:
Toolbarand the status bar placeholder respect the top safe margins so that titles and action buttons remain legible around notches.Tabs,Sheet, andFloatingActionButtoninstances mark their internal containers as safe areas so navigation controls are padded above gesture/navigation bars.UI fragment templates can opt-in to safe areas declaratively using the
safeAreaflag, ensuring generated components stay within the padded region.
This means that many applications will work on devices such as the iPhone X/14 family or Android devices with edge-to-edge displays. You need to intervene when you use custom containers that you position flush against a screen edge or when you perform your own painting.
Marking your own containers as safe
If you create a container that should always stay clear of the unsafe portions of the screen (for example, a bottom navigation bar, an on-screen joystick, or a floating tool palette), enable safe-area padding explicitly:
Form form = new Form(new BorderLayout());
Container bottomBar = new Container(BoxLayout.x());
bottomBar.setSafeArea(true);
bottomBar.addAll(new Button("Home"), new Button("Search"), new Button("Profile"));
form.add(BorderLayout.SOUTH, bottomBar);
form.show();Safe-area padding is applied when the container doesn’t have a scrollable parent. For scrollable content, you can assume the user can scroll the component into view instead.
Most layouts never need to know where the safe area begins, but if you draw manually (for example, inside paint() or on the glass pane) you can query it directly:
Form form = Display.getInstance().getCurrent();
Rectangle safe = form.getSafeArea();
Graphics g = null; // e.g. inside paint()
g.setClip(safe.getX(), safe.getY(), safe.getWidth(), safe.getHeight());
// Custom drawing code that should avoid the notch/gesture areasThe rectangle returned by Form#getSafeArea() is updated automatically whenever the OS reports a change (rotation, multitasking gestures, showing or hiding the system navigation area, etc.). In unusual situations where you adjust the safe-area root yourself (for example, when animating a container in from off-screen) you can force a recalculation by calling Form#setSafeAreaChanged().
Safe-Area roots and advanced layouts
Safe-area padding is calculated relative to a "safe-area root." Forms are roots by default, but you can mark any container as a root using Container#setSafeAreaRoot(true) when you need precise control, for example, when preparing a side menu that starts off-screen and slides in:
Container drawer = new Container(BoxLayout.y());
drawer.setSafeAreaRoot(true); // Ensure safe margins apply before the drawer is visible
drawer.setSafeArea(true);Marking the drawer as both a root and a safe area prevents a jump the moment it becomes visible, because the safe padding is already applied while it’s off-screen.
Remember that safe areas apply across platforms. Always verify your screens on actual devices (or in the Codename One simulator with a device skin that exposes cut-outs) to make sure critical UI elements remain inside the padded region.
The second layer is the glass pane which allows you to draw arbitrary things on top of everything. The order in the image is indeed right:
ContentPaneis lowestLayeredPaneis secondGlassPaneis painted last
It’s important to notice that a layered pane is on top of the ContentPane and doesn’t stretch to the title. A GlassPane stretches all the way but with a "lightweight" title area, for example, the Toolbar API. |
The GlassPane allows developers to overlay UI on top of existing UI and paint as they see fit. This is useful for things that provide notification but don’t want to intrude with application functionality.
7.3. Dialog
A Dialog is a special kind of Form that can occupy a portion of the screen. It also has the more functionality of the modal show method.
When showing a dialog you have two basic options: modeless and modal:
Modal dialogs (the default) block the current EDT thread until the dialog is dismissed. To understand how they do it, read about
invokeAndBlock.
Modal dialogs are a useful way to prompt the user since the code can assume the user responded in the next line of execution. This promotes a linear and intuitive way of writing code.Modeless dialogs return, so a call to show such a dialog can’t assume anything in the next line of execution. This is useful for features such as progress indicators where you aren’t waiting for user input.
For example: a modal dialog can be expressed as such:
if(Dialog.show("Click Yes Or No", "Select one", "Yes", "No")) {
// user clicked yes
} else {
// user clicked no
}Notice that during the show call above the execution of the next line was "paused" until you got a response from the user and once the response was returned you could proceed directly.
All usage of Dialog must be within the Event Dispatch Thread (the default thread of Codename One). This is true for modal dialogs. The Dialog class knows how to "block the EDT" without blocking it. |
To learn more about invokeAndBlock which is the workhorse behind the modal dialog functionality check out the EDT section.
The Dialog class contains many static helper methods to show user notifications, but also allows a
developer to create a Dialog instance, add information to its content pane and show the dialog.
Dialogs contain a ContentPane like Form. |
When showing a dialog in this way, you can either ask Codename One to position the dialog in a specific location based on the BorderLayout concept of locations, or position it by spacing it in pixels from the four edges of the screen.
For example: you could do something like this to show a simple modal Dialog:
Dialog d = new Dialog("Title");
d.setLayout(new BorderLayout());
d.add(BorderLayout.CENTER, new SpanLabel("Dialog Body", "DialogBody"));
d.showPacked(BorderLayout.SOUTH, true);
You can turn the code above to a modless Dialog by flipping the boolean true argument to false. |
You can position a Dialog by determining the space from the edges for example: with this code you can occupy the bottom portion of the screen:
Dialog d = new Dialog("Title");
d.setLayout(new BorderLayout());
d.add(BorderLayout.CENTER, new SpanLabel("Dialog Body", "DialogBody"));
d.show(hi.getHeight() / 2, 0, 0, 0);
hi is the name of the parent Form in the sample above. |
7.3.1. Styling dialogs
It’s important to style a Dialog using getDialogStyle() or
setDialogUIID methods rather than styling the dialog object directly.
The reason for this is that the Dialog is a Form that takes up the whole screen. The Form that’s visible behind the Dialog is rendered as a screenshot. Customizing the actual UIID of the Dialog won’t produce the desired results.
7.3.2. Tint and blurring
By default a Dialog uses a platform specific tint color when it’s showing for example: notice the background in the image below is tinted:
Form hi = new Form("Tint Dialog", new BoxLayout(BoxLayout.Y_AXIS));
Button showDialog = new Button("Tint");
showDialog.addActionListener((e) -> Dialog.show("Tint", "Is On/* omitted */", "OK", null));
hi.add(showDialog);
hi.show();
The tint color can be manipulated on the parent form, you can set it to any AARRGGBB value to set any color using the setTintColor method. Notice that this is invoked on the parent form and not on the Dialog!
| This is an AARRGGBB value and not an RRGGBB value! This means that 0 will be transparent. |
You can also manipulate this default value globally using the theme constant tintColor. The sample below tints the background in green:
Form hi = new Form("Tint Dialog", new BoxLayout(BoxLayout.Y_AXIS));
hi.setTintColor(0x7700ff00);
Button showDialog = new Button("Tint");
showDialog.addActionListener((e) -> Dialog.show("Tint", "Is On/* omitted */", "OK", null));
hi.add(showDialog);
hi.show();
You can apply Gaussian blur to the background of a dialog to highlight the foreground further and produce an attractive effect. You can use the setDefaultBlurBackgroundRadius to apply this globally, you can use the theme constant dialogBlurRadiusInt to do the same or you can do this on a per Dialog basis using setBlurBackgroundRadius.
Not all device types support blur you can test if your device supports it using Display.getInstnace().isGaussianBlurSupported(). If blur isn’t supported the blur setting will be ignored: |
Form hi = new Form("Blur Dialog", new BoxLayout(BoxLayout.Y_AXIS));
Dialog.setDefaultBlurBackgroundRadius(8);
Button showDialog = new Button("Blur");
showDialog.addActionListener((e) -> Dialog.show("Blur", "Is On/* omitted */", "OK", null));
hi.add(showDialog);
hi.show();
It might be a bit hard to notice the blur effect with the tinting so here is the same code with tinting disabled:
hi.setTintColor(0);
7.3.3. Popup dialog
A popup dialog is a common mobile paradigm showing a Dialog that points at a specific component. It’s a standard Dialog that’s shown in a unique way:

Styling the arrow of the popup dialog
When Codename One was young you needed a popup arrow implementation but your low-level graphics API was pretty basic. As a workaround you created a version of the 9-piece image border that supported pointing arrows at a component.
Today Codename One supports pointing an arrow from the RoundRectBorder class. This is implicit for the PopupDialog UI. This allows for better customization of the border (color etc.) and it looks better on newer displays. It also works on all OSs. Right now the iOS theme has the old image border approach.
| This will change with a future update where all OSes will align and iOS will use the lightweight popup too |
You can make all OSes act the same way by overriding the PopupDialog UIID and defining its style to RoundRectBorder |
The new RoundRectBorder support works by setting the track component property on border. When that’s done the border implicitly points to the right location.
If you still need deeper customization of the arrow you can still use the old 9-piece border functionality illustrated below.
Legacy 9-Piece Border arrow
One of the harder aspects of a popup dialog is the construction of the theme elements required for arrow styling. To get that sort of behavior you will need a custom image border and 4 arrows pointing in each direction that will be overlaid with the border.
The sizes of the arrow images should be similarly proportioned and fit within the image borders whitespace.
The block image of the dialog should have empty pixels in the sides to reserve space for the arrow. For example: if the arrows are all 32×32 pixels then the PopupDialog image should have 32 pixels of transparent pixels around it. |
You will need to define the following theme constants for the arrow to work:
Then style the PopupDialog UIID with the image for the Dialog itself.
7.4. InteractionDialog
Dialogs in Codename One can be modal or modeless, the former blocks the calling thread and the latter doesn’t. For example, there is another definition to those terms: A modal dialog blocks access to the rest of the UI while a modeless dialog "floats" on top of the UI.
In that sense, all dialogs in Codename One are modal; they block the parent form since they’re effectively forms that show the "parent" in their background. InteractionDialog has an API that’s like the Dialog API but, unlike dialog, it never blocks anything. Neither the calling thread nor the UI.
InteractionDialog isn’t a Dialog since it doesn’t share the same inheritance hierarchy. For example, it acts and "feels" like a Dialog although it’s a Container in the LayeredPane. |
InteractionDialog is a container that’s positioned within the layered pane. Notice that because of that
design, you can have one such dialog at the moment and, if you add something else to the layered pane, you
might run into trouble.
Using the interaction dialog is pretty trivial and like dialog:
InteractionDialog dlg = new InteractionDialog("Hello");
dlg.setLayout(new BorderLayout());
dlg.add(BorderLayout.CENTER, new Label("Hello Dialog"));
Button close = new Button("Close");
close.addActionListener((ee) -> dlg.dispose());
dlg.addComponent(BorderLayout.SOUTH, close);
Dimension pre = dlg.getContentPane().getPreferredSize();
int displayWidth = Display.getInstance().getDisplayWidth();
int dialogWidth = Math.max(pre.getWidth() + pre.getWidth() / 6, displayWidth * 2 / 3);
dlg.show(0, 0, displayWidth - dialogWidth, 0);
This will show the dialog on the right-hand side of the screen, which is pretty useful for a floating in place dialog.
The InteractionDialog can be shown at absolute or popup locations. This is inherent to its use case which is "non-blocking." When using this component you need to be aware of its location. |
To make popup behavior feel natural on touch devices you can call setDisposeWhenPointerOutOfBounds(true) so the dialog automatically dismisses as soon as the user taps outside the title or content area. Internally the dialog listens for pointer pressed/released events and will call dispose() for you when the interaction happens beyond its bounds, so you no longer need to wire that logic manually.
By default the dialog is placed on the form’s layered pane, but you can switch between the global layered pane and form-specific layered pane using setFormMode(boolean). Setting form mode to true keeps the dialog coupled with the showing form even when the global layered pane is used elsewhere in your app.
Finally, recent updates added animation toggles so you can fine-tune presentation. setAnimateShow(boolean) turns the show/dispose animations on or off, while setRepositionAnimation(boolean) enables a "grow/shrink" reposition effect during those animations when you want a more dynamic transition.
7.5. Label
Label represents a text, icon, or both. Label is also the base class of Button which in turn is the base class for RadioButton & CheckBox. Thus the functionality of the Label class extends to all these components.
Label text can be positioned in one of 4 locations as such:

Label allows a single line of text, line breaking is an expensive operation on mobile devices [1] and so the Label class doesn’t support it.
| SpanLabel supports many lines with a single label, notice that it does carry a performance penalty for this functionality. |
Labels support tickering and the ability to end with "…" if there isn’t enough space to render the label. Developers can determine the placement of the label to its icon in a few powerful ways.
7.5.1. Label gap
The gap between the label text & the icon defaults to 2 pixels due to legacy settings. The setGap method of Label accepts a gap size in pixels.
Two pixels is low for most cases & it’s hard to customize for each Label.
You can use the theme constant labelGap which is a floating point value you can specify in millimeters that will allow you to determine the default gap for a label. You can also customize this manually using the method Label.setDefaultGap(int) which determines the default gap in pixels.
7.5.2. Autosizing labels
One of the common requests you received over the years is a way to let text "fit" into the allocated space so the font will match almost the width available. In some designs this is important but it’s also tricky. Measuring the width of a String is an expensive operation on some OSes., there is no other way other than trial & error to find the "best size."
Still although something is "slow" you might still want to use it for some cases, this isn’t something you should use in a renderer, infinite scroll etc. and recommend minimizing the usage of this feature as much as possible.
This feature is applicable to Label and its subclasses (for example: Button), with components such as TextArea (for example: SpanButton) the choice between shrinking and line break would require some complex logic.
To activate this feature use setAutoSizeMode(true) for example:
Form hi = new Form("AutoSize", BoxLayout.y());
Label a = new Label("Short Text");
a.setAutoSizeMode(true);
Label b = new Label("Much Longer Text than the previous linenull");
b.setAutoSizeMode(true);
Label c = new Label("MUCH MUCH MUCH Much Longer Text than the previous line by a pretty big marginnull");
c.setAutoSizeMode(true);
Label a1 = new Button("Short Text");
a1.setAutoSizeMode(true);
Label b1 = new Button("Much Longer Text than the previous linenull");
b1.setAutoSizeMode(true);
Label c1 = new Button("MUCH MUCH MUCH Much Longer Text than the previous line by a pretty big marginnull");
c1.setAutoSizeMode(true);
hi.addAll(a, b, c, a1, b1, c1);
hi.show();
7.6. TextField and TextArea
The TextField class derives from the TextArea class, and both are used for text input in Codename One.
TextArea defaults to multi-line input and TextField defaults to single line input but both can be used in both cases. The main differences between TextField and TextArea are:
Blinking cursor is rendered on
TextFieldDataChangeListener is available in
TextField. This is crucial for character by character input event trackingDone listener is available in the
TextFieldDifferent
UIID
The semantic difference between TextField & TextArea dates back to the ancestor of Codename One: LWUIT. Feature phones don’t have "proper" in-place editing capabilities & thus TextField was introduced to allow such input. |
Because it lacks the blinking cursor capability TextArea is often used as a multi-line label and is used internally in SpanLabel, SpanButton etc.
A common use case is to have an important text component in edit mode as you enter a Form. Codename One forms support this exact use case through the Form.setEditOnShow(TextArea) method. |
TextField & TextArea support constraints for various types of input such as NUMERIC, EMAIL, URL, etc. Those usually
affect the virtual keyboard used, but might not limit input in some platforms. For example: on iOS even with NUMERIC
constraint you would still be able to input characters.
| If you need to prevent specific types of input check out the validation section. |
The following sample shows off simple text field usage:

The Toolbar section contains an elaborate TextField search sample with DataChangeListener and rather unique styling. |
7.6.1. Masking
A common use case when working with text components is the ability to "mask" input for example: in the credit card number above you would want 4 digits for each text field and don’t want the user to tap Next 3 times.
Masking allows you to accept partial input in one field and implicitly move to the next, this can be used to all types of complex input thanks to the text component API. E.g with the code above you can mask the credit card input so the cursor jumps to the next field implicitly using this code:
Then implement the method automoveToNext as:
Notice you can invoke stopEditing(Runnable) where you receive a callback as editing is stopped.
7.6.2. The virtual keyboard
A common misconception for developers is assuming the virtual keyboard represents "keys." For example: developers often override the "keyEvent" callbacks which are invoked for physical keyboard typing and expect those to occur with a virtual keyboard.
This isn’t the case since a virtual keyboard is a different beast. With a virtual keyboard characters typed might produce a different output due to autocorrect. Some keyboards don’t even have "keys" in the traditional sense or don’t type them in the traditional sense (for example: swiping).
The constraint property for the TextField/TextArea is crucial for a virtual keyboard. |
When working with a virtual keyboard it’s important that the parent Container for the TextField/TextArea is scrollable. Otherwise the component won’t be reachable or the UI might be distorted when the keyboard appears. |
Action Button client property
By default, the virtual keyboard on Android has a "Done" button, you can customize it to be a search icon, a send icon, or a go icon using a hint such as this:
This will adapt the icon for the action on the keys.
Next and done on iOS
You try to hide a lot of the platform differences in Codename One, input is ** different between OSes. A common reliance is the ability to send the "Done" event when the user presses the Done button. This button doesn’t always exist for example: if there is an Enter button (due to multiline input) or if there is a Next button in that place.
To unify the behavior you slightly customized the iOS keyboard as such:


| This works with 3rd party keyboards too… |
For example, this behavior might not be desired so to block that you can do:
This will hide the toolbar for that given field.
You can customize the color of the Done button in the toolbar by setting the ios.doneButtonColor display property. For example: To change the color to red, you could do Display.getInstance().setProperty("ios.doneButtonColor", String.valueOf(0xff0000)). |
7.6.3. Clearable text field
iOS has a convention where an X can be placed after the text field to clear it. Some Android apps have it but there is no native support for that as of this writing.
You can wrap a TextField with a clearable wrapper to get this effect on all platforms. For example: replace this:
With this:
You can also specify the size of the clear icon if you wish. This is technically a Container with the text field style and a button to clear the text at the edge.
7.7. TextComponent
When building input forms you sometimes want to adapt to the native OS behavior and create a UI that’s a bit more distinct to the native OS. TextField and TextArea are low-level, you can create an Android style UI with such components but it might look out of place in iOS.
For example: this is how most of you would expect the UI to look on iOS and Android respectively:
Doing this with text fields is possible but would require code that looks a bit different and jumps through hoops. TextComponent allows this exact UI without forcing developers to write OS specific code:
TextModeLayout tl = new TextModeLayout(3, 2);
Form f = new Form("Pixel Perfect", tl);
TextComponent title = new TextComponent().label("Title");
TextComponent price = new TextComponent().label("Price");
TextComponent location = new TextComponent().label("Location");
TextComponent description = new TextComponent().label("Description").multiline(true);
f.add(tl.createConstraint().horizontalSpan(2), title);
f.add(tl.createConstraint().widthPercentage(30), price);
f.add(tl.createConstraint().widthPercentage(70), location);
f.add(tl.createConstraint().horizontalSpan(2), description);
f.setEditOnShow(title.getField());
f.show();This code uses the TextModeLayout which is discussed in the layouts section |
The text component uses a builder approach to set various values for example:
TextComponent t = new TextComponent().
text("This appears in the text field").
hint("This is the hint").
label("This is the label").
multiline(true);The code is pretty self-explanatory and more convenient than typical setters/getters. It automatically handles the floating hint style of animation when running on Android.
7.7.1. Error handling
The validator class supports text component and it should "work." But the cool thing is that it uses the material design convention for error handling!
If you add to the sample above a Validator:
You would see something that looks like this on Android:
The underlying system is the errorMessage method which you can chain like the other methods on TextComponent as such:
TextComponent tc = new TextComponent().
label("Input Required").
errorMessage("Input is essential in this field");7.7.2. InputComponent and PickerComponent
To keep the code common and generic you use the InputComponent abstract base class and derive the other classes from that. PickerComponent is the other option.
A picker can work with your existing sample using code like this:
This produces the following which looks pretty standard:
The one tiny thing you should notice with the PickerComponent is that you don’t construct the picker component using new PickerComponent(). Instead you use create methods such as PickerComponent.createDate(new Date()). The reason for that’s that you have many types of pickers and it wouldn’t make sense to have one constructor.
7.7.3. Underlying theme constants and UIID’s
These varying looks are implemented through a combination of layouts, theme constants and UIID’s. The most important UIID’s are: TextComponent, FloatingHint & TextHint.
There are many related theme constants that can manipulate some pieces of this functionality:
textComponentErrorColora hex RGB color which defaults to null in which case this has no effect. When defined this will change the color of the border and label to the given color to match the material design styling. This implements the red border underline in cases of error and the label text color changetextComponentErrorLineBorderBooltoggles the material-style underline that appears on validation errors. Set it tofalseif you prefer to supply a different border when errors are showntextComponentOnTopBooltoggles the on top mode which makes things look like they do on Android. This defaults to true on Android and false on other OSes. This can also be manipulated through theonTopMode(boolean)method inInputComponent, but the layout will use the theme constanttextComponentAnimBooltoggles the animation mode which again can be manipulated by a method inInputComponent. If you want to keep the UI static without the floating hint effect set this to false. Notice this defaults to true on AndroidtextComponentFieldUIIDsets the UIID of the text field to something other thanTextFieldthis is useful for platforms such as iOS where the look of the text field is different within the text component. This allows you to make the background of the text field transparent when it’s within theTextComponentand make it different from the regular text fieldinputComponentErrorMultilineBoolmakes error labels multi-line by default so longer validation messages can wrap instead of being clipped
7.8. Button
Button is a subclass of Label and as a result it inherits all its functionality, specifically icon placement, tickering, etc.
Button adds to the mix some more states such as a pressed UIID state and pressed icon.
Button supports more icon states such as rollover and disabled icon. |
Button also exposes some functionality for subclasses specifically the setToggle method call which has no meaning when invoked on a Button but has a lot of implications for CheckBox & RadioButton.
Button event handling can be performed through an ActionListener or through a Command.
Changes in a Command won’t be reflected into the Button after the command was set to the Button. |
Here is a trivial hello world style Button:
Form hi = new Form("Button");
Button b = new Button("My Button");
hi.add(b);
b.addActionListener((e) -> Log.p("Clicked"));
Such a button can be styled to look like a link using code like this or by making these settings in the theme and using code such as btn.setUIID("Hyperlink"):
Form hi = new Form("Button");
Button b = new Button("Link Button");
b.getAllStyles().setBorder(Border.createEmpty());
b.getAllStyles().setTextDecoration(Style.TEXT_DECORATION_UNDERLINE);
hi.add(b);
b.addActionListener((e) -> Log.p("Clicked"));
7.8.1. Uppercase buttons
Buttons on Android’s material design UI use upper case styling which isn’t the case for iOS. To solve this you have the method setCapsText(boolean) in Button which has the corresponding isCapsText, isCapsTextDefault & setCapsTextDefault(boolean). This is pretty core to Codename One so to prevent this from impacting everything unless you explicitly invoke setCapsText(boolean) the default value of true will apply when the UIID is Button, RaisedButton or for the built-in Dialog buttons.
You also have a theme constant: capsButtonTextBool. This constant controls caps text behavior from the theme and is set to true in the Android native theme.
7.8.2. Raised Button
Raised button is a style of button that’s available on Android and used to highlight an important action within a form. To confirm with the material design UI guidelines you might want to leverage a raised button UI element on Android but use a regular button everywhere else.
First you need to know whether a raised button exists in the theme. On Android this will return true but on other OSes it will return false. A potential future update might make another platform true based on UI guidelines in other OSes.
For this purpose you have got the theme constant hasRaisedButtonBool which will return true on Android but will be false elsewhere. You can use it like this:
if(UIManager.getInstance().isThemeConstant("hasRaisedButtonBool", false)) {
// that means we can use a raised button
}To enable this you have the RaisedButton UIID that derives from Button and will act like it except for the places where hasRaisedButtonBool is true in which case it will look like this:

Notice that you can customize the colors of these buttons now since the border respects user colors…
In this case set the background color to purple and the foreground to white:

Form f = new Form("Pixel Perfect", BoxLayout.y());
Button b = new Button("Raised Button", "RaisedButton");
Button r = new Button("Flat Button");
f.add(b);
f.add(r);
f.show();7.8.3. Ripple effect
The ripple effect in material design highlights the location of the finger and grows as a circle to occupy the full area of the component as the user presses the button.
You can perform a ripple effect by darkening the touched area and growing that in a quick animation.
Ripple effect can be applied to any component but you have it turned on for buttons on Android which also applies to things like title commands, side menu elements etc. This might not apply at this moment to lead components like multi-buttons but that might change in the future.
Component has a property to enable the ripple effect setRippleEffect(boolean) and the corresponding isRippleEffect(). You can turn it on or off individually in the component level. For example, Button has static setButtonRippleEffectDefault(boolean) and isButtonRippleEffectDefault(). These allow you to define the default behavior for all the buttons and that can be configured through the theme constant buttonRippleBool which is on by default on the native Android theme.
7.9. CheckBox/RadioButton
CheckBox & RadioButton are subclasses of button that allow for either a toggle state or exclusive selection state.
Both CheckBox & RadioButton have a selected state that allows you to determine their selection.
RadioButton doesn’t allow you to "deselect" it, the way to "deselect" a RadioButton is by selecting another RadioButton. |
The CheckBox can be added to a Container like any other Component but the RadioButton must be associated with a ButtonGroup otherwise if you have more than one set of RadioButton’s in the form you might have an issue.
Notice in the sample below that you associate all the radio buttons with a group but don’t do anything with the group as the radio buttons keep the reference internally. You also show the opposite side functionality and icon behavior:

Both of these components can be displayed as toggle buttons (see the toggle button section below), or use the default check mark/filled circle appearance based on the type/OS.
7.9.1. Toggle Button
A toggle button is a button that’s pressed and stays pressed. When a toggle button is pressed again it’s released from the pressed state. Hence the button has a selected state to show if it’s pressed or not like the CheckBox/RadioButton components in Codename One.
To turn any CheckBox or RadioButton to a toggle button use the setToggle(true) method. Or you can use the static createToggle method on both CheckBox and RadioButton to create a toggle button directly.
Invoking setToggle(true) implicitly converts the UIID to ToggleButton unless it was changed by the user from its original default value. |
You can convert the sample above to use toggle buttons as such:

That’s half the story though: to get the full effect of some cool toggle button UI’s you can use a ComponentGroup. This allows you to create a button bar effect with the toggle buttons.
For example, to enclose the CheckBox components in a vertical ComponentGroup and the RadioButton’s in a horizontal group, change the last line of the code above as such:

7.10. ComponentGroup
ComponentGroup is a special container that can be either horizontal or vertical (BoxLayout X_AXIS or Y_AXIS respectively).
ComponentGroup "restyles" the elements within the group to have a UIID that allows you to create a "round border" effect that groups elements together.
The following code adds 4 component groups to a Container to show the various UIID changes:
hi.add("Three Labels").
add(ComponentGroup.enclose(new Label("GroupElementFirst UIID"), new Label("GroupElement UIID"), new Label("GroupElementLast UIID"))).
add("One Label").
add(ComponentGroup.enclose(new Label("GroupElementOnly UIID"))).
add("Three Buttons").
add(ComponentGroup.enclose(new Button("ButtonGroupFirst UIID"), new Button("ButtonGroup UIID"), new Button("ButtonGroupLast UIID"))).
add("One Button").
add(ComponentGroup.enclose(new Button("ButtonGroupOnly UIID")));
Notice the following about the code above and the resulting image:
Buttons have a different UIID than other element types. Their styling is slightly different in such UI’s so you need to pay attention to that.
When an element is placed alone within a
ComponentGroupits a special caseUIID.
By default, ComponentGroup does nothing. You need to explicitly activate it in the theme by setting a theme property to true. Specifically you need to set ComponentGroupBool to true for ComponentGroup to do something otherwise its a box layout container! The ComponentGroupBool flag is true by default in the iOS native theme. |
When ComponentGroupBool is set to true, the component group will change the styles of all components placed within it to match the element UIID given to it (GroupElement by default) with special caveats to the first/last/ elements. For example:
With one element in a component group it will have the UIID:
GroupElementOnlyWith two elements in a component group they will have the UIID’s
GroupElementFirst,GroupElementLastWith three elements in a component group they will have the UIID’s
GroupElementFirst,GroupElement,GroupElementLastWith four elements in a component group they will have the UIID’s
GroupElementFirst,GroupElement,GroupElement,GroupElementLast
This allows you to define special styles for the edges.
You can customize the UIID set by the component group by calling setElementUIID in the component group for example: setElementUIID("ToggleButton") for three elements result in the following UIID’s:
ToggleButtonFirst, ToggleButton, ToggleButtonLast
7.11. MultiButton
MultiButton is a composite component (lead component) that acts like a versatile Button. It supports up to 4 lines of text (it doesn’t automatically wrap the text), an emblem (usually navigational arrow, or check box) and an icon.
MultiButton can be used as a button, a CheckBox or a RadioButton for creating rich UI’s.
The MultiButton was inspired by the aesthetics of the UITableView iOS component. |
A common source of confusion in the MultiButton is the difference between the icon and the emblem, since both may have an icon image associated with them. The icon is an image representing the entry while the emblem is an optional visual representation of the action that will be undertaken when the element is pressed. Both may be used simultaneously or individually of one another:

7.11.1. Styling the MultiButton
Since the MultiButton is a composite component setting its UIID will impact the top level UI.
To customize everything you need to customize the UIID’s for MultiLine1, MultiLine2, MultiLine3, MultiLine4 & Emblem.
You can customize the individual UIID’s through the API directly using the setIconUIID, setUIIDLine1, setUIIDLine2, setUIIDLine3, setUIIDLine4 & setEmblemUIID.
Recent versions also include a badge overlay that can be rendered in the corner of the main icon. Use setBadgeText() to display a value (for example a notification count) and setBadgeUIID() if you need a custom UIID instead of the default Badge styling. When you need to inspect or adjust the badge style programmatically, getBadgeStyleComponent() returns the component whose styles are applied to the badge so you can tweak padding, colors or borders before showing the MultiButton.
7.12. SpanButton
SpanButton is a composite component (lead component) that looks/acts like a Button but can break lines rather than crop them when the text is long.
Unlike the MultiButton it uses the TextArea internally to break lines seamlessly. The SpanButton is far simpler than the MultiButton and as a result isn’t as configurable:

SpanButton is slower than both Button and MultiButton. Recommend using it when there is a genuine need for its functionality. |
7.13. SpanLabel
SpanLabel is a composite component (lead component) that looks/acts like a Label but can break lines rather than crop them when the text is long.
SpanLabel uses the TextArea internally to break lines seamlessly and so doesn’t provide all the elaborate configuration options of Label.
One of the features of label that moved into SpanLabel to some extent is the ability to position the icon. For example, unlike a Label the icon position is determined by the layout manager of the composite so setIconPosition accepts a BorderLayout constraint:

SpanLabel is slower than Label. Recommend using it when there is a genuine need for its functionality. |
7.14. OnOffSwitch
The OnOffSwitch allows you to write an application where the user can swipe a switch between two states (on/off). This is a common UI paradigm in Android and iOS, although it’s implemented in a radically different way in both platforms.
This is a rather elaborate component because of its unique design on iOS, but you’re able to accommodate most of the small behaviors of the component into your version, and it seamlessly adapts between the Android style and the iOS style.
The image below was generated based on the default use of the OnOffSwitch:
OnOffSwitch onOff = new OnOffSwitch();
hi.add(onOff);
As you can understand the difference between the way iOS and Android render this component has triggered two different implementations within a single component. The Android implementation uses standard buttons and is the default for non-iOS platforms.
You can force the Android or iOS mode by using the theme constant onOffIOSModeBool. |
7.14.1. Validation
Validation is an inherent part of text input, and the Validator class allows that. You can enable validation
through the Validator class to add constraints for a specific component.
It’s also possible to define components that would be enabled/disabled based on validation state and the way in which validation errors are rendered (change the components UIID, paint an emblem on top, etc.). A Constraint is an interface
that represents validation requirements. You can define a constraint in Java or use some built-in
constraints such as LengthConstraint, RegexConstraint, etc.
This sample below continues from the place where the TextField sample above stopped by adding validation to that code:

When the form components are bound to a model with @Bindable, the
same constraints can be expressed as field annotations — @Required,
@Length, @Regex, @Email, @Url, @Numeric, @ExistIn,
@Validate — and the generated binder wires them into a Validator
exposed through Binding#getValidator(). See the
Validation annotations section in the
component binding chapter for the full reference.
7.15. InfiniteProgress
The InfiniteProgress indicator spins an image infinitely to show that a background process is still working.
| This style of animation is often nicknamed "washing machine" as it spins endlessly. |
InfiniteProgress can be used in one of two ways either by embedding the component into the UI through something like this:
InfiniteProgress can also appear over the entire screen, thus blocking all input. This tints the background while the infinite progress rotates:
Dialog ip = new InfiniteProgress().showInifiniteBlocking();
// do some long operation here using invokeAndBlock or do something in a separate thread and callback later
// when you are done just call
ip.dispose();
The image used in the InfiniteProgress animation is defined by the native theme. You can override that definition either by defining the theme constant infiniteImage or by invoking the setAnimation method.
Despite the name of the method setAnimation expects a static image that will be rotated internally. Don’t use an animated image. |
7.16. InfiniteScrollAdapter and InfiniteContainer
InfiniteScrollAdapter & InfiniteContainer allow you to create a scrolling effect that "never" ends with the typical Container/Component paradigm.
The motivation behind these classes is simple, say you have a lot of data to fetch from storage or from the internet. You can fetch the data in batches and show progress sign while you do this.
Infinite scroll fetches the next batch of data dynamically as you reach the end of the Container. InfiniteScrollAdapter & InfiniteContainer represent two similar ways to do that task.
Let start by exploring how you can achieve this UI that fetches data from a webservice:

The first step is creating the webservice call, you won’t go into too much detail here as webservices & IO are discussed later in the guide:
| The demo code here doesn’t do any error handling! This is a bad practice and it’s taken here to keep the code short and readable. Proper error handling is used in the Property Cross demo. |
The fetchPropertyData is a simplistic tool that fetches the next page of listings for the nestoria webservice. Notice that this method is synchronous and will block the calling thread (legally) until the network operation completes.
Now that you have a webservice lets proceed to create the UI. Check out the code annotations below:
| Don’t violate the EDT in the callback. It’s invoked on the event dispatch thread and it’s crucial |
7.16.1. The InfiniteContainer
InfiniteContainer was introduced to simplify and remove some boilerplate of the InfiniteScrollAdapter. It takes a more traditional approach of inheriting the Container class to provide its functionality.
Unlike the InfiniteScrollAdapter the InfiniteContainer accepts an index and amount to fetch. This is useful for tracking your position but also important since the InfiniteContainer also implements Pull To Refresh as part of its functionality.
Converting the code above to an InfiniteContainer is pretty simple you moved all the code into the callback fetchComponents method and returned the array of Component’s as a response.
Unlike the InfiniteScrollAdapter you can’t use the ContentPane directly so you’ve to use a BorderLayout and place the InfiniteContainer there:
7.17. List, MultiList, renderers & models
7.17.1. InfiniteContainer/InfiniteScrollAdapter vs. List/ContainerList
Your recommendation is to always go with Container, InfiniteContainer or InfiniteScrollAdapter.
Recommend avoiding List or its subclasses/related classes specifically ContainerList & MultiList.
Recommend replacing ComboBox with Picker but that’s a different discussion. |
A Container with ~5000 nested containers within it can perform on par with a List and probably exceed its performance when used.
Larger sets of data are manageable on phones or tablets so the benefits for lists are dubious.
In API you found that even experienced developers experienced a great deal of pain when wrangling the Swing styled lists and their stateless approach.
Since animation, swiping and other capabilities that are so common in mobile are so hard to do with lists you see no actual reason to use them.
7.17.2. Why isn’t list deprecated
You deprecated ContainerList which performs badly and has some inherent complexity issues. List has some unique use cases and is still used all over Codename One.
MultiList is a reasonable version of List that’s far easier to use without most of the pains related to renderer configuration.
Some cases justify using List or MultiList, but they’re rarer than usual, hence the recommendation.
7.17.3. MVC in lists
A Codename One List doesn’t contain components, but rather arbitrary data; this seems odd at first but makes sense. If you want a list to contain components, use a Container.
The advantage of using a List in this way is that you can display it in many ways (for example: fixed focus positions, horizontally, etc.), and that you can have more than a million entries without performance overhead. You can also do some pretty nifty things, like filtering the list on the fly or fetching it dynamically from the Internet as the user scrolls down the list.
To achieve these things the list uses two interfaces: ListModel and ListCellRenderer.
List model represents the data; its responsibility is to return the arbitrary object within the list at a given offset. Its second responsibility is to tell the list when the data changes, so the list can refresh.
| Think of the model as an array of objects that can tell you when it changes. |
The list renderer is like a rubber stamp that knows how to draw an object from the model, it’s called many times per entry in an animated list and must be fast. Unlike standard Codename One components, it’s used to draw the entry in the model and is discarded, hence it has no memory overhead, but if it takes too long to process a model value it can be a big bottleneck!
| Think of the render as a translation layer that takes the "data" from the model and translates it to a visual representation. |
This is all generic, but a bit too much for most, doing a list correctly requires some understanding. The main source of confusion for developers is the stateless nature of the list and the transfer of state to the model (for example: a checkbox list needs to listen to action events on the list and update the model, in order for the renderer to display that state). Once you understand that it’s easy.
7.17.4. Understanding MVC
A quick recap of what MVC is:
Model - Represents the data for the component (list), the model can tell you how many items are in it and which item resides at a given offset within the model. This differs from a simple
Vector(or array), since all access to the model is controlled (the interface is simpler), and unlike aVector/Array, the model can tell you of changes that occur within it.View - The view draws the content of the model. It’s a "dumb" layer that has no notion of what’s displayed and knows how to draw. It tracks changes in the model (the model sends events) and redraws itself when it changes.
Controller - The controller accepts user input and performs changes to the model, which in turn cause the view to refresh.

Codename One’s List component uses the MVC paradigm in its implementation. List itself is the Controller (with a bit of the View mixed in). The ListCellRenderer interface is the rest of the View and the ListModel is (you guessed it by now) the Model.
When the list is painted, it iterates over the visible elements in the model and asks the model for the data, it then draws them using the renderer. Notice that because of this both the model and the renderer must be fast and that’s hard.
Why is this useful
Since the model is a lightweight interface, it can be implemented by you and replaced in runtime if so desired, this allows many use cases:
A list can contain thousands of entries but load the portion visible to the user. Since the model will be queried for the elements that are visible to the user, it won’t need to load the large data set into memory until the user starts scrolling down (at which point other elements may be offloaded from memory).
A list can cache efficiently. For example: a list can mirror data from the server into local RAM without actually downloading all the data. Data can also be mirrored from storage for better performance and discarded for better memory use.
The is no need for state copying. Since renderers allow you to display any object type, the list model interface can be implemented by the application’s data structures (for example: persistence/network engine), which would return internal application data structures saving you the need of copying application state into a list specific data structure. Note that this advantage applies with a custom renderer which is pretty difficult to get right.
Using the proxy pattern you can layer logic such as filtering, sorting, caching, etc. On top of existing models without changing the model source code.
You can reuse generic models for many views, for example: a model that fetches data from the server can be initialized with different arguments, to fetch different data for different views. View objects in different Forms can display the same model instance in different view instances, thus they would update automatically when you change one global model.
Most of these use cases work best for lists that grow to a larger size, or represent complex data, which is what the list object is designed to do.
7.17.5. Important - lists and Layout managers
When working with lists, you want the list to handle the scrolling (otherwise it will perform badly). This means you should place the list in a non-scrollable container (no parent can be scrollable), notice that the content pane is scrollable by default, so you should disable that.
It’s also recommended to place the list in the CENTER location of a BorderLayout to produce the most effective results. For example:
7.17.6. MultiList & DefaultListModel
After this long start, here is the first sample of creating a list using the MultiList.
The MultiList is a preconfigured list that contains a ready made renderer with defaults that make sense for the most common use cases. It still retains most of the power available to the List component but reduces the complexity of one of the hardest things to grasp for most developers: rendering.
The full power of the ListModel is still available and allows you to create a million entry list with a few lines of code. For example the objects that the model returns should always be in the form of Map objects and not an arbitrary object like the standard List allows.
Here is a simple example of a MultiList containing a highly popular subject matter:

createListEntry is trivial:
private Map<String, Object> createListEntry(String name, String date) {
Map<String, Object> entry = new HashMap<>();
entry.put("Line1", name);
entry.put("Line2", date);
return entry;
}One major piece is missing here: the cover images for the books. A simple approach would be to place the image objects into the entries using the "icon" property as such:
private Map<String, Object> createListEntry(String name, String date, Image cover) {
Map<String, Object> entry = new HashMap<>();
entry.put("Line1", name);
entry.put("Line2", date);
entry.put("icon", cover);
return entry;
}
Since the MultiList uses the GenericListCellRenderer internally you can use URLImage to dynamically fetch the data. This is discussed in the graphics section of this guide. |
Going further with the ListModel
Suppose that GRRM was prolific and wrote 1 million books. The default list model won’t make much sense in that case but you would still be able to render everything in a list model.
You will fake it a bit but notice that 1M components won’t be created even if you somehow scroll all the way down…
The ListModel interface can be implemented by anyone in this case you did a stupid simple implementation:
You can now replace the existing model by removing all the model related logic and changing the constructor call as such:

7.17.7. List cell renderer
The Renderer is a simple interface with 2 methods:
The most simple/naive implementation may choose to implement the renderer as follows:
This will compile and work, but won’t give you much, notice that you won’t see the List selection move on the List, this is because the renderer returns a Label with the same style regardless if it’s selected or not.
Now make it a bit more useful:
In this renderer you set the Label.setFocus(true) if it’s selected, calling to this method doesn’t give the focus to the Label, it renders the label as selected.
Then you invoke Label.getAllStyles().setBgTransparency(100) to give the selection semi transparency, and 0 for full transparency if not selected.
That’s still not efficient because you create a new Label each time the method is invoked.
To make the code tighter, keep a reference to the Component or extend it as DefaultListCellRenderer does:
Now look at a more advanced Renderer:
In this renderer you want to render a Contact object to the Screen, you build the Component in the constructor and in the getListCellRendererComponent you update the Labels' texts according to the Contact object.
Notice that in this renderer you return a focus Label with semi transparency, as mentioned before, the focus component can be modified within this method.
For example, you can change the focus Component to have an icon:
7.17.8. Generic list cell renderer
As part of the GUI builder work, you needed a way to customize rendering for a List, but the renderer/model approach seemed impossible to adapt to a GUI builder (it seems the Swing GUI builders had a similar issue). Your solution was to introduce the GenericListCellRenderer, which while introducing limitations and implementation requirements still manages to make life easier, both in the GUI builder and outside of it.
GenericListCellRenderer is a renderer designed to be as simple to use as a Component-Container hierarchy, you effectively crammed most of the common renderer use cases into one class. To enable that, you need to know the content of the objects within the model, so the GenericListCellRenderer assumes the model contains Map objects. Since Maps can contain arbitrary data the list model is still generic and allows storing application specific data. Furthermore a Map can still be derived and extended to provide domain specific business logic.
The GenericListCellRenderer accepts two container instances (more later on why at least two, and not one), which it maps to individual Map entries within the model, by finding the appropriate components within the given container hierarchy. Components are mapped to the Map entries based on the name property of the component (getName/setName) and the key/value within the Map, for example:
For a model that contains a Map entry like this:
"Foo": "Bar" "X": "Y" "Not": "Applicable" "Number": Integer(1)
A renderer will loop over the component hierarchy in the container, searching for components whose name matches Foo, X, Not, and Number, and assigning the appropriate value to them.
| You can also use image objects as values, and they will be assigned to labels as expected. For example, you can’t assign both an image and a text to a single label, since the key will be taken. That isn’t a big problem, since two labels can be used in such a renderer. |
To make matters even more attractive the renderer seamlessly supports list tickering when appropriate, and if a CheckBox appears within the renderer, it will toggle a boolean flag within the Map seamlessly.
One issue that crops up with this approach is that, if a value is missing from the Map, it’s treated as empty and the component is reset.
This can pose an issue if you hardcode an image or text within the renderer and you don’t want them replaced (for example: an arrow graphic on a Label within the renderer). The solution for this is to name the component with Fixed in the end of the name, for example: HardcodedIconFixed.
Naming a component within the renderer with $number will automatically set it as a counter component for the offset of the component within the list.
Styling the GenericListCellRenderer is slightly different, the renderer uses the UIID of the Container passed to the generic list cell renderer, and the background focus uses that same UIID with the word "Focus" appended to it.
Note that the generic list cell renderer will grant focus to the child components of the selected entry if they’re focusable, thus changing the style of said entries. For example: a Container might have a child Label that has one style when the parent container is unselected and another when it’s selected (focused), this can be achieved by defining the label as focusable. Notice that the component will never receive direct focus, since it’s still part of a renderer.
Finally, the generic list cell renderer accepts two or four instances of a Container, rather than the obvious choice of accepting one instance. This allows the renderer to treat the selected entry differently, which is important to tickering, although it’s also useful for the fisheye effect [3]. Since it might not be practical to seamlessly clone the Container for the renderer’s needs, Codename One expects the developer to provide two separate instances, they can be identical in all respects, but they must be separate instances for tickering to work. The renderer also allows for a fisheye effect, where the selected entry is actually different from the unselected entry in its structure, it also allows for a pinstripe effect, where odd/even rows have different styles (this is accomplished by providing 4 instances of the containers selected/unselected for odd/even).
The best way to learn about the generic list cell renderer and the Map model is by playing with them in the old GUI builder. Notice they can be used in code without any dependency on the GUI builder and can be useful at that.
Here is a simple example of a list with checkboxes that gets updated automatically:
list.setRenderer(new GenericListCellRenderer(createGenericRendererContainer(), createGenericRendererContainer()));
Custom UIID of entry in GenenricListCellRenderer/MultiList
With MultiList/GenenricListCellRenderer one of the common issues is making a UI where a specific component
within the list renderer has a different UIID style based on data. For example: this can be helpful to mark a label within the
list as red, for instance, for a list of monetary transactions.
This can be achieved with a custom renderer, but that’s a pretty difficult task.GenericListCellRenderer (MultiList uses GenericListCellRenderer internally) has another option.
Normally, to build the model for a renderer of this type, you use something like:
What if you want componentName to be red? Just use:
This will apply the UIID "red" to the component, which you can then style in the theme. Notice that once you start doing this, you need to define this entry for all entries, for example:
Otherwise the component will stay red for the next entry (since the renderer acts like a rubber stamp).
Rendering prototype
Because of the rendering architecture of a List its pretty hard to calculate the right preferred size for such a component. The default behavior includes querying a few entries from the model then constructing their renderers to get a "sample" of the preferred size value.
As you might guess this triggers a performance penalty that’s paid with every reflow of the UI. The solution is to use setRenderingPrototype.
setRenderingPrototype accepts a "fake" value that represents a reasonably large amount of data and it will be used to calculate the preferred size. For example: for a multiList that should render 2 lines of text with 20 characters and a 5mm square icon you can do something like this:
7.17.9. ComboBox
The ComboBox is a specialization of List that displays a single selected entry. When clicking that entry a popup is presented allowing the user to pick an entry from the full list of entries.
The ComboBox UI paradigm isn’t as common on OSes such as iOS where there is no native equivalent to it. Recommend using either the Picker class or the AutoCompleteTextField. |
ComboBox is notoriously hard to style as it relies on a complex dynamic of popup renderer and instantly visible renderer. The UIID for the ComboBox is ComboBox
but if you set it to something else all the other UIID’s will also change their prefix. For example: the ComboBoxPopup
UIID will become MyNewUIIDPopup.
The combo box defines the following UIID’s by default:
ComboBoxComboBoxItemComboBoxFocusPopupContentPanePopupItemPopupFocus
The ComboBox also defines theme constants that allow some native themes to manipulate its behavior for example:
popupTitleBool- shows the "label for" value as the title of the popup dialogpopupCancelBodyBool- Adds a cancel button into the popup dialogcenteredPopupBool- shows the popup dialog in the center of the screen instead of under the popupotherPopupRendererBool- Uses a different list cell render for the popup than the one used for theComboBoxitself. When this isfalsePopupItem&PopupFocusbecome irrelevant. Notice that the Android native theme defines this totrue.
Since a ComboBox is a List you can use everything you learned about a List to build a ComboBox including models, GenericListCellRenderer etc.
For example: the demo below uses the GRRM demo data from above to build a ComboBox:

7.18. Slider
A Slider is an empty component that can be filled horizontally or vertically to allow indicating progress, setting volume etc. It can be editable to allow the user to determine its value or none editable to relay that information to the user. It can have a thumb on top to show its current position.

The interesting part about the slider is that it has two separate style UIID’s, Slider & SliderFull. The Slider UIID is always painted and SliderFull is rendered on top based on the amount the Slider should be filled.
Slider is highly customizable for example: a slider can be used to replicate a 5-star rating widget as such. Notice that this slider will work when its given its preferred size otherwise more stars will appear. That’s why you place it within a FlowLayout:
The slider itself is initialized in the code below. Notice that you can achieve almost the same result using a theme by setting the Slider & SliderFull UIID’s (both in selected & unselected states).
In fact doing this in the theme might be superior as you could use one image that contains 5 stars already and that way you won’t need the preferred size hack below:
private void initStarRankStyle(Style s, Image star) {
s.setBackgroundType(Style.BACKGROUND_IMAGE_TILE_BOTH);
s.setBorder(Border.createEmpty());
s.setBgImage(star);
s.setBgTransparency(0);
}
private Slider createStarRankSlider() {
Slider starRank = new Slider();
starRank.setEditable(true);
starRank.setMinValue(0);
starRank.setMaxValue(10);
Font fnt = Font.createTrueTypeFont("native:MainLight", "native:MainLight").
derive(Display.getInstance().convertToPixels(5, true), Font.STYLE_PLAIN);
Style s = new Style(0xffff33, 0, fnt, (byte)0);
Image fullStar = FontImage.createMaterial(FontImage.MATERIAL_STAR, s).toImage();
s.setOpacity(100);
s.setFgColor(0);
Image emptyStar = FontImage.createMaterial(FontImage.MATERIAL_STAR, s).toImage();
initStarRankStyle(starRank.getSliderEmptySelectedStyle(), emptyStar);
initStarRankStyle(starRank.getSliderEmptyUnselectedStyle(), emptyStar);
initStarRankStyle(starRank.getSliderFullSelectedStyle(), fullStar);
initStarRankStyle(starRank.getSliderFullUnselectedStyle(), fullStar);
starRank.setPreferredSize(new Dimension(fullStar.getWidth() * 5, fullStar.getHeight()));
return starRank;
}
private void showStarPickingForm() {
Form hi = new Form("Star Slider", new BoxLayout(BoxLayout.Y_AXIS));
hi.add(FlowLayout.encloseCenter(createStarRankSlider()));
hi.show();
}
This slider goes all the way to 0 stars which is less common. You can use a Label to represent the first star and have the slider work between 0 - 8 values to provide 4 more stars. |
7.19. Table
Table is a composite component (but it isn’t a lead component), this means it’s a subclass of Container. It’s effectively built from many components.
Table is based on the TableLayout class. It’s important to be familiar with that layout manager when working with Table. |
Here is a trivial sample of using the standard table component:
Form hi = new Form("Table", new BorderLayout());
TableModel model = new DefaultTableModel(
new String[] {"Col 1", "Col 2", "Col 3"},
new Object[][] {
{"Row 1", "Row A", "Row X"},
{"Row 2", "Row B", "Row Y"},
{"Row 3", "Row C", "Row Z"},
{"Row 4", "Row D", "Row K"},
}) {
public boolean isCellEditable(int row, int col) {
return col != 0;
}
};
Table table = new Table(model);
hi.add(BorderLayout.CENTER, table);
hi.show();
| In the sample above the title area and first column aren’t editable. The other two columns are editable. |
The more "interesting" capabilities of the Table class can be utilized through the TableLayout. You can use the layout constraints (also exposed in the table class) to create spanning and elaborate UI’s.
For example:
Form hi = new Form("Table", new BorderLayout());
TableModel model = new DefaultTableModel(
new String[] {"Col 1", "Col 2", "Col 3"},
new Object[][] {
{"Row 1", "Row A", "Row X"},
{"Row 2", "Row B can now stretch", null},
{"Row 3", "Row C", "Row Z"},
{"Row 4", "Row D", "Row K"},
}) {
public boolean isCellEditable(int row, int col) {
return col != 0;
}
};
Table table = new Table(model) {
@Override
protected TableLayout.Constraint createCellConstraint(Object value, int row, int column) {
TableLayout.Constraint con = super.createCellConstraint(value, row, column);
if (row == 1 && column == 1) {
con.setHorizontalSpan(2);
}
con.setWidthPercentage(33);
return con;
}
};
hi.add(BorderLayout.CENTER, table);
hi.show();
To customize the table cell behavior you can derive the Table to create a "renderer like" widget, but unlike the list this component is "kept" and used as is. This means you can bind listeners to this component and work with it as you would with any other component in Codename One.
The example above can be extended to include far more capabilities:
Form hi = new Form("Table", new BorderLayout());
TableModel model = new DefaultTableModel(
new String[] {"Col 1", "Col 2", "Col 3"},
new Object[][] {
{"Row 1", "Row A", "Row X"},
{"Row 2", "Row B can now stretch", null},
{"Row 3", "Row C", "Row Z"},
{"Row 4", "Row D", "Row K"},
}) {
public boolean isCellEditable(int row, int col) {
return col != 0;
}
};
Table table = new Table(model) {
@Override
protected Component createCell(Object value, int row, int column, boolean editable) {
Component cell;
if (row == 1 && column == 1) {
Picker p = new Picker();
p.setType(Display.PICKER_TYPE_STRINGS);
p.setStrings("Row B can now stretch", "This is a good value",
"So Is This", "Better than text field");
p.setSelectedString((String)value);
p.setUIID("TableCell");
p.addActionListener(e -> getModel().setValueAt(row, column, p.getSelectedString()));
cell = p;
} else {
cell = super.createCell(value, row, column, editable);
}
if (row > -1 && row % 2 == 0) {
cell.getAllStyles().setBgColor(0xeeeeee);
cell.getAllStyles().setBgTransparency(255);
}
return cell;
}
@Override
protected TableLayout.Constraint createCellConstraint(Object value, int row, int column) {
TableLayout.Constraint con = super.createCellConstraint(value, row, column);
if (row == 1 && column == 1) {
con.setHorizontalSpan(2);
}
con.setWidthPercentage(33);
return con;
}
};
hi.add(BorderLayout.CENTER, table);
hi.show();

To line wrap table cells you can override the createCell method and return a TextArea instead of a TextField since the TextArea defaults to the multi-line behavior this should work seamlessly. For example:
Form hi = new Form("Table", new BorderLayout());
TableModel model = new DefaultTableModel(
new String[] {"Name", "Description", "Status"},
new Object[][] {
{"Row 1", "A short value", "OK"},
{"Row 2", "A much longer value that wraps to multiple lines", "OK"},
{"Row 3", "Another long table cell that needs wrapping", "Pending"},
});
Table table = new Table(model) {
@Override
protected Component createCell(Object value, int row, int column, boolean editable) {
if (row > -1 && column == 1) {
TextArea cell = new TextArea(String.valueOf(value));
cell.setUIID("TableCell");
cell.setEditable(false);
cell.setGrowByContent(true);
return cell;
}
return super.createCell(value, row, column, editable);
}
@Override
protected TableLayout.Constraint createCellConstraint(Object value, int row, int column) {
TableLayout.Constraint con = super.createCellConstraint(value, row, column);
con.setWidthPercentage(column == 1 ? 50 : 25);
return con;
}
};
hi.add(BorderLayout.CENTER, table);
hi.show();Notice that you don’t need to do anything else as binding to the TextArea is built-in to the Table. |
| You must set the column width constraint when you want multi-line to work. Otherwise the preferred size of the column might be too wide and the remaining columns might not have space left. |


7.19.1. Sorting tables
Sorting tables by clicking the titles is something that should work out of the box by using an API like setSortSupported(true):
Form hi = new Form("Table", new BorderLayout());
TableModel model = new DefaultTableModel(
new String[] {"Col 1", "Col 2", "Col 3"},
new Object[][] {
{"Row 1", "Row A", 1},
{"Row 2", "Row B", 4},
{"Row 3", "Row C", 7.5},
{"Row 4", "Row D", 2.24},
});
Table table = new Table(model);
table.setSortSupported(true);
hi.add(BorderLayout.CENTER, table);
hi.add(BorderLayout.NORTH, new Button("Button"));
hi.show();Notice this works with numbers, Strings and might work with dates but you can support any object type by overriding the method protected Comparator createColumnSortComparator(int column) which should return a comparator for your custom object type in the column.
7.20. Tree
Tree allows displaying hierarchical data such as folders and files in a collapsible/expandable UI. Like the Table it’s a composite component (but it isn’t a lead component).
Like the Table it works in consort with a model to construct its user interface on the fly but doesn’t use a stateless renderer (as List does).
The data of the Tree arrives from a model for example: this:
Will result in this:

Since Tree is hierarchy based you can’t have a simple model like you’ve for the Table as deep hierarchy is harder to represent with arrays. |
A more practical "real world" example would be working with XML data. You can use something like this to show an XML Tree:
The try(Stream) syntax is a try with resources clogic that implicitly closes the stream. |

The model for the XML hierarchy is implemented as such:
7.21. ShareButton
ShareButton is a button you can add into the UI to let a user share an image or block of text.
The ShareButton uses a set of predefined share options on the simulator. On Android & iOS the ShareButton is mapped to the OS native sharing functionality and can share the image/text with the services configured on the device (for example: Twitter, Facebook etc.).
| Sharing text is trivial but to share an image you need to save it to the FileSystemStorage. Notice that saving to Storage won’t work! |
In the sample code below you take a screenshot which is saved to FileSystemStorage for sharing:
Form hi = new Form("ShareButton");
ShareButton sb = new ShareButton();
sb.setText("Share Screenshot");
hi.add(sb);
Image screenshot = Image.createImage(hi.getWidth(), hi.getHeight());
hi.revalidate();
hi.setVisible(true);
hi.paintComponent(screenshot.getGraphics(), true);
String imageFile = FileSystemStorage.getInstance().getAppHomePath() + "screenshot.png";
try(OutputStream os = FileSystemStorage.getInstance().openOutputStream(imageFile);) {
ImageIO.getImageIO().save(screenshot, os, ImageIO.FORMAT_PNG, 1);
} catch(IOException err) {
Log.e(err);
}
sb.setImageToShare(imageFile, "image/png");
ShareButton behaves differently on the device… |

The ShareButton features some share service classes to allow plugging in more share services. For example, this functionality is relevant to devices where native sharing isn’t supported. This code isn’t used on iOS/Android… |
7.21.1. Share Result Callback
The share API can report what the user did with the share sheet. Register a ShareResultListener on either ShareButton or directly with Display.share(…) and you receive a single ShareResult describing the outcome:
SHARED_TO(packageName)— the user picked a destination.packageNameis the chosen target’s identifier: an Android package name (for example,com.whatsapp) or, on iOS, aUIActivityTypesuch ascom.apple.UIKit.activity.PostToTwitter. It may benullwhen the platform doesn’t expose the selection (for example, older Android, Web Share API).DISMISSED— the user cancelled without picking a target. iOS reports this reliably; Android’s chooser has no public dismissal signal, so on Android the listener simply doesn’t fire on cancel.FAILED— the share couldn’t be completed.getError()may carry a short platform-supplied message.
The listener is always invoked on the EDT, exactly once per share request.
ShareButton sb = new ShareButton();
sb.setTextToShare("Check this out!");
sb.setShareResultListener(result -> {
if (result.isSharedTo()) {
Log.p("Shared to " + result.getPackageName());
} else if (result.isDismissed()) {
Log.p("User dismissed the share sheet");
} else if (result.isFailed()) {
Log.p("Share failed: " + result.getError());
}
});
form.add(sb);If you call Display directly instead of using ShareButton, pass the listener as the final argument to the new overload:
When the share is dispatched through the non-native fallback dialog (platforms without isNativeShareSupported), the listener still fires: it reports DISMISSED when the user picks the Cancel button, and the underlying ShareService implementations report SHARED_TO once they call ShareService.finish(). Custom ShareService subclasses can call deliverResult(ShareResult.failed("…")) from inside share(…) to publish a failure explicitly; otherwise finish() falls back to a default SHARED_TO(commandName).
7.22. iOS Share Extension Authoring Helper
An iOS share extension is a separate app target that the system shows inside UIActivityViewController when the user shares from another app (Safari, Photos, etc.). It runs in a sandboxed process and persists payloads to the host app via an App Group shared NSUserDefaults suite.
Codename One’s build pipeline already wires .ios.appext zip archives under src/main/resources into the generated Xcode project. The IOSShareExtensionBuilder helper generates that archive for you so you don’t have to create the extension target in Xcode first.
7.22.1. What the helper produces
For a single call the helper writes four files at the root of the extension bundle:
Info.plist— declares theNSExtensiondictionary, activation rules (SupportsText/SupportsWebURL/SupportsImage), and the principal class (ShareViewController).<ExtensionName>.entitlements— declarescom.apple.security.application-groupswith the configured App Group identifier.ShareViewController.swift— aSLComposeServiceViewControllersubclass that extracts text / URL / image attachments fromextensionContext, packs them into a dictionary, and writes that dictionary toUserDefaults(suiteName: appGroupId)under the keycn1.shareExtension.payload.buildSettings.properties— Xcode build setting overrides (deployment target, Swift version, entitlements path, plist path) picked up by the iOS build pipeline.
7.22.2. Generating the bundle
Call the builder from a Maven plugin, an Ant task or a one-shot main:
The next iOS build picks up the .ios.appext archive automatically; no Xcode steps are required.
If you prefer a directory layout (for example, to commit the generated sources or to feed a future ios/app_extensions/ pipeline) use writeTo(File) instead of writeAppext(File) — the file contents are identical.
7.22.3. Reading the payload from the host app
The host app reads the most recent payload from the same App Group at startup or when it resumes:
// Inside an iOS native interface
NSUserDefaults* shared =
[[NSUserDefaults alloc] initWithSuiteName:@"group.com.example.myapp.shared"];
NSDictionary* payload = [shared dictionaryForKey:@"cn1.shareExtension.payload"];The payload dictionary contains:
text— the user-composed text (String).items— an array of{ kind, value }dictionaries wherekindis"text","url"or"image". For images,valueis a file URL inside the App Group container.timestamp— aDoubleUNIX time.
Expose this to your CN1 code via a small native interface and clear the key once handled so the next share is unambiguous.
7.22.4. Activation rules and validation
The builder validates its inputs before writing anything:
extensionNamemust be a non-empty identifier (letters, digits,_,-). It becomes the Xcode target name and the.appexbundle name. The extension’s bundle id is set to<hostBundleId>.<extensionName>by the iOS build pipeline.appGroupIdmust start withgroup.(an Apple requirement). Create the matching App Group in your Apple Developer account and add it to both the host app’s and the extension’s provisioning profile.At least one of
acceptText,acceptURLs,acceptImagesmust be enabled, otherwise iOS will never present your extension.
The default deployment target is iOS 12.0; override with setDeploymentTarget("13.0") if you need newer APIs in your customized controller.
7.22.5. Customising the generated controller
The generated Swift controller covers the common case (read attachments, persist to App Group, finish the request). If you need bespoke logic — custom UI, server upload, image transcoding — treat the helper’s output as a starting point: run it once, copy the directory under ios/app_extensions/MyShareExtension/, edit ShareViewController.swift, and zip it back into .ios.appext (or wait for the directory-based pipeline tracked by issue #3427).
Provisioning profiles for the extension target aren’t generated by the helper. You still need to provision the extension’s bundle id (<hostBundleId>.<extensionName>) and add the App Group capability to it on the Apple Developer portal, alongside the host app. |
7.23. Tabs
The Tabs Container arranges components into groups within "tabbed" containers. Tabs is a container type that allows leafing through its children using labeled toggle buttons. The tabs can be placed in many different ways (top, bottom, left or right) with the default being determined by the platform. This class also allows swiping between components to leaf between said tabs (for this purpose the tabs themselves can also be hidden).
Since Tabs are a Container its a common mistake to try and add a Tab using the add method. That method won’t work since a Tab can have both an Image and text String associated with it:
Form hi = new Form("Tabs", new BorderLayout());
Tabs t = new Tabs();
Style s = UIManager.getInstance().getComponentStyle("Tab");
FontImage icon1 = FontImage.createMaterial(FontImage.MATERIAL_QUESTION_ANSWER, s);
Container container1 = BoxLayout.encloseY(new Label("Label1"), new Label("Label2"));
t.addTab("Tab1", icon1, container1);
t.addTab("Tab2", new SpanLabel("Some text directly in the tab"));
hi.add(BorderLayout.CENTER, t);
A common usage for Tabs is the swipe to proceed effect which is common in iOS applications. In the code below you use RadioButton and LayeredLayout with hidden tabs to produce that effect:
Form hi = new Form("Swipe Tabs", new LayeredLayout());
Tabs t = new Tabs();
t.hideTabs();
Style s = UIManager.getInstance().getComponentStyle("Button");
FontImage radioEmptyImage = FontImage.createMaterial(FontImage.MATERIAL_RADIO_BUTTON_UNCHECKED, s);
FontImage radioFullImage = FontImage.createMaterial(FontImage.MATERIAL_RADIO_BUTTON_CHECKED, s);
((DefaultLookAndFeel)UIManager.getInstance().getLookAndFeel()).setRadioButtonImages(radioFullImage, radioEmptyImage, radioFullImage, radioEmptyImage);
Container container1 = BoxLayout.encloseY(new Label("Swipe the tab to see more"),
new Label("You can put anything here"));
t.addTab("Tab1", container1);
t.addTab("Tab2", new SpanLabel("Some text directly in the tab"));
RadioButton firstTab = new RadioButton("");
RadioButton secondTab = new RadioButton("");
firstTab.setUIID("Container");
secondTab.setUIID("Container");
new ButtonGroup(firstTab, secondTab);
firstTab.setSelected(true);
Container tabsFlow = FlowLayout.encloseCenter(firstTab, secondTab);
hi.add(t);
hi.add(BorderLayout.south(tabsFlow));
t.addSelectionListener((i1, i2) -> {
switch(i2) {
case 0:
if(!firstTab.isSelected()) {
firstTab.setSelected(true);
}
break;
case 1:
if(!secondTab.isSelected()) {
secondTab.setSelected(true);
}
break;
}
});

Notice that you used setRadioButtonImages to explicitly set the radio button images to the look you want for the carousel. |
7.23.1. Animated tab indicator
Modern Material 3 (NavigationBar) and iOS 26 tab bars animate a small
underline between tabs when the user changes selection. Tabs ships
this as an opt-in feature gated by the tabsAnimatedIndicatorBool
theme constant; the iOS Modern and Android Material themes turn it on
by default, so apps shipping against those themes get the effect for
free.
To enable in a custom theme:
#Constants {
tabsAnimatedIndicatorBool: true;
tabsAnimatedIndicatorDurationInt: 200; /* tween duration in ms */
tabsAnimatedIndicatorThicknessMm: 1; /* underline thickness */
}
TabIndicator {
/* The indicator picks up its color from this UIID's fg. If the
UIID isn't defined or has fgColor == 0, the indicator falls
back to the currently-selected tab's fgColor. */
color: #007aff;
background-color: transparent;
padding: 0;
margin: 0;
}To toggle programmatically (for example, add it to a Tabs instance whose theme hasn’t enabled it):
Tabs tabs = new Tabs();
tabs.setAnimatedIndicator(true);The indicator animates its x / width from the previously selected
tab’s bounds to the new selection’s bounds using a Motion.createEaseInOutMotion
over the configured duration (200ms default, matching Material 3’s
spec). Rapid double-taps start the animation from the current
interpolated position rather than from a stale baseline, so the
indicator chains cleanly.
7.24. MediaManager & MediaPlayer
MediaPlayer is a peer component, understanding this is crucial if your application depends on such a component. You can learn about peer components and their issues here. |
The MediaPlayer allows you to control video playback. To use the MediaPlayer you need to first load the Media object from the MediaManager.
The MediaManager is the core class responsible for media interaction in Codename One.
You should also check out the Capture class for things that aren’t covered by the MediaManager. |
In the demo code below you use the gallery functionality to pick a video from the device’s video gallery:
final Form hi = new Form("MediaPlayer", new BorderLayout());
hi.setToolbar(new Toolbar());
Style s = UIManager.getInstance().getComponentStyle("Title");
FontImage icon = FontImage.createMaterial(FontImage.MATERIAL_VIDEO_LIBRARY, s);
hi.getToolbar().addCommandToRightBar("", icon, (evt) -> {
Display.getInstance().openGallery((e) -> {
if(e != null && e.getSource() != null) {
String file = (String)e.getSource();
try {
Media video = MediaManager.createMedia(file, true);
hi.removeAll();
hi.add(BorderLayout.CENTER, new MediaPlayer(video));
hi.revalidate();
} catch(IOException err) {
Log.e(err);
}
}
}, Display.GALLERY_VIDEO);
});
hi.show();

| Video playback in the simulator will work with JavaFX enabled. This is the default for Java 8 or newer so recommend using that. |
7.25. ImageViewer
The ImageViewer allows you to inspect, zoom and pan into an image. It also allows swiping between images if you have a set of images (using an image list model).
The ImageViewer is a complex rich component designed for user interaction. If you want to display an image use Label if you want the image to scale seamlessly use ScaleImageLabel. |
You can use the ImageViewer as a tool to view a single image which allows you to zoom in/out to that image as such:
| You can simulate pinch to zoom on the simulator by dragging the right button away from the top left corner to zoom in and towards the top left corner to zoom out. On Mac touchpads you can drag two fingers to achieve that. |


You can work with a list of images to produce a swiping effect for the image viewer where you can swipe from one image to the next and also zoom in/out on a specific image:
Form hi = new Form("ImageViewer", new BorderLayout());
Image red = Image.createImage(100, 100, 0xffff0000);
Image green = Image.createImage(100, 100, 0xff00ff00);
Image blue = Image.createImage(100, 100, 0xff0000ff);
Image gray = Image.createImage(100, 100, 0xffcccccc);
ImageViewer iv = new ImageViewer(red);
iv.setImageList(new DefaultListModel<>(red, green, blue, gray));
hi.add(BorderLayout.CENTER, iv);
Notice that you use a ListModel to allow swiping between images.
ImageViewer also supports optional side arrows (material font icons) and an optional thumbnail strip for direct image navigation:
When arrows are enabled, tapping near the left/right edge will move to the previous/next image. When thumbnails are enabled, tapping a thumbnail jumps directly to that image.
All three options can be configured with theme constants (using the ImageViewer UIID prefix):
imageviewerNavigationArrowsBool=true|falseimageviewerThumbnailsBool=true|falseimageviewerThumbnailBarHeightMM=<floating point millimeters>
EncodedImage’s aren’t always fully loaded and so when you swipe if the images are large you might see delays! |
You can dynamically download images directly into the ImageViewer with a custom list model like this:

This fetches the images in the URL asynchronously and fires a data change event when the data arrives to automatically refresh the ImageViewer when that happens.
7.26. ScaleImageLabel & ScaleImageButton
ScaleImageLabel & ScaleImageButton allow you to position an image that will grow/shrink to fit available space. In that sense they differ from Label & Button which keeps the image at the same size.
The default UIID of ScaleImageLabel is Label, but the default UIID of ScaleImageButton is ScaleImageButton. The reasoning for the difference is that the Button UIID includes a border and a lot of legacy. |
You can use ScaleImageLabel/ScaleImageButton interchangeably. The major difference between these components is the buttons ability to handle click events/focus.
Here is a simple example that also shows the difference between the scale to fill and scale to fit modes:

| When styling these components keep in mind that changing attributes such as background behavior might cause an issue with their functionality or might not work. |
7.27. Toolbar
The Toolbar API provides deep customization of the title bar area with more flexibility for example: placing a TextField
for search or buttons in arbitrary title area positions. The Toolbar API replicates some native functionality
available on Android/iOS and integrates with features such as the side menu to provide fine grained control over the title area behavior.
The Toolbar needs to be installed into the Form in order for it to work. You can setup the Toolbar in one of these three ways:
form.setToolbar(new Toolbar());- allows you to activate theToolbarto a specificFormand not for the entire applicationToolbar.setGlobalToolbar(true);- enables theToolbarfor all the forms in the appTheme constant
globalToobarBool- this is equivalent toToolbar.setGlobalToolbar(true);
The basic functionality of the Toolbar includes the ability to add a command to the following 4 places:
Left side of the title -
addCommandToLeftBarRight side of the title -
addCommandToRightBarSide menu bar (the drawer that opens when you click the icon on the top left or swipe the screen from left to right) -
addCommandToSideMenuOverflow menu (the menu that opens when you tap the 3 vertical dots in the top right corner) -
addCommandToOverflowMenu
The code below provides a brief overview of these options:



You can set a title with a String but if you would want the component to be a text field or a multi
line label you can use setTitleComponent(Component) which allows you to install any component into the
title area.
| The code below demonstrates searching using custom code but the Toolbar also has built-in support for search covered in the next section |
The customization of the title area allows for some pretty powerful UI effects for example: the code below allows searching dynamically within a set of entries and uses some neat tricks:
Toolbar.setGlobalToolbar(true);
Style s = UIManager.getInstance().getComponentStyle("Title");
Form hi = new Form("Toolbar", new BoxLayout(BoxLayout.Y_AXIS));
TextField searchField = new TextField("", "Toolbar Search"); (1)
searchField.getHintLabel().setUIID("Title");
searchField.setUIID("Title");
searchField.getAllStyles().setAlignment(Component.LEFT);
hi.getToolbar().setTitleComponent(searchField);
FontImage searchIcon = FontImage.createMaterial(FontImage.MATERIAL_SEARCH, s);
searchField.addDataChangeListener((i1, i2) -> { (2)
String t = searchField.getText();
if(t.length() < 1) {
for(Component cmp : hi.getContentPane()) {
cmp.setHidden(false);
cmp.setVisible(true);
}
} else {
t = t.toLowerCase();
for(Component cmp : hi.getContentPane()) {
String val = null;
if(cmp instanceof Label) {
val = ((Label)cmp).getText();
} else {
if(cmp instanceof TextArea) {
val = ((TextArea)cmp).getText();
} else {
val = (String)cmp.getPropertyValue("text");
}
}
boolean show = val != null && val.toLowerCase().indexOf(t) > -1;
cmp.setHidden(!show);
cmp.setVisible(show); (3)
}
}
hi.getContentPane().animateLayout(250);
});
hi.getToolbar().addCommandToRightBar("", searchIcon, (e) -> { (4)
searchField.startEditingAsync();
});
hi.add("A Game of Thrones").
add("A Clash Of Kings").
add("A Storm Of Swords").
add("A Feast For Crows").
add("A Dance With Dragons").
add("The Winds of Winter").
add("A Dream of Spring");
hi.show();| 1 | You use a TextField the whole time and style it to make it (and its hint) look like a regular title. An alternative way is to replace the title component dynamically. |
| 2 | You use the DataChangeListener to update the search results as you type them. |
| 3 | Hidden & Visible use the opposite flag values to say similar things (for example: when hidden is set to false you would want to set visible to true). Visible indicates whether a component can be seen. It will still occupy the physical space on the screen even when it isn’t visible. Hidden will remove the space occupied by the component from the screen, but some code might still try to paint it., visible is redundant but you use it with hidden for good measure. |
| 4 | The search button is totally unnecessary here. You can click the TextField!For example, that isn’t intuitive to most users so a button is added to start editing. |


7.27.1. Search mode
While you can implement search manually, using the built-in search offers a simpler and uniform UI.

You can customize the appearance of the search bar by using the UIID’s: ToolbarSearch, TextFieldSearch & TextHintSearch.
In the sample below you fetch all the contacts from the device and enable search through them, notice it expects and image called duke.png which is the default Codename One icon renamed and placed in the src folder:
7.27.2. South Component
A common feature in side menu bar is the ability to add a component to the "south" part of the side menu.
Notice that this feature works with the on-top and permanent versions of the side menu and not with the legacy versions:
This places the component below the side menu bar. Notice that this component controls its entire UIID & is separate from the SideNavigationPanel UIID so if you set that component you might want to place it within a container that has the SideNavigationPanel UIID so it will blend with the rest of the UI.
7.27.3. Title animations
Modern UI’s often animate the title upon scrolling to balance the highly functional smaller title advantage with the gorgeous large image based title. This is pretty easy to do with the Toolbar API through the Title animation API.
The code below shows off an attractive title based on a book by GRRM on top of text [5] that’s scrollable. As the text is scrolled the title fades out:
Toolbar.setGlobalToolbar(true);
Form hi = new Form("Toolbar", new BoxLayout(BoxLayout.Y_AXIS));
EncodedImage placeholder = EncodedImage.createFromImage(Image.createImage(hi.getWidth(), hi.getWidth() / 5, 0xffff0000), true);
URLImage background = URLImage.createToStorage(placeholder, "400px-AGameOfThrones.jpg",
"http://awoiaf.westeros.org/images/thumb/9/93/AGameOfThrones.jpg/400px-AGameOfThrones.jpg");
background.fetch();
Style stitle = hi.getToolbar().getTitleComponent().getUnselectedStyle();
stitle.setBgImage(background);
stitle.setBackgroundType(Style.BACKGROUND_IMAGE_SCALED_FILL);
stitle.setPaddingUnit(Style.UNIT_TYPE_DIPS, Style.UNIT_TYPE_DIPS, Style.UNIT_TYPE_DIPS, Style.UNIT_TYPE_DIPS);
stitle.setPaddingTop(15);
SpanButton credit = new SpanButton("This excerpt is from A Wiki Of Ice And Fire. Please check it out by clicking here!");
credit.addActionListener((e) -> Display.getInstance().execute("http://awoiaf.westeros.org/index.php/A_Game_of_Thrones"));
hi.add(new SpanLabel("A Game of Thrones is the first of seven planned novels in A Song of Ice and Fire, an epic fantasy series by American author George R. R. Martin. It was first published on 6 August 1996. The novel was nominated for the 1998 Nebula Award and the 1997 World Fantasy Award,[1] and won the 1997 Locus Award.[2] The novella Blood of the Dragon, comprising the Daenerys Targaryen chapters from the novel, won the 1997 Hugo Award for Best Novella. ")).
add(new Label("Plot introduction", "Heading")).
add(new SpanLabel("A Game of Thrones is set in the Seven Kingdoms of Westeros, a land reminiscent of Medieval Europe. In Westeros the seasons last for years, sometimes decades, at a time.\n\n" +
"Fifteen years prior to the novel, the Seven Kingdoms were torn apart by a civil war, known alternately as \"Robert's Rebellion\" and the \"War of the Usurper.\" Prince Rhaegar Targaryen kidnapped Lyanna Stark, arousing the ire of her family and of her betrothed, Lord Robert Baratheon (the war's titular rebel). The Mad King, Aerys II Targaryen, had Lyanna's father and eldest brother executed when they demanded her safe return. Her second brother, Eddard, joined his boyhood friend Robert Baratheon and Jon Arryn, with whom they had been fostered as children, in declaring war against the ruling Targaryen dynasty, securing the allegiances of House Tully and House Arryn through a network of dynastic marriages (Lord Eddard to Catelyn Tully and Lord Arryn to Lysa Tully). The powerful House Tyrell continued to support the King, but House Lannister and House Martell both stalled due to insults against their houses by the Targaryens. The civil war climaxed with the Battle of the Trident, when Prince Rhaegar was killed in battle by Robert Baratheon. The Lannisters finally agreed to support King Aerys, but then brutallynull ")).
add(credit);
ComponentAnimation title = hi.getToolbar().getTitleComponent().createStyleAnimation("Title", 200);
hi.getAnimationManager().onTitleScrollAnimation(title);
hi.show();


Most the code above creates the "look" of the application. The key piece of code above is this:
ComponentAnimation title = hi.getToolbar().getTitleComponent().createStyleAnimation("Title", 200);
hi.getAnimationManager().onTitleScrollAnimation(title);In the first line you create a style animation that will translate the style from the current settings to the destination UIID (the first argument) within 200 pixels of scrolling. You then bind this animation to the title scrolling animation event.
7.28. BrowserComponent & WebBrowser
BrowserComponent is a peer component, understanding this is crucial if your application depends on such a component. You can learn about peer components and their issues here. |
The WebBrowser component shows the native device web browser when supported by the device and the
HTMLComponent when the web browser isn’t supported on the given device. If you intend to target smartphones
you should use the BrowserComponent directly instead of the WebBrowser.
The BrowserComponent can point at an arbitrary URL to load it:
Form hi = new Form("Browser", new BorderLayout());
BrowserComponent browser = new BrowserComponent();
browser.setURL("https://www.codenameone.com/");
hi.add(BorderLayout.CENTER, browser);
| The scrollbars appear in the simulator, device versions of the browser component act differently and support touch scrolling. |
A BrowserComponent should be in the center of a BorderLayout. Otherwise its preferred size might be zero before the HTML finishes loading/layout in the native layer and layout might be wrong as a result. |
You can use WebBrowser and BrowserComponent interchangeably for most basic usage. For example, if you need access to JavaScript or native browser functionality then there is no use in going through the WebBrowser abstraction.
The BrowserComponent has full support for executing local web pages from within the jar. The basic support uses the jar:/// URL as such:
BrowserComponent wb = new BrowserComponent();
wb.setURL("jar:///Page.html");On Android a native indicator might show up when the web page is loading. This can be disabled using the Display.getInstance().setProperty("WebLoadingHidden", "true"); call. You need to invoke this once. |
7.28.1. Troubleshooting "Failed to create CEF browser" on Linux
In the Simulator, BrowserComponent is rendered by the bundled CEF (Chromium Embedded Framework) port. On Linux, BrowserComponent.isNativeBrowserSupported() may return true and yet creating the component throws RuntimeException: Failed to create CEF browser, with a root cause similar to:
java.lang.UnsatisfiedLinkError: .../codenameone-cef-*-linux64.zip-extracted/lib/linux64/libjcef.so:
.../lib/linux64/libjawt.so: version `SUNWprivate_1.1' not found
(required by .../lib/linux64/libjcef.so)The native CEF library (libjcef.so) is loaded with a sibling libjawt.so shipped inside the CEF archive. That copy of libjawt.so expects symbols (SUNWprivate_1.1) provided by the JDK’s own libjawt.so and the matching libjvm.so. When the JVM running the Simulator doesn’t expose those symbols at load time — typically because the dynamic linker doesn’t have the JDK’s native library directories on its search path — the load fails before any browser is created. This is purely a Simulator/desktop concern; the same code runs unchanged on Android and iOS.
The fix is to launch the IDE (and therefore the Simulator JVM) with JAVA_HOME and LD_LIBRARY_PATH pointing at a supported JDK. For example, on Linux Mint / Ubuntu wrap the IDE startup script:
#!/bin/bash
export JAVA_HOME=/usr/lib/jvm/java-17-openjdk-amd64
export LD_LIBRARY_PATH=$JAVA_HOME/lib:$JAVA_HOME/lib/server${LD_LIBRARY_PATH:+:$LD_LIBRARY_PATH}
exec /path/to/your/ide "$@"After relaunching the IDE through this wrapper, BrowserComponent instantiation succeeds in the Simulator. Any JDK from 11 through 25 that’s supported for running the Simulator works — the important part is that LD_LIBRARY_PATH resolves to that JDK’s lib and lib/server directories so the bundled libjcef.so finds a compatible libjawt/libjvm pair.
If BrowserComponent instantiation fails on Linux, log the environment with CN.getProperty("java.home", "<unset>"), CN.getProperty("JAVA_HOME", "<unset>") and CN.getProperty("LD_LIBRARY_PATH", "<unset>"). An <unset> value for LD_LIBRARY_PATH while the IDE was launched from a desktop shortcut is the typical fingerprint of this problem — desktop launchers don’t source your shell profile. |
| This issue doesn’t affect packaged native applications, only the desktop Simulator running on Linux. |
7.28.2. BrowserComponent hierarchy
When Codename One packages applications into native apps it hides a lot of details to make the process simpler. One of the things hidden is the fact that you aren’t dealing with a JAR anymore, so
getResource/getResourceAsStream are problematic… Both of these APIs support hierarchies and a concept of package
relativity both of which might not be supported on all OSes.
Codename One has its own getResourceAsSteam in the Display class and that works fine, but it requires that all files be in the src root directory.
| That’s why recommend that you place files inside res files. A resource file allows you to add arbitrary data files and you can have as many resource files as you need. |
For web developers this isn’t enough since hierarchies are used often to represent the various dependencies, this means that many links & references are relative. To work with such hierarchies place all your resources in a hierarchy under the HTML package in the project source directory (src/html). The build server will tar the entire content of that package and add an html.tar file into the native package. This tar is seamlessly extracted on the device when you actually need the resources and with new application versions (not on every launch). Assuming the resources are under the HTML root package they can be displayed with code like this:
try {
browserComponent.setURLHierarchy("/htmlFile.html");
} catch(IOException err) {
/* omitted */
}Notice that the path is relative to the HTML directory and starts with / but inside the HTML files you should use
relative (not absolute) paths.
Also notice that an IOException can be thrown due to the process of untarring. Its unlikely to happen but is entirely possible.
7.28.3. NavigationCallback
At the core of the BrowserComponent you have the BrowserNavigationCallback. It might not seem like the most important interface within the browser but it’s the "glue" that allows the JavaScript code to communicate back into the Java layer.
You can bind a BrowserNavigationCallback by invoking setBrowserNavigationCallback on the BrowserComponent. At that point with every navigation within the browser the callback will get invoked.
The shouldNavigate method from the BrowserNavigationCallback is invoked in a native thread and NOT ON THE EDT!it’s crucial that this method returns and that it won’t do any changes on the UI. |
The shouldNavigate indicates to the native code whether navigation should proceed or not. For example: if a user clicks a specific link you might choose to do something in the Java code so you can return false and block the navigation. You can invoke https://www.codenameone.com/javadoc/com/codename1/ui/Display.html#callSerially java.lang.Runnable-[callSerially] to do the actual task in the Java side:
Form hi = new Form("BrowserComponent", new BorderLayout());
BrowserComponent bc = new BrowserComponent();
bc.setPage( "<html lang=\"en\">\n" +
" <head>\n" +
" <meta charset=\"utf-8\">\n" +
" <script>\n" +
" function fnc(message) {\n" +
" document.write(message);\n" +
" };\n" +
" </script>\n" +
" </head>\n" +
" <body >\n" +
" <p><a href=\"http://click\">Demo</a></p>\n" +
" </body>\n" +
"</html>", null);
hi.add(BorderLayout.CENTER, bc);
bc.setBrowserNavigationCallback((url) -> {
if(url.startsWith("http://click")) {
Display.getInstance().callSerially(() -> bc.execute("fnc('<p>You clicked!</p>')"));
return false;
}
return true;
});

The JavaScript Bridge is implemented on top of the BrowserNavigationCallback. |
7.28.4. JavaScript
| The JavaScript bridge is sometimes confused with the JavaScript Port. The JavaScript bridge allows you to communicate with JavaScript from Java (and vice versa). The JavaScript port allows you to compile the Codename One application into a JavaScript application that runs in a standard web browser without code changes (think GWT without source changes and with thread support).+ You discuss the JavaScript port further later in the guide. |
Use the BrowserComponent API to interact with JavaScript. It replaces the deprecated com.codename1.JavaScript package.
What was wrong with the old API
The old API provided a synchronous wrapper around an inherently asynchronous process, and made extensive use of invokeAndBlock() underneath the covers. This resulted in a nice API with high-level abstractions that played with a synchronous programming model, but it came with a price-tag in performance, complexity, and predictability. Let’s take a simple example, getting a reference to the "window" object:
This code looks harmless enough, but this is actually expensive. It issues a command to the BrowserComponent, and uses invokeAndBlock() to wait for the command to go through and send back a response. invokeAndBlock() is a magical tool that allows you to "block" without blocking the EDT, but it has its costs, and shouldn’t be overused. Most of the Codename One APIs that use invokeAndBlock() show this in their name. For example: Component.animateLayoutAndWait(). This provides you the expectation that this call could take some time, and helps to alert you to the underlying cost.
The problem with the ctx.get("window") call is that it looks the same as a call to Map.get(key). There’s no sign that this call is expensive and could take time. One call like this probably isn’t a big deal, but it doesn’t take long before you have dozens or even hundreds of calls like this littered throughout your codebase, and they can be hard to pick out.
The new API
The new API fully embraces the asynchronous nature of JavaScript. It uses callbacks instead of return values, and provides convenience wrappers with the appropriate "AndWait()" naming convention to allow for synchronous usage. Let’s look at a simple example:
In all the sample code below, you can assume that variables named bc represent an instance of BrowserComponent: |
This code should output "The result was 7" to the console. It’s fully asynchronous, so you can include this code anywhere without worrying about it "bogging down" your code. The full signature of this form of the execute() method is:
The first parameter is a JavaScript expression. This JavaScript MUST call either callback.onSuccess(result) or callback.onError(message, errCode) at some point in order for your callback to be called.
The second parameter is your callback that’s executed from the JavaScript side, when callback.onSuccess(res) is called. The callback takes a single parameter of type JSRef which is a generic wrapper around a JavaScript variable. JSRef has accessors to retrieve the value as some primitive types. For example: getBoolean(), getDouble(), getInt(), toString(), and it provides some introspection through the getType() method.
| It’s worth noting that the callback method can take a single parameter. If you need to pass many parameters, you may consider including them in a single string which you parse in your callback. |
Synchronous wrappers
As mentioned before, the new API also provides an executeAndWait() wrapper for execute() that will work synchronously. It, as its name suggests, uses invokeAndBlock under the hood so as not to block the EDT while it’s waiting.
For example:
Prints The result was 7.
When using the andWait() variant, it’s critical that your JavaScript calls your callback method at some point - otherwise it will block indefinitely. You provide variants of executeAndWait() that include a timeout in case you want to hedge against this possibility. |
Multi-use callbacks
The callbacks you pass to execute() and executeAndWait() are single-use callbacks. You can’t, for example, store the callback variable on the JavaScript side for later use (for example: to respond to a button click event). If you need a "multi-use" callback, you should use the addJSCallback() method instead. Its usage looks identical to execute(), the difference is that the callback will live on after its first use. For example: Consider the following code:
The above example, assumes that jQuery is loaded in the webpage that you’re interacting with, and you’re adding a click handler to a button with ID "somebutton." The click handler calls your callback.
If you run this example, the first time the button is clicked, you’ll see "Button was clicked" printed to the console as expected. For example, the 2nd time, you’ll get an exception. This is because the callback passed to execute() is single-use.
You need to change this code to use the addJSCallback() method as follows:
Now it will work no matter how many times the button is clicked.
Passing parameters to JavaScript
Often, the JavaScript expressions that you execute will include parameters from your Java code. Escaping these parameters is tricky at worst, and annoying at best. For example: If you’re passing a string, you need to make sure that it escapes quotes and new lines or it will cause the JavaScript to have a syntax error. You provide variants of execute() and addJSCallback() that allow you to pass your parameters and have them automatically escaped.
For example, suppose you want to pass a string with text to set in a textarea within the webpage. You can do something like:
The gist is that you embed placeholders in the JavaScript expression that are replaced by the corresponding entry in an array of parameters. The ${0} placeholder is replaced by the first item in the parameters array, the ${1} placeholder is replaced by the 2nd, etc.
Proxy objects
The new API also includes a JSProxy class that encapsulates a JavaScript object simplify the getting and setting of properties on JavaScript objects - and the calling of their methods. It provides essentially three core methods, along with many variants of each to allow for async or synchronous usages, parameters, and timeouts.
For example: You might want to create a proxy for the window.location object so that you can access its properties more from Java:
Then you can retrieve its properties using the get() method:
Or synchronously:
You can also set its properties:
And call its methods:
Legacy JSObject support
This section describes the now deprecated JSObject approach. It’s here for reference by developers working with older code. You suggest using the new API when starting a new project.
BrowserComponent can communicate with the HTML code using JavaScript calls. For example: you can create HTML like this:
Form hi = new Form("BrowserComponent", new BorderLayout());
BrowserComponent bc = new BrowserComponent();
bc.setPage( "<html lang=\"en\">\n" +
" <head>\n" +
" <meta charset=\"utf-8\">\n" +
" <script>\n" +
" function fnc(message) {\n" +
" document.write(message);\n" +
" };\n" +
" </script>\n" +
" </head>\n" +
" <body >\n" +
" <p>Demo</p>\n" +
" </body>\n" +
"</html>", null);
TextField tf = new TextField();
hi.add(BorderLayout.CENTER, bc).
add(BorderLayout.SOUTH, tf);
bc.addWebEventListener("onLoad", (e) -> bc.execute("fnc('<p>Hello World</p>')"));
tf.addActionListener((e) -> bc.execute("fnc('<p>" + tf.getText() +"</p>')"));
hi.show();
| Notice that opening an alert in an embedded native browser might not work |
You use the execute method above to execute custom JavaScript code. You also have an executeAndReturnString method that allows you to receive a response value from the JavaScript side.
Coupled with shouldNavigate you can effectively do everything which is what the JavaScript Bridge tries to do.
The JavaScript bridge
While it’s possible to build everything on top of execute and shouldNavigate, both of these methods have their limits. That’s why Codename One introduced the JavaScript package, it allows you to communicate with JavaScript using intuitive code/syntax.
The JavascriptContext class lays the foundation by enabling you to call JavaScript code directly from Java. It provides automatic type conversion between Java and JavaScript types as follows:
| Java Type | JavaScript Type |
|---|---|
|
|
|
|
|
|
|
|
|
|
| Not Allowed |
| JavaScript Type | Java Type |
|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| This conversion table is more verbose than necessary, since JavaScript functions and arrays are, in fact Objects themselves, so those rows are redundant. All JavaScript objects are converted to JSObject. |
You can access JavaScript variables from the context by using code like this:

Notice that when you work with numeric values or anything related to the types mentioned above your code must be aware of the typing. For example: in this case the type is Double and not String:
You can also query the context for objects and change their value for example:
This code effectively navigates to the Codename One home page by fetching the DOM’s window object and setting its location property to https://www.codenameone.com/.
7.28.5. Cordova/PhoneGap integration
PhoneGap was one of the first web app packager tools in the market: a tool that’s effectively a browser component within a native wrapper coupled with native access APIs, and Cordova is the open source extension of this popular project.
Codename One supports embedding PhoneGap/Cordova applications directly into Codename One applications. This is easy to do with the BrowserComponent and JavaScript integration. The main aspect that this integration requires is support for Cordova plugins & its JavaScript APIs.
The effort to integrate Cordova/PhoneGap support into Codename One is handled within an open-source GitHub project here. The chief benefits of picking Codename One rather than using Cordova directly are:
Build Cloud
Better Native Code Support
Better Protection Of IP
IDE Integration Java - JavaScript - HTML
Easy, doesn’t Require A Mac, Automates Certificates/Signing
Migration To Java
This is discussed further in the original announcement.
7.29. Text editors
RichTextArea and CodeEditor are introduced here as components, but editing is broad enough to have
its own chapter. See Chapter 8, Rich Text and Code Editing for rich HTML, syntax highlighting, completion, diagnostics,
touch and desktop selection, scrolling, bidirectional text, input methods, backend selection, and the
port-level TextInputClient contract.
7.30. AutoCompleteTextField
The AutoCompleteTextField allows you to write text into a text field and select a completion entry from the list in a similar way to a search engine.
This is easy to incorporate into your code, replace your usage of TextField with AutoCompleteTextField and define the data that the autocomplete should work from. A default implementation accepts a String array or a ListModel for completion strings, this can work well for a "small" set of thousands (or tens of thousands) of entries.
For example: This is a trivial use case that can work well for smaller sample sizes:
Form hi = new Form("Auto Complete", new BoxLayout(BoxLayout.Y_AXIS));
AutoCompleteTextField ac = new AutoCompleteTextField("Short", "Shock", "Sholder", "Shrek");
ac.setMinimumElementsShownInPopup(5);
hi.add(ac);
For example, if you wish to query a database or a web service you will need to derive the class and perform more advanced filtering by overriding the filter method:

7.30.1. Using images in AutoCompleteTextField
One question that comes up frequently is "How do you customize the results of the auto complete field"?
This sounds difficult to most people as you can work with Strings so how do you represent more data or format the date correctly?
The answer is actually pretty simple, you still need to work with Strings because autocomplete is fundamentally a text field. For example, that doesn’t preclude your custom renderer from fetching data that might be placed in a different location and associated with the result.
The following source code presents an autocomplete text field with images in the completion popup and two lines for every entry:
final String[] characters = { "Tyrion Lannister", "Jaime Lannister", "Cersei Lannister", "Daenerys Targaryen",
"Jon Snow", "Petyr Baelish", "Jorah Mormont", "Sansa Stark", "Arya Stark", "Theon Greyjoy"
// snipped the rest for clarity
};
Form current = new Form("AutoComplete", BoxLayout.y());
AutoCompleteTextField ac = new AutoCompleteTextField(characters);
final int size = Display.getInstance().convertToPixels(7);
final EncodedImage placeholder = EncodedImage.createFromImage(Image.createImage(size, size, 0xffcccccc), true);
final String[] actors = { "Peter Dinklage", "Nikolaj Coster-Waldau", "Lena Headey"}; (1)
final Image[] pictures = {
URLImage.createToStorage(placeholder, "tyrion","http://i.lv3.hbo.com/assets/images/series/game-of-thrones/character/s5/tyrion-lannister-512x512.jpg"),
URLImage.createToStorage(placeholder, "jaime","http://i.lv3.hbo.com/assets/images/series/game-of-thrones/character/s5/jamie-lannister-512x512.jpg"),
URLImage.createToStorage(placeholder, "cersei","http://i.lv3.hbo.com/assets/images/series/game-of-thrones/character/s5/cersei-lannister-512x512.jpg")
};
ac.setCompletionRenderer(new ListCellRenderer() {
private final Label focus = new Label(); (2)
private final Label line1 = new Label(characters[0]);
private final Label line2 = new Label(actors[0]);
private final Label icon = new Label(pictures[0]);
private final Container selection = BorderLayout.center(
BoxLayout.encloseY(line1, line2)).add(BorderLayout.EAST, icon);
@Override
public Component getListCellRendererComponent(com.codename1.ui.List list, Object value, int index, boolean isSelected) {
for(int iter = 0 ; iter < characters.length ; iter++) {
if(characters[iter].equals(value)) {
line1.setText(characters[iter]);
if(actors.length > iter) {
line2.setText(actors[iter]);
icon.setIcon(pictures[iter]);
} else {
line2.setText(""); (3)
icon.setIcon(placeholder);
}
break;
}
}
return selection;
}
@Override
public Component getListFocusComponent(com.codename1.ui.List list) {
return focus;
}
});
current.add(ac);
current.show();| 1 | you have duplicate arrays that are partial for clarity. This is a separate list of data element but you can fetch the more data from anywhere |
| 2 | You create the renderer UI instantly in the fields with the helper methods for wrapping elements which is pretty cool & terse |
| 3 | In a renderer it’s important to always set the value if you don’t have a value in place |

7.31. Picker
Picker occupies the limbo between native widget and lightweight widget. Picker is more like TextField/TextArea in the sense that it’s a Codename One widget that calls the native code during editing.
The reasoning for this is the highly native UX and functionality related to this widget type which should be obvious from the screenshots below.
At this time there are 4 types of pickers:
Time
Date & Time
Date
Strings
If a platform doesn’t support native pickers an internal fallback implementation is used. This is the implementation you always use in the simulator so assume different behavior when building for the device.
| While Android supports Date, Time native pickers it doesn’t support the Date & Time native picker UX and will fall back in that case. |
The sample below includes al picker types:
Form hi = new Form("Picker", new BoxLayout(BoxLayout.Y_AXIS));
Picker datePicker = new Picker();
datePicker.setType(Display.PICKER_TYPE_DATE);
Picker dateTimePicker = new Picker();
dateTimePicker.setType(Display.PICKER_TYPE_DATE_AND_TIME);
Picker timePicker = new Picker();
timePicker.setType(Display.PICKER_TYPE_TIME);
Picker stringPicker = new Picker();
stringPicker.setType(Display.PICKER_TYPE_STRINGS);
Picker durationPicker = new Picker();
durationPicker.setType(Display.PICKER_TYPE_DURATION);
Picker minuteDurationPicker = new Picker();
minuteDurationPicker.setType(Display.PICKER_TYPE_DURATION_MINUTES);
Picker hourDurationPicker = new Picker();
hourDurationPicker.setType(Display.PICKER_TYPE_DURATION_HOURS);
datePicker.setDate(new Date());
dateTimePicker.setDate(new Date());
timePicker.setTime(10 * 60); // 10:00AM = Minutes since midnight
stringPicker.setStrings("A Game of Thrones", "A Clash Of Kings", "A Storm Of Swords", "A Feast For Crows",
"A Dance With Dragons", "The Winds of Winter", "A Dream of Spring");
stringPicker.setSelectedString("A Game of Thrones");
hi.add(datePicker).add(dateTimePicker).add(timePicker)
.add(stringPicker).add(durationPicker)
.add(minuteDurationPicker).add(hourDurationPicker);
hi.show();








The text displayed by the picker on selection is generated automatically by the updateValue() method. You can override it to display a custom formatted value and call setText(String) with the correct display string.
A common use case is to format date values based on a specific appearance and Picker has built-in support for a custom display formatter. Just use the setFormatter(SimpleDateFormat) method and set the appearance for the field.
When using lightweight picker mode (setUseLightweightPopup(true)), you can add custom quick-action buttons to the popup. This is useful for actions like setting the date to "Today" or "+7 Days" without scrolling the wheels manually:
Button placement options are:
Picker.LightweightPopupButtonPlacement.BETWEEN_CANCEL_AND_DONE(default)Picker.LightweightPopupButtonPlacement.ABOVE_SPINNERPicker.LightweightPopupButtonPlacement.BELOW_SPINNER
7.32. SwipeableContainer
The SwipeableContainer allows you to place a component such as a MultiButton on top of more "options" that can be exposed by swiping the component to the side.
This swipe gesture is commonly used in touch interfaces to expose features such as delete, edit etc. It’s trivial to use this component by determining the components placed on top and bottom (the revealed component):
You can combine some demos above including the Slider stars demo to rank GRRM’s books in an interactive way:

7.33. EmbeddedContainer
EmbeddedContainer solves a problem that exists within the GUI builder and the class makes no sense outside of the context of the GUI builder.
The necessity for EmbeddedContainer came about due to iPhone inspired designs that relied on tabs (iPhone style tabs at the bottom of the screen) where different features of the application are within a different tab.
This didn’t mesh well with the GUI builder navigation logic and so it needed a rethink. The aim was to reuse GUI as much as possible while still enjoying the advantage of navigation being managed for you.
Android does this with Activities and the iPhone itself has a view controller, both approaches are problematic for Codename One. The problem is that you have what’s effectively two incompatible hierarchies to mix and match.
The Component/Container hierarchy is powerful enough to represent such a UI but you needed a "marker" to show to the UIBuilder where a "root" component exists so navigation occurs within the given "root." Here EmbeddedContainer comes into play, its a simple container that can contain another GUI from the GUI builder. Nothing else. You can place it in any form of UI and effectively have the UI change appropriately and navigation would default to "sensible values."
Navigation replaces the content of the embedded container; it finds the embedded container based on the component that broadcast the event. If you want to navigate manually use the showContainer() method which accepts a component, you can give any component that’s under the EmbeddedContainer you want to replace and Codename One will be smart enough to replace that component.
The nice part about using the EmbeddedContainer is that the resulting UI can be refactored to provide a more traditional form based UI without duplicating effort and can be adapted to a more tablet oriented UI (with a sidebar) again without much effort.
7.34. MapComponent
| The MapComponent uses a somewhat outdated tiling API which isn’t as rich as modern native maps. Recommend using the GoogleMap’s Native cn1lib to integrate native mapping functionality into the Codename One app. |
The MapComponent uses the OpenStreetMap webservice by default to display a navigatable map.
The code was contributed by Roman Kamyk and was originally used for a LWUIT application.

The screenshot above was produced using the following code:
The example below shows how to integrate the MapComponent with the Google Location API. Make sure to get your secret API key from the Google Location data API at: https://developers.google.com/maps/documentation/places/

7.35. Chart Component
The charts package enables Codename One developers to add charts and visualizations to their apps without
having to include external libraries or embedding web views. You also wanted to harness the new features in the
graphics pipeline to maximize performance.
7.35.1. Device support
Since the charts package makes use of 2D transformations and shapes, it requires some graphics features that aren’t yet available on all platforms. The following platforms are supported:
Simulator
Android
iOS
7.35.2. Features
Built-in support for many common types of charts including bar charts, line charts, stacked charts, scatter charts, pie charts and more.
Pinch Zoom - The ChartComponent class includes optional pinch zoom support.
Panning Support - The ChartComponent class includes optional support for panning.
7.35.3. Chart types
The com.codename1.charts package includes models and renderers for many different types of charts. It’s also
extensible so that you can add your own chart types if required. The following screenshots show a small
sampling of the types of charts that can be created.












| The above screenshots were taken from the ChartsDemo app. You can start playing with this app by checking it out from your git repository. |
7.35.4. How to create a chart
Adding a chart to your app involves four steps:
Build the model. You can construct a model (aka data set) for the chart using one of the existing model classes in the
com.codename1.charts.modelspackage. Essentially, this is where you add the data that you want to display.Set up a renderer. You can create a renderer for your chart using one of the existing renderer classes in the
com.codename1.charts.rendererspackage. The renderer allows you to specify how the chart should look. For example: the colors, fonts, styles, to use.Create the Chart View. Use one of the existing view classes in the
com.codename1.charts.viewspackage.Create a ChartComponent. To add your chart to the UI, you need to wrap it in a ChartComponent object.
You can check out the ChartsDemo app for specific examples, but here is a high-level view of some code that creates a Pie Chart:
7.36. Calendar
The Calendar class allows you to display a traditional calendar picker and optionally highlight days in various ways.
| You recommend developers use the Picker UI rather than use the calendar to pick a date. It looks better on the devices. |
Simple usage of the Calendar class looks something like this:

7.37. ToastBar
The ToastBar class allows you to display none-obtrusive status messages to the user at the bottom of the screen. This is useful for such things as informing the user of a long-running task (like downloading a file in the background), or popping up an error message that doesn’t require a response from the user.
Simple usage of the ToastBar class looks something like this:

You can show a progress indicator in the ToastBar like this:

You can automatically clear a status message/progress after a timeout using the setExpires method as such:
You can also delay the showing of the status message using showDelayed as such:

7.37.1. Actions in ToastBar
Probably the best usage example for actions in toast is in the gmail style undo. If you aren’t a gmail user then the gmail app essentially never prompts for confirmation!
It does whatever you ask and pops a "toast message" with an option to undo. If you clicked by mistake you have 3-4 seconds to take that back.
This simple example shows you how you can undo any addition to the UI in a similar way to gmail:
Form hi = new Form("Undo", BoxLayout.y());
Button add = new Button("Add");
add.addActionListener(e -> {
Label l = new Label("Added this");
hi.add(l);
hi.revalidate();
ToastBar.showMessage("Added, click here to undonull", FontImage.MATERIAL_UNDO,
ee -> {
l.remove();
hi.revalidate();
});
});
hi.add(add);
hi.show();7.38. SignatureComponent
The SignatureComponent provides a widget that allows users to draw their signature in the app.
Simple usage of the SignatureComponent class looks like:
Form hi = new Form("Signature Component");
hi.setLayout(new BoxLayout(BoxLayout.Y_AXIS));
hi.add("Enter Your Name:");
hi.add(new TextField());
hi.add("Signature:");
SignatureComponent sig = new SignatureComponent();
sig.addActionListener((evt)-> {
System.out.println("The signature was changed");
Image img = sig.getSignatureImage();
// Now we can do whatever we want with the image of this signature.
});
hi.addComponent(sig);
hi.show();
7.39. Accordion
The Accordion displays collapsible content panels.
Simple usage of the Accordion class looks like:
Form f = new Form("Accordion", new BoxLayout(BoxLayout.Y_AXIS));
f.setScrollableY(true);
Accordion accr = new Accordion();
accr.addContent("Item1", new SpanLabel("The quick brown fox jumps over the lazy dog\n"
+ "The quick brown fox jumps over the lazy dog"));
accr.addContent("Item2", new SpanLabel("The quick brown fox jumps over the lazy dog\n"
+ "The quick brown fox jumps over the lazy dog\n "
+ "The quick brown fox jumps over the lazy dog\n "
+ "The quick brown fox jumps over the lazy dog\n "
+ ""));
accr.addContent("Item3", BoxLayout.encloseY(new Label("Label"), new TextField(), new Button("Button"), new CheckBox("CheckBox")));
f.add(accr);
f.show();
7.40. Floating hint
FloatingHint wraps a text component with a special container that can animate the hint label into a title label when the text component is edited or has content within it:
Form hi = new Form("Floating Hint", BoxLayout.y());
TextField first = new TextField("", "First Field");
TextField second = new TextField("", "Second Field");
hi.add(new FloatingHint(first)).
add(new FloatingHint(second)).
add(new Button("Go"));
hi.show();
7.41. Floating Button
The material design floating action button is a powerful tool for promoting an action within your application.
FloatingActionButton is a round button that resides on top of the UI typically in the bottom right-hand side.
It has a drop shadow to distinguish it from the UI underneath and it can hide two or more actions under the surface. For example: you can create a simple single click button such as this:
FloatingActionButton fab = FloatingActionButton.createFAB(FontImage.MATERIAL_ADD);
fab.addActionListener(e -> ToastBar.showErrorMessage("Not implemented yetnull"));
fab.bindFabToContainer(form.getContentPane());Which will place a + sign button that will perform the action. Or you can create a nested action
where a click on the button will produce a submenu for users to pick from for example:
FloatingActionButton fab = FloatingActionButton.createFAB(FontImage.MATERIAL_ADD);
fab.createSubFAB(FontImage.MATERIAL_PEOPLE, "");
fab.createSubFAB(FontImage.MATERIAL_IMPORT_CONTACTS, "");
fab.bindFabToContainer(form.getContentPane());
Those familiar with this widget know that there are many nuances to this UI that may be implemented/exposed in the future. The current API is intentionally simple and minimal for the common use cases, with the plan to refine it based on feedback.
7.41.1. Using floating Button as a badge
Floating buttons can also be used to badge an arbitrary component in the style popularized by iOS/macOS. A badge appears in the top right corner and includes special numeric details such as unread count..
The code below adds a simple badge to a chat button:
Form hi = new Form("Badge");
Button chat = new Button("Chat");
FontImage.setMaterialIcon(chat, FontImage.MATERIAL_CHAT, 7);
FloatingActionButton badge = FloatingActionButton.createBadge("33");
hi.add(badge.bindFabToContainer(chat, Component.RIGHT, Component.TOP));
TextField changeBadgeValue = new TextField("33");
changeBadgeValue.addDataChangedListener((i, ii) -> {
badge.setText(changeBadgeValue.getText());
badge.getParent().revalidate();
});
hi.add(changeBadgeValue);
hi.show();The code above results in this, notice you can type into the text field to change the badge value:

7.42. SplitPane
The split pane component is a bit desktop specific but works reasonably well on devices. To get the image below you changed SalesDemo.java in the kitchen sink by changing this:
To:
private Container encloseInMaximizableGrid(Component cmp1, Component cmp2) {
return new SplitPane(SplitPane.VERTICAL_SPLIT, cmp1, cmp2, "25%", "50%", "75%");
}
This is self-explanatory but "mostly." you have 5 arguments the first 3 make sense:
Split orientation
Components to split
The last 3 arguments seem weird but they also make sense once you understand them, they’re:
The least position of the split - 1/4 of available space
The default position of the split - middle of the screen
The most position of the split - 3/4 of available space
The units don’t have to be percentages they can be mm (millimeters) or px (pixels).
8. Rich Text and Code Editing
Codename One includes two full-document editors. Use
RichTextArea when users
compose formatted prose and the application stores HTML. Use
CodeEditor for source code,
configuration files, queries, or any text that benefits from syntax highlighting, line numbers,
completion, and diagnostics. Both are lightweight Codename One components and share the same editing,
selection, scrolling, undo, and platform-input infrastructure. When you only need to display
formatted text — no editing — use
RichTextComponent, the
read-only, word-wrapping renderer described later in this chapter; it reuses the same document model
and styling engine.

8.1. Editor architecture and backend selection
Both components extend
AbstractEditorComponent.
The public components send semantic commands and queries to one of two backends:
A port can provide a native peer through
CodenameOneImplementation.createNativeEditorPeer(…).Otherwise the components use the pure Codename One engine in
com.codename1.ui.editor. It paints text, selections, carets, gutters, diagnostics, and completion UI withGraphicsandFont, and it drives keyboard and IME input through the low-level text-input contract.
Backend selection is transparent to application code. isNativeEditor() reports the native-peer case.
The pure engine is the default renderer on every platform; there is no browser fallback.
Editor initialization can be asynchronous for a native peer. Commands issued immediately after
construction are queued. Use onReady(Runnable) or a ready listener when work must run only after the
backend exists. Reads use callbacks (getHtml(…), getText(…), and getCursorPosition(…)) so
the same application code works with either backend.
8.1.1. The editor package
The com.codename1.ui.editor package separates editing mechanics from feature-specific rendering.
EditorDocument owns normalized UTF-16 text and line offsets. EditorView owns the caret, selection,
composition range, scrolling, hit testing, clipboard commands, and undo transactions. CodeView and
RichView extend that surface instead of creating independent input implementations.
The code layer adds incremental tokenization, palettes, completion, diagnostics, indentation, and the
line-number gutter. The rich layer keeps InlineStyles, RichBlocks, hyperlink targets, and image
runs parallel to the text. Every mutation, including undo and redo, updates those parallel models in
the same transaction. HtmlImporter and HtmlSerializer are model adapters; they don’t implement a
second HTML tokenizer. Fragment parsing and entity decoding go through the framework’s tolerant
HTMLParser, which extends XMLParser. The parser’s fragment mode retains modern attributes such as
data-* while the legacy HTMLComponent path keeps its existing validation behavior.
EditorHost is the narrow bridge between a view and its owner. It starts and stops platform text
input, pushes updated editing state to the port, and reports semantic editor events. This split lets
the same document and interaction engine run inside the full editors and inside the lightweight
EditField component.
8.2. Focus, change events, and editability
focusEditor() moves focus into the editing surface and opens the virtual keyboard when appropriate.
blurEditor() relinquishes focus and dismisses the active platform input session. setEditable(false)
keeps the document visible while preventing edits; CodeEditor.setReadOnly(true) is the code-oriented
equivalent.
Register an addChangeListener(…) listener to observe user edits and programmatic mutations. Avoid
saving on every keystroke when serialization or storage is expensive; debounce the listener, then read
the document through the asynchronous callback.
8.3. Platform text input and input methods
The pure editor doesn’t treat a key release as text. Modern input can come from a virtual keyboard,
autocorrect, dictation, handwriting, a hardware keyboard, or an input method editor (IME). The platform
therefore drives a
TextInputClient with
semantic operations:
commitText(…)inserts final text, including accepted autocorrect and dictation results.setComposingText(…)replaces the current marked-text range while an IME is still composing.finishComposing()finalizes that range.deleteSurroundingText(…)implements soft-keyboard deletion without manufacturing key codes.onKeyCommand(…)carries navigation, selection, clipboard, undo, and redo commands.Geometry methods map UTF-16 offsets to caret and selection rectangles so native candidate windows, selection handles, and accessibility UI align with the lightweight rendering.
TextInputConfig tells the
port which keyboard constraint, return-key action, autocorrection, capitalization, and multiline
behavior the client needs. Rich prose enables normal language assistance; source editing disables
autocorrection and automatic capitalization. The immutable
TextInputState returns the
authoritative text, selection, and composing range to the port after each edit.
All offsets in this contract are UTF-16 indices, matching Java String, Android Editable, and Apple
string indices. The document canonicalizes CRLF and bare CR line endings to LF before it updates the
caret, undo history, formatting runs, or platform state. Port authors must deliver composition updates
on the EDT and must stop the input session when the client loses focus.
TextInputClient, TextInputConfig, and TextInputState are general port-level APIs. Custom
lightweight editing components can implement the same protocol, but ordinary applications normally use
RichTextArea or CodeEditor and don’t bind an input client directly. |
8.4. Lightweight fields with EditField
TextArea and TextField keep their established native editing behavior. When an application wants
Codename One to retain control of painting, selection, scrolling, focus, and clipboard handling for a
plain field, use
EditField. It offers an API
familiar from TextField — hint text, constraint, single-line or multiline mode, rows and columns,
data-change listeners, and action events — but renders and edits entirely through the pure
com.codename1.ui.editor engine, with no native peer. Adoption is opt-in per component; existing
TextField and TextArea usages are unaffected.
EditField title = new EditField("", "Title", TextArea.ANY);
title.setSingleLineTextArea(true);
title.setColumns(80);
EditField notes = new EditField();
notes.setSingleLineTextArea(false);
notes.setRows(5);
notes.setColumns(30);EditField extends EditorView directly, so selection, caret navigation, arrow-key movement, undo,
and clipboard commands are the same mechanics the full editors use. A single-line EditField fires
its action event on the return key and strips embedded newlines; a multiline EditField grows to its
configured row count. Because there is no native overlay, the field behaves identically on every
platform that implements the low-level text-input contract.
8.5. Selection, bidirectional text, and scrolling
On touch devices, a tap places the caret, a long press selects a word, and draggable handles adjust the selection. The loupe follows a handle or long-press placement gesture. A normal one-finger drag scrolls the document and doesn’t turn the swipe into a selection. On desktop, mouse drag selects text, double-click selects a word, triple-click selects a line, and the mouse wheel or trackpad scrolls the document. Standard command/control shortcuts handle copy, cut, paste, select all, undo, and redo.
Hebrew, Arabic, and mixed left-to-right/right-to-left lines use Unicode bidirectional layout. Glyph painting, hit testing, caret movement, and selection rectangles share the same visual runs. Set the component’s RTL flag to choose the paragraph base direction.
8.6. RichTextArea
RichTextArea accepts and returns an HTML fragment. The importer maps common paragraph, heading,
blockquote, preformatted, list, link, image, bold, italic, underline, strike-through, color, highlight,
and relative-size markup into a document model. getHtml(…) emits canonical HTML from that model; it
preserves meaning rather than the input’s exact whitespace, tag aliases, or attribute order.
Form hi = new Form("Compose", new BorderLayout());
RichTextArea editor = new RichTextArea();
editor.setPlaceholder("Write something...");
editor.setHtml("<h2>Trip itinerary</h2><p>Meet at the <b>main lobby</b>.</p>");
Toolbar tb = hi.getToolbar();
tb.addCommandToRightBar("B", null, e -> editor.bold());
tb.addCommandToRightBar("I", null, e -> editor.italic());
tb.addCommandToRightBar("List", null, e -> editor.insertUnorderedList());
tb.addCommandToRightBar("Save", null, e ->
editor.getHtml(html -> Log.p("User wrote: " + html)));
hi.add(BorderLayout.CENTER, editor);
hi.show();
The formatting methods act on the current selection: bold(), italic(), underline(),
strikeThrough(), ordered and unordered lists, indentation, alignment, foreground and highlight
colors, block formats, and font sizes. queryCommandState(…) keeps toolbar toggles synchronized with
the selection. removeFormat() clears inline formatting; undo() and redo() restore text together
with inline styles, paragraph attributes, links, and image runs.
Use setHtml(…) to replace the document and insertHtml(…) to insert a fragment at the selection.
Fragment insertion retains its formatting and block structure. createLink(url) stores the target in
the model, and removeLink() removes it. insertImage(url) accepts normal URLs, data URIs, and supported
application resources; the source is retained so getHtml(…) can emit an img element when the
document is saved and reloaded.
8.6.1. HTML, RTF, Markdown, and AsciiDoc
setContent(…) and insertContent(…) accept a RichTextFormat. HTML is parsed directly with the
shared HTMLParser. Markdown and AsciiDoc use their own bidirectional model adapters; they never pass
through HTML. Headings, emphasis, inline code, links, images, lists, quotes, and literal blocks are
mapped directly to the rich model and serialized directly back with getMarkdown(…) or
getAsciiDoc(…). The RTF importer likewise maps paragraph breaks, Unicode escapes, bold, italic,
underline, strike-through, and skips metadata destinations such as font and color tables.
Editing and reading the same format returns canonical output for that format. Requesting a different
output format performs an explicit model conversion, just as getHtml(…) canonicalizes a visual
rich-text document.
editor.setContent("# Release notes\n\nThis is **ready**.", RichTextFormat.MARKDOWN);
editor.insertContent("{\\rtf1\\ansi {\\i pasted notes}}", RichTextFormat.RTF);
editor.insertContent("== Details\n\n* Portable\n* Lightweight", RichTextFormat.ASCIIDOC);Rich paste uses ClipboardContent, a MIME-keyed container exposed by Display.copyToClipboard(…)
and Display.getClipboardContent(). RichTextClipboardData is its convenience subtype for
text/plain, text/html, text/rtf, text/markdown, and text/asciidoc. A writer publishes all
representations in one operation and a reader selects the richest format it understands; plain
EditorView consumers use text/plain. Copying a rich selection publishes canonical HTML, RTF,
Markdown, AsciiDoc, and the required plain fallback. Java SE publishes native DataFlavor values,
Android publishes native plain and HTML clip data, the JavaScript port uses ClipboardItem when the
browser allows it, and iOS publishes pasteboard types. A port that only has a text clipboard still
publishes plain text externally and retains the complete ClipboardContent for in-application use.
The negotiation API belongs at the implementation boundary, not inside RichTextArea. Port authors
override clipboard handling in CodenameOneImplementation and return the formats actually present on
the system clipboard. Applications can use the same API for domain-specific formats without changing
the editor.
RTF is also recognized when a clipboard provider returns it as a string beginning with an RTF header. Format import is intentionally a practical interchange subset, not a layout-compatible word processor: unsupported RTF destinations and advanced Markdown or AsciiDoc extensions degrade to the supported text and structure rather than controlling document layout.
| Treat imported HTML as document data, not as a browser page. The pure importer doesn’t execute scripts. Keep image URLs and link destinations subject to the same trust and validation rules used by the rest of the application. |
8.7. Read-only rich text with RichTextComponent
RichTextComponent (in com.codename1.ui) is the read-only counterpart to RichTextArea. It renders
multi-styled, word-wrapped text — headings, bold, italic, underline, strike-through, inline code,
colored and highlighted spans, per-paragraph alignment and indentation, ordered and unordered lists,
block quotes, preformatted blocks, inline images, and tappable hyperlinks — without any of the editing
machinery. It sits between a single-style SpanLabel (one style for the whole component) and a full
BrowserComponent (a native web view): a lightweight native component that keeps a distinct style per
character, measures and paints text directly, and reports an accurate height-for-width preferred size,
so it embeds cleanly inside ordinary layouts. It’s the modern replacement for the deprecated
HTMLComponent.
It shares the editor’s document model and the RichRunPainter styling primitive, so styled text
rendered read-only matches what the editor produces for the same content.
Content is supplied in any of the interchange formats the rich model understands, or built up programmatically from styled runs:
RichTextComponent view = new RichTextComponent();
// From Markdown, HTML, or any RichTextFormat:
view.setMarkdown("# Trip summary\n\n"
+ "Departs **09:40**, arrives *11:15*. See the [itinerary](app://itinerary) for details.\n\n"
+ "- Window seat\n"
+ "- Carry-on only");
// view.setHtml("<h1>Trip summary</h1><p>Departs <b>09:40</b> ...</p>");
// view.setContent(source, RichTextFormat.ASCIIDOC);
// Or assembled run by run with editor TextStyle values:
RichTextComponent built = new RichTextComponent();
built.append("Status: ", TextStyle.DEFAULT)
.append("confirmed", TextStyle.DEFAULT.withBold(true).withForeColor(0x1a7f37));
form.add(view);Hyperlinks in the content fire an ActionListener whose event source is the link target string, so the
application decides what a link means:
view.addLinkListener(e -> Display.getInstance().execute((String) e.getSource()));The component resolves inline images through an ImageResolver, keeping image loading and caching policy
in the application rather than the component. Return null to render a placeholder:
view.setImageResolver(src -> myImageCache.get(src));By default (SizeMode.SHRINK) the component is exactly as tall as its wrapped content at the width it
is given, which is ideal inside a scrollable Form. SizeMode.SCROLL instead keeps the size the
parent assigns and scrolls the content vertically. setTextAlign(…) overrides the alignment of every
paragraph, and preferredSizeForWidth(width) is a stateless height-for-width query for custom layout
managers.
The same trust guidance applies as for RichTextArea — imported HTML is document data, not a
browser page; validate link targets and image sources with the application’s own rules. |
8.8. CodeEditor
CodeEditor provides incremental highlighting for java, kotlin, javascript, python, css,
xml, json, and c. It includes a line-number gutter, light and dark palettes, automatic bracket and
quote closing, tab expansion, automatic indentation, horizontal and vertical scrolling, and read-only
viewing.
Form hi = new Form("Editor", new BorderLayout());
CodeEditor editor = new CodeEditor();
editor.setLanguage("java");
editor.setTheme("light"); // or "dark"
editor.setShowLineNumbers(true);
editor.setText("public class Main {\n\n}");
hi.add(BorderLayout.CENTER, editor);
hi.show();
Choose the language with setLanguage(…), select "light" or "dark" with setTheme(…), toggle
the gutter with setShowLineNumbers(…), and configure indentation with setTabSize(…).
insertAtCursor(…) replaces the active selection, while getCursorPosition(…) reports the current
UTF-16 caret offset asynchronously.
The Codename One Playground uses CodeEditor directly for its Java and CSS source panes. This
uses the same language highlighting, line-number gutter, keyboard navigation, diagnostics, and
diagnostic tooltips available to applications. Compiler diagnostics are passed to
setDiagnostics(…) with their source ranges; status messages use lightweight Codename One
components beneath the editor. The Playground doesn’t install or bundle a separate editor engine.
Source editing disables platform spelling and autocorrection; the only wavy underlines the editor
draws are diagnostics supplied through setDiagnostics(…).
8.8.1. Custom syntax highlighters
Built-in languages use grammar-specific incremental lexical analyzers. JSON doesn’t accept single-quoted
strings, CSS doesn’t interpret // as a comment, XML tracks tags and attributes, Python carries
triple-quoted strings across lines, and C-family numeric prefixes are validated by radix. These rules
are lexical by design; a compiler or language server remains the authority for diagnostics.
Third-party libraries can register a SyntaxHighlighter under any language ID. The highlighter
receives one line and the state returned for the preceding line, then returns ordered token spans and
the next state. Tokens can use the built-in semantic kinds or provide explicit light and dark RGB
colors. Registration is global and the pure renderer invokes the Java highlighter directly, so a
custom language needs no platform-specific grammar.
SyntaxHighlighter properties = (line, state) -> {
List<SyntaxToken> tokens = new ArrayList<>();
int equals = line.indexOf('=');
if (equals > 0) {
tokens.add(new SyntaxToken(0, equals, SyntaxToken.PROPERTY,
0x005cc5, 0x9cdcfe));
}
return new SyntaxHighlightResult(tokens, 0);
};
CodeEditor.registerSyntaxHighlighter("properties", properties);
CodeEditor editor = new CodeEditor("properties", "accent=#0a66c2");8.8.2. Asynchronous code completion
A CodeCompletionProvider receives the complete source and caret offset, then delivers proposals
through its callback. The callback can run after a local analysis or network/language-server request;
the editor doesn’t block the EDT while proposals are produced.
editor.setCompletionProvider((sourceEditor, code, cursor, results) -> {
List<CodeCompletion> proposals = new ArrayList<>();
proposals.add(new CodeCompletion("println(String value)", "println()")
.setType("method")
.setDetail("void"));
proposals.add(new CodeCompletion("private").setType("keyword"));
results.onSucess(proposals);
});Return an empty list or null to dismiss the popup. A proposal can use different display and insertion
text, plus a type badge and detail string.
8.8.3. Diagnostics
setDiagnostics(…) accepts 1-based source ranges. Errors, warnings, and informational entries appear
under only the supplied character range, with a gutter marker for the affected line. Hover the range
or marker on desktop, or tap it on touch devices, to display its message.
editor.setDiagnostics(Arrays.asList(
new CodeDiagnostic(6, 9, 6, 16, "Cannot resolve method prinln")
.setSeverity(CodeDiagnostic.ERROR),
new CodeDiagnostic(3, 5, "Value is never read")
.setSeverity(CodeDiagnostic.WARNING)
));Replace the list whenever a compiler, linter, or language server publishes a newer analysis. Passing an empty list clears the current diagnostics.
8.9. Port integration checklist
The pure engine drives the editors on every platform, so a port must implement the low-level
text-input contract: isTextInputSupported(), startTextInput(…), updateTextInputState(…), and
stopTextInput(…) in CodenameOneImplementation. The binding must distinguish committed from
composing text, preserve UTF-16 offsets, map native navigation and clipboard actions to
TextInputClient.KEY_*, update native selection state after programmatic edits, and anchor candidate
UI with the supplied caret geometry.
A port with a better platform editor can instead supply a native peer and implement the existing semantic command/query channel. In both cases application code, change listeners, ready handling, and asynchronous queries remain the same.
Accessibility Semantics
Codename One components are lightweight: they’re painted by Codename One instead of being represented by a native widget on every platform. The accessibility semantics API builds an explicit, immutable virtual tree from those components and presents it to VoiceOver, TalkBack, Windows UI Automation, AT-SPI, Java Access Bridge, and web accessibility APIs.
The semantic tree is separate from the visual tree. This is important for renderer-backed controls, merged cards, decorative content, custom controls, and applications that need a reading order different from paint order.
9. Built-in semantics
Standard components work without extra configuration. Button, CheckBox, RadioButton, Slider, text fields, lists, tables, tabs, labels, dialogs, and containers infer appropriate roles, values, states, collection metadata, and standard actions. Renderer-backed List rows are exposed as stable virtual children even though no Component exists for each painted row.
Component.setAccessibilityText() remains supported. It’s a compatibility alias for the semantic label. New code should use getSemantics() when it needs more than a label.
Button save = new Button("Save");
save.getSemantics()
.setHint("Saves the edited profile")
.setIdentifier("profile-save");Changes to text, selection, focus, enabled state, bounds, scrolling, ranges, tabs, and the current Form automatically invalidate the native semantic tree. Custom components should call accessibilityChanged() after a semantic value changes outside a standard setter.
10. Roles, names, values, and state
AccessibilityRole contains portable control roles including buttons, toggle buttons, switches, checkboxes, radio buttons, headings, links, images, text and search fields, sliders, progress indicators, lists, grids, rows, cells, headers, tabs, dialogs, alerts, menus, toolbars, combo boxes, trees, and separators. A port maps an unsupported role to the closest native role without discarding its label or state.
wifiSwitch.getSemantics()
.setRole(AccessibilityRole.SWITCH)
.setLabel("Wi-Fi")
.setChecked(AccessibilityCheckedState.CHECKED)
.setEnabled(Boolean.TRUE)
.setHint("Double tap to turn Wi-Fi off");title.getSemantics() .setHeadingLevel(2) .setIdentifier("network-heading");
Tri-state controls use UNCHECKED, CHECKED, or MIXED. Nullable Boolean properties distinguish an explicit state from an unspecified state. Available properties include selected, expanded, enabled, invalid, busy, read-only, required, multiline, obscured, pressed, and current. setValidationError() supplies both the error message and invalid state. setPaneTitle() describes a newly displayed pane or screen, and setModal(true) identifies a modal scope.
Use setRoleDescription() only when the platform role isn’t sufficiently specific. Localize labels, hints, descriptions, errors, pane titles, role descriptions, and custom action labels.
11. Ranges and editable values
AccessibilityRange describes minimum, maximum, current value, increment, and an optional spoken value. The spoken value is useful for ranges such as ratings and durations where a raw number is ambiguous.
rating.getSemantics()
.setRole(AccessibilityRole.SLIDER)
.setLabel("Rating")
.setRange(new AccessibilityRange(0, 5, 3, 1, "3 out of 5"));Editable controls can provide SET_VALUE or SET_TEXT actions. Sliders and other adjustable controls should expose INCREMENT and DECREMENT. Standard components infer these actions.
12. Custom accessibility actions
An AccessibilityAction has a stable ID, a localized label, an enabled state, and a handler. Handlers always execute on the Codename One EDT, including when the action originates on a native accessibility thread.
card.getSemantics().addAction(new AccessibilityAction(
"archive",
"Archive message",
new AccessibilityAction.Handler() {
public boolean perform(Component component, Object argument) {
archiveMessage();
return true;
}
}
));Use the standard IDs in AccessibilityAction for activation, long press, increment, decrement, set value, set text, selection, character or word cursor movement, focus, show-on-screen, dismiss, expand, collapse, scrolling, and clipboard operations. A custom ID must be stable and its label must not be null.
13. Grouping and virtual descendants
AccessibilityGrouping controls how a component participates in the semantic tree:
AUTOuses normal component inference.LEAFexposes the component but none of its descendants.GROUPexposes the component as a semantic container and retains its descendants.MERGE_DESCENDANTScombines descendant labels, descriptions, values, state, and actions into one node.EXCLUDEremoves the component but promotes its descendants to the semantic parent.EXCLUDE_SUBTREEremoves the component and all descendants.
summaryCard.getSemantics()
.setRole(AccessibilityRole.GENERIC)
.setGrouping(AccessibilityGrouping.MERGE_DESCENDANTS);For content that’s painted without child components, attach an AccessibilityChildProvider, or add standalone AccessibilityNode children. Every virtual node must use a stable virtualKey. Stable keys preserve native focus while rows are updated or recycled.
chart.getSemantics().setChildProvider(new AccessibilityChildProvider() {
public List<AccessibilityNode> getAccessibilityChildren(Component owner) {
List<AccessibilityNode> result = new ArrayList<AccessibilityNode>();
for (ChartPoint point : points) {
AccessibilityNode node = new AccessibilityNode("point-" + point.getId());
node.setRole(AccessibilityRole.IMAGE)
.setLabel(point.getLabel())
.setValue(point.getFormattedValue())
.setBounds(point.getBounds());
result.add(node);
}
return result;
}
});Virtual bounds are relative to the owning component. Component nodes use their clipped absolute bounds.
14. Traversal order
Visual order is the default reading order. setSortKey() assigns an ordered semantic key among siblings. setTraversalBefore() and setTraversalAfter() express a direct relationship when a numeric order would be fragile.
cancel.getSemantics().setSortKey(1);
continueButton.getSemantics().setSortKey(2);
help.getSemantics().setTraversalAfter(continueButton);Keep traversal relationships within the same semantic parent. The tree builder resolves these constraints deterministically and preserves stable node IDs.
15. Live regions and screen changes
Set AccessibilityLiveRegion.POLITE for non-urgent updates and ASSERTIVE for errors or urgent status. OFF is the default. Live changes produce the corresponding platform notification or ARIA live update.
status.getSemantics()
.setRole(AccessibilityRole.ALERT)
.setLiveRegion(AccessibilityLiveRegion.POLITE);
status.setText("Upload complete");Form changes and nodes with a pane title produce screen or pane transition notifications. Display.announceForAccessibility() remains available for an exceptional announcement that isn’t represented by persistent UI. Prefer a live region for state that’s visible on screen.
16. User accessibility preferences
Semantics describe what a control means. Accessibility preferences describe how the user wants the interface presented. Read these preferences through Display or the matching static shortcuts in CN:
| API | Meaning |
|---|---|
| The user requests stronger foreground and background contrast. |
| The user requests labels, shapes, or patterns in addition to color. |
| Returns |
| Nonessential motion should be removed or replaced with an instant or cross-fade change. |
| Blur and translucent surfaces should use an opaque alternative. |
| The system requests a heavier text weight. |
| The operating system is transforming the displayed colors. |
| Switches should include a visible on/off distinction. |
| A screen reader or touch-exploration service is active. |
An unavailable preference returns false; an unavailable color-vision mode returns UNKNOWN. Don’t hide accessibility support behind isScreenReaderEnabled(). A screen reader can start after the application launches, and other assistive technologies consume the same semantic tree.
if (CN.isHighContrastEnabled()) {
animatedChart.setUIID("HighContrastChart");
}
// Important state always uses text or an icon as well as color. The
// preference is an extra signal, not permission to use color alone.
if (CN.isDifferentiateWithoutColorEnabled()
|| CN.getColorVisionDeficiency() != AccessibilityColorVisionDeficiency.NONE) {
connectionStatus.setText("Disconnected: action required");
}
if (CN.isReduceMotionEnabled()) {
animatedChart.putClientProperty("animate", Boolean.FALSE);
}
if (CN.isReduceTransparencyEnabled()) {
animatedChart.setUIID("OpaqueChart");
}Never use getColorVisionDeficiency() == NONE as permission to convey information only through color. The setting can be unavailable, a person might not enable a system filter, and contrast can change with lighting and display hardware. Design the default interface with redundant cues, then use preferences for further adaptation. |
Preference detection uses each platform’s public signals. iOS and Mac Catalyst expose contrast, differentiate-without-color, motion, transparency, bold text, inversion, grayscale, switch labels, and VoiceOver; Apple doesn’t expose the selected color-filter type, so the deficiency value is UNKNOWN. Android reads high-text contrast, display inversion and color-correction mode, animation scale, font-weight adjustment, and touch exploration. Windows reads High Contrast, client-area animation, and screen-reader settings. Linux detects the GTK HighContrast theme, disabled GTK animation, and ATK bridge activation. JavaScript uses forced-colors, prefers-contrast, prefers-reduced-motion, and prefers-reduced-transparency. The Java SE simulator provides deterministic controls for every portable signal.
17. Collections
AccessibilityCollectionInfo describes row and column counts, hierarchy, and selection mode. AccessibilityCollectionItemInfo describes row and column index, spans, position and size in a set, nesting level, and header status.
grid.getSemantics().setCollectionInfo(
new AccessibilityCollectionInfo(20, 3, false,
AccessibilityCollectionInfo.SELECTION_MULTIPLE));cell.getSemantics().setCollectionItemInfo( new AccessibilityCollectionItemInfo( 4, 1, 2, 1, 5, 20, 1, false));
Row and column indexes are zero-based. Position and set size are one-based; use -1 when unknown. Lists, tables, tabs, and their items infer this metadata where possible.
Renderer-backed lists keep the full model size in their collection metadata but materialize only the visible rows, a small navigation buffer, and the selected row as virtual children. Forward and backward semantic scroll actions move the window. This keeps accessibility-tree work proportional to the viewport instead of invoking a cell renderer for every row whenever a large list scrolls.
18. Inspecting and testing semantics
AccessibilityInspector returns an immutable snapshot. A snapshot is safe to inspect without racing native accessibility callbacks and includes stable IDs, hierarchy, bounds, resolved state, actions, range and collection data. toJson() is suitable for diagnostic reports and tooling.
Semantic setters always mark the cached tree dirty. Pull-based native ports rebuild it on the Codename One EDT only while assistive technology is active or when a tool explicitly requests a snapshot; the browser keeps its off-screen ARIA projection synchronized continuously. Applications should still publish complete semantics unconditionally—this runtime optimization is transparent to application code.
AccessibilityTreeSnapshot tree =
AccessibilityInspector.snapshot(myForm);AccessibilityAssertions.assertNoErrors(tree); AccessibilityAssertions.assertNoUnlabeledInteractiveNodes(tree);
String diagnosticJson = tree.toJson(); AccessibilityNodeSnapshot hit = tree.getNodeAt(screenX, screenY);
AccessibilityAssertions.audit() reports machine-readable AccessibilityIssue values for unlabeled controls, invalid ranges, duplicate identifiers or actions, invalid collection positions, missing parents, cycles, unnamed dialogs, and unlabeled custom actions. Warnings also identify suspicious role/state combinations and empty bounds.
The Java SE Component Inspector provides Copy Accessibility Tree JSON and Audit Accessibility Tree actions. Tests should assert resolved semantic properties instead of platform-specific spoken sentences. The scripts/hellocodenameone suite contains the cross-port conformance fixture used by native CI.
19. Diagnosing and correcting an inaccessible screen
Accessibility review works best as a repeatable loop instead of a final checklist:
Use the keyboard to reach every operation. Verify visible focus, logical order, escape from modal UI, and operation without pointer gestures.
Open Tools → Component Inspector. Select the form or a suspicious component, then choose Audit Accessibility Tree. Start with errors, such as an unlabeled interactive node, invalid range, or unnamed dialog.
Choose Copy Accessibility Tree JSON and inspect the resolved role, label, value, state, actions, bounds, and child order. This catches cases where the visual component hierarchy doesn’t match the virtual accessibility hierarchy.
Use Simulate → Accessibility Preferences to test high contrast, reduced motion, reduced transparency, inversion, grayscale, and each color-vision filter. Also test Simulate → Larger Text at Accessibility 5. Look for clipped text, color-only state, invisible focus, unreadable overlays, and motion that remains essential to understanding the result.
Correct the component API or theme. Run the audit again, add a focused assertion, and verify the native screen reader before considering the issue closed.
The simulator menu changes the values returned by Display and CN. Color-vision, inversion, and grayscale choices also filter the simulator canvas, so screenshots show approximately what remains distinguishable. These filters are diagnostic approximations; they don’t replace testing with platform display filters or users.

The following icon-only custom control is painted and responds to a pointer, but initially has no usable name, role, or keyboard-equivalent action. The audit reports it as an unlabeled interactive node. Repair the semantic contract at the custom-control boundary:
iconOnlyButton.getSemantics()
.setRole(AccessibilityRole.BUTTON)
.setLabel("Delete message")
.setHint("Removes this message from the conversation")
.setIdentifier("message-delete")
.addAction(new AccessibilityAction(
AccessibilityAction.ACTIVATE,
null,
new AccessibilityAction.Handler() {
public boolean perform(Component component, Object argument) {
deleteMessage();
return true;
}
}));Don’t fix the warning by adding a label alone if the role, current state, range, or available actions are still wrong. For example, a custom switch needs SWITCH, checked state, and activation; a chart needs virtual descendants for its meaningful data points; a renderer-backed grid needs collection and item metadata.

19.1. Assertions that prevent regressions
Snapshot the finished form and assert behavior that matters to a user. Prefer stable identifiers and resolved semantics over implementation class names or platform-specific speech:
AccessibilityTreeSnapshot tree = AccessibilityInspector.snapshot(form);
AccessibilityAssertions.assertNoErrors(tree);
AccessibilityAssertions.assertNoUnlabeledInteractiveNodes(tree);
AccessibilityNodeSnapshot save = tree.getNodeByIdentifier("profile-save");
assert save.getRole() == AccessibilityRole.BUTTON;
assert save.getAction(AccessibilityAction.ACTIVATE) != null;Keep targeted assertions for traversal order, validation errors, live-region behavior, ranges, and stable virtual keys. The scripts/hellocodenameone accessibility fixture invokes every portable preference API and exercises the resolved semantic tree on each native CI platform.
19.2. Native verification
The simulator finds portable problems, but the final pass must use VoiceOver, TalkBack, Narrator, Orca, or the browser accessibility tree. Navigate in both directions, activate every action, change adjustable values, enter and leave collections, trigger errors, and confirm that focus moves sensibly after a dialog, navigation, deletion, or live update. Record the platform, assistive-technology version, input method, and failed semantic node in the bug report; attach the inspector JSON when the native result differs from the portable snapshot.
20. Platform mappings
| Target | Native representation | Notable behavior |
|---|---|---|
iOS, iPadOS, and Mac Catalyst |
| Traits, values, frames, custom actions, adjustable actions, live announcements, and screen/layout transitions |
Android |
| Class/role mapping, checked and mixed state, headings, pane titles, errors, ranges, collections, focus, hit testing, and custom actions |
Windows native | UI Automation fragment-root provider | Virtual fragments, control types, names, values, state, bounds, navigation, focus lookup, hit testing, and action dispatch |
Linux native | Transparent GTK semantic widgets exposed through ATK/AT-SPI | Roles, names, descriptions, state, hierarchy, bounds, and action dispatch |
Java SE simulator and desktop | Swing | Roles, states, values, geometry, accessible actions, and Component Inspector integration |
JavaScript | A synchronized off-screen DOM tree | ARIA roles, names, state, ranges, live regions, collection metadata, traversal order, and action routing; the painted canvas is hidden from the accessibility tree |
The API intentionally goes beyond a label-only model: it includes stable virtual children, explicit traversal constraints, collection spans and set metadata, pane transitions, machine-readable inspection, and built-in semantic audits. Platform accessibility tools remain the final verification step because screen readers can apply platform-specific presentation rules.
For underlying platform guidance, see the Apple UIAccessibility protocol, Android accessibility principles, Microsoft UI Automation provider overview, and W3C WAI-ARIA.
MCP Headless API
The Model Context Protocol (MCP) headless API lets an application expose itself to a large language model agent. An agent such as Claude Desktop, Claude Code, Codex, or opencode can read the current screen, drive the user interface, and call tools the application publishes.
The API reuses the accessibility semantics tree. The same immutable tree that describes the screen to VoiceOver and TalkBack also describes it to the agent, so any application is drivable without extra code. Application specific data and actions are exposed through the existing com.codename1.ai.Tool contract.
The socket transport runs anywhere the port can bind the loopback interface, which includes an application running on a device, so an agent can attach to a build on a phone as well as to the simulator. It’s blocked on a release build; see Development builds only. The stdio transport needs process standard input and so is supported by the JavaSE port, which powers the simulator and the desktop tooling.
21. The MCP menu
Every desktop Codename One tool, including the simulator and Codename One Settings, gets a native MCP pull-down menu. The menu is added by the JavaSE port, so a tool gets it without any code of its own. It’s the main way a user turns a tool into something an agent can drive.
The menu has these items:
Expose This Tool To Agents starts and stops the loopback MCP server for the running tool.
Install in MCP Hosts registers this tool with the MCP hosts detected on the machine, such as Claude Desktop, Claude Code, Codex, and opencode. After a host restarts, the tool appears as an MCP server the agent can use.
Remove From MCP Hosts removes that registration.
Detect MCP Hosts lists the hosts found on the machine and where their configuration lives.
Debug Logging controls how much of the MCP conversation is echoed to the log.
Install writes a command that launches MCPStdioLauncher, a small bridge that relays the host’s standard input and output to the running tool’s socket. Hosts speak stdio and the tool serves a socket, so the bridge lets a stdio host such as Claude Desktop drive the already-running, human-visible tool.
22. Starting the server
Invoking the API is the switch. There is no build hint or property to set. The socket server lets an agent attach to a session a person is watching, which is the usual choice in the simulator:
MCP.startSocketServer(8765);A tool that a host launches as a subprocess can serve over standard input and output instead:
MCP.startStdioServer();The stdio transport is the standard MCP local transport, exchanging newline delimited JSON-RPC messages. While it runs, application logging is redirected away from standard output so it can’t corrupt the protocol stream. The stdio transport lives in the JavaSE port because it needs process standard input, which isn’t available on every target.
23. Development builds only
The socket server refuses to bind on a release build and throws an IllegalStateException instead.
The reason is what an attached agent can do. It reads the screen and drives the user interface, and the loopback interface is shared by everything on the device rather than being private to one application. On a phone that means any other installed application can connect to the port and drive yours. That’s a reasonable trade while you’re developing, because it’s how an agent attaches to a running build, and a poor one in an application a user installs.
A development build is a debuggable Android package or a development provisioned iOS build. Any other target counts as a release build, so a port that can’t tell the difference withholds the server rather than exposing it.
The JavaSE port is the exception, and it’s worth understanding before you rely on this. That port runs the simulator, the designer and the desktop tooling, and it can’t distinguish those from a desktop application packaged for distribution: there’s no debuggable flag and no provisioning profile to read. It reports a development build in every case, because reporting otherwise would take the MCP menu away from every desktop tool. A packaged desktop application is therefore not gated by this, and one that needs to withhold the server from its own release build has to supply that signal itself.
Nothing binds a port unless the application calls a starter, and an application that never calls one has no server at all. The gate matters for the case where a starter is left in the code by accident, which is the way a debugging facility usually reaches production.
The same distinction is available to application code, so a starter can be left in place and simply not fire in a shipped build:
if (Display.getInstance().isDebuggableBuild()) {
MCP.startSocketServer(8765);
}A build that ships to devices you control, such as a kiosk fleet, a test lab, or a managed enterprise deployment, can lift the block:
MCP.setAllowOnReleaseBuilds(true);
MCP.startSocketServer(8765);Treat that call the way you’d treat any other decision to expose a control surface, because the device itself becomes the boundary.
24. Built-in user interface tools
Every server registers a small set of tools that read and drive the screen through the accessibility tree. An agent calls ui_snapshot to get the semantics tree of the current form as JSON, including the identifier, role, label, value, and state of each node, and the identifiers of the actions each node supports.
The agent drives the screen with ui_perform_action, which performs an action such as activate or setText on a node from the snapshot. The convenience tools ui_activate and ui_set_text wrap the common cases, and ui_find locates nodes by identifier, by label, or by screen coordinate.
Actions run on the Codename One EDT, so an agent never touches the live component tree directly. Each action returns whether it succeeded together with a fresh snapshot.
25. Publishing application tools
An application publishes its own data and actions as MCP tools. A Tool has a name, a description, a JSON schema for its parameters, and a handler:
MCP.addTool(new Tool(
"current_user",
"Returns the signed in user",
"{\"type\":\"object\",\"properties\":{}}",
new ToolHandler() {
@Override
public String invoke(String argumentsJson) {
return "{\"name\":\"" + signedInUser + "\"}";
}
}));The server merges these tools with the built-in tools when a host lists the available tools, and routes each call to the matching handler. The same Tool type is used by the Codename One AI client, so a tool defined once serves both a hosted agent and an in-application model.
26. Screenshots and the simulator
The server exposes a screenshot of the current form as an MCP image resource, so a vision capable model can see the screen alongside the semantic tree. The resource is enabled by default and can be disabled per server.
The JavaSE simulator drives the same MCP menu described above, so an application can be exposed and driven from the running simulator during development.
27. Debug logging
Because an agent drives the tool on its own, it helps to watch what it does. The server echoes the MCP conversation to the Codename One log at a level chosen through the menu’s Debug Logging item or in code:
MCP.setVerbosity(MCPVerbosity.FULL);The levels of MCPVerbosity are, from quietest to loudest: OFF, ERRORS (only failed calls), SUMMARY (one line per call), and FULL (every request and response). Each level includes the one below it.
28. Registering with installed hosts
The Install and Remove items in the MCP menu call MCPClientRegistrar, which detects the MCP hosts installed on the machine and writes a server entry into each host configuration, so an end user doesn’t edit configuration by hand. Detection and registration are available to any Codename One tool, and they run inside the runtime because they use the portable FileSystemStorage.
A caller describes the server with an MCPClientDescriptor (a name and the command that launches it) and registers it with the detected hosts. Hosts whose configuration format isn’t yet supported are reported so the user can add the entry manually.
Media and Audio
29. MediaManager and MediaPlayer
MediaPlayer is a peer component, understanding this is crucial if your application depends on such a component. You can learn about peer components and their issues here. |
The MediaPlayer allows you to control video playback. To use the MediaPlayer you need to first load the Media object from the MediaManager.
The MediaManager is the core class responsible for media interaction in Codename One.
You should also check out the Capture class for things that aren’t covered by the MediaManager. |
In the demo code below you use the gallery functionality to pick a video from the device’s video gallery:
final Form hi = new Form("MediaPlayer", new BorderLayout());
hi.setToolbar(new Toolbar());
Style s = UIManager.getInstance().getComponentStyle("Title");
FontImage icon = FontImage.createMaterial(FontImage.MATERIAL_VIDEO_LIBRARY, s);
hi.getToolbar().addCommandToRightBar("", icon, (evt) -> {
Display.getInstance().openGallery((e) -> {
if(e != null && e.getSource() != null) {
String file = (String)e.getSource();
try {
Media video = MediaManager.createMedia(file, true);
hi.removeAll();
hi.add(BorderLayout.CENTER, new MediaPlayer(video));
hi.revalidate();
} catch(IOException err) {
Log.e(err);
}
}
}, Display.GALLERY_VIDEO);
});
hi.show();

| Video playback in the simulator will work with JavaFX enabled. This is the default for Java 8 or newer so recommend using that. |
30. PCM Audio Buffers, Mixing, and Effects
AudioBuffer stores raw interleaved float PCM samples in the [-1, 1] range, and WAVWriter writes those samples to a WAV file.
The portable live PCM source in Codename One is microphone capture: create an AudioBuffer with MediaManager.getAudioBuffer(…), then create a recorder with MediaRecorderBuilder.redirectToAudioBuffer(true). The builder’s path value is the buffer key in this mode; it isn’t a file path.
String bufferKey = "voice-buffer";
AudioBuffer livePcm = MediaManager.getAudioBuffer(bufferKey, true, 8192);
livePcm.addCallback(buffer -> {
float[] frame = new float[buffer.getSize()];
buffer.copyTo(frame);
// Process or copy this frame before the next callback arrives.
});
Media recorder = MediaManager.createMediaRecorder(
new MediaRecorderBuilder()
.path(bufferKey)
.samplingRate(44100)
.audioChannels(1)
.redirectToAudioBuffer(true));
recorder.play();
// Later:
recorder.cleanup();
MediaManager.releaseAudioBuffer(bufferKey);When the VideoIO API is available, it can also produce PCM from a prerecorded video file. VideoIO.getVideoIO().openReader(path).readAudio() returns the decoded audio track as an AudioBuffer, so video audio can be mixed or processed with the same APIs shown below. VideoIO support is platform-gated with VideoIO.isSupported(), and JavaScript currently reports no decoded audio track even though frame decoding and encoding are supported.
Codename One still doesn’t expose a standalone portable decoder that converts an arbitrary prerecorded audio-only file, such as MP3 or AAC, into an AudioBuffer without going through a video container API. Use the normal Media APIs to play those files. If you need offline PCM editing for audio-only formats, decode them before passing samples to Codename One, or add a platform decoder API for that format.
When you need to combine PCM clips before writing or playing them, use AudioMixer. It creates a sample-accurate timeline on one sample clock. Each track must use the same sample rate and channel count as the mixer. Track offsets are supplied in milliseconds and are rounded to the nearest sample frame on the mixer clock; if you already know the exact frame position, use addTrackAtFrame(…).
The mixed buffer is clipped to the normalized PCM range [-1, 1], so it can be passed directly to WAVWriter. The mixer doesn’t resample or convert channel layouts; downsample or otherwise convert source buffers before adding them if they’re not already on the target clock.
AudioEffects provides small platform-neutral PCM transforms that compose with the mixer:
equalize(…) is a simple three-band tone shaper for lightweight cleanup and demos. removeCenter(…), isolateCenter(…), and midSide(…) use classic stereo mid/side processing. They can reduce, isolate, or enhance centered dialog only when the source is stereo and the voice is actually centered. These methods aren’t source-separation, speech-isolation, or noise-reduction APIs.
AudioMixer and the simple buffer-wide AudioEffects operations use the com.codename1.util.Simd float-array API internally when the current platform supports it. Stateful filters, such as the equalizer, stay scalar because each sample depends on the previous filter state. You can force scalar behavior for diagnostics with AudioMixer.setSimdOptimizationsEnabled(false) or AudioEffects.setSimdOptimizationsEnabled(false).
31. Animations
There are many ways to animate and liven the data within a Codename One application, layout animations are probably chief among them. But first you need to understand some basics such as layout reflows.
31.1. Layout reflow
Layout in tools such as HTML is implicit, when you add something into the UI it’s automatically placed. Other tools such as Codename One use explicit layout, that means you’ve to explicitly request the UI to layout itself after making changes!
| Like many such rules exceptions occur. For example, if the device is rotated or window size changes a layout will occur automatically. |
When adding a component to a UI that’s already visible, the component won’t show by default.
| When adding a component to a form which isn’t shown on the screen, there is no need to tell the UI to repaint or reflow. This happens implicitly. |
The chief advantage of explicit layout is performance.
For example, imagine adding 100 components to a form. If the form was laid out automatically, layout would have happened 100 times instead of once when adding was finished. In fact layout reflows are often considered the #1 performance issue for HTML/JavaScript applications.
| Smart layout reflow logic can alleviate some pains of the automatic layout reflows but since the process is implicit it’s almost impossible to optimize complex usages across browsers/devices. A major JavaScript performance tip is to use absolute positioning which is akin to not using layouts at all! |
That’s why, when you add components to a form that’s already showing, you should invoke revalidate() or animate the layout appropriately. This also enables the layout animation behavior explained below.
31.2. Layout animations
To understand animations you need to understand a couple of things about Codename One components. When you add a component to a container, it’s added but not positioned anywhere. A novice might notice the setX/setY/setWidth/setHeight methods on a component and try to position it.
This won’t work since these methods are meant for the layout manager, which is implicitly invoked when a form is shown (internally in Codename One). The layout manager uses these methods to position/size the components based on the hints given to it.
If you add components to a form that’s showing, it’s your responsibility to invoke revalidate/layoutContainer to arrange the newly added components (see Layout Reflows).
animateLayout() method is a fancy form of revalidate that animates the components into their laid out position. After changing the layout & invoking this method the components move to their new sizes/positions seamlessly. Form exposes convenience wrappers such as animateLayout*() that forward to the underlying content pane, so you can call the methods directly on the form unless you specifically need to animate a nested container.
This sort of behavior creates a special case where setting the size/position makes sense. When you set the size/position in the demo code here you’re positioning the components at the animation start position above the frame:
Form hi = new Form("Layout Animations", new BoxLayout(BoxLayout.Y_AXIS));
Button fall = new Button("Fall"); (1)
fall.addActionListener((e) -> {
for (int iter = 0; iter < 10; iter++) {
Label b = new Label("Label " + iter);
b.setWidth(fall.getWidth());
b.setHeight(fall.getHeight());
b.setY(-fall.getHeight());
hi.add(b);
}
hi.animateLayout(20000); (2)
});
hi.add(fall);Notice these things about this example:
| 1 | You used a button to do the animation rather than doing it on show. Since show() implicitly lays out the components it wouldn’t have worked. |
| 2 | You used hi.animateLayout(20000);, which delegates to the Form content pane. If you need to animate a specific container (for example, a nested layout), call animateLayout() on that container instead. |
This results in:

31.2.1. Unlayout animations
While layout animations are powerful effects for adding elements into the UI and drawing attention to them. The inverse of removing an element from the UI is often more important. For example, when you delete or remove an element you want to animate it out.
Layout animations don’t do that since they will try to bring the animated item into place. The exact opposite of a layout animation is the "unlayout animation." Container.animateUnlayout(int, int, Runnable) and the Form.animateUnlayout*() helpers trigger this transition either asynchronously (with a completion callback) or synchronously via the AndWait variants.
The "unlayout animation" takes a valid laid out state and shifts the components to an invalid state that you defined in advance. For example, you can fix the example above to flip the "fall" button into a "rise" button when the buttons come into place and this will allow the buttons to float back up to where they came from in the exact reverse order.
| An unlayout animation always leaves the container in an invalidated state. |
Form hi = new Form("Layout Animations", new BoxLayout(BoxLayout.Y_AXIS));
Button fall = new Button("Fall");
fall.addActionListener((e) -> {
if (hi.getContentPane().getComponentCount() == 1) {
fall.setText("Rise");
for (int iter = 0; iter < 10; iter++) {
Label b = new Label("Label " + iter);
b.setWidth(fall.getWidth());
b.setHeight(fall.getHeight());
b.setY(-fall.getHeight());
hi.add(b);
}
hi.animateLayout(20000);
} else {
fall.setText("Fall");
for (int iter = 1; iter < hi.getContentPane().getComponentCount(); iter++) { (1)
Component c = hi.getContentPane().getComponentAt(iter);
c.setY(-fall.getHeight()); (2)
}
hi.animateUnlayoutAndWait(20000, 255); (3)
hi.removeAll(); (4)
hi.add(fall);
hi.revalidate();
}
});
hi.add(fall);You will notice some similarities with the unlayout animation but the differences represent the exact opposite of the layout animation:
| 1 | You loop over existing components (not newly created ones) |
| 2 | You set the desired end position not the desired starting position |
| 3 | You used the animateUnlayoutAndWait(…) variant to block until completion; animateUnlayout(duration, opacity, callback) provides the non-blocking alternative when you want to continue and run code from a callback instead. |
| 4 | After the animation completes you need to actually remove the elements since the UI is now in an invalid position with elements outside of the screen but still physically there! |
31.2.2. Hiding & visibility
A common trick for animating Components in Codename One is to set their preferred size to 0 and then invoke animateLayout() thus triggering an animation to hide said Component. several issues with this trick but one of the biggest ones is the fact that setPreferredSize has been deprecated for quite a while.
Instead of using that trick you can use setHidden/isHidden who effectively encapsulate this functionality and a bit more.
One of the issues setHidden tries to solve is the fact that preferred size doesn’t include the margin in the total and thus a component might still occupy space despite being hidden. When you request the margin change the current margins are cached, the component is given zero margins while hidden, and those cached values are restored when it’s shown again—without resetting the UIID or other style state.
This functionality might be undesirable which is why there is a version of the setHidden method that accepts a boolean flag indicating whether the margin cache should be manipulated. You can effectively hide/show a component without deprecated code using something like this:
Button toHide = new Button("Will Be Hidden");
Button hide = new Button("Hide It");
hide.addActionListener((e) -> {
hide.setEnabled(false);
boolean t = !toHide.isHidden();
toHide.setHidden(t);
toHide.getParent().animateLayoutAndWait(200);
toHide.setVisible(!t);
hide.setEnabled(true);
});Notice that the code above uses setVisible(), which shouldn’t be confused with setHidden. setVisible() toggles the visibility of the component it would still occupy the same amount of space |
31.2.3. Synchronicity in animations
Most animations have two or three variants:
Standard animation for example,
animateLayout(int)or the non-blockinganimateUnlayout(int, int, Runnable)And wait variant for example,
animateLayoutAndWait(int)/animateUnlayoutAndWait(int, int)Callback variant for example,
animateLayoutFade(int, int, Runnable)
The standard animation is invoked when you don’t care about the completion of the animation. You can do this for a standard animation.
| Unlayout animations always leave the container in an invalid state, so even the standard helper expects you to tidy up either in the callback or after the animation finishes. |
The AndWait variant blocks the calling thread until the animation completes. This is useful for sequencing animations one after the other e.g this code from the kitchen sink demo:
arrangeForInterlace(effects);
effects.animateUnlayoutAndWait(800, 20);
effects.animateLayoutFade(800, 20);First the UI goes through an "unlayout" animation, once that completes the layout itself is performed.
The AndWait calls needs to be invoked on the Event Dispatch Thread despite being "blocking." This is a common convention in Codename One powered by a unique capability of Codename One: invokeAndBlock.You can learn more about invokeAndBlock in the
EDT section. |
The callback variant is like the invokeAndBlock variant but uses a more conventional callback semantic which is more familiar to some developers. It accepts a Runnable callback that will be invoked after the fact. For example, you can change the unlayout call from before to use the callback semantics as such:
hi.animateUnlayout(20000, 255, () -> {
hi.removeAll();
hi.add(fall);
hi.revalidate();
});Animation fade and hierarchy
There are several more variations on the standard animate methods. Several methods accept a numeric fade argument. This is useful to fade out an element in an "unlayout" operation or fade in a regular animation.
The value for the fade argument is a number between 0 and 255 where 0 represents full transparency and 255 represents full opacity.
Some animate layout methods are hierarchy based. They work like the regular animateLayout methods but recurse into the entire Container hierarchy. These methods work well when you have components in a nested hierarchy that need to animate into place. This is demonstrated in the opening sequence of the kitchen sink demo:
for(int iter = 0 ; iter < demoComponents.size() ; iter++) {
Component cmp = (Component)demoComponents.elementAt(iter);
if(iter < componentsPerRow) {
cmp.setX(-cmp.getWidth());
} else {
if(iter < componentsPerRow * 2) {
cmp.setX(dw);
} else {
cmp.setX(-cmp.getWidth());
}
}
}
boxContainer.setShouldCalcPreferredSize(true);
boxContainer.animateHierarchyFade(3000, 30);The demoComponents Vector contains components from separate containers and this code would not work with a simple animate layout.
Avoid the hierarchy version where possible. Its slower but more importantly, it’s flaky. Since the size/position of the Container might be affected by the layout the animation could get clipped and skip. These are hard issues to debug. |
31.2.4. Sequencing animations via AnimationManager
All the animations go through a per-form queue: the AnimationManager. This effectively prevents two animations from mutating the UI in parallel so you won’t have collisions between two conflicting sides. Things get more interesting when you try to do something like this:
cnt.add(myButton);
int componentCount = cnt.getComponentCount();
cnt.animateLayout(300);
cnt.removeComponent(myButton);
if(componentCount == cnt.getComponentCount()) {
// this will happen...
}The reason this happens is that the second remove gets postponed to the end of the animation so it won’t break the animation. This works for remove and add operations on a Container as well as other animations.
The simple yet problematic fix would be:
cnt.add(myButton);
int componentCount = cnt.getComponentCount();
cnt.animateLayoutAndWait(300);
cnt.removeComponent(myButton);
if(componentCount == cnt.getComponentCount()) {
// this probably won't happen...
}Why might that still fail?
Events come in constantly during the run of the EDT [6], so an event might come in that might trigger an animation in your code. Even if you’re on the EDT keep in mind that you don’t actually block it and an event might come in.
In those cases an animation might start and you might be unaware of that animation and it might still be in action when you expect remove to work.
Animation manager to the rescue
AnimationManager has built-in support to fix this exact issue.
You can flush the animation queue and run synchronously after all the animations finished and before new ones come in by using something like this:
cnt.add(myButton);
int componentCount = cnt.getComponentCount();
cnt.animateLayout(300);
cnt.getAnimationManager().flushAnimation(() -> {
cnt.removeComponent(myButton);
if(componentCount == cnt.getComponentCount()) {
// this shouldn't happen...
}
});31.3. Low-level animations
The Codename One event dispatch thread has a special animation "pulse" allowing an animation to update its state and draw itself. Code can make use of this pulse to implement repetitive polling tasks that have little to do with drawing.
This is helpful since the callback will always occur on the event dispatch thread.
Every component in Codename One contains an animate() method that returns a boolean value, you can also implement the Animation interface in an arbitrary component to implement your own animation. To receive animation events you need to register yourself within the parent form, it’s the responsibility of the parent for to call animate().
If the animate method returns true then the animation will be painted (the paint method of the Animation interface would be invoked).
| It’s important to deregister animations when they aren’t needed to conserve battery life. |
If you derive from a component, which has its own animation logic you might damage its animation behavior by deregistering it, so use care with the low-level API’s.
For example, you can add more animation logic using code like this:
myForm.registerAnimated(this);private int spinValue;
@Override
public boolean animate() {
if(userStatusPending) {
spinValue++;
super.animate();
return true;
}
return super.animate();
}31.3.1. Why not just write code in paint
Animations comprise two parts, the logic (deciding the position, etc.) and the painting. The paint method should be dedicated to painting, not to the actual moving of the components.
The separation of concerns allows you to avoid redundant painting for example, if animate didn’t trigger a change return false to avoid the overhead related to animations.
You discuss low-level animations in more details within the animation section of the clock demo.
31.4. Transitions
Transitions allow you to replace one component with another, most typically forms or dialogs are replaced with a transition but a transition can be applied to replace any arbitrary component.
Developers can implement their own custom transition and install it to components by deriving the Transition class, although most commonly the built in CommonTransitions class is used for almost everything.
You can define transitions for forms/dialogs/menus globally either via the theme constants or via the LookAndFeel class. Or you can install a transition on top-level components via setter methods.
| When working with high-level animations you can select Slow Motion option in the simulator to slow down animations and inspect their details |
Themes define the default transitions used when showing a form, these differ based on the OS. In most platforms the default is Slide whereas in iOS the default is SlideFade which slides the content pane and title while fading in/out the content of the title area.
SlideFade is problematic without a title area. If you have a Form that lacks a title area you would recommend to disable SlideFade at least for that Form. |
Check out the full set of theme constants in the Theme Constants Section.
31.4.1. Replace
To apply a transition to a component you can use the Container.replace() method as such:
Form hi = new Form("Replace", new BoxLayout(BoxLayout.Y_AXIS));
Button replace = new Button("Replace Pending");
Label replaceDestiny = new Label("Destination Replace");
hi.add(replace);
replace.addActionListener((e) -> {
replace.getParent().replaceAndWait(replace, replaceDestiny, CommonTransitions.createCover(CommonTransitions.SLIDE_VERTICAL, true, 800));
replaceDestiny.getParent().replaceAndWait(replaceDestiny, replace, CommonTransitions.createUncover(CommonTransitions.SLIDE_VERTICAL, true, 800));
});Replace even works when you have a layout constraint in place for example, replacing a component in a border layout will do the "right thing." But, some layouts such as TableLayout might be tricky in such cases so recommend wrapping a replaceable Component in a border layout and replacing the content. |
Container.replace() can also be used with a null transition at which point it replaces instantly with no transition.
31.4.2. Slide transitions
The slide transitions are used to move the Form/Component in a sliding motion to the side or up/down. Four basic types of slide transitions exist:
Slide - the most commonly used transition
Fast Slide - historically this provided better performance for old device types. It’s no longer recommended for newer devices
Slide Fade - the iOS default where the title area features a fade transition
Cover/Uncover - a kind of slide transition where the source or destination form slides while the other remains static in place
The code below demonstrates the usage of all the main transitions:
Toolbar.setGlobalToolbar(true);
Form hi = new Form("Transitions", new BoxLayout(BoxLayout.Y_AXIS));
Style bg = hi.getContentPane().getUnselectedStyle();
bg.setBgTransparency(255);
bg.setBgColor(0xff0000);
Button showTransition = new Button("Show");
Picker pick = new Picker();
pick.setStrings("Slide", "SlideFade", "Cover", "Uncover", "Fade", "Flip");
pick.setSelectedString("Slide");
TextField duration = new TextField("10000", "Duration", 6, TextArea.NUMERIC);
CheckBox horizontal = CheckBox.createToggle("Horizontal");
pick.addActionListener((e) -> {
String s = pick.getSelectedString().toLowerCase();
horizontal.setEnabled(s.equals("slide") || s.indexOf("cover") > -1);
});
horizontal.setSelected(true);
hi.add(showTransition).
add(pick).
add(duration).
add(horizontal);
Form dest = new Form("Destination");
bg = dest.getContentPane().getUnselectedStyle();
bg.setBgTransparency(255);
bg.setBgColor(0xff);
dest.setBackCommand(
dest.getToolbar().addCommandToLeftBar("Back", null, (e) -> hi.showBack()));
showTransition.addActionListener((e) -> {
int h = CommonTransitions.SLIDE_HORIZONTAL;
if(!horizontal.isSelected()) {
h = CommonTransitions.SLIDE_VERTICAL;
}
switch(pick.getSelectedString()) {
case "Slide":
hi.setTransitionOutAnimator(CommonTransitions.createSlide(h, true, duration.getAsInt(3000)));
dest.setTransitionOutAnimator(CommonTransitions.createSlide(h, true, duration.getAsInt(3000)));
break;
case "SlideFade":
hi.setTransitionOutAnimator(CommonTransitions.createSlideFadeTitle(true, duration.getAsInt(3000)));
dest.setTransitionOutAnimator(CommonTransitions.createSlideFadeTitle(true, duration.getAsInt(3000)));
break;
case "Cover":
hi.setTransitionOutAnimator(CommonTransitions.createCover(h, true, duration.getAsInt(3000)));
dest.setTransitionOutAnimator(CommonTransitions.createCover(h, true, duration.getAsInt(3000)));
break;
case "Uncover":
hi.setTransitionOutAnimator(CommonTransitions.createUncover(h, true, duration.getAsInt(3000)));
dest.setTransitionOutAnimator(CommonTransitions.createUncover(h, true, duration.getAsInt(3000)));
break;
case "Fade":
hi.setTransitionOutAnimator(CommonTransitions.createFade(duration.getAsInt(3000)));
dest.setTransitionOutAnimator(CommonTransitions.createFade(duration.getAsInt(3000)));
break;
case "Flip":
hi.setTransitionOutAnimator(new FlipTransition(-1, duration.getAsInt(3000)));
dest.setTransitionOutAnimator(new FlipTransition(-1, duration.getAsInt(3000)));
break;
}
dest.show();
});
hi.show();


SlideFade is problematic without a title area. If you have a Form that lacks a title area you would recommend to disable SlideFade at least for that Form. |


31.4.3. Fade and flip transitions
The fade transition is pretty trivial and accepts a time value since it has no directional context.

The FlipTransition is also pretty simple but unlike the others it isn’t a part of the CommonTransitions. It has its own FlipTransition class.
| This transition looks different on devices as it uses native perspective transforms available there |

31.4.4. Bubble transition
BubbleTransiton morphs a component into another component using a circular growth motion.
The BubbleTransition accepts the component that will grow into the bubble effect as one of its arguments. It’s primarily
designed for Dialog transitions although it could work for more creative use cases:
| The code below manipulates styles and look. This is done to make the code more "self contained." Real world code should probably use the theme |
Form hi = new Form("Bubble");
Button showBubble = new Button("+");
showBubble.setName("BubbleButton");
Style buttonStyle = showBubble.getAllStyles();
buttonStyle.setBorder(Border.createEmpty());
buttonStyle.setFgColor(0xffffff);
buttonStyle.setBgPainter((g, rect) -> {
g.setColor(0xff);
int actualWidth = rect.getWidth();
int actualHeight = rect.getHeight();
int xPos, yPos;
int size;
if(actualWidth > actualHeight) {
yPos = rect.getY();
xPos = rect.getX() + (actualWidth - actualHeight) / 2;
size = actualHeight;
} else {
yPos = rect.getY() + (actualHeight - actualWidth) / 2;
xPos = rect.getX();
size = actualWidth;
}
g.setAntiAliased(true);
g.fillArc(xPos, yPos, size, size, 0, 360);
});
hi.add(showBubble);
hi.setTintColor(0);
showBubble.addActionListener((e) -> {
Dialog dlg = new Dialog("Bubbled");
dlg.setLayout(new BorderLayout());
SpanLabel sl = new SpanLabel("This dialog should appear with a bubble transition from the button", "DialogBody");
sl.getTextUnselectedStyle().setFgColor(0xffffff);
dlg.add(BorderLayout.CENTER, sl);
dlg.setTransitionInAnimator(new BubbleTransition(500, "BubbleButton"));
dlg.setTransitionOutAnimator(new BubbleTransition(500, "BubbleButton"));
dlg.setDisposeWhenPointerOutOfBounds(true);
dlg.getTitleStyle().setFgColor(0xffffff);
Style dlgStyle = dlg.getDialogStyle();
dlgStyle.setBorder(Border.createEmpty());
dlgStyle.setBgColor(0xff);
dlgStyle.setBgTransparency(0xff);
dlg.showPacked(BorderLayout.NORTH, true);
});
hi.show();
31.4.5. Morph transitions
Android’s material design has a morphing effect where an element from the previous form (activity) animates into a different component on a new activity. Codename One has a morph effect in the Container class but it doesn’t work as a transition between forms and doesn’t allow for multiple separate components to transition at once.

To support this behavior you have the MorphTransition class that provides this same effect coupled with a fade to the rest of the UI (see Figure 219, “Morph Transition”).
Since the transition is created before the form exists you can’t reference explicit components within the form
when creating the morph transition (to show which component becomes which) so you need to refer
to them by name. This means you need to use setName(String) on the components in the source/destination
forms so the transition will be able to find them:
Form demoForm = new Form(currentDemo.getDisplayName());
demoForm.setScrollable(false);
demoForm.setLayout(new BorderLayout());
Label demoLabel = new Label(currentDemo.getDisplayName());
demoLabel.setIcon(currentDemo.getDemoIcon());
demoLabel.setName("DemoLabel");
demoForm.addComponent(BorderLayout.NORTH, demoLabel);
demoForm.addComponent(BorderLayout.CENTER, wrapInShelves(n));
// ...
demoForm.setBackCommand(backCommand);
demoForm.setTransitionOutAnimator(
MorphTransition.create(3000).morph(
currentDemo.getDisplayName(),
"DemoLabel"));
f.setTransitionOutAnimator(
MorphTransition.create(3000).
morph(currentDemo.getDisplayName(),
"DemoLabel"));
demoForm.show();Snapshot mode
By default MorphTransition paints both endpoints by re-rendering the live
source / destination components every frame at the interpolated bounds.
That works well when the source is fully visible — a card in the body
of one form morphing to a card in the next.
It runs into edge cases when the source lives inside a scrolling
container that has children extending past the source’s bounds, or
when the source has dynamic content (a video frame, a BrowserComponent,
a custom-painted background) that should be visually frozen for the
duration of the animation. The legacy live-paint path can leak
off-viewport pixels into the morph because the layered pane that holds
the source during the animation doesn’t carry the original parent’s clip.
To opt into the image-snapshot path call snapshotMode(true) on the
builder:
snapshotMode(true) captures each (source, dest) pair as a clipped
Image at initTransition(), then the tween draws those images at the
interpolated bounds rather than re-painting the live components.
Off-viewport children of the source are clipped at capture time (the
image’s own bounds are the clip), so they can’t leak into the morph.
The default MorphTransition behavior (live paint, no snapshots) is
unchanged for back-compat. Use snapshot mode opportunistically when
the live-paint output exhibits the off-viewport leak, or when the
source’s children produce frame-by-frame visual change you want to
freeze.
31.4.6. SwipeBackSupport
iOS7+ allows swiping back one form to the previous form, Codename One has an API to enable back swipe transition:
SwipeBackSupport.bindBack(currentForm, destination);That one command will enable swiping back from currentForm. LazyValue allows you to pass a value lazily:
This effectively allows you to pass a form and create it as necessary (for example, for a GUI builder app you don’t have the actual previous form instance), notice that the arguments aren’t used for this case but will be used in other cases.
The code below should work for the transition sample above. Notice that this API was designed to work with "Slide Fade" transition and might have issues with other transition types:
SwipeBackSupport.bindBack(dest, (args) -> hi);32. The EDT - Event Dispatch Thread
32.1. What’s The EDT
Codename One allows developers to create as many threads as they want; however to interact with the Codename One user interface components a developer must use the EDT. The EDT stands for "Event Dispatch Thread" but it handles a lot more than "events."
The EDT is the main thread of Codename One, by using one thread Codename One can avoid complex synchronization code and focus on simple functionality that assumes one thread.
| This has huge advantages for your code. You can normally assume that all code will occur on a single thread and avoid complex synchronization logic. |
You can visualize the EDT as a loop such as this:
Normally, every call you receive from Codename One will occur on the EDT. For example, every event, calls to paint(), and lifecycle calls (start etc.) should all occur on the EDT.
This is pretty powerful, however it means that as long as your code is processing nothing else can happen in Codename One!
If your code takes too long to execute then no painting or event processing will occur during that time, so a call to Thread.sleep() will actually stop everything! |
The solution is pretty simple, if you need to perform something that requires intensive CPU you can spawn a thread.
Codename One’s networking code automatically spawns its own network thread (see the NetworkManager). However, this also poses a problem…
Codename One assumes all modifications to the UI are performed on the EDT. If you spawn a separate thread, how do you force its modifications back into the EDT?
Codename One includes helper methods in the Display class to help in these situations: isEDT(), callSerially(Runnable), callSeriallyOnIdle(Runnable), and callSeriallyAndWait(Runnable) (with an optional timeout overload).
isEDT() is useful for generic code that needs to test whether the current code is executing on the EDT.
32.2. Call Serially (And Wait)
callSerially(Runnable) should normally be called off the EDT (in a separate thread), the run method within the submitted runnable will be invoked on the EDT.
The Runnable passed to the callSerially and callSeriallyAndWait methods isn’t a Thread. Use the Runnable interface as a convenient callback interface: |
| You can write this code more concisely using Java 8 lambda code as such: |
This allows code to leave the EDT and then later on return to it to perform things within the EDT.
The callSeriallyAndWait(Runnable) method blocks the current thread until the method completes, this is useful for cases such as user notification e.g.:
If you’re unsure use callSerially. The use cases for callSeriallyAndWait are rare. When you do need to wait, the overload that accepts a timeout lets background threads marshal results back to the EDT without risking an indefinite stall if the EDT is busy. |
If the work you’re posting back to the EDT is expensive and can wait until the UI finishes its current pass, use callSeriallyOnIdle(). This queues the runnable for execution after the EDT completes painting, animations, and any other queued tasks. Deferring longer tasks to the idle queue helps avoid starving animations and transitions when bursts of background callbacks arrive together.
32.2.1. callSerially On The EDT
One of the misunderstood topics is why you’d ever want to invoke callSerially when you’re still on the EDT. This is best explained by example. Say you have a button that has quite a bit of functionality tied to its events e.g.:
A user added an action listener to show a Dialog.
A framework the user installed added some logging to the button.
The button repaints a release animation as its being released.
However, this might cause a problem if the first event being handled (the dialog) causes an issue with the
following events. For example, a dialog will block the EDT (using invokeAndBlock), events will keep happening but since
the event you’re in "already happened" the button repaint and the framework logging won’t occur. The same problem
also occurs if you show a form which might trigger logic that relies on the current form still being present.
One of the solutions to this problem is to wrap the action listeners body with a callSerially. In this case the callSerially
will postpone the event to the next cycle (loop) of the EDT and let the other events in the chain complete. Notice
that you shouldn’t use this normally since it includes an overhead and complicates application flow, however when
you run into issues in event processing this is worth trying to see if its the cause.
| You should never invoke callSeriallyAndWait on the EDT since this would effectively mean sleeping on the EDT. That method throws an exception if its invoked from the EDT. |
If you need to run logic on the EDT but must ensure nothing inside it blocks, the Display class also provides invokeWithoutBlocking() and invokeWithoutBlockingWithResultSync(). These helpers temporarily disable invokeAndBlock() during the runnable. Any nested call to invokeAndBlock() while blocking is disabled results in a BlockingDisallowedException. Framework code that wraps user callbacks can use these methods to guard against accidental nested blocking that would otherwise deadlock or stall the UI, yet still obtain a return value when needed via invokeWithoutBlockingWithResultSync().
32.3. Debugging EDT Violations
Two types of EDT violations exist:
Blocking the EDT thread so the UI performance is considerably slower.
Invoking UI code on a separate thread
Codename One provides a tool to help you detect some of these violations some caveats may apply though…
It’s an imperfect tool. It might fire "false positives" meaning it might detect a violation for legal code and it might miss some illegal calls. However, it’s a valuable tool in the process of detecting hard to track bugs that are sometimes reproducible on the devices (due to race condition behavior).
To activate this tool select the Debug EDT menu option in the simulator and pick the level of output you wish to receive:

Full output will include stack traces to the area in the code that’s suspected in the violation.
32.4. Invoke And Block
Invoke and block is the exact opposite of callSeriallyAndWait(), it blocks the EDT and opens a separate thread for the runnable call. This functionality is inspired by the Foxtrot API, which is
a remarkably powerful tool most Swing developers don’t know about.
This is best explained by an example. Typical Java code reads as a single sequence as such:
This works well normally but on the EDT it might be a problem, if one of the operations is slow it might slow the whole EDT (painting, event processing etc.). Normally you can move operations into a separate thread e.g.:
This means that operation C will happen in parallel to operation B which might be a problem…
For example, instead of using operation names lets use a more "real world" example:
Notice that the first and last operations must be conducted on the EDT but the middle operation might be slow!
Since updateUIWithContentOfFile needs readAndParseFile to occur before it starts doing the new thread won’t be enough.
A simplistic approach is to do something like this:
However, updateUIWithContentOfFile should be executed on the EDT and not on a random thread. The right way to do this would therefore be something like this:
This is legal and would work reasonably well, however it gets complicated as you add more and more features that need to be chained serially after all these are 3 methods!
Invoke and block solves this in a unique way you can get almost the exact same behavior by using this:
Or this with Java 8 syntax:
Invoke and block effectively blocks the current EDT in a legal way. It spawns a separate thread that runs the run() method and when that run method completes it goes back to the EDT.
All events and EDT behavior still work while invokeAndBlock is running, this is because invokeAndBlock() keeps calling the main thread loop internally.
Notice that invokeAndBlock comes at a slight performance penalty. Also notice that nesting invokeAndBlock calls (or over using them) isn’t recommended.However, they’re convenient when working with multiple threads/UI. |
Even if you never call invokeAndBlock directly you’re probably using it indirectly in APIs such as Dialog that show a dialog while blocking the current thread e.g.:
public void actionPerformed(ActionEvent ev) {
// will return true if the user clicks "OK"
if(!Dialog.show("Question", "How Are You", "OK", "Not OK")) {
// ask what went wrongnull
}
}Notice that the dialog show method will block the calling thread until the user clicks OK or Not OK…
Other APIs such as NetworkManager.addToQueueAndWait() also make use of this feature. Pretty much every "AndWait" method or blocking method uses this API internally! |
To explain how invokeAndBlock works you can return to the sample above of how the EDT works:
invokeAndBlock() works in a similar way to this pseudo-code:
The EDT is effectively "blocked" but invokeAndBlock "redoes" it from within…
As you can see this is a simple approach for thread programming in UI, you don’t need to block your flow and track the UI thread. You can program in a way that seems sequential (top to bottom) but uses multi-threading correctly without blocking the EDT.
33. Graphics, drawing, images, and fonts
| Drawing is considered a low-level API that might introduce some platform fragmentation. |
33.1. Basics - where and how to draw manually
The Graphics class handles drawing basics, shapes, images, and text. Developers never instantiate it directly; the Codename One API passes it in.
You can gain access to a Graphics object using one of the following methods:
Derive Component or a subclass of
Component-Componentincludes many methods that let developers change drawing behavior. Override them to change how the component is drawn:paint(Graphics)- invoked to draw the component, this can be overridden to draw the component from scratch.paintBackground(Graphics)/paintBackgrounds(Graphics)- these allow overriding the way the component background is painted although you would probably be better off implementing a painter (see below).paintBorder(Graphics)- allows overriding the process of drawing a border, notice that border drawing might differ based on the style of the component.paintComponent(Graphics)- allows painting the components contents while leaving the default paint behavior to the style.paintScrollbars(Graphics),paintScrollbarX(Graphics),paintScrollbarY(Graphics)allows overriding the behavior of scrollbar painting.
Implement the painter interface; this interface can be used as a
GlassPaneor a background painter.The painter interface is simple and includes one paint method. It lets developers perform custom painting without subclassing
Component. Painters can be chained together to create elaborate paint behavior with the PainterChain class.Glass pane - a glass pane allows developers to paint on top of the form painting. This allows an overlay effect on top of a form.
At first, a glass pane may seem like overriding the Form’s paint method and drawing after
super.paint(g)completes. It isn’t the same. When a component repaints by invokingrepaint(), that component is drawn, and Form’spaint()method isn’t invoked. The glass pane painter is invoked in those cases and behaves as expected.Background painter - the background painter is installed through the style. By default, Codename One installs its own custom background painter. Installing a custom painter lets a developer define how the component background is drawn.
Many background-style behaviors can also be achieved using styles alone.
A common mistake is overriding the paint(Graphics) method of Form. The problem is that a form has child components that may request a repaint. To avoid that, place a paintable component in the center of the Form, or override the glass pane or background painter. |
A paint method can be implemented as such:
// hide the title
Form hi = new Form("", new BorderLayout());
hi.add(BorderLayout.CENTER, new Component() {
@Override
public void paint(Graphics g) {
// red color
g.setColor(0xff0000);
// paint the screen in red
g.fillRect(getX(), getY(), getWidth(), getHeight());
// draw hi world in white text in the top left corner of the screen
g.setColor(0xffffff);
g.drawString("Hi World", getX(), getY());
}
});
hi.show();
33.1.1. Painting with gradients
Solid colors are the starting point. Graphics also understands "paint" objects
that describe gradients and other patterns. You can pass an instance of
Paint
to setColor(Paint) in place of an integer color value to activate a gradient for
later fill and draw operations. The
LinearGradientPaint
class is the most common option and accepts a list of color stops along a line:
The fillLinearGradient() convenience methods (with optional repeat flag)
provide a shorthand when you need a two-color gradient without constructing
your own Paint object.
Radial gradients are equally straightforward using
fillRadialGradient() or fillRectRadialGradient(), which can render circular
and rectangular radial transitions respectively. These APIs accept the
inner/outer colors, focal point, and spread so you can combine them with linear
gradients to build sophisticated backgrounds and lighting effects.
For the full CSS gradient range, Graphics exposes a single fillGradient
method that consumes a Gradient value object. Gradient is a Paint
subclass with three concrete forms - LinearGradient, RadialGradient,
ConicGradient - following the same pattern as the Shape hierarchy:
Gradient carries the cycle method (CYCLE_NONE / CYCLE_REPEAT /
CYCLE_REFLECT) for repeating / reflected fills. Each port implements
fillGradient via the fastest native shader available - Java2D
LinearGradientPaint / RadialGradientPaint on the simulator,
LinearGradient / RadialGradient / SweepGradient shaders on Android - and
falls back to a software rasterizer that calls Gradient#sampleArgb per
pixel where no native shader exists.
33.1.2. Image blur
Graphics.gaussianBlur(Image, float radius) returns a blurred copy of an image
using the platform’s fastest path (Core Image on iOS, RenderScript /
RenderEffect on Android, JHLabs GaussianFilter in the simulator). The same
blur is reachable from CSS via the filter: blur(<length>) and
backdrop-filter: blur(<length>) properties, which are stored on the
component’s Style as filterBlurRadius and backdropFilterBlurRadius.
33.2. Glass pane
The GlassPane `in Codename One is inspired by the Swing `GlassPane & LayeredPane with a few twists.
You tried to imagine how Swing developers would have implemented the glass pane knowing what they do now about painters and Swings learning curve. But first: what’s the glass pane?
A typical Codename One application is essentially composed of 3 layers (this is a gross simplification though), the background painters are responsible for drawing the background of all components including the main form. The component draws its own content (which might overrule the painter) and the glass pane paints last…

Essentially the glass pane is a painter that allows you to draw an overlay on top of the Codename One application.
Overriding the paint method of a form isn’t a substitute for glasspane as it would appear to work initially, when you enter a Form. For example, when modifying an element within the form that element gets repainted not the entire
Form!
If you have a form with a Button and text drawn on top using the Form’s paint method it would get erased whenever the button gets focus.
The glass pane is called whenever a component gets painted,
it paints within the clipping region of the component hence it won’t break the rest of the components on the Form which weren’t modified.
You can set a painter on a form using code like this:
hi.setGlassPane(new Painter() {
@Override
public void paint(Graphics g, Rectangle rect) {
}
});Or you can use Java 8 lambdas to tighten the code a bit:
hi.setGlassPane((g, rect) -> {
});PainterChain allows you to chain many painters together to perform different logical tasks such as a validation painter coupled with a fade out painter. The sample below shows a crude validation panel that allows you to draw error icons next to components while exceeding their physical bounds as is common in many user interfaces
Form hi = new Form("Glass Pane", new BoxLayout(BoxLayout.Y_AXIS));
Style s = UIManager.getInstance().getComponentStyle("Label");
s.setFgColor(0xff0000);
s.setBgTransparency(0);
Image warningImage = FontImage.createMaterial(FontImage.MATERIAL_WARNING, s).toImage();
TextField tf1 = new TextField("My Field");
tf1.getAllStyles().setMarginUnit(Style.UNIT_TYPE_DIPS);
tf1.getAllStyles().setMargin(5, 5, 5, 5);
hi.add(tf1);
hi.setGlassPane((g, rect) -> {
int x = tf1.getAbsoluteX() + tf1.getWidth();
int y = tf1.getAbsoluteY();
x -= warningImage.getWidth() / 2;
y += (tf1.getHeight() / 2 - warningImage.getHeight() / 2);
g.drawImage(warningImage, x, y);
});
hi.show();
33.3. Shapes & transforms
The graphics API provides a high performance shape API that allows drawing arbitrary shapes by defining paths and curves and caching the shape drawn in the GPU.
33.4. Device support
Shapes and transforms ship with all Codename One’s actively maintained ports (Android, iOS, JavaScript, and desktop/Simulator). Older platforms that have reached end of life may lack these APIs, so keep the guard code shown below if you still target them with legacy builds.
Notice that perspective transform is missing from the desktop/simulator port. No real equivalent to perspective transform in Java SE that you could use.
33.5. A 2D drawing app
You can show shape drawing with a simple example of a drawing app, that allows the user to tap the screen to draw a contour picture.
The app works by keeping a GeneralPath in memory, and adding points as Bézier curves. Whenever a point is added, the path is redrawn to the screen.
The center of the app is the DrawingCanvas class, which extends Component:
public class DrawingCanvas extends Component {
GeneralPath p = new GeneralPath();
int strokeColor = 0x0000ff;
int strokeWidth = 10;
public void addPoint(float x, float y){
// To be written
}
@Override
protected void paintBackground(Graphics g) {
super.paintBackground(g);
Stroke stroke = new Stroke(
strokeWidth,
Stroke.CAP_BUTT,
Stroke.JOIN_ROUND, 1f
);
g.setColor(strokeColor);
// Draw the shape
g.drawShape(p, stroke);
}
@Override
public void pointerPressed(int x, int y) {
addPoint(x-getParent().getAbsoluteX(), y-getParent().getAbsoluteY());
}
}Conceptually this is basic component. You will be overriding the
paintBackground()
method to draw the path. You keep a reference to a
GeneralPath
object (which is the concrete implementation of the Shape interface in Codename One) to store each successive
point in the drawing. You also parametrize the stroke width and color.
The implementation of the paintBackground() method (shown above) should be straight forward. It creates
a stroke of the appropriate width, and sets the color on the graphics context. Then it calls drawShape() to render the path of points.
33.5.1. Implementing addpoint()
The addPoint method is designed to allow you to add points to the drawing. A simple implementation that uses straight lines rather than curves might look like this:
You introduced a couple house-keeping member vars (lastX and lastY) to store the last point that was added
that you know whether this is the first tap or a later tap. The first tap triggers a moveTo() call, whereas
later taps trigger lineTo() calls, which draw lines from the last point to the current point.
A drawing might look like this:

33.5.2. Using Bézier curves
Your previous implementation of addPoint() used lines for each segment of the drawing. Now make a change to allow for smoother edges by using quadratic curves instead of lines.
Codename One’s GeneralPath class includes two methods for drawing curves:
See the General Path javadocs for the full API.
You will make use of the quadTo()
method to append curves to the drawing as follows:
This change should be straight forward except, perhaps, the business with the odd variable. Since
quadratic curves require two points (also to the implied starting point), you can’t take the last tap
point and the current tap point. You need a point between them to act as a control point. This is where you get
the curve from. The control point works by exerting a sort of "gravity" on the line segment, to pull the line towards
it. This results in the line being curved. The example uses the odd marker to alternate the control point between positions
above the line and below the line.
A drawing from the resulting app looks like:

33.5.3. Detecting platform support
The DrawingCanvas example is a bit naive in that it assumes that the device supports the shape API. Running this code on a device that doesn’t support the Shape API would draw a blank canvas where the shape was
expected to be drawn. You can fall back gracefully if you make use of the
Graphics.isShapeSupported() method. For example:
33.6. Transforms
The Graphics class has included limited support for 2D transformations for some time now including scaling, rotation, and translation:
scale(x,y): Scales drawing operations by a factor in each direction.translate(x,y): Translates drawing operations by an offset in each direction.rotate(angle): Rotates about the origin.rotate(angle, px, py): Rotates about a pivot point.
scale() and rotate() methods are available on platforms that support Affine transforms. See table X for a compatibility list. |
33.6.1. Device support
All current Codename One ports expose affine transforms (that’s: scale() and
rotate()). Use the following table as a quick reference when deciding whether
you need a fallback path.
Platform | Affine Supported |
Simulator/Desktop | Yes |
iOS | Yes |
Android | Yes |
JavaScript | Yes |
You can check if a particular Graphics context supports rotation and scaling using the isAffineSupported() method.
For example:
public void paint(Graphics g){
if ( g.isAffineSupported() ){
// Do something that requires rotation and scaling
} else {
// Fallback behavior here
}
}33.7. Example: Drawing an analog clock
The following sections implement an analog clock component. This will show three key concepts in Codename One’s graphics:
Using the
GeneralPathclass for drawing arbitrary shapes.Using
Graphics.translate()to translate your drawing position by an offset.Using
Graphics.rotate()to rotate your drawing position.
There are three separate things that need to be drawn in a clock:
The tick marks. For example: most clocks will have a tick mark for each second, larger tick marks for each hour, and sometimes even larger tick marks for each quarter-hour.
The numbers. You will draw the clock numbers (1 through 12) in the appropriate positions.
The hands. You will draw the clock hands to point at the appropriate points to display the current time.
33.7.1. The AnalogClock Component
Your clock will extend the Component class, and override the paintBackground() method to draw the clock as follows:
public class AnalogClock extends Component {
Date currentTime = new Date();
@Override
public void paintBackground(Graphics g) {
// Draw the clock in this method
}
}33.7.2. Setting up the parameters
Before you actually draw anything, take a moment to figure out what values you need to know to draw an effective clock. Minimally, you need two values:
The center point of the clock.
The radius of the clock.
The clock also exposes the following parameters to help customize how it’s rendered:
The padding (that’s: the space between the edge of the component and the edge of the clock circle.
The tick lengths. The example uses 3 different lengths of tick marks on this clock. The longest ticks will be displayed at quarter points (that’s: 12, 3, 6, and 9). Slightly shorter ticks will be displayed at the five-minute marks (that’s: where the numbers appear), and the remaining marks (corresponding with seconds) will be short:
33.7.3. Drawing the tick marks
For the tick marks, you will use a single GeneralPath object, making use of the moveTo() and lineTo() methods
to draw each individual tick:
This example uses a little bit of trigonometry to calculate the (x,y) coordinates of the tick marks based on
the angle and the radius. If math isn’t your thing, don’t worry. This example makes use of the identities: x=r*cosθ and y=r*sinθ. |
At this point your clock should include a series of tick marks orbiting a blank center as shown below:

33.7.4. Drawing the numbers
The Graphics.drawString(str, x, y) method allows you to draw text at any point of a component. The tricky part
here is calculating the correct x and y values for each string so that the number appears in the correct location.
For the purposes of this tutorial, you will use the following strategy. For each number (1 through 12):
Use the
Graphics.translate(x,y)method to apply a translation from the clock’s center point to the point where the number should appear.Draw number (using
drawString()) at the clock’s center. It should be rendered at the correct point due to your translation.Invert the translation performed in step 1:
This example is, admittedly, a little contrived to allow for a demonstration of the Graphics.translate() method.
You could have as passed the exact location of the number to drawString() rather than draw at the clock
center and translate to the correct location. |
Now, you should have a clock with tick marks and numbers as shown below:

33.7.5. Drawing the hands
The clock will include three hands: Hour, Minute, and Second. You will use a separate GeneralPath object for each hand. For the positioning/angle of each, use the following strategy:
Draw the hand at the clock center pointing toward
12(straight up).Translate the hand slightly down so that it overlaps the center.
Rotate the hand at the appropriate angle for the current time, using the clock center as a pivot point.
Drawing the Second Hand:
For the "second" hand, you will use a simple line from the clock center to the inside edge of the medium tick mark at the 12 o’clock position:
And you will translate it down slightly so that it overlaps the center. This translation will be performed on the GeneralPath object directly rather than through the Graphics context:
Rotating the Second Hand::
The rotation of the second hand will be performed in the Graphics context through the rotate(angle, px, py) method.
This requires you to calculate the angle. The px and py arguments constitute the pivot point of the rotation,
which, in your case will be the clock center.
| The rotation pivot point is expected to be in absolute screen coordinates rather than relative coordinates of the component. You therefore need to get the absolute clock center position to perform the rotation: |
Remember to call resetAffine() after you’re done with the rotation, or you will see some unexpected
results on your form. |
Drawing the Minute And Hour Hands:
The mechanism for drawing the hour and minute hands is largely the same as for the minute hand, with a couple of added complexities though:
You will make these hands trapezoidal, and almost triangular rather than using a simple line, which means the
GeneralPathconstruction will be slightly more complex.Calculation of the angles will be slightly more complex because they need to consider many parameters. For example: The hour hand angle is informed by both the hour of the day and the minute of the hour.
The remaining drawing code is as follows:
33.7.6. The final result
At this point, you have a complete clock as shown below:

33.7.7. Animating the clock
The current clock component is cool, but it’s static. It displays the time at the point the clock was created. You discussed low-level animations in the animation section of the guide, here you will show a somewhat more elaborate example.
To animate your clock so that it updates once per second, you need to do two things:
Implement the
animate()method to show when the clock needs to be updated/re-drawn.Register the component with the form so that it will receive animation "pulses."
The animate() method in the AnalogClock class:
This method will be invoked on each "pulse" of the EDT. It checks the last time the clock was rendered and returns
true if the clock hasn’t been rendered in the current "time second" interval. Otherwise it returns false. This
ensures that the clock will be redrawn when the time changes.
33.8. Starting and stopping the animation
Animations can be started and stopped through the Form.registerAnimated(component) and
Form.deregisterAnimated(component) methods. You chose to encapsulate these calls in start() and stop()
methods in the component as follows:
The code to instantiate the clock, and start the animation would be something like:
33.9. Shape clipping
Clipping is one of the core tenants of graphics programming, you define the boundaries for drawing and when you exceed said boundaries things aren’t drawn. Shape clipping allows you to clip based on any arbitrary Shape and not a rectangle, this allows some unique effects generated in runtime.
For example: this code allows you to draw a rather complex image of duke:
Image duke = null;
try {
// duke.png is just the default Codename One icon copied into place
duke = Image.createImage("/duke.png");
} catch(IOException err) {
Log.e(err);
}
final Image finalDuke = duke;
Form hi = new Form("Shape Clip");
// We create a 50 x 100 shape, this is arbitrary since we can scale it easily
GeneralPath path = new GeneralPath();
path.moveTo(20,0);
path.lineTo(30, 0);
path.lineTo(30, 100);
path.lineTo(20, 100);
path.lineTo(20, 15);
path.lineTo(5, 40);
path.lineTo(5, 25);
path.lineTo(20,0);
Stroke stroke = new Stroke(0.5f, Stroke.CAP_ROUND, Stroke.JOIN_ROUND, 4);
hi.getContentPane().getUnselectedStyle().setBgPainter((Graphics g, Rectangle rect) -> {
g.setColor(0xff);
float widthRatio = ((float)rect.getWidth()) / 50f;
float heightRatio = ((float)rect.getHeight()) / 100f;
g.scale(widthRatio, heightRatio);
g.translate((int)(((float)rect.getX()) / widthRatio), (int)(((float)rect.getY()) / heightRatio));
g.setClip(path);
g.setAntiAliased(true);
g.drawImage(finalDuke, 0, 0, 50, 100);
g.setClip(path.getBounds());
g.drawShape(path, stroke);
g.translate(-(int)(((float)rect.getX()) / widthRatio), -(int)(((float)rect.getY()) / heightRatio));
g.resetAffine();
});
hi.show();
| Notice that this functionality isn’t available on all platforms so you need to test if shaped clipping is supported using isShapeClipSupported(). |
33.10. The coordinate system
The Codename One coordinate system follows the example of Swing (and many other - but not all-graphics libraries) and places the origin in the upper left corner of the screen. X-values grow to the right, and Y-values grow downward as illustrated below:

The screen origin is in the top left corner of the screen. Given this information, consider the method
call on the Graphics context g:
g.drawRect(10,10, 100, 100);Where would this rectangle be drawn on the screen?
If you answered something like "10 pixels from the top, and 10 pixels from the left of the screen,"
you might be right. It depends on whether the graphics has a translation or transform applied to it. If there is
currently a translation of (20,20) (that’s: 20 pixels to the right, and 20 pixels down), then the rectangle would be
rendered at (30, 30).
You can always find out the current translation of the graphics context using the Graphics.getTranslateX()
and Graphics.getTranslateY() methods:
// Find out the current translation
int currX = g.getTranslateX();
int currY = g.getTranslateY();
// Reset the translation to zeroes
g.translate(-currX, -currY);
// Now we are working in absolute screen coordinates
g.drawRect(10, 10, 100, 100);
// This rectangle should now be drawn at the exact screen
// coordinates (10,10).
//Restore the translation
g.translate(currX, currY);This example glosses over issues such as clipping and transforms which may cause it to not work as you
expect. For example: When painting a component inside its paint() method, there is a clip applied to the context so that
the content you draw within the bounds of the component will be seen. |
If, also, there is a transform applied that rotates the context 45 degrees clockwise, then the rectangle will be drawn at a 45-degree angle with its top left corner somewhere on the left edge of the screen.
You don’t have to worry about the exact screen coordinates for the things you paint. Most of the time, you will be concerned with relative coordinates.
33.10.1. Relative coordinates
Usually, when you’re drawing onto a Graphics context, you’re doing so within the context of a Component’s
paint() method (or one of its variants). In this case, you don’t care what the exact screen coordinates
are of your drawing. You’re concerned with their relative location within the coordinate. You can leave
the positioning (and even sizing) of the coordinate up to Codename One. Thank you for reading.
To show this, create a simple component called Rectangle component, that draws a rectangle on the screen. You will use the component’s position and size to dictate the size of the rectangle to be drawn. And you will keep a 5 pixel padding between the edge of the component and the edge of your rectangle:
class RectangleComponent extends Component {
public void paint(Graphics g){
g.setColor(0x0000ff);
g.drawRect(getX()+5, getY()+5, getWidth()-10, getHeight()-10);
}
}The result is as follows:

The x and y coordinates that are passed to the drawRect(x,y,w,h) method are relative to the
component’s parent’s origin — not the component itself.. Its parent. This is why you the x position is getX()+5
and not 5. |
33.10.2. Transforms and rotations
Unlike the Graphics drawXXX primitives, methods for setting transformations, including scale(x,y) and
rotate(angle), are always applied in screen coordinates. This can be confusing at first, because you
may be unsure whether to provide a relative coordinate or an absolute coordinate for a given method.
The general rule is:
All coordinates passed to the drawXXX() and fillXXX() methods will be subject to the graphics context’s transform and translation settings.
All coordinates passed to the context’s transformation settings are considered to be screen coordinates, and aren’t subject to current transform and translation settings.
Take your RectangleComponent as an example. Suppose you want to rotate the rectangle by 45 degrees,
your first try might look something like:
class RectangleComponent extends Component {
@Override
protected Dimension calcPreferredSize() {
return new Dimension(250,250);
}
public void paint(Graphics g) {
g.setColor(0x0000ff);
g.rotate((float) (Math.PI / 4.0));
g.drawRect(getX() + 5, getY() + 5, getWidth() - 10, getHeight() - 10);
g.rotate(-(float) (Math.PI / 4.0));
}
}When performing rotations and transformations inside a paint() method, always remember to revert your
transformations at the end of the method so that it doesn’t pollute the rendering pipeline for later components. |
The behavior of this rotation will vary based on where the component is rendered on the screen. To show this, try to place five of these components on a form inside a BorderLayout and see how it looks:
The result is as follows:

This may not be an intuitive outcome since you drew 10 rectangle components, but you see a portion of one
rectangle. The reason is that the rotate(angle) method uses the screen origin as the pivot point for the rotation.
Components nearer to this pivot point will experience a less dramatic effect than components farther from it. In
your case, the rotation has caused all rectangles except the first one to be rotated outside the bounds of their
containing component, and are therefore being clipped. A more sensible solution for your component would be to place
the rotation pivot point somewhere inside the component. That way all the components would look the same.
Some possibilities would be:
Top Left Corner:

Center:

You could also use the Graphics.setTransform() class to apply rotations and other complex transformations
(including 3D perspective transforms), but that belongs to its own topic as it’s a little bit more complex.
33.10.3. Global alpha & Anti-Aliasing
Up to this point you’ve relied on the per-pixel alpha stored in images and gradients. Graphics
also lets you apply a global alpha multiplier to every draw call by using
setAlpha(int) or concatenateAlpha(int) after checking isAlphaSupported().
Both methods accept values from 0 (fully transparent) to 255 (fully opaque)
and remain active until you change them again. concatenateAlpha() is
especially handy when you need to temporarily fade a component because it
returns the previous alpha so you can restore it later.
Anti-aliasing can likewise be toggled at runtime. Call isAntiAliasingSupported()
and isAntiAliasedTextSupported() to discover which hints the current port
exposes, then use setAntiAliased(boolean) and setAntiAliasedText(boolean) to
opt into smoother edges for shapes and glyphs respectively. These switches make
it easy to balance rendering quality versus speed depending on the type of
content you draw.
33.10.4. Event coordinates
The coordinate system and event handling are tied. You can listen for touch events on a component by
overriding the pointerPressed(x,y) method. The coordinates received in this method will be absolute screen
coordinates, so you may need to do some conversions on these coordinates before using them in your drawXXX()
methods.
For example: a pointerPressed() callback method can look like this:
In this case you translated these points so that they would be relative to the origin of the parent component.
This is because the drawXXX() methods for this component take coordinates relative to the parent component.
33.11. Images
Codename One has a few image types: loaded, RGB (built-in), RGB (Codename One), Mutable,
EncodedImage, SVG, MultiImage, FontImage & Timeline. URLImage, FileEncodedImage, FileEncodedImageAsync,
and StorageEncodedImage/Async also exist, and are covered in the IO section.
All image types are seamless to use and will work with drawImage and various image related image
APIs for the most part with caveats on performance etc.
For animation images the code must invoke the animate() method on the image (this is done automatically by Codename One when placing the image as a background or as an icon!You need to do it if you invoke drawImage in code rather than use a built-in component). |
Performance and memory wise you should read the section below and be aware of the image types you use.
The Codename One designer tries to conserve memory and be "clever" by using EncodedImage. While these are great for low memory you need to understand the complexities of image locking and be aware that you might pay a penalty if you don’t.
Here are the pros/cons and logic behind every image type. This covers the logic of how it’s created:
33.11.1. Loaded Image
This is the basic image you get when loading an image from the jar or network using
Image.createImage(String), Image.createImage(InputStream) & Image.createImage(byte[, int, int)],…
| Some other APIs might return this image type but those APIs do so explicitly! |
In some platforms calling getGraphics() on an image like this will throw an exception as it’s immutable). This is true for most other images as well.
This restriction might not apply for all platforms.
The image is stored in RAM based on device logic and should be reasonably efficient in drawing speed. For example, it takes up a lot of RAM.
To calculate the amount of RAM taken by a loaded image you use the following formula:
Image Width * Image Height * 4 = Size In RAM in Bytes
For example: a 50×100 image will take up 20,000 bytes of RAM.
The logic behind this is simple, every pixel contains 3 color channels and an alpha component hence 3 bytes for color and one for alpha.
| This isn’t the case for all images but it’s common and you prefer calculating for the worst case scenario. Even with JPEGs that don’t include an alpha channel some OSes might require that more byte. |
33.11.2. The RGB image’s
There are two types of RGB constructed images that are different from one another but since they’re both technically "RGB image’s" you’re bundling them under the same subsection.
Internal
This is a close cousin of the loaded image. This image is created using the method Image.createImage(int array, int, int) and receives the AARRGGBB data to form the image. It’s more efficient than the Codename One RGB image but can’t be modified, at least not on the pixel level.
The goal of this image type is to provide an easy way to render RGB data that isn’t modified efficiently at platform native speeds. It’s technically a standard "Loaded Image" internally.
RGBImage class
RGBImage is effectively an AARRGGBB array that can be drawn by Codename One.
On most platforms this is inefficient but for some pixel level manipulations there is no other way.
An RGBImage is constructed with an int array (int[]) that includes width*height elements. You can then change the colors and alpha channel directly within the array and draw the image to any source using standard image drawing APIs.
| This is inefficient in rendering speed and memory overhead. Only use this technique if there is absolutely no other way! |
33.11.3. EncodedImage
EncodedImage is the workhorse of Codename One. Images returned from resource files are EncodedImage and many APIs expect it.
The EncodedImage is effectively a loaded image that’s "hidden" and extracted as needed to remove the memory overhead associated with loaded image. When creating an EncodedImage the PNG (or JPEG etc.) is loaded to an array in RAM. Such images are small (relatively) so they can be kept in memory without much overhead.
When image information is needed (pixels) the image is decoded into RAM and kept in a weak/sort reference. This allows the image to be cached for performance and allows the garbage collector to reclaim it when the memory becomes scarce.
Since the fully decoded image can be pretty big (width X height X 4) the ability to store the encoded image can be pretty stark. For example: taking your example above a 50×100 image will take up 20,000 bytes of RAM for a loaded image but an EncodedImage can reduce that to 1kb-2kb of RAM.
An EncodedImage might be more expensive than a loaded image as it will take up both the encoded size and the loaded size. The cost might be slightly bigger sometimes. It’s main value is its ability to shrink. |
When drawing an EncodedImage it checks the weak reference cache and if the image is cached then it’s shown otherwise the image is loaded the encoded image cache it then drawn.
EncodedImage isn’t final and can be derived to produce complex image fetching strategies for example: the URLImage class that can dynamically download its content from the web.
EncodedImage can be instantiated through the create methods in the EncodedImage class. Pretty much any image can be converted into an EncodedImage through the createFromImage(Image, boolean) method.
33.11.4. MultiImage
Multi images don’t physically exist as a concept within the Codename One API so there is no way to actually create them and they’re in no way distinguishable from EnclodedImage.
The built-in support for multi images is in the resource file loading logic where a MultiImage is decoded and the version that matches the current DPI is physically loaded. From that point on user code can treat it like any other EnclodedImage.
The 9-image borders use multi images by default to keep their appearance more refined on the different DPI’s.
33.11.5. FontImage & Material design icons
FontImage allows using an icon font as if it was an image. You can specify the character, color and size and then treat the FontImage as if its a regular image. The huge benefits are that the font image can adapt to platform conventions in color and scale to adapt to DPI.
You can generate icon fonts using free tools on the internet such as this. Icon fonts are a simple and powerful technique to create a small, modern applications.
Icon fonts can be created in 2 basic ways the first is explicitly by defining all the elements within the font:
Form hi = new Form("Icon Font");
Font materialFont = FontImage.getMaterialDesignFont();
int w = Display.getInstance().getDisplayWidth();
FontImage fntImage = FontImage.createFixed("\uE161", materialFont, 0xff0000, w, w);
hi.add(fntImage);
hi.show();
| The samples use the built-in material design icon font. This is for convenience so the sample will work out of the box, for everyone. For example you should be able to do this with any arbitrary icon font off the internet as long as its a valid TTF file. |
A more common and arguably "correct" way to construct such an icon would be through the Style object. The Style object can provide the color, size and background information needed by FontImage.
There are two versions of this method: the first one expects the Style object to have the correct icon font set to its font attribute. The second accepts a Font object as an argument. The latter is useful for a case where you want to reuse the same Style object that you defined for a general UI element for example: you can set an icon for a Button like this and it will take up the style of the Button:
Form hi = new Form("Icon Font");
Font materialFont = FontImage.getMaterialDesignFont();
int size = Display.getInstance().convertToPixels(6, true);
materialFont = materialFont.derive(size, Font.STYLE_PLAIN);
Button myButton = new Button("Save");
myButton.setIcon(FontImage.create("\uE161", myButton.getUnselectedStyle(), materialFont));
hi.add(myButton);
hi.show();
Notice that for this specific version of the method the size of the font is used to determine the icon size. In the other methods for FontImage creation the size of the font is ignored! |
Material design icons
There are many icon fonts on the web, but the field is rather volatile and constantly changing. For example, you wanted to have built-in icons that would allow you to create better looking demos and built-in components.
That’s why you picked the material design icon font for inclusion in the Codename One distribution. It features a stable core set of icons, that aren’t IP encumbered.
You can use the built-in font directly as demonstrated above but there are far better ways to create a material design icon. To find the icon you want you can check out the material design icon gallery. For example: you used the save icon in the samples above.
To recreate the save icon from above you can do something like:
Form hi = new Form("Icon Font");
Button myButton = new Button("Save");
myButton.setIcon(FontImage.createMaterial(FontImage.MATERIAL_SAVE, myButton.getUnselectedStyle()));
hi.add(myButton);
Notice that the icon is smaller now as it’s calculated based on the font size of the Button UIID. |
You can even write the code in a more terse style using:
Form hi = new Form("Icon Font");
Button myButton = new Button("Save");
FontImage.setMaterialIcon(myButton, FontImage.MATERIAL_SAVE);
hi.add(myButton);This will produce the same result for slightly shorter syntax.
FontImage can conflict with some complex APIs that expect a "real" image underneath. Some odd issues can often be resolved by using the toImage() or toEncodedImage() methods to convert the scaled FontImage to a loaded image. |
33.11.6. Timeline
Timelines allow rudimentary animation and enable GIF importing using the Codename One Designer. Effectively a timeline is a set of images that can be moved rotated, scaled & blended to provide interesting animation effects. It can be created manually using the Timeline class.
33.11.7. Image masking
Image masking allows you to manipulate images by changing the opacity of an image according to a mask image. The mask image can be hardcoded or generated dynamically, it’s then converted to a Mask object that can be applied to any image. Notice that the masking process is computationally intensive, it should be done once and cached/saved.
The code below can convert an image to a rounded image:
Toolbar.setGlobalToolbar(true);
Form hi = new Form("Rounder", new BorderLayout());
Label picture = new Label("", "Container");
hi.add(BorderLayout.CENTER, picture);
hi.getUnselectedStyle().setBgColor(0xff0000);
hi.getUnselectedStyle().setBgTransparency(255);
Style s = UIManager.getInstance().getComponentStyle("TitleCommand");
Image camera = FontImage.createMaterial(FontImage.MATERIAL_CAMERA, s);
hi.getToolbar().addCommandToRightBar("", camera, (ev) -> {
try {
int width = Display.getInstance().getDisplayWidth();
Image capturedImage = Image.createImage(Capture.capturePhoto(width, -1));
Image roundMask = Image.createImage(width, capturedImage.getHeight(), 0xff000000);
Graphics gr = roundMask.getGraphics();
gr.setColor(0xffffff);
gr.fillArc(0, 0, width, width, 0, 360);
Object mask = roundMask.createMask();
capturedImage = capturedImage.applyMask(mask);
picture.setIcon(capturedImage);
hi.revalidate();
} catch(IOException err) {
Log.e(err);
}
});
Notice that this example is simplistic to be self contained. You often recommend that developers ship "ready made" mask images with their application which can allow complex effects on the images.
33.11.8. URLImage
URLImage is an image created with a URL, it implicitly downloads and adapts the image in the given URL while
caching it locally. The typical adapt process scales the image or crops it to fit into the same size which is a
hard restriction because of the way URLImage is implemented.
The simple use case is pretty trivial:
Or you can use the similar URLImage.createToFileSystem method instead of the Storage version.
This image can now be used anywhere a regular image will appear, it will initially show the placeholder image
and then seamlessly replace it with the file after it was downloaded and stored. Notice that if you make changes
to the image itself (for example: the scaled method) it will generate a new image which won’t be able to fetch the actual
image.
Since ImageIO is used to perform the operations of the adapter interface its required that ImageIO will work.
it’s working in Java SE, Android, iOS & Windows Phone. |
If the file in the URL contains an image that’s too big it will scale it to match the size of the placeholder precisely!
An option also exists to fail if the sizes don’t match. Notice that the image that will be saved is the scaled
image, this means you will have little overhead in downloading images that are the wrong size although you
will get some artifacts.
The last argument is powerful, its an interface called URLImage.ImageAdapter and you can implement it to adapt the downloaded image in any way you like. For example: you can use an image mask to automatically create a rounded version of the downloaded image.
To do this you can override:
In the adapter interface and return the processed encoded image. If you do heavy processing (for example: rounded edge images) you would need to convert the processed image back to an encoded image so it can be saved. You would then also want to show that this operation should run asynchronously through the appropriate method in the class.
If you need to download the file instantly and not wait for the image to appear before download initiates you can explicitly invoke the fetch() method which will asynchronously fetch the image from the network. Notice that the downloading will still take time so the placeholder is still required.
Authenticated image URLs — RequestDecorator
The standard createToStorage path doesn’t expose the underlying
ConnectionRequest, so attaching an Authorization header (or any
other custom header / cookie / timeout) requires the RequestDecorator
hook. Two ways to install one:
For per-image overrides (for example one endpoint needs an extra API-version
header on top of the global bearer token), use the
createToStorage(placeholder, key, url, adapter, RequestDecorator)
overload. Per-instance decorators run after the global default so they
can override or augment whatever the default set:
When a decorator is installed (global or per-call), URLImage skips the
default Util.downloadImageToStorage path and builds a
ConnectionRequest inline so the decorator can inspect / mutate it
before it’s queued. The legacy path remains the default for back-compat
when no decorator is set.
Mask adapter
A URLImage can be created with a mask adapter to apply an effect to an image. This allows you to round downloaded images or apply any sort of masking for example: you can adapt the round mask code above as such:
URLImage in lists
The biggest problem with image download service is with lists. You decided to attack this issue at the core by
integrating URLImage support directly into GenericListCellRenderer which means it will work with MultiList,
List & ContainerList. To use this support define the name of the component (name not UIID) to end with
_URLImage and give it an icon to use as the placeholder. This is easy to do in the multilist by changing the
name of icon to icon_URLImage then using this in the data:
Make sure you also set a "real" icon to the entry in the GUI builder or in handcoded applications. This is important
since the icon will be implicitly extracted and used as the placeholder value. Everything else should be handled
automatically. You can use setDefaultAdapter & setAdapter on the generic list cell renderer to install adapters
for the images. The default is a scale adapter although you might change that to scale fill in the future:
The createListEntry method then looks like this:
private Map<String, Object> createListEntry(String name, String date, String coverURL) {
Map<String, Object> entry = new HashMap<>();
entry.put("Line1", name);
entry.put("Line2", date);
entry.put("icon_URLImage", coverURL);
entry.put("icon_URLImageName", name);
return entry;
}
33.12. Charts
Codename One includes a charting toolkit in the com.codename1.charts package
that’s designed to integrate with regular UI layouts. Charts are drawn by
creating an appropriate dataset and renderer pair, instantiating the matching
chart view class, and wrapping it in a
ChartComponent
it can be added to a form:
The following classes are available for different kinds of visualisations:
| Chart class | Dataset & renderer | Notes |
|---|---|---|
| Draws categorical data as vertical bars. The | |
| Represents each data point as a circle whose size is proportional to a third value. | |
| Combines several XY chart types in a single plot using | |
| Smooths line series with cubic interpolation. Pass a smoothness factor to the constructor to control the curve. | |
| Renders one or more gauges on a dial, making it useful for KPI dashboards. | |
| Shows hierarchical proportions as concentric rings around a common center. | |
| Connects series of points using straight line segments. Supports optional fill areas and point markers. | |
| Splits a circle into slices that are proportional to each category value. | |
| Draws a spider/web chart that compares multiple categories across the same set of axes. | |
| Variation of | |
| Abstract base class for circular charts. Use subclasses such as | |
| Plots unconnected X/Y points with configurable marker shapes. | |
| Extends |
34. 3D Graphics and Shaders
The com.codename1.gpu package provides a portable, hardware accelerated 3D
graphics API focused on games but useful anywhere you need GPU rendered content.
It runs from one code base on the JavaSE simulator (OpenGL via JOGL), Android
(OpenGL ES 2), iOS and Mac Catalyst (Metal), the native Windows port (Direct3D
11), and the JavaScript port (WebGL). The API integrates with the normal Codename
One UI: a 3D scene lives inside a regular component that you add to a Form like
any other.
Your
|
3D is a low-level, GPU dependent feature. Always guard usage with
CN.isGpuSupported() (or RenderView.isSupported()); on a platform without a
backend the RenderView reports unsupported so you can fall back to 2D. |
34.1. Concepts
The API is intentionally "hybrid": a low level command layer (buffers, textures, render state, draw calls) for full control, plus high level helpers (meshes, materials, a camera) for common cases. Crucially, you never write shader source. Instead you describe a Material (a lighting model plus color and texture) and the engine generates the matching platform shader behind the scenes: GLSL ES on OpenGL ES and WebGL, GLSL on the desktop simulator, Metal Shading Language on iOS and Mac, and HLSL on the native Windows (Direct3D) port. This "engine-managed shader" approach is what keeps the same application code rendering identically across a range of different GPUs.
The main types are:
RenderView - the
Componentthat hosts the GPU surface. You give it aRenderer.Renderer - your callback:
onInit,onResize,onFrame,onDispose. These run on the platform render thread, never the EDT.GraphicsDevice - the command surface passed to your renderer. It creates buffers and textures, clears, sets the viewport, the camera and the light, and issues
drawcalls.Mesh, Material, Camera, Light - the high level scene building blocks.
34.2. A first scene: A spinning cube
The renderer below draws a Phong lit cube. Primitives.cube builds the geometry,
a Material describes the surface, and a Camera supplies the view. Notice there
is no shader code anywhere.
setContinuous(true) runs an animation loop. For a static scene leave it off and
call view.requestRender() whenever something changes; this conserves battery.

34.3. Materials
A Material is a declarative description of a surface. Its Type selects the
lighting model:
| Type | Description |
|---|---|
| Flat color/texture, no lighting. Ideal for UI, emissive surfaces. |
| Diffuse (Lambert) lighting from one directional light. |
| Diffuse + specular highlight (uses |
| Unlit, for screen aligned sprites and billboards. |
| Unlit background, rendered behind the scene. |
A material also carries a base color (setColor, packed 0xAARRGGBB), an
optional Texture (setTexture), and a RenderState controlling depth testing,
alpha blending and face culling. Textures come from a Codename One Image or raw
ARGB pixels:

34.4. Meshes and buffers
Primitives builds common shapes (cube, quad). For custom geometry, allocate a
VertexBuffer
with a VertexFormat, fill the interleaved float data, and (optionally) an
IndexBuffer:
VertexBuffer vb = device.createVertexBuffer(VertexFormat.POSITION_NORMAL_TEXCOORD, 4);
vb.setData(new float[] { /* px,py,pz, nx,ny,nz, u,v per vertex null */ });
IndexBuffer ib = device.createIndexBuffer(6);
ib.setData(new int[] { 0, 1, 2, 0, 2, 3 });
Mesh mesh = new Mesh(vb, ib, PrimitiveType.TRIANGLES);Vertex buffers are allocated through the platform SIMD allocator, which on iOS
(ParparVM) places the data at a fixed, aligned native address so it can be handed
to Metal with no intermediate copy. You don’t need to do anything special to get
this; just write into getData() and call setDirty() when you mutate it.
34.5. Loading models
Real scenes use authored geometry. GltfLoader loads a glTF 2.0 model, both the
binary .glb container and the JSON .gltf form with embedded buffers.
loadModel returns the mesh together with the base-color texture from the model’s
own material, so a textured model renders with no extra setup:
The model below is the Khronos "BoomBox" glTF sample (a CC0 model carrying its own base-color texture), loaded this way and drawn Phong lit:

34.6. Animation
Drive a value (a rotation angle, a position) over time and redraw. A continuous
RenderView calls onFrame every frame; an on-demand view redraws when you call
requestRender(). The grid below captures six fixed rotation stages of a spinning
cube, each drawn into its own viewport in a single frame:

34.7. Camera and math
Camera builds
the view and projection matrices from an eye position, a look-at target and lens
settings (setPerspective or setOrthographic). All matrix helpers live in
Matrix4
(column-major float[16]): translation, scaling, rotation, multiply,
lookAt, perspective, ortho. Pass a model matrix as the third argument to
draw, or null for the identity.
34.8. Platform notes
JavaSE simulator - OpenGL through JOGL, loaded from an isolated class so a missing or failing GL driver degrades to a built in software rasterizer instead of breaking the simulator. Lets you develop and debug 3D without a device.
Android - OpenGL ES 2 via a
GLSurfaceViewhosted as a native peer.iOS and Mac Catalyst - Metal. Shaders are generated as Metal Shading Language and compiled at runtime; vertex/index data is uploaded to `MTLBuffer`s, zero-copy where the SIMD allocation permits.
Native Windows - Direct3D 11. Shaders are generated as HLSL and compiled with
D3DCompile; the offscreen render target is read back and composited into the UI.JavaScript - WebGL on a
<canvas>peer; the generated GLSL ES runs unmodified.
Querying capabilities at runtime:
34.9. Threading
Renderer callbacks run on the platform render thread, not the Codename One EDT.
Don’t touch UI components from inside them. To move data the other way (for
example to update a HUD label from a game loop), use CN.callSerially(…).
35. Augmented Reality
The com.codename1.ar package composites virtual 3D content into the live camera image: the session tracks the device’s position in the real world, detects surfaces, recognizes registered images and faces, and keeps virtual objects locked to real-world positions as the user moves. It’s backed by ARKit on iOS and by ARCore (Google Play Services for AR) on Android, behind one portable API.
Referencing any class in the package is enough to wire the build: the class scanner injects the camera permission, the NSCameraUsageDescription plist entry (override the text with the ios.NSCameraUsageDescription build hint), links ARKit and SceneKit on iOS and adds the ARCore dependency plus the com.google.ar.core manifest entry on Android. Apps that never touch the package pay no size, permission or store-visibility cost. By default the Android manifest marks AR optional so the app still installs on devices without ARCore; set the android.ar.required=true build hint to make the app AR-only.
Always guard AR functionality behind |
35.1. Concepts
| Type | Role |
|---|---|
| Static entry point: support and capability checks, permission request, session opening. |
| The running AR experience. One session may be open at a time; it owns the view, the anchors and the detected planes, and delivers all events. |
| The component that renders the camera image composited with the anchored content. Add it to a form like any other component. |
| An immutable position + rotation in world space: meters, right-handed, Y up, -Z forward from the initial camera direction. Converts to a |
| A detected real-world surface (floor, table, wall) that grows and refines as the session learns the environment. |
| The intersection of a screen-point ray with real-world geometry; the bridge from a tap to a world position. |
| A tracked fixed point in the real world. The attachment point for content; also delivered for recognized images ( |
| The content placed at an anchor: a small scene graph of nodes carrying glTF models or |
| The real-world lighting estimate, polled per frame to shade content so it blends in. |
35.2. Getting started: Place a model on the floor
The canonical AR loop is: open a session, show its view, wait for a plane, hit test a tap, anchor content at the hit.
if (!AR.isSupported()) {
ToastBar.showInfoMessage("AR is not supported on this device");
return;
}
final ARSession session = AR.open(new ARSessionOptions());
final ARView view = session.createView();
Form f = new Form("AR", new BorderLayout());
f.add(BorderLayout.CENTER, view);
f.show();
// modelBytes is a .glb asset, e.g. loaded from getResourceAsStream
view.addPointerReleasedListener(e -> {
float xn = (e.getX() - view.getAbsoluteX()) / (float) view.getWidth();
float yn = (e.getY() - view.getAbsoluteY()) / (float) view.getHeight();
session.hitTest(xn, yn).ready(hits -> {
if (hits.length > 0) {
ARAnchor anchor = hits[0].createAnchor();
anchor.setNode(new ARNode(ARModel.fromGltf(modelBytes)));
}
});
});ARSessionOptions configures the session before it opens: the tracking mode (WORLD or FACE), which plane orientations to detect, whether to estimate lighting, and the reference images to recognize. The defaults open a world tracking session with horizontal plane detection and light estimation, which suits the place-content-on-a-surface use case above.
35.3. Plane detection
Planes are delivered through ARPlaneListener as immutable snapshots: an ADDED event when a new surface is found, UPDATED snapshots (sharing the same getId()) as the surface grows, and REMOVED when a plane merges into another. ARSession.getPlanes() always reflects the latest snapshots.
session.addPlaneListener(ev -> {
ARPlane p = ev.getPlane();
System.out.println(ev.getKind() + " " + p.getType()
+ " " + p.getExtentX() + "x" + p.getExtentZ() + "m");
});The plane’s local frame has X/Z spanning the surface and Y along the normal; getCenterPose() positions that frame in the world. ARPlane.Type distinguishes upward-facing horizontal surfaces (floors, tables), downward-facing ones (ceilings) and vertical surfaces (walls) - request vertical detection with ARSessionOptions.planeDetection(ARPlaneDetection.HORIZONTAL_AND_VERTICAL).
35.4. Hit testing and anchors
hitTest(xNorm, yNorm) shoots a ray from a normalized view coordinate into the world and resolves - on the EDT - with the intersections ordered nearest first. Prefer ARHitResult.createAnchor() over session.createAnchor(pose) when placing on detected geometry: the platform can then anchor to the exact native raycast, which tracks better as the environment refines.
Anchors survive tracking refinements: the session updates getPose() over time and reports the change through ARAnchorListener. Remove an anchor (and its content) with detach(). Content attaches through setNode(ARNode):
ARNode root = new ARNode(ARModel.fromMesh(
Primitives.sphere(0.15f, 24, 32, false), 0xffdd4433));
root.setLocalPosition(0, 0.15f, 0); // rest on the surface, not in it
anchor.setNode(root);Node transforms are relative to the anchor, in meters. Nodes may nest (addChild), carry glTF assets (ARModel.fromGltf) or portable meshes (ARModel.fromMesh), and any mutation after attachment - position, rotation, scale, visibility, children - re-syncs the platform renderer automatically.
35.5. Light estimation
session.getLightEstimate() returns the latest estimate of the real-world lighting. It refreshes every frame without firing events, so poll it when rendering-relevant decisions are made. The ambient intensity is normalized so 1.0 means neutral indoor lighting; the color correction is a per-channel scale where {1, 1, 1} is neutral. Platform renderers already apply the estimate to anchored content; the API exposes it for custom logic such as prompting the user when the room is too dark.
35.6. Image tracking
Register printed images - posters, game boards, product labels - and the session anchors content to them when the camera sees them:
ARSessionOptions opts = new ARSessionOptions().referenceImages(new ARReferenceImage[]{
new ARReferenceImage("poster", posterPngBytes, 0.42f) // physical width in meters
});
ARSession session = AR.open(opts);
session.addAnchorListener(ev -> {
if (ev.getKind() == ARAnchorEvent.Kind.ADDED
&& ev.getAnchor() instanceof ARImageAnchor) {
ARImageAnchor img = (ARImageAnchor) ev.getAnchor();
System.out.println("Recognized " + img.getReferenceImageName());
img.setNode(new ARNode(ARModel.fromGltf(overlayModel)));
}
});The physical width matters: the platform uses it to estimate the image’s distance, so measure the real print. The anchor pose is centered on the physical image with local X/Z spanning its surface.
35.7. Face tracking
Face tracking is a distinct session configuration using the front camera; open it with ARSessionOptions.trackingMode(ARTrackingMode.FACE) after checking AR.getCapabilities().isFaceTrackingSupported(). Detected faces arrive as `ARFaceAnchor`s through the anchor listener, carrying the head pose plus optional finer geometry:
getRegionPose(ARFaceRegion)returns the pose of a named region. Availability differs per platform (ARCore supplies the nose tip and forehead regions, ARKit supplies the eyes), which is why code must always handle anullregion.getMeshVertices()/getMeshTriangles()expose the tracked face mesh where the platform provides one, ornullwhere it doesn’t.
35.8. Events and threading
Every listener fires on the EDT and every getter reflects the state as of the events delivered so far, so AR code follows normal Codename One threading rules with no extra synchronization. High-frequency refinements (anchor and plane updates, camera pose, light estimate) are coalesced: a slow EDT sees the latest values rather than a backlog. This contrasts with the com.codename1.gpu.Renderer callbacks used by the VR API, which run on the render thread.
35.9. The simulator and debugging
The Codename One simulator ships a simulated AR backend modeled on the Android emulator’s virtual scene, so the full AR loop is debuggable with breakpoints without a device. When a session opens, the simulator "detects" the floor (and, when requested, a wall) of a virtual room after a short startup delay, mimicking real AR initialization. The AR view renders the room and every anchored model; drive the virtual device camera with the mouse (drag to look around) and keyboard (W/A/S/D or the arrow keys to move, Q/E for up and down).

The Simulate menu’s AR Simulation window drives the paths that are hard to reproduce on demand with real hardware: force degraded tracking states and failure reasons, change the light estimate, re-run plane detection, trigger recognition of a registered reference image, and toggle a simulated face anchor for FACE sessions.
On devices, use the standard native tools: the generated Xcode project debugs the ARKit session and SceneKit scene directly (including Instruments), and Android Studio attaches to the Gradle project for ARCore logging. Note that Apple’s iOS Simulator has no ARKit support - real ARKit behavior needs a physical device - while the Android emulator can run ARCore against its own virtual scene.
35.10. Platform notes
Dependencies: injected automatically as described above. The ARCore dependency adds about 2 MB to Android binaries; iOS links the system ARKit/SceneKit frameworks at no size cost.
Capabilities: face tracking requires a capable front camera (a TrueDepth camera on iOS). Check
ARCapabilitiesper feature rather than assuming.Face regions: ARCore supplies
NOSE_TIP,FOREHEAD_LEFTandFOREHEAD_RIGHT; ARKit suppliesLEFT_EYEandRIGHT_EYE. Code that uses regions must handle anullregion.ARCore installation: on Android, Play Services for AR may need installing or updating; when
AR.opentriggers that flow it throws with a message saying to retry once installation completes.tvOS / watchOS: AR compiles out entirely;
AR.isSupported()reportsfalse.
36. Virtual Reality and 360 Media
The com.codename1.vr package renders application scenes in stereoscopic VR and displays 360-degree panoramas, built entirely on the portable com.codename1.gpu pipeline and the com.codename1.sensors motion sensors. There is no platform SDK dependency: everything here runs wherever Display.getInstance().isGpuSupported() is true, which includes the simulator, and adds nothing to the build for apps that don’t use it.
Like |
36.1. Concepts
| Type | Role |
|---|---|
| The stereo component: clears the frame, splits the viewport per eye, positions the cameras from head tracking and invokes your renderer once per eye. |
| Your scene callback: |
| Which eye a frame is for: |
| Interpupillary distance (default 0.064m), per-eye field of view, clip planes and the stereo default. |
| Wires the gyroscope, accelerometer and magnetometer into an orientation with thread-safe snapshots for the render thread. |
| The deterministic sensor-fusion math behind the tracker, usable on its own. |
| Per-eye camera math over the existing |
| A 360-degree panorama viewer: an equirectangular image on the inside of a sphere with drag or gyroscope look-around. |
| Extension point feeding dynamic textures (procedural animation, future video) to |
36.2. Getting started: A stereo scene
A VRRenderer draws the same scene for every eye; the camera differences produce the depth effect. The view configures the viewport and camera before each onEyeFrame, so the renderer only issues draw calls:
VRView vr = new VRView(new VRRenderer() {
Mesh cube;
Material material;
public void onInit(GraphicsDevice device) {
cube = Primitives.cube(device, 0.5f);
material = new Material(Material.Type.PHONG).setColor(0xff3366ff);
}
public void onEyeFrame(GraphicsDevice device, VREye eye, Camera camera) {
device.draw(cube, material, Matrix4.translation(0, 0, -2));
}
public void onDispose(GraphicsDevice device) { }
});
vr.setContinuous(true); // head tracked scenes want continuous rendering
Form f = new Form("VR", new BorderLayout());
f.add(BorderLayout.CENTER, vr);
f.show();setStereo(false) switches to a single centered viewpoint (VREye.CENTER) at runtime, useful for a non-headset preview of the same scene. setPosition(x, y, z) moves the viewer through the world; setClearColor(argb) sets the background.

36.3. Head tracking
VRView starts its HeadTracker when the component appears and stops it when it leaves the screen; the sensors draw power only between the two. The tracker fuses the gyroscope with the accelerometer (tilt reference) and, when present, the magnetometer (yaw reference) through a complementary filter - tune the blend via getHeadTracker().getFilter().setGyroWeight(float).
Call recenter() to make the current view direction the new "straight ahead," keeping pitch and roll - the standard VR recentering gesture. On devices without a gyroscope the tracker falls back to accelerometer tilt: pitch and roll stay accurate but yaw has no stable reference. HeadTracker.isSupported() reports whether any usable motion hardware exists; without it the orientation simply stays put and the scene still renders.
36.4. The 360 photo viewer
Media360View displays equirectangular panoramas - the format produced by 360 cameras and phone panorama modes, where longitude maps to X and latitude to Y:
Media360View pano = new Media360View();
pano.setImage(EncodedImage.create("/panorama.jpg"));
f.add(BorderLayout.CENTER, pano);
Dragging looks around with the grab-the-world gesture; setHeadTrackingEnabled(true) adds gyroscope look composed with the drag, and setStereo(true) renders side by side for cardboard-style viewers. Photo spheres are captured from a single point, so stereo intentionally uses zero eye separation - there is no parallax information in the image to reproduce. setYaw/setPitch position the view programmatically and reset() returns to straight ahead.
36.5. 360 video and dynamic content
There is no platform path from media frames to GPU textures yet, so 360 video isn’t supported directly. TextureSource is the extension point for dynamic content: the view calls createTexture once on the render thread and updateTexture before every frame, so procedurally animated panoramas work today and a future media-to-texture bridge can plug in without API changes.
pano.setTextureSource(new TextureSource() {
public Texture createTexture(GraphicsDevice device) {
return device.createTexture(1024, 512, initialPixels);
}
public boolean updateTexture(GraphicsDevice device, Texture texture) {
// mutate pixels and re-upload as needed; return true when changed
return false;
}
public void dispose(GraphicsDevice device) { }
});36.6. The simulator
Both VRView and Media360View run in the simulator through the desktop 3D backend, and the Simulate menu’s Motion / Gesture Simulation window feeds synthetic sensor data to the HeadTracker, so head-tracked scenes are drivable from the desktop. Drag-look in Media360View works with the mouse as it does with a finger.
36.7. Limitations and notes
Lens distortion: the stereo output is undistorted side-by-side rendering. Barrel distortion for lens-based viewers requires an offscreen render pass the portable GPU API doesn’t expose yet, so there is no distortion setting to configure.
Battery: continuous rendering plus live sensors is the most power-hungry mode a phone UI can run; stop or pause the view whenever it isn’t visible (the component does this automatically on hide).
Coordinates: the world frame matches the AR and 3D graphics APIs (meters, right-handed, Y up, -Z forward), letting content and math move between the three without conversion.
37. Game Development
Codename One is a general purpose UI toolkit, but it ships with a package built
specifically for games: com.codename1.gaming.
It gives you the things games need — a tight update loop, sprite primitives,
pollable input, low latency sound effects and rigid body physics — and renders on
the GPU through the com.codename1.gpu package.
Everything written here runs unchanged on every Codename One target, including iOS.
This chapter covers the real time game surface. For the "casual game"
approach — building game elements out of regular Component`s and letting the
layout system render them — the techniques in the Chapter 31, Animations chapter are
often a better fit. Reach for `com.codename1.gaming when you want a frame driven
loop and GPU sprite rendering. |
37.1. Sample games
The samples project ships several runnable starting points. Each is a single file built entirely from art generated at runtime — no asset files — so you can copy one and start changing it immediately. The rest of this chapter draws on them to show how the pieces fit together.
![]() | ![]() | ![]() |
|
|
|
Two more samples show how far the same 2D primitives stretch — one flat, one faked into 3D:
CardGameSample— a 2D Memory (Concentration) match. Each card is aSpritein a grid; flipping one animates its horizontal scale through zero and swaps the image at the thin point, and taps are hit-tested against sprite bounds throughGameInput. A compact illustration of flat 2D play with no camera tricks at all. Dissected in Section 37.6, “Case study: The card game (flat 2D)”.BoardGameSample— faux-3D checkers on an isometric board. Every tile and piece is still a flatSprite, but laying them out in an isometric (2:1 diamond) projection and raising the pieces off their tiles with a drop shadow gives a convincing 3D look without any GPU 3D, perspective camera or models. The screen pixel-to-board-cell mapping (and its inverse, for picking) is the same math behind any isometric strategy or tycoon game; it also implements the full move/jump/chain /crown rules and a small AI so you can play it solo. Dissected in Section 37.7, “Case study: Faux-3D checkers (isometric projection)”.
The action samples are driven by the joystick and buttons in Section 37.4, “On-screen touch controls”, so they’re equally playable on a touch device and in the desktop simulator (where the arrow keys and mouse stand in for the stick); the card and board games are pure tap.
37.2. The game loop: GameView
GameView
is the heart of the package. It’s a GPU surface (a
RenderView)
that runs the frame loop for you — a display link on device, the dependency-free
software rasterizer in the simulator — so there’s no EDT busy loop and no frame
rate to manage. You build your world by adding Sprite`s to its `Scene, advance
the game in update(double), and the view draws the scene every frame.
The dt passed to update is the wall clock time since the previous frame.
Multiplying movement by it keeps the game running at the same speed regardless of
the actual frame rate ("delta timing"). Notice there’s no draw method — positioning
sprites is all you do; the GPU renderer handles the rest (see Section 37.5, “Sprites”).
37.2.1. Lifecycle
start() begins continuous rendering, stop() halts it, and pause()/resume()
suspend update while the view keeps drawing the last frame. start() is safe to
call before or after the form is shown.
setClearColor(int argb) sets the background the view is cleared to each frame.
37.2.2. Fixed timestep and interpolation
Variable time steps are simple but make physics nondeterministic. Call
setFixedTimestep(seconds) to have update invoked at a fixed interval instead;
the loop accumulates real time and may call update several times in one frame to
catch up (capped to avoid a "spiral of death" after a long pause). The leftover
fraction is available from getInterpolationAlpha() (0 to 1) so you can interpolate
rendered positions between physics states:
37.2.3. Threading
update(double) runs on the render thread, together with drawing. Keep it
non-blocking — offload asset loading, networking or other long work to a background
thread and hand the result back with
CN.callSerially.
37.3. Input: GameInput
Games usually want to ask "is the left key down right now?" rather than handle a
stream of events. GameInput,
obtained from GameView.getInput(), captures the view’s key and pointer events
and exposes them as state. There are two flavors:
Level state, true for as long as the input is held:
isKeyDown(int),isGameKeyDown(int gameAction),isPointerDown().Edge state, true only during the single frame the transition happened:
wasKeyPressed(int),wasKeyReleased(int),wasPointerPressed(),wasPointerReleased(). Edges are cleared at the end of each frame, afterupdatehas run.
isGameKeyDown works with the device independent game actions Display.GAME_UP,
GAME_DOWN, GAME_LEFT, GAME_RIGHT and GAME_FIRE, so directional input works
the same across keyboards and devices. Pointer coordinates are reported relative
to the `GameView’s top left.
37.4. On-screen touch controls
A keyboard is fine in the simulator, but a phone has no arrow keys. Every
GameView comes with a TouchControls
(from getControls()) that draws an on-screen virtual joystick and buttons and
feeds them into the same GameInput — so the input code you already wrote for
the keyboard works untouched on touch devices.
The joystick reports analog direction through
GameInput#getAxisX()/getAxisY()(each -1 to 1), and at the same time presses the digital game actionsGAME_LEFT/GAME_RIGHT/GAME_UP/GAME_DOWNonce it crosses its dead zone, soisGameKeyDown(…)keeps working.A button holds down a key code while it’s pressed, so
isKeyDown(int)andwasKeyPressed(int)report it exactly like a hardware key. Map it to a game action withDisplay.getInstance().getKeyCode(Display.GAME_FIRE), or to any key code of your own.
Anchor controls to a corner of the view’s safe area with the alignment constants
(TouchControls.LEFT / CENTER / RIGHT and TOP / CENTER / BOTTOM) and a
margin. The framework keeps them clear of notches and home indicators and
repositions them automatically when the view resizes or the device rotates — you
never recompute coordinates:
The joystick (bottom-left) and JUMP button (bottom-right) are visible in the
sample screenshots above. There are also absolutely
positioned overloads (addJoystick(centerX, centerY, radius)), and
setVisible(false) hides the overlay — handy when a real keyboard is attached.
Multi-touch is supported, so the player can steer and press a button at once.
37.5. Sprites
A Sprite
is a lightweight data holder: an image plus position, rotation, scale, a normalized
anchor and an ARGB tint. It describes what and where; a
SpriteRenderer
turns it into a GPU textured quad each frame using the com.codename1.gpu package — an orthographic camera mapping one world unit to one pixel, a
com.codename1.gpu.Material.Type#SPRITE material and alpha blending. Because a
sprite never touches the GPU directly you create one with just an
com.codename1.ui.Image; the renderer uploads and caches the matching texture on
demand.
getX()/getY() is the location of the anchor point (the image center by
default), and rotation and scale pivot around that anchor.
getBounds() returns the axis aligned bounding box and intersects(Sprite) does a
quick box overlap test, handy for broad phase collision before you involve physics.
37.5.1. Scenes
A Scene is a
z-ordered collection of sprites with an optional camera offset, drawn for you by
the renderer. Sprites are drawn from lowest to highest zOrder, so higher z-order
sprites appear on top; the camera offset (setCamera(int, int)) scrolls the whole
scene. GameView.getScene() is the scene the view draws.
You don’t need a GameView to render sprites: a SpriteRenderer is itself a
com.codename1.gpu.Renderer, so you can host one in a plain RenderView.
37.5.2. Sprite sheets and animation
SpriteSheet
slices one atlas image into a grid of equally sized frames, cutting and caching
each frame on first use (cutting a sub image copies pixels, so caching matters).
AnimatedSprite
is a Sprite that cycles through a sequence of frames over time; the scene advances
it every frame, so adding it to the scene is all you need.
A sprite sheet is just a strip (or grid) of frames like the run cycle above: the
arms and legs swing a little further each frame, and playing them in sequence reads
as motion. AnimatedSprite also accepts a plain com.codename1.ui.Image[] when you
build the frames yourself, which is what `ScrollerGameSample’s runner does:
Setting a negative scale flips the sprite horizontally, so a single set of frames
faces both ways — no mirrored art needed (sprites are drawn double-sided for
exactly this reason). play(), pause(), stop(), setLooping(boolean) and
setCurrentFrame(int) control playback.
37.6. Case study: The card game (flat 2D)

CardGameSample is Memory (Concentration): sixteen face-down cards in a four-by-four
grid, tap two and they stay up when they match, flip back when they don’t. It’s
the smallest complete example of turn-based 2D play with com.codename1.gaming — no joystick, no physics, no camera — which makes the three techniques it does
use easy to see in isolation.
One sprite per card. Each card is a Sprite positioned at its grid slot. There
are exactly two images at any moment: the shared card-back image and the card’s
own face (all generated at runtime with Image.createImage and Graphics calls,
so the sample needs no assets). Changing what a card shows is just
sprite.setImage(…).
A flip you can fake with scale. A real card flip is a 3D rotation, but squeezing the sprite’s horizontal scale through zero and swapping the image at the thin point reads exactly the same to the eye:
This is the same negative/positive scale trick the scroller uses to flip its runner, driven over time to play as an animation.
Polled taps against sprite bounds. There are no buttons to wire up;
update(double) polls the GameInput edge state and hit-tests the tap against
each card’s bounding box:
The rest of the sample is a small state machine living in plain fields: the
first and second face-up cards, a mismatchTimer that counts down in update
before flipping a failed pair back, and a moves counter surfaced through the
form title. Note the timer: in a game loop you don’t schedule callbacks, you
subtract dt from a countdown field each frame and act when it crosses zero.
37.7. Case study: Faux-3D checkers (isometric projection)

BoardGameSample plays a full game of checkers — moves, forced captures, chained
jumps, crowning, and a small AI opponent — on a board that looks convincingly 3D — yet there is no perspective camera and no Model anywhere: every tile and piece
is a flat Sprite. The 3D impression comes entirely from where the flat art is
placed, a technique (isometric or "2.5D" projection) that powered decades of
strategy and tycoon games and still works just as well on a GPU sprite pipeline.
The projection. Board cell (r, c) maps to screen pixels by laying the grid out
as 2:1 diamonds — columns step right-and-down, rows step left-and-down:
Picking is the inverse. Because the mapping is linear it inverts with two divisions, turning a tap back into a board cell — no per-tile hit testing required:
Depth from z-order. Cells further down the screen must draw over the cells
behind them, and within one cell the stacking is tile, then shadow, then
selection/move markers, then the piece. Both rules collapse into a single
number — (r + c) strides the cells from back to front, and a small offset
layers the sprites within a cell:
That pair of lines is also the whole "3D height" illusion: the piece is drawn
raised off its tile while its shadow stays put, and the eye reads the gap as
elevation. The piece art helps — an elliptical top face over a darker side rim,
again just fillArc calls on a runtime-generated image.
Rebuild, don’t mutate. After every move the sample throws away all its dynamic
sprites (pieces, shadows, markers) and recreates them from the board[][] array
in one syncPieces() pass. With a few dozen sprites this costs nothing, and it
keeps the scene a pure function of the game state — there is no way for the
display to drift out of sync with the rules, which eliminates the whole class of
"the board shows X but the game thinks Y" bugs. The game logic itself
(destinations, forced captures, chaining, crowning) never touches a sprite; it
reads and writes the int[][] board only.
When fake 3D stops being enough — you want the camera to move through the world rather than look at it — the next section covers the real thing.
37.8. 3D and perspective
GameView renders on the GPU through the com.codename1.gpu
package, so the same scene can be shown in 3D. Every view has a
GameCamera
that starts in 2D mode; switching it to perspective turns flat sprites into
camera-facing billboards in a 3D world and lets you draw 3D meshes alongside them.
That’s the basis for deeper gameplay modes — an over-the-shoulder racer, an
isometric or top-down view with real depth, a 2.5D shooter.

Gaming3DDemoSample (above) is built entirely from the primitives this section
describes — a textured ground plane, lit cube Model meshes, and billboarded
Sprite coins and trees, all orbited by a perspective camera.
37.8.1. Perspective camera and billboard sprites
Call GameCamera#setPerspective(float, float, float) and position the camera with
setPosition / setTarget. Once in perspective mode a Sprite is placed in world
space with Sprite#setPosition(double, double, double) and is drawn as a billboard
that always faces the camera, so your existing 2D art keeps working in 3D:
World coordinates are right-handed with y up (the com.codename1.gpu convention),
and a sprite’s size is world units rather than pixels — use Sprite#setSize(float,
float) or Sprite#setScale(float) to pick a world-space size. Move the camera each
frame in update(double) to follow the player.
37.8.2. 3D models
Model draws a
real 3D mesh — a com.codename1.gpu.Material plus a position, rotation, and scale.
Because GPU meshes need the com.codename1.gpu.GraphicsDevice, build them in
GameView#onSetup(com.codename1.gpu.GraphicsDevice), the render-thread hook that
runs once before the first frame:
onSetup is also where you load real assets with com.codename1.gpu.GltfLoader
(glTF .glb/.gltf models). Models are drawn opaque and depth-written before the
alpha-blended billboards, and the billboards depth-test against them, so closer
geometry correctly hides what’s behind it. GameView#getLight() controls the
directional light that shades lit material types.
37.8.3. Meshes and textures
The built-in meshes are com.codename1.gpu.Primitives#cube(GraphicsDevice, float)
and Primitives#quad(GraphicsDevice, float); a quad rotated flat makes a ground or
a wall. Model#setScale(float, float, float) reshapes one cube mesh into crates,
pillars or buildings of any proportion, so a whole skyline can share a single mesh.
Lit materials multiply their base color by a texture, so you can detail a surface — a grid on the ground for depth, say — by drawing an com.codename1.ui.Image and
uploading it with com.codename1.gpu.GraphicsDevice#createTexture(com.codename1.ui.Image):
For richer geometry, load glTF (.glb/.gltf) assets with
com.codename1.gpu.GltfLoader from onSetup.
37.9. Low latency audio: SoundPool
Music and video use the regular MediaManager, but rapid overlapping sound
effects — gunshots, coins, footsteps — need a different tool.
SoundPool
loads short clips once and triggers them with minimal latency, mixing several at
the same time.
play returns a voice id (or -1 if the pool is momentarily exhausted — it never
blocks on the hot path). The parameters are: volume 0 to 1, pan -1 (left) to 1
(right), rate playback speed/pitch (1.0 is normal), and loop (0 once, -1
forever, n extra repeats). stop, pause, resume, stopAll, autoPause and
autoResume manage playback; release() frees the pool.
On platforms with a purpose built low latency audio engine — Android’s SoundPool,
iOS AVAudioEngine, the desktop javax.sound.sampled mixer and WebAudio in the
browser — the pool uses it directly with full volume/pan/pitch support. Where none
exists it falls back to a MediaManager based pool that still works everywhere but
has higher latency and ignores pan and rate. isNativeAccelerated() tells you which
path is active.
To react as a sound finishes — chaining clips, recycling a game object when its
effect ends — register a
VoiceListener.
It’s called on the EDT with the voice id as each voice completes. Not every native
engine can report completion, so guard with isVoiceCompletionSupported():
Load your sounds once, up front — ideally on a background thread with
SoundPool.loadAsync(…) — and keep the SoundEffect references for the life of
the game. Decoding on the fly defeats the purpose. |
37.10. Physics
The com.codename1.gaming.physics
package adds 2D rigid body physics. It’s an idiomatic wrapper around a pure Java
port of the well known Box2D engine, so it runs on every platform — including
iOS, where it’s translated to C with no native code.
37.10.1. Units: Pixels, meters and the y-axis
Box2D is tuned for objects a few meters across, so the world works in meters
internally while exposing pixels to you. The conversion is governed by
setPixelsPerMeter(float) (default 30). The wrapper also flips the y-axis — Box2D
points y up, the screen points y down — so your code stays in screen coordinates.
The practical consequence: a positive gravity y pulls bodies down the screen.
37.10.2. Worlds and bodies
Create a PhysicsWorld,
populate it with PhysicsBody
objects, and step it once per frame from your update:
Bodies come in three kinds, the
BodyType
values: STATIC (immovable — ground, walls), KINEMATIC (moved by you via
velocity, unaffected by forces) and DYNAMIC (fully simulated). Bodies can be
boxes, circles or polygons (createBox, createCircle, createPolygon) and
respond to setLinearVelocity, applyForce, applyLinearImpulse, applyTorque,
setBullet (continuous collision for fast objects), setFixedRotation and more.
For an arbitrary outline, createShape(x, y, shape, type) takes a Codename One
com.codename1.ui.geom.Shape — typically the same com.codename1.ui.geom.GeneralPath
you would draw with — and builds the collision fixtures from it, flattening any
Bezier curves. Each subpath becomes a fixture (so a figure with several outlines is a
compound body); a closed convex subpath of up to eight points becomes a solid polygon
usable by any body type, while a concave, larger, or open subpath becomes a one-sided
edge chain (ideal for static terrain). This lets the hit-shape and the drawn shape
come from one piece of geometry:
37.10.3. Driving sprites from physics
A body can drive a sprite directly. Sprite implements
PhysicsLinkable,
so linking the two means world.step(…) updates the sprite’s position and
rotation automatically (in pixels, screen space) — and the scene draws it there:
37.10.4. Collisions
Register a ContactListener
to be told when bodies start and stop touching. Callbacks fire from inside
step(…) — on the game loop thread — so you can read and update game state
directly, but you must not create or destroy bodies during the callback; defer
that until after step returns.
If you need a feature the wrapper doesn’t expose, PhysicsWorld.getNativeWorld()
and PhysicsBody.getNativeBody() give you the underlying engine objects (which
work in meters, y up).
37.10.5. Joints
Joints constrain how two bodies move relative to each other — hinges, ropes, axles,
welds. PhysicsWorld creates them in pixel coordinates and returns a
PhysicsJoint
handle:
createWeldJoint and createPrismaticJoint (a sliding axis) round out the set.
37.10.6. Debugging physics
When sprites and bodies drift apart it helps to see the raw simulation. Call
world.debugDraw(Graphics) to overlay every fixture, joint and contact straight onto
a Codename One Graphics — shapes, centers of mass and bounding boxes — in pixel
space, with the y-axis flip already applied. Choose what to show with
setDebugDrawFlags(shapes, joints, boundingBoxes), and soften the translucent shape
fill with setDebugFillAlpha(alpha). Because it draws to an ordinary Graphics you
can render it over a regular Codename One component, not only a GameView.
37.11. Putting it together: Anatomy of a game
Every sample follows the same shape, which is the recipe for your own game:
Subclass
GameViewand, in its constructor, create yourSpriteandAnimatedSpriteobjects and add them togetScene().Allocate GPU resources in
onSetup(GraphicsDevice)— meshes, textures and 3DModelobjects — because those need the device.Add controls (a joystick and buttons) once the view has a size.
Advance the world in
update(double dt): readgetInput(), move sprites or step aPhysicsWorld, scale all movement bydt, and triggerSoundPooleffects.Show it: add the view to a
Formand callstart().
The samples project has several runnable examples to copy from:
CasualGameSample— sprites, per-sprite animation, collision and particle bursts in a top-down arena (see Section 37.1, “Sample games”).ScrollerGameSample— anAnimatedSpritewalk cycle, a parallax backdrop and a scrollingScenecamera.Gaming3DDemoSample— lit cubeModelobjects, a textured ground and billboarded sprites under a perspective camera.GamingDemoSample— the physics tour, built on aPhysicsWorldwith a floor and walls, tap-to-drop balls that bounce (eachSpritelinked to its body) and aSoundPoolblip whose pitch varies per drop.CardGameSample— a flat 2D Memory match: a grid of cardSpriteobjects with a flip animation and tap hit-testing.BoardGameSample— faux-3D checkers: flat sprites placed in an isometric projection, with screen-to-cell picking, full rules and a small AI.
Each is a single self-contained file that generates its art at runtime, so it needs no assets — a compact starting point you can copy and reshape.
37.12. Performance notes
Keep
updatenon-blocking — it runs on the render thread. Load assets off the render thread and hand them back withCN.callSerially.Reuse images: the renderer caches one GPU texture per
Image, so sharing an image across many sprites uploads it once. Cache cut sprite frames (useSpriteSheet, which does it for you) rather than re-slicing every frame.Load every
SoundEffectup front and reuse it.Tune
setPixelsPerMeterso your moving bodies are on the order of a meter (tens of pixels) in size; bodies far larger or smaller than that make the simulation unstable.
The physics engine in com.codename1.gaming.physics.box2d is a derived work of
JBox2D (a Java port of the Box2D engine), used under the BSD 2-Clause license;
see the project NOTICE file for attribution.
38. The Game Builder
The Game Builder is a visual level / map editor for the
com.codename1.gaming API. You lay out a game world — tiles,
characters, items, the camera — set per-object behavior values, preview it live, and
Build it into your project as a data file plus a small Java companion that the runtime
plays. It’s to games what the GUI builder is to forms.
This chapter covers the whole feature: the underlying model, the editor UI, building a level, defining game rules, the supported game types, and the Maven workflow.
38.1. How it fits together
A game built with this tool has three layers:
| Layer | Role | Who authors it |
|---|---|---|
Level data ( | A JSON description of the scene: grid, layers, placed elements + their properties, camera, lights. | The Game Builder (visual) |
Companion class ( | A thin | Generated once, then you edit the |
Gaming engine ( | Renders and runs the scene on the GPU, with pollable input, sound and optional Box2D physics. | The framework |
The key idea: the editor produces data, your companion adds rules, the engine runs
it. Because the level is data you can re-edit it any time without touching your code,
and your onUpdate logic is preserved across regeneration.
38.1.1. The level model — com.codename1.gaming.level
| Class | Purpose |
|---|---|
| The saveable level: |
| A placed thing: |
| A named band: |
| Resolve an |
| A turnkey |
| Board isometric math, fast single-tileset grids, and 3D lighting / terrain data. |
Loading and playing a level at runtime is three lines:
38.2. Getting started
Create a scene from a Java 17 Codename One project:
mvn cn1:create-game-scene -DclassName=com.example.game.Level1 -Dmode=2d-Dmode is 2d (default), 3d or board. This writes
common/src/main/resources/games/Level1.game (an empty level of that type) and
common/src/main/java/com/example/game/Level1.java (the GameSceneView companion).
Open the editor bound to the project — the same way cn1:guibuilder launches the GUI
builder:
mvn cn1:gamebuilderThe editor itself is delivered through Maven: the goal resolves the
com.codenameone:codenameone-gamebuilder artifact from Maven Central (the same mechanism
that ships the Designer / CSS-compiler jar with the plugin), so there is no separate
install step. The cn1:gamebuilder goal only applies to Java 17 Codename One projects.
38.3. The editor at a glance

Top bar — the project / scene dropdown (switch scenes, rename, or start a new scene of any game type), undo / redo, the grid and snap toggles, zoom, a text-size toggle (Small / Medium / Large), the
</>button (opens the scene’s Java in your IDE), Live (play in place) and Build (save into the project).Tool rail (left) — Select, Move, Brush, Fill, Erase, Pan.
Resizable panels — drag the thin divider on the inner edge of the left panel or the inspector to resize it.
Hierarchy — the scene card plus the layers. Each layer shows its item count, a visibility eye (hides the layer), a lock (prevents edits) and a ⋮ menu to rename or delete it; drag a placed object onto another layer (or above/below a sibling) to move or reorder it. Placed objects nest under their layer, and unique objects (the player) carry a UNIQUE badge.
Canvas — the editable stage is the bright-bordered rectangle with the grid; painting only happens inside it.
Asset Library (center-bottom) — pick a pack tab, then click a thumbnail to select an asset. Selecting a tile asset switches to a tile layer; selecting an actor switches to an entity layer, so the brush always works on the next click. Import (top-right) brings in your own artwork as a new asset.
Inspector (right) — scene settings when nothing is selected, or the selected object’s properties.
Because it’s a desktop application, every command is also available from the native
menu bar (drawn by the OS), grouped by convention: File (New 2D / 3D / Board, Open
Scene, Save), Edit (Undo, Redo, Delete Selection), View (Toggle Grid / Snap, Zoom
In / Out, Show Generated Code), Tools (Select / Move / Brush / Fill / Erase / Pan),
Layer (Add Layer) and Game (Play / Stop). The standard accelerators work too — Cmd/Ctrl+Z undo, Cmd/Ctrl+S save, Cmd/Ctrl+R play, Cmd/Ctrl+= / Cmd/Ctrl+-
zoom. Every on-screen control also has a tooltip.
38.4. Building a level
Choose a game type — scene dropdown → New scene → 2D Platformer, 3D Map or Board (or scaffold with
-Dmode).Paint terrain — pick the Brush, click a tile in the Asset Library, then click/drag inside the stage. Fill flood-fills a region; Erase clears cells.
Place characters and items — click an actor asset and click on the stage to stamp it. With Snap on, actors land on grid cells. The Player is unique — stamping it again moves it.
Organize with layers — placed objects nest under their layer in the hierarchy, so you can always see which band each one is on. The eye hides a layer while you work (its name dims), the lock prevents edits to it, the chevron collapses its children, and + adds a layer. To move a selected object to a different layer (changing its draw order), use the Layer picker in the Inspector’s Transform section.
Undo / redo every change with the toolbar arrows.
Save with Build — it writes
Level1.gameand, the first time, the companionLevel1.java.
38.5. Defining game rules
Game rules live in two complementary places.
38.5.1. Data — set in the Inspector

Select an object to edit its Transform (name, position, Layer dropdown) and its Behavior properties — the typed values that parameterize how it acts:
| Object | Behavior properties |
|---|---|
Player / Hero |
|
Coin / Gem |
|
Enemy (slime) |
|
Door / Goal |
|
Torch |
|
Card / Token / Dice |
|
These defaults come from the asset — the Inspector’s read-only Asset section shows
the id, kind, size and unique flag, and Edit asset defaults… lets you change an
asset’s default size and properties (for example, tune ground/coin). Use Add property… to
attach your own game metadata (hitPoints, value, …) to a single object, readable at
runtime via el.getInt(…) / el.getDouble(…). This is the player marks
which element the preview and arrow keys drive (otherwise a player/hero/spawn asset
is used).
Scene-wide rules are set in the Inspector when nothing is selected: gravity,
background theme, grid Cols / Rows / Tile size and the Mode. These are saved
into the .game file and are available at runtime on each GameElement.
38.5.2. Logic — written in the companion
The behavior values are data; the behavior itself is code you write in the generated
companion’s onUpdate(double dt). GameSceneView realizes every element into a sprite
whose getUserData() is the source GameElement, so you read the properties you set in
the editor:
Win/lose conditions, scoring, enemy AI and level transitions (using a door’s target)
are all decided here. For rigid-body games use
com.codename1.gaming.physics inside onUpdate. In short: the editor decides the layout and the numbers; your companion
decides the behavior; the engine runs it.
38.6. Game types
The mode (chosen per scene) plus the asset pack determine how the same level model is realized:
| Mode | Realized as | Packs | Use for |
|---|---|---|---|
| `Sprite`s in pixel space, tile grids | Platformer, Top-Down RPG | platformers, shooters, top-down adventures |
|
| Board & Card | board games, strategy, card games |
|
| 3D Kit | 3D maps, arena / tycoon layouts |
Switch type from the scene dropdown’s New scene buttons or scaffold with
-Dmode=2d|3d|board. In 3D mode the Inspector also exposes the camera rig, lighting and
terrain; placed elements become meshes (import your own glTF via GltfLoader from the
companion’s buildModels hook).

In 3D mode the board is edited top-down (placement, terrain and lighting), and the grid autofits the canvas so it stays usable at any size and zoom. Each placed element reads as a single object on the grid rather than a flat sprite filling the board.
38.7. Live preview

Press Live to play the level in place inside a device frame with a HUD. The preview ships default behaviors so common cases work without any code: in a 2D platformer the arrow keys move the player and Up / Space jumps (gravity and tile collision are simulated), coins/gems are collected for score, and enemies patrol and cost a life on contact. The on-screen hint shows the controls, and the SCORE / LIVES HUD is live. Press Stop to return to editing — playing never mutates the level.
For a 3D map the preview switches to a true perspective view — a receding ground grid with the placed meshes rendered as depth-sorted objects under an orbiting camera — so you see 3D gameplay rather than a flat top-down board:

The in-editor preview is for quick iteration; for full-fidelity play on device, run the
companion in your app, where the scene is rendered by the GPU-accelerated
GameSceneView.
38.8. Build, save and run
Build writes the level to src/main/resources/games/<Scene>.game and (once) the
companion <Scene>.java. To show the scene in your app, instantiate the companion and
start() it:
The level is plain data, so you can ship many .game files and load whichever level the
player selects.
38.9. Maven goals
| Goal | Purpose |
|---|---|
| Scaffold a |
| Launch the editor bound to the current project. |
38.10. Extending
Asset packs are JSON (
{"packs":[{"id","name","assets":[{"id","kind","w","h","color","unique","source","defaults"}]}]}) loaded byAssetCatalog.load. Add your own pack with real art.Asset art follows the SVG/Lottie approach: reference source art per asset and let the build translate it to code/raster; where no art is supplied the catalog draws a recognizable placeholder so a level always renders.
Behaviors can be factored into reusable helpers driven entirely from the property bag, keeping levels data-only.
38.10.1. Importing your own art
To bring in custom artwork, click Import in the Asset Library header and pick an image.

The image is added to a Custom pack as a new asset (a tile when a tile layer is
active, otherwise an actor), selected and ready to paint or stamp immediately. When the
editor is bound to a project, the picture is copied into
src/main/resources/games/assets/ and recorded in games/custompack.json, so it
survives reloading and ships with the project — the generated game resolves it through
the same AssetCatalog.
39. Game Assets
Every visible thing in a Game Builder level — the ground a player walks on, a coin to collect, an enemy, a 3D crate — is drawn from an asset. This chapter explains what an asset is, how assets are organized into packs and resolved by the catalog, where their artwork comes from, and how to create your own (either by authoring a pack JSON entry or by importing an image inside the editor). It closes with a note on terrain materials, a related-but-separate concept, and pointers for finding more art.
The classes live in com.codename1.gaming.level: AssetDef, AssetPack and
AssetCatalog.
39.1. What an asset is
An asset is a reusable template — an AssetDef — not a thing in your level. It says
"this is what a coin looks like and what default values a coin has," and any number of
coins in any number of levels reference that one definition by id.
An AssetDef carries:
| Field | Meaning |
|---|---|
| The stable string key (for example, |
| The human-readable display name shown in the editor palette (for example, |
|
|
| The natural pixel size of the art (default 32×32). |
| A base ARGB colour used to render a flat placeholder until real artwork is available
(default |
| Whether a level should hold at most one of these (for example, the player / spawn point). |
| An optional reference to the source art (a resource path, an SVG/Lottie key, or the
|
| The default authoring property values copied onto a freshly placed element — a coin’s
|
39.1.1. Asset (template) versus placed element (instance)
Keep this distinction clear:
An asset (
AssetDef) is the shared template. There is exactly onecoindefinition.A placed element (
GameElement) is one instance in a level. It stores its own position, size and property values, and references the template throughGameElement#getAssetId().
When you drop a coin into a level, the editor creates a GameElement whose assetId is
coin and copies the asset’s defaultProperties() into the element’s own property bag
(see StarterPacks.addActor, which does exactly this with el.properties().putAll(def.defaultProperties())).
You can then tweak that one coin’s value without affecting the template or any other
coin. Changing the asset’s size or art, conversely, affects how every instance that
references it’s drawn.
39.2. How assets are structured
Assets are grouped into packs, and packs are indexed by a catalog:
AssetPack— a named, ordered group ofAssetDef`s (`add(def),get(id),assets()). The order is the order they appear in the palette. AGameLevelnames the pack it draws from viaGameLevel#getAssetPack().AssetCatalog— holds one or more packs and answers two questions for any asset id:def(id)returns theAssetDef(used for kind, size and default props), andimage(id)returns the artwork. Real art is supplied viasetImage(id, image); until thenimage(id)returns a cached solid-colour placeholder sized from the def and tinted with itsgetColor(), so a level always realizes to something visible.
39.2.1. The built-in packs
The editor ships four starter packs in the classpath resource /gamebuilder-packs.json,
loaded by StarterPacks.loadCatalog() (which calls AssetCatalog.load(InputStream)).
The same catalog drives both the editor palette and a generated game’s runtime loader.
| Pack id | Name | Asset ids |
|---|---|---|
| Platformer |
|
| Top-Down RPG |
|
| Board & Card |
|
| 3D Kit |
|
StarterPacks.defaultPackFor(mode) picks kit3d for MODE_3D, board for MODE_BOARD
and platformer otherwise.
The JSON format is {"packs":[{"id":..,"name":..,"assets":[ … ]}]}. Here is one real
asset entry from the platformer pack — the player:
{ "id": "player", "name": "Player", "kind": "actor",
"w": 28, "h": 32, "color": "#4D86FF", "unique": true,
"defaults": { "lives": 3, "jumpHeight": 96 } }Each JSON key maps onto an AssetDef field (see AssetDef.fromMap): kind is
"tile" or "actor", w/h are the pixel size, color is #rrggbb, unique is a
boolean, source is the optional art reference, and defaults becomes
defaultProperties().
39.3. Where the art comes from
An AssetDef names an art format — TYPE_IMAGE, TYPE_SHEET or TYPE_MESH — and a
getSource() art file. AssetCatalog.resolveArt() loads each asset’s art from that file
into the catalog, so the same definition drives the editor palette and a shipped game.
39.3.1. Static images (TYPE_IMAGE)
A single .png/.jpg. resolveArt() decodes it; image(id) returns it and the level
realizer wraps it in a com.codename1.gaming.Sprite. The starter packs ship one image file
per asset (at the flat resource root, loaded as /<id>.png), so every starter sprite — ground, the player, the mountains — is a real file you can open in any editor and replace.
39.3.2. Sprite sheets (TYPE_SHEET)
One image laid out as a grid of equal frames, plus a frame size and rate (frameW,
frameH, fps). resolveArt() builds a com.codename1.gaming.SpriteSheet; the realizer
creates an animated com.codename1.gaming.AnimatedSprite that the scene advances each
frame. The starter coin is a six-frame sheet, so it spins at runtime with no code;
image(id) returns its first frame for the editor palette.
39.3.3. Meshes (TYPE_MESH)
A glTF/.glb model for a 3D level. resolveArt() keeps the file’s bytes and
GameSceneView.buildModels loads them with com.codename1.gpu.GltfLoader, realizing a
com.codename1.gaming.Model (and falling back to a primitive cube for an asset that has no
mesh). Sprite sheets and glTF loading are existing Codename One features; the asset model
just makes them first-class so the editor and runtime treat them as assets.
39.3.4. Imported art (the editor’s Import button)
The Import action opens the gallery (Display#openGallery) and hands the chosen image’s
bytes to GameBuilder.registerImportedAsset(…), which builds an image AssetDef (kind
from the active layer), adds it to a Custom pack and persists the PNG to
<gamesDir>/assets/ plus the pack definition to <gamesDir>/custompack.json. On the next
launch ProjectIO.loadCustomPack reads them back, so an imported image survives a reload.
Sprite sheets and glTF meshes are added the same way at the file level — drop the file into
<gamesDir>/assets/ and add a pack entry with the matching type (and frame size for a
sheet); resolveArt then loads it like any other asset. (A dedicated sheet/mesh import UI is
a natural follow-up.)
39.3.5. Generating the starter images
The bundled starter PNGs are produced once by a build-time generator
(StarterArtGenerator, which draws each sprite with Graphics through AssetArt) and
committed as resources — there’s no art-drawing code in the shipped runtime. Re-run the
generator after changing a starter sprite or pack.
In every case the catalog falls back to the flat-colour placeholder when an asset’s art is missing, so a level is never un-renderable.
39.4. Creating your own asset
There are two practical paths.
39.4.1. Path 1: Author a pack JSON entry
Add an entry to a pack’s assets array using the same format as the built-ins. For
example, a collectible key:
{
"id": "key",
"name": "Key",
"kind": "actor",
"w": 24,
"h": 24,
"color": "#E0C040",
"unique": false,
"defaults": { "opens": "door", "value": 1 }
}Field by field:
id— unique string key your placed elements and any art will reference. Required.name— display name in the palette. Optional; defaults to the id.kind—"tile"to paint into grid cells,"actor"for a free-form entity. Anything other than"tile"is treated as an actor.w/h— natural pixel size. Optional; default 32.color—#rrggbbplaceholder colour used until real art is supplied. Optional.unique—trueto limit the level to one instance. Optional; defaultfalse.defaults— a map of default property values copied onto each placed element.source— the art file the runtime loads: a.png/.jpg(image, sheet) or a.glb/.gltf(mesh). Optional; the starter packs default it to<id>.png.type—"image","sheet"or"mesh". Optional; inferred fromsource(a.glbis a mesh) orframeW(a sheet) when omitted.frameW/frameH/frames/fps— sprite-sheet frame size, frame count (0 = all) and playback rate, for a"sheet"asset.
You can add this to a copy of gamebuilder-packs.json, or build a pack in code with
new AssetPack(id, name).add(new AssetDef(…)) and register it with
catalog.addPack(pack). To give it real art, point source at a bundled art file and
call catalog.resolveArt(), or supply an image directly with
catalog.setImage("key", image).
39.4.2. Path 2: Import an image in the editor
The no-code path: open your level in the Game Builder, select the layer you want the
asset to belong to (a tile layer for tiles, an entity/actor layer otherwise), and use the
Import action ("Import your own image as a new asset"). Pick a PNG (or other supported
image), and the editor creates the AssetDef and files it under the Custom pack. Once bound to a project, the editor also saves the PNG and a pack-JSON entry
under the project’s games/assets/ directory as described above. The new asset appears in the palette and is immediately
placeable.
39.5. Terrain materials
3D terrain surfaces use a different, pluggable concept: materials, not sprite assets. A
Material (com.codename1.gaming.level.Material) describes a surface — a base colour,
whether it’s solid (blocks movement), a friction multiplier, and an optional
artId for textured rendering — and is referenced everywhere by its string id.
Materials are resolved through MaterialRegistry, a process-wide registry that ships six
built-ins (MaterialRegistry.GRASS, ROAD, STONE, SAND, WATER, DIRT). WATER
is registered as solid. Applications add their own without changing the level format:
Unknown ids resolve to a neutral gray placeholder, so a level that references a not-yet-registered material still loads. Materials cover terrain cells and `TerrainFeature`s; the sprite/model assets covered above are a separate system.
39.6. Where to get more
Reuse the built-in packs. The four starter packs cover platformer, top-down RPG, board/card and a small 3D kit out of the box — start there and only add what you need.
Import your own art. Any PNG (or supported sprite image) can be imported through the editor’s Import action and becomes a first-class asset in your project’s Custom pack. Authoring at the asset’s natural pixel size keeps it crisp.
Author packs as JSON. For larger sets, hand-author or generate
AssetPackJSON entries alongside the built-ins so the whole pack loads throughAssetCatalog.load.Use external game-art sources. Plenty of open game-art libraries and your own design tools (vector editors, pixel-art tools) can produce sprite sheets and tiles. Whichever source you use, you are responsible for honoring its license — check the terms for attribution and commercial-use requirements before shipping art you didn’t create.
40. Events
Most events in Codename One are routed via the high-level events (for example, action listener) but sometimes you need access to low-level events (for example, when drawing via Graphics) that provide more fine grained access. Typically working with the higher level events is far more potable since it might map to different functionality on different devices.
40.1. High-level events
High-level events are broadcast using an addListener/setListener - publish/subscribe system. Most of them are channeled via the EventDispatcher class which further simplifies that and makes sending events far easier.
All events are fired on the Event Dispatch Thread, the EventDispatcher makes sure of that. |
40.1.1. Chain of events
Since all events fire on the EDT some complexities occur. E.g.:
You have two listeners monitoring the same event (or related events for example, pointer event and button click event both of which will fire when the button is touched).
When the event occurs you can run into a scenario like this:
First event fires
It shows a blocking dialog or invokes an "AndWait" API
Second event fires after the dialog was dismissed!
This happens because events are processed in-order per cycle. Since the old EDT cycle is stuck (because of the Dialog) the rest of the events within the cycle can’t complete. New events are in a new EDT cycle so they can finish fine!
A workaround to this issue is to wrap the code in a callSerially, you shouldn’t do this universally as this can create a case of shifting the problem to the next EDT cycle. But, using callSerially will allow the current cycle to flush which should help.
Another workaround for the issue is avoiding blocking calls within an event chain.
40.1.2. Action events
The most common high-level event is the ActionListener which allows binding a generic action event to pretty much anything. This is so ubiquitous in Codename One that it’s even used for networking (as a base class) and for some low-level event options.
For example, you can bind an event callback for a Button by using:
Button b = new Button("Click Me");
b.addActionListener(new ActionListener() {
public void actionPerformed(ActionEvent ev) {
// button was clicked, you can do anything you want herenull
}
});Or thanks to the Java 8 lambdas you can write it as:
Button b = new Button("Click Me");
b.addActionListener((ev) -> {
// button was clicked, you can do anything you want here.
});Notice that the click will work whether the button was touched using a mouse, finger or keypad shortcut seamlessly with an action listener. Many components work with action events for example, buttons, text components, slider etc.
Quite a few high-level event types exist that are more specific to requirements.
Types of action events
When an action event is fired it’s given a type, but this type might change as the event evolves for example, a command triggered by a pointer event won’t include details of the original pointer event.
You can get the event type from getEventType(), this also gives you a rather exhaustive list of the possible event types for the action event.
Modern gesture components also publish custom action types. For example, SwipeableContainer dispatches ActionEvent.Type.Swipe when the top component is fully opened, allowing code to react to swipe gestures without monitoring low-level drags. Listening for these higher level events keeps gesture handling portable across touch and desktop targets.
Source of event
ActionEvent has a source object, what that source is depends on the event type. For most component based events this is the component but there are some nuances.
The getComponent() method might not get the actual component.
In case of a lead component such as MultiButton the underlying Button will be returned and not the MultiButton itself.
To get the component that you would logically think of as the source component use the getActualComponent() method.
Event consumption
An ActionEvent can be consumed, once consumed it will no longer proceed down the chain of event processing. This is useful for some cases where you would like to block behavior from proceeding down the path.
For example, the event dispatch thread allows you to listen to errors on the EDT using:
Display.getInstance().addEdtErrorHandler((e) -> {
Exception err = (Exception)e.getSource();
// null
});This will work great but you will still get the default error message from the EDT over that exception. To prevent the event from proceeding to the default error handling you can do this:
Display.getInstance().addEdtErrorHandler((e) -> {
e.consume();
Exception err = (Exception)e.getSource();
// null
});Notice that you can check if an event was already consumed using the isConsumed() method but it’s pretty unlikely that you will receive a consumed event as the system will stop sending it.
NetworkEvent
NetworkEvent is a subclass of ActionEvent that’s passed to actionPerformed callbacks made in relation to generic network code. For example:
NetworkManager.getInstance().addErrorListener(new ActionListener<NetworkEvent>() {
public void actionPerformed(NetworkEvent ev) {
// now we have access to the methods on NetworkEvent that provide more information about the network specific flags
}
});Or with Java 8 lambdas:
NetworkManager.getInstance().addErrorListener((ev) -> {
// now we have access to the methods on NetworkEvent that provide more information about the network specific flags
});The NetworkEvent allows the networking code to reuse the EventDispatcher infrastructure and to simplify event firing through the EDT. But you should notice that some code might not be equivalent for example, you could do this to read the input stream:
ConnectionRequest r = new ConnectionRequest() {
@Override
protected void readResponse(InputStream input) throws IOException {
// read the input stream
}
};Or you can do something similar using this code:
ConnectionRequest r = new ConnectionRequest();
r.addResponseListener((e) -> {
byte[] data = (byte[])e.getMetaData();
// work with the byte data
});These seem similar but they have one important distinction. The latter code is invoked on the EDT, so if data is big it might slow down processing. The ConnectionRequest is invoked on the network thread and so can process any amount of data without slowing down the UI.
MessageEvent and the Cross-Platform message bus
Bridging to native code often means passing messages between Codename One Java and platform specific code. The cross-platform message bus provides a high-level abstraction for that by letting you post messages to the native layer and subscribe for messages that originate there. Use Display.postMessage() to send an MessageEvent to the platform, and Display.addMessageListener() to receive events that arrive from native code, JavaScript bridges, or background services. Message events include helpers like isPromptForAudioRecorder(), isPromptForAudioPlayer(), and getPromptPromise() that allow you to hook into permission prompts emitted by the JavaScript port so custom UI can respond to platform requests while keeping the event dispatch on the EDT. This API complements NetworkEvent by covering native-to-Java messaging without requiring direct low-level callbacks.
40.1.3. DataChangeListener
The DataChangedListener is used in several places to show that the underlying model data has changed:
TextField - the text field provides an action listener but that "fires" when the data input is complete.
DataChangeListenerfires with every key entered and thus allows functionality such as "auto complete" and is indeed used internally in the Codename One AutoCompleteTextField.TableModel & ListModel - the model for the Table class notifies the view that its content has changed via this event, thus allowing the UI to refresh.
An exhaustive example of search implemented using the DataChangedListener appears in the Toolbar section.
40.1.4. FocusListener
The focus listener allows you to track the "selected" or focused component. It isn’t as useful as it used to be in feature phones.
You can bind a focus listener to the Component itself and receive an event when it gained focus, or you can bind the listener to the Form and receive events for every focus change event within the hierarchy.
40.1.5. ScrollListener
ScrollListener allows tracking scroll events so UI elements can be adapted if necessary.
Scrolling is seamless and this event isn’t necessary, but if developers wish to "shrink" or "fade" an element on scrolling this interface can be used to achieve that. Notice that you should bind the scroll listener to the actual scrollable component and not to an arbitrary component.
For example, in this code from the Flickr demo the Toolbar is faded based on scroll position:
public class CustomToolbar extends Toolbar implements ScrollListener {
private int alpha;
public CustomToolbar() {
}
public void paintComponentBackground(Graphics g) {
int a = g.getAlpha();
g.setAlpha(alpha);
super.paintComponentBackground(g);
g.setAlpha(a);
}
public void scrollChanged(int scrollX, int scrollY, int oldscrollX, int oldscrollY) {
alpha = scrollY;
alpha = Math.max(alpha, 0);
alpha = Math.min(alpha, 255);
}
}| A better way of implementing this exact effect uses title animations illustrated here. |
40.1.6. SelectionListener
The SelectionListener event is used to broadcast list model selection changes to the list view. Since list supports the ActionListener event callback its the better option since it’s more coarse grained.
SelectionListener gets fired too often for events and that might result in a performance penalty. When running on non-touch devices list selection could be changed with the keypad and a specific fire button click would fire the action event, for those cases SelectionListener made a lot of sense. But, in touch devices this API isn’t as useful.
40.1.7. StyleListener
StyleListener allows components to track changes to the style objects. For example, if the developer does something like:
This will trigger a style event that will eventually lead to the component being repainted. This is quite important for the component class but not an important event for general user code. It’s recommended that developers don’t bind a style listener.
40.1.8. Component state change events
Component instances now publish lifecycle hooks that fire when they become initialized on a form and when they’re removed. You can subscribe with Component.addStateChangeListener() to receive ComponentStateChangeEvent instances that show whether the component is transitioning to the initialized state. This is useful for running setup or teardown logic alongside focus, scroll, and selection listeners.
40.1.9. Event dispatcher
When creating your own components and objects you sometimes want to broadcast your own events, for that purpose Codename One has the EventDispatcher class which saves a lot of coding effort in this regard. For example, if you wish to provide an ActionListener event for components you can add this to your class:
private final EventDispatcher listeners = new EventDispatcher();
public void addActionListener(ActionListener a) {
listeners.addListener(a);
}
public void removeActionListener(ActionListener a) {
listeners.removeListener(a);
}Then when you need to broadcast the event use:
40.2. Low-level events
Low-level events map to "system" events directly. Touch events are considered low-level since they might expose platform specific nuances to your code.
For example, one platform might send many events during drag while another might send a few. The high-level event handling hides those complexities but some of them trickle down into the low-level event handling.
| Codename One tries to hide some complexities from the low-level events as well. But, due to the nature of the event types it’s a more challenging task. |
Low-level events can be bound in one of 3 ways:
When you override event callbacks on a Component the Component in question must be focusable and have focus at that point. This can be an advantage for some use cases as it will save you the need of handling unrelated events. |
Each of those has advantages and disadvantages, specifically:
'Form' based events and callbacks deliver pointer events in the 'Form' coordinate space.
'Component' based events require focus
'Form' based events can block existing functionality from proceeding through the event chain for example, you can avoid calling super in a form event and thus block other events from happening (for example, block a listener or component event from triggering).
Listener | Override Form | Override Component | |
Coordinate System | Form | Form | Component |
Block current functionality | Yes, just avoid super | Partially (event consume) | No |
40.2.1. Low-level event types
There are two basic types of low-level events: Key and Pointer.
Key events are relevant to physical keys and won’t trigger on virtual keyboard keys, to track those use a TextField with a DataChangeListener as mentioned above. |
The pointer events (touch events) can be intercepted by overriding one or more of these methods in Component or Form. Notice that unless you want to block functionality you should probably invoke super when overriding:
Notice that most pointer events have a version that accepts an array as an argument, this allows for multi-touch event handling by sending all the touched coordinates. Desktop and pen-enabled devices can also trigger hover events without a press. To respond to those you can override the pointerHover* callbacks on Form or Component, which are invoked before a button receives focus or a drag begins on those platforms.
While you can override longPointerPress, there is no need. The dedicated Component.addLongPressListener() helper wires long press detection into an action listener so you can keep gesture logic in the high-level API.
Drag lifecycles also expose a completion hook. When Component.addDragFinishedListener() is registered it receives ActionEvent.Type.DragFinished once the framework has completed its cleanup, allowing you to reset state or trigger follow-up actions that should occur after the drag image is hidden.
40.2.2. Drag event sanitation
Drag events are quite difficult to handle across devices. Some devices send a ridiculous number of events for even the lightest touch while others send too little. It seems like too many drag events wouldn’t be a problem, but if you drag over a button then it might disable the buttons action event (since this might be the user trying to scroll).
Drag sensitivity is about the component being dragged which is why you have the method getDragRegionStatus that allows you to "hint" to the drag API whether you’re interested in drag events or not and if so in which directional bias.
For example, if your component is a painting app where you’re trying to draw using drag gestures you would use code such as:
public class MyComponent extends Component {
protected int getDragRegionStatus(int x, int y) {
return DRAG_REGION_LIKELY_DRAG_XY;
}
}This indicates that you want all drag events on both AXIS to be sent as soon as possible. Notice that this doesn’t disable event sanitation.
40.3. BrowserNavigationCallback
The BrowserNavigationCallback isn’t quite an "event" but there is no real "proper" classification for it.
| The callback method of this interface is invoked off the EDT! You must NEVER block this method and must not access UI or Codename One sensitive elements in this method! |
The browser navigation callback is invoked directly from the native web component as it navigates to a new page. Because of that it’s invoked on the native OS thread and gives you a unique opportunity to handle the navigation ourselves as you see fit. That’s why it MUST be invoked on the native thread, since the native browser is pending on your response to that method, spanning an invokeAndBlock/callSerially would be to slow and would bog down the browser.
41. Device Input and Form Factors
Codename One runs on a wide range of hardware, from phones and tablets to desktops, foldables, and devices driven by a mouse or a stylus. This chapter covers the cross-platform APIs that expose that hardware: rich pointer detail (mouse buttons, pen pressure and tilt, the pointing device type), the mouse wheel, foldable device posture, and multi-display / desktop-window awareness.
These APIs are additive: on a device or platform that doesn’t report a given capability the value falls back to a sensible default, so a single code base keeps working everywhere.
41.1. Rich pointer events
The classic pointerPressed, pointerReleased and pointerDragged callbacks carry only the x/y
coordinates of the touch. Modern devices provide far more detail: which mouse button was used, the
kind of pointing device (finger, mouse, stylus or eraser), the pressure applied, the stylus tilt,
the contact area and the keyboard modifiers held at the time.
That detail is exposed through the immutable
PointerEvent
snapshot. There are two ways to read it.
41.1.1. From an ActionEvent
Any pointer listener receives an ActionEvent; call getPointerEvent() on it:
41.1.2. By polling
When you’re inside a pointer callback you can also poll the current values directly from CN
(or Display), mirroring the existing CN.isShiftKeyDown() family:
Values have safe defaults. On a plain touch screen the button is BUTTON_PRIMARY, the pressure
is 1.0 and the type is TYPE_TOUCH (or TYPE_UNKNOWN on ports that don’t classify the device). |
41.2. Two and three button mice
PointerEvent.getButton() returns one of BUTTON_PRIMARY, BUTTON_SECONDARY, BUTTON_MIDDLE,
BUTTON_BACK or BUTTON_FORWARD. CN.getPressedButtonMask() returns a bitmask of every button
currently held (MASK_PRIMARY, MASK_SECONDARY, …), which is useful during a drag.
The real button is reported on every desktop port - macOS, Windows and Linux - and in the browser, so the right, middle and (where the mouse has them) back and forward buttons are all distinguished. On a plain touch screen there is only the primary button.
For the common case of a context menu, use the unified addContextMenuListener. It fires for a
secondary (right) mouse click, a stylus barrel button click and a long press, so the same code
handles desktop and touch:
41.3. Mouse wheel and trackpad scrolling
By default the mouse wheel and trackpad scroll a scrollable container automatically. To react to
the wheel yourself - for example control plus wheel to zoom, or horizontal scrolling - add a
addMouseWheelListener. The listener receives a
WheelEvent;
consuming it prevents the default scroll.
A positive getDeltaY() reveals content above (the user scrolled down); a positive getDeltaX()
reveals content to the left. isPrecise() is true for high resolution devices such as trackpads.
On the desktop simulator, hold shift while turning the wheel to produce horizontal scrolling.
WheelEvent is a single universal scroll-gesture API: it’s fed by the mouse wheel and trackpad on
the desktop, by the wheel / external trackpad on Android, and by the trackpad, Magic Mouse and
mouse wheel on iOS and iPadOS (captured natively and routed through the same pipeline). Continuous
trackpad scrolling reports isPrecise() == true, while a notched wheel reports false. On the
Apple Watch the Digital Crown also feeds this same pipeline, so a list scrolls under the crown and a
mouse wheel listener receives the crown as a WheelEvent.
41.4. Trackpad gestures (magnify and rotate)
Beyond scrolling, the trackpad reports magnify (pinch) and rotate gestures. Override
pinch(float scale) to zoom and rotation(float radians) to rotate; both return true to mark the
gesture as handled. pinch is also driven by a two finger pinch on touch screens, so the same code
works on mobile and the desktop.
The trackpad gestures are wired on every desktop port: the macOS trackpad, the Windows touch screen
and gesture-capable touchpads (through the system WM_GESTURE messages), and the Linux touchpad
(through the GTK touchpad gesture events). scale is an incremental zoom factor (just above or below
1.0) and radians is the incremental rotation since the previous callback, so accumulate them to
track the total.
A Windows precision touchpad usually reports a pinch as control plus wheel rather than a system
gesture, so it also arrives through the universal wheel API. Handle that case with a
addMouseWheelListener that checks isControlDown() (shown above) if you target those devices. |
41.5. Stylus and pen support
When a stylus is used (Apple Pencil, S-Pen, Surface Pen) the pointer type is TYPE_STYLUS, or
TYPE_ERASER for the eraser end. The PointerEvent then also carries:
getPressure()- normalized pressure between0.0and1.0.getTiltX()/getTiltY()- tilt in degrees (altitude and azimuth on iOS).getContactSize()- normalized size of the contact area.
For drawing surfaces a dedicated addStylusListener fires on press, drag and release only when the
pointer is a stylus or eraser:
Pen hover (the pen moving above the screen without touching, available on devices such as the S-Pen
and the M2 iPad with Apple Pencil) flows through the existing pointerHover callbacks; the snapshot
reports isHovering() as true.
Touch-enabled desktops are handled too: on a Windows or Linux PC with a touch screen the finger
reports TYPE_TOUCH, and a Windows pen reports TYPE_STYLUS, so the same drawing and gesture code
runs on a touch laptop as on a phone. Display.getInstance().isTouchScreenDevice() is true on those
machines.
41.6. Foldable devices and posture
Foldable and dual screen devices (Galaxy Fold, Galaxy Flip, Pixel Fold, Surface Duo) change shape
at runtime. Query the live posture through
DevicePosture:
getPosture()-POSTURE_FLAT,POSTURE_HALF_OPENED,POSTURE_CLOSEDorPOSTURE_UNKNOWN.getHingeAngle()- hinge angle in degrees (-1when unknown).getFoldOrientation()-FOLD_ORIENTATION_VERTICAL,FOLD_ORIENTATION_HORIZONTALorFOLD_ORIENTATION_NONE.getFoldBounds(Rectangle)- the region the hinge occludes, in display coordinates, or null when there is no separating fold. Treat it likeForm.getSafeArea(): keep interactive content out of it, or split a master and detail layout across the two halves.
React to fold changes with a posture listener:
To exercise this in the desktop simulator, use the Simulate → Foldable menu: enable foldable mode, then pick a posture (flat, half-opened or closed), the fold orientation (vertical or horizontal) and the hinge angle. The running app receives the same posture changes and listener callbacks it would on a real foldable device.
Foldable support on Android is opt-in so it never adds weight to apps that don’t use it. Enable it
with the android.foldableSupport=true build hint (the version can be overridden with
android.windowVersion). Note that the hinge angle isn’t available on Android, so
getHingeAngle() returns -1 there.
41.7. Desktop windowing and external displays
Some mobile devices run in a desktop windowing mode where the app shares the screen with other
windows: Samsung DeX, Android desktop windowing and iPad Stage Manager. CN.isDesktopMode()
reports this. It’s distinct from CN.isDesktop(), which reports a genuine desktop platform
(Windows, macOS or Linux).
CN.getDisplayCount() returns the number of attached displays and CN.isExternalDisplayConnected()
is a convenience for getDisplayCount() > 1. On the desktop port these reflect the real monitors
attached to the machine.
41.8. Apple TV remote
On Apple TV the Siri Remote is delivered through the standard key handling, so the same
keyPressed/keyReleased and game-key code you write for other platforms works on the TV. The
directional buttons map to the arrow / game keys, the click maps to enter (fire), the menu button
maps to the back key, and play/pause maps to the media play/pause key. No TV specific API is
required.
42. File system, storage, network, and parsing
42.1. JAR resources
Resources packaged within the "JAR" don’t belong in this section of the developer guide, but they’re often confused with Storage and FileSystemStorage, so this is a good place to clarify them.
You can place arbitrary files within the src directory of a Codename One project. The file is packaged into the final distribution. In standard Java SE you can do something like:
InputStream i = getClass().getResourceAsStream("/myFile");This isn’t guaranteed to work on all platforms and will probably fail on some. Instead, use something like:
InputStream i = Display.getInstance().getResourceAsStream(getClass(), "/myFile");This isn’t the limitation. You can’t use hierarchies, so something like this fails:
InputStream i = Display.getInstance().getResourceAsStream(getClass(), "/res/myFile");You can’t use relative paths either, so this also fails (notice the missing first slash):
InputStream i = Display.getInstance().getResourceAsStream(getClass(), "myFile");Those limitations exist for portability. iOS and Android handle resources differently, so supporting the full Java SE semantics is unrealistic.
This is even worse sometimes. Because of the way iOS works with resources, some file names can fail. For example, names with the @ character or more than one . can cause problems (for example, file.ext.act). |
Just like in Java SE, the entries within the "JAR" are read and can’t be modified. You can access the stream, but not the actual file.
42.2. Storage
Storage is accessed through the Storage class. It’s a flat, filesystem-like interface that can list, delete, and write named storage entries.
The Storage API also provides convenient methods to write objects to Storage and read them back with readObject and writeObject.
Objects in Storage are deleted when an app is uninstalled, but they’re retained between application updates. A notable exception is Android, which on some devices keeps objects in Storage after uninstalling an app. To force Android to remove them on uninstall, use the build hint android.allowBackup=false. |
The sample code below demonstrates listing storage content, adding and viewing entries, and deleting entries:


42.2.1. The preferences API
Storage also offers a simple API in the form of the Preferences class. The Preferences class lets developers store simple variables, strings, numbers, booleans, and similar values without writing storage code. This is a common use case in applications. For example, you might need to store a server token:
You can then read the token like this:
String token = Preferences.get("token", null);The backing store filename defaults to "codenameone.properties", but you can override it by calling Preferences.setPreferencesLocation(String) before your app touches the API. This is useful when you need separate preference namespaces per user or when you want to plug in an encrypted storage layer.
When you have a batch of updates, prefer the Preferences.set(Map<String,Object>) overload so that all values are persisted with a single disk write.
Preferences can also tell interested code when a key changes. Register a PreferenceListener with addPreferenceListener() to react to updates made in other parts of your code or triggered remotely through Codename One Push.
Remember to remove listeners you no longer need to avoid leaks.
This gets somewhat confusing with primitive numbers for example: if you use Preferences.set("primitiveLongValue", myLongNumber) then invoke Preferences.get("primitiveLongValue", 0) you might get an exception!This would happen because the value is physically a Long object but you’re trying to get an Integer. The workaround is to remain consistent and use code like this Preferences.get("primitiveLongValue", (long)0). |
42.3. File system
FileSystemStorage provides file system access. It maps to the underlying OS’s file system API providing most of the common operations expected from a file API somewhat in the vain of java.io.File & java.io.FileInputStream for example: opening, renaming, deleting etc.
Notice that the file system API is somewhat platform specific in its behavior. All paths used the API should be absolute otherwise they aren’t guaranteed to work.
The main reason java.io.File & java.io.FileInputStream weren’t supported directly has a lot to do with the richness of those two APIs. They effectively allow saving a file anywhere, but mobile devices are far more restrictive and don’t allow apps to see/change files that are owned by other apps.
42.3.1. File paths & app home
All paths in FileSystemStorage are absolute, this simplifies the issue of portability since the concept of relativity and current working directory aren’t portable.
All URLs use the / as their path separator you try to enforce this behavior even on Windows.
Directories end with the / character and thus can be distinguished by their name.
The FileSystemStorage API provides a getRoots() call to list the root directories of the file system (you can then "dig in" through the listFiles API). For example, this is confusing and unintuitive for developers.
To simplify the process of creating/reading files Codename One provides the getAppHomePath() method. This method allows you to get the path to a directory where files can be stored/read.
You can use this directory to place an image to share as you did in the share sample.
| A common Android hack is to write files to the SDCard storage to share them among apps. Android 4.x disabled the ability to write to arbitrary directories on the SDCard even when the appropriate permission was requested. |
42.3.2. Native file chooser
Use Display.openFileChooser() or the shorter CN.openFileChooser() when the user needs to select a general document such as a PDF, text file, private key, or import file. This is different from Display.openGallery(), which is intended for photo and video library media.
The callback source is a String path that can be read with FileSystemStorage.openInputStream(). If the user cancels the picker the event source is null.
CN.openFileChooser(evt -> {
if(evt == null || evt.getSource() == null) {
return;
}
String path = (String)evt.getSource();
try(InputStream in = FileSystemStorage.getInstance().openInputStream(path)) {
String text = Util.readToString(in, "UTF-8");
// import the selected file
} catch(IOException err) {
Log.e(err);
}
}, "pdf,txt");The second argument is a comma-separated accept list. It can contain filename extensions such as pdf,txt,p8, MIME types such as application/pdf, or null// for any file. JavaSE uses the native AWT file dialog. Android uses the system document picker and copies content URIs into an app-readable file path when needed. Ports without a native document picker fall back to a Codename One file tree.
No photo-library or media permissions are added by this API. On Android the system document picker grants read access to the selected document. On iOS this API should be implemented with a document picker, not the photo library; ios.NSPhotoLibraryUsageDescription is only needed for openGallery().
A more advanced usage of the FileSystemStorage API can be a FileSystemStorage Tree:

42.3.3. Storage vs. file system
The question of storage vs. file system is often confusing for novice mobile developers. This embeds two separate questions:
Why are there 2 APIs where one would have worked?
Which one should you pick?
The main reasons for the 2 APIs are technical. Many OSes provide 2 ways of accessing data specific to the app and this is reflected within the API. For example: on Android the FileSystemStorage maps to APIs such as java.io.FileInputStream whereas the Storage maps to Context.openFileInput().
The secondary reason for the two APIs is conceptual. FileSystemStorage is more powerful and in a sense provides more ways to fail, this is compounded by the complex on-device behavior of the API. Storage is designed to be friendlier to the uninitiated and more portable.
You should pick Storage unless you have a specific need that prevents it. Some APIs such as Capture expect a FileSystemStorage URI so in those cases this would also be a need.
Another case where FileSystemStorage is beneficial is the case of hierarchy or native API usage. If you need a directory structure or need to communicate with a native API the FileSystemStorage approach is easier.
In some OSes the FileSystemStorage API can find the content of the Storage API. As one is implemented on top of the other. This is undocumented behavior that can change at any moment! |
To summarize the differences between the 3 file storage options:
| Option | Storage | File System | JAR Resource |
|---|---|---|---|
Main Use Case | General application Data | low-level access | Ship data within the app |
Initial State | Blank | Blank | As defined by developer |
Modifiable | Yes | Yes | No |
Supports Hierarchies | No | Yes | No |
42.4. SQL
SQLite is a small SQL database designed for embedding into an application. Codename One exposes it
through com.codename1.db, an API similar in spirit to JDBC but much smaller, since the
abstractions JDBC needs for pluggable drivers make no sense for a local file.
Use it when you have tabular data, need to query it, or have enough of it that loading the lot into
memory is unreasonable. For a handful of values Storage is simpler.
The Database API opens a database by name:
Some SQLite apps ship with a "ready made" database. You allow you to replace the DB file by using the code:
String path = Display.getInstance().getDatabasePath("databaseName");You can then use the FileSystemStorage class to write the content of your DB file into the path. Notice that it must be a valid SQLite file!
In the JavaScript port databases live in a browser storage pool rather than a filesystem, so
getDatabasePath() returns the name within that pool and FileSystemStorage can’t open it. |
The browser engine changed. Earlier JavaScript builds kept databases in WebSQL, which
Chrome removed and Firefox never implemented; the current engine is SQLite compiled to WebAssembly,
and it can’t read a WebSQL store. If your application ran on a browser old enough to still have one,
openOrCreate refuses to create a database whose name it finds there rather than handing you an
empty one, because an application that writes as it goes would overwrite the user’s data with an
empty state. Export what the old store holds from a build that still reads it, or set the
cn1.db.ignoreLegacyWebSql property to true to continue with a new empty database — nothing
removes the old store, so an application that has finished with it needs that property to move on. |
This is useful for applications that need to synchronize with a central server or applications that ship with a large database as part of their core product.
Working with a database is pretty trivial, the application logic below can send arbitrary queries to the database and present the results in a Table. You can probably integrate this code into your app as a debugging tool:


42.4.1. Encrypting a database
Pass a DatabaseConfig to encrypt a database at rest. Check that the platform can do it first:
if (Database.isEncryptionSupported()) {
DatabaseConfig config = DatabaseConfig.managed();
Database db = Database.openOrCreate("secure.db", config);
config.wipe();
}There are three ways to key a database.
DatabaseConfig.passphrase(String)The key is derived from a secret your application supplies, usually one the user typed. Nothing is stored on the device, so losing the passphrase loses the data.
DatabaseConfig.managed()A random key is generated on first use and kept in the platform key store, the Android Keystore or the iOS keychain. Your application never handles the key. This is the right default when there is nobody to prompt.
DatabaseConfig.rawKey(byte[])Thirty-two bytes of key material you already have, for instance issued by your server. No key derivation is applied, so the bytes must already be uniformly random.
A passphrase written into your source code isn’t a secret. String literals are recoverable
from a shipped .ipa or .apk in minutes, so a constant passphrase buys you nothing against anyone
holding the file. If your application can’t ask a human for one, use managed(): a random key in
the platform key store beats a constant compiled into the binary. |
Encryption protects data at rest, and nothing else. It’s no defense against a rooted or jailbroken device, a debugger attached to the running process, or a memory dump, because the key is in memory for as long as the database is open.
Managed keys aren’t recoverable. Losing the key store entry, through an application uninstall, a device wipe or, on Android, restoring a backup onto a different device, leaves the database permanently unreadable. Android keystore keys can’t be exported; iOS keychain entries do survive an encrypted backup and restore. If the data has to outlive the device, use a passphrase your user or your server holds.
The simulator has no hardware key store, so a managed key there is protected only by a
software derived key in your desktop user profile. It’s fine for development, and it’s no evidence
that real user data is protected. DatabaseConfig.isKeyHardwareBacked() reports the
difference, and the simulator logs a warning the first time you use a managed key. |
What encryption costs your build
Nothing is added to an application that doesn’t use it. The build scans your own classes — not the framework’s — and decides from what they reference:
| What your code references | What the build adds |
|---|---|
nothing in | Nothing at all. No SQLite engine on the platforms that bundle one, no browser payload. |
| The plain SQLite engine where the platform needs one: compiled into the native Windows and Linux binaries, and about 1.5MB of WebAssembly in a JavaScript build. Android and iOS use the engine already in the operating system. |
| The cipher as well. On Android that’s |
On Android, encryption raises android.min_sdk_version to 23 and requires
android.useAndroidX=true, because that’s SQLCipher’s floor. If your application targets an older
API level the build will raise it for you, and devices below API 23 will no longer see your app in
the store. This applies as soon as anything in your code mentions DatabaseConfig, so a build hint
alone won’t opt out of it — remove the reference if you need the lower floor. |
Converting an existing database
An application that already ships a plaintext database can convert it in place:
if (!Database.isEncrypted("myapp.db")) {
Database.encrypt("myapp.db", DatabaseConfig.managed());
}Database.decrypt is the reverse, and Database.changeKey re-keys a database that’s already open.
An interruption leaves the original file intact, and schema metadata such as PRAGMA user_version
survives.
How that’s achieved differs by platform, which matters only if you’re watching the filesystem. Most
platforms re-key the file in place. Android can’t: its SQLCipher engine re-keys only between two
encrypted states and refuses to convert to or from plaintext, so the port writes the converted
database alongside the original and swaps it in once it’s complete. A .cn1migrate file next to
your database means a conversion was interrupted partway; the original is still the live one, and
the leftover is cleaned up on the next attempt.
The on-disk format
Every platform reads and writes one format, so a database created on a phone can be pulled off the
device and opened in the simulator while you are debugging. The parameters are fixed: AES-256 in CBC
mode, PBKDF2-HMAC-SHA512 key derivation at 256000 iterations, a 4096 byte page size and per-page
HMAC-SHA512. This is the SQLCipher 4 format, so standard tools such as the sqlcipher command line
client can open these files too.
42.4.2. Transactions
Transactions are flat, because that’s the only model all the underlying engines can express. A
beginTransaction() while one is already open throws, and so does a commitTransaction() or
rollbackTransaction() with none open. Both end the transaction and return the connection to
autocommit, and closing a database with one open rolls it back.
A commit can fail. SQLite checks a deferred constraint when the transaction commits, not when the
offending row is inserted, so that’s where the failure surfaces. When it does, the transaction is
over: the port ends it for you and beginTransaction() works again straight away. Don’t roll back
afterward, because there’s nothing left to roll back and the call throws. The engines don’t agree
here on their own — Android ends the transaction before it reports the failure, while the SQLite C
API and JDBC leave it open — so the port reconciles them and your code sees one behaviour.
42.4.3. Attaching a second database
ATTACH makes another database part of the connection, and SQLite holds it until you detach it or
close the connection. Codename One counts an attached database as open, so deleting it, converting
it or changing its key is refused while it’s attached, the same as for the database you opened
directly. That’s the protection you want: unlinking a file SQLite still has open loses everything
written through it.
SQLite lets you attach one file under several schema names at once. The file stays protected until
the last of them is detached, so a DETACH of one name doesn’t release a database the connection
still holds under another.
Write the filename as a single quoted literal, or bind it as a parameter. SQLite also accepts an
expression there — ATTACH '/data/' || name AS aux — but nothing can tell which file that names
until the engine evaluates it, which is after the database is already attached and too late to
refuse. Those
are rejected, and the message says so; build the name in your own code and pass it as a parameter.
Run ATTACH and DETACH through execute(). executeQuery() refuses them, because a cursor runs
its statement when it’s stepped — so the attachment would happen after the bookkeeping, and the
file could then be deleted while SQLite still holds it.
A path that runs through a symbolic link identifies the same database as the resolved path does.
The engine resolves links when it reports what it opened, so Codename One resolves them too before
it decides two names are one file — on the platforms where the engine does. Windows is the
exception, because SQLite’s Windows layer collapses . and .. as text and steps over a junction
rather than through it, so the unresolved name is what identifies the file there.
Name the file with an absolute path from Database.getDatabasePath(). A relative name is resolved
by SQLite against the process working directory, which is a different place on every platform and
isn’t something a Codename One application controls, while Codename One would look for it in the
database directory — so the database protected wouldn’t be the database attached. Those are
rejected on every port whose engine has a working directory to resolve against; in the browser,
where a name is an entry in a storage pool and means the same thing either way, they’re accepted.
If an attachment turns out to name a database that something else is deleting or converting, it’s
detached again and the next call on that connection throws to tell you.
42.4.4. Threading
A Database and its cursors aren’t thread safe. Either give each thread its own connection, or
wrap one in ThreadSafeDatabase, which routes every call through a single worker thread:
Database threadSafeDb = new ThreadSafeDatabase(Database.openOrCreate("shared.db"));The wrapper costs a thread handoff per call, so a connection per thread is faster when the threads don’t genuinely need to share one.
42.4.5. Text and column indexes
Text is stored and read back exactly as written, for every character a Java String can hold:
accented characters, scripts outside ASCII, emoji, and even the character with code point zero,
which SQLite stores in a TEXT value like any other. A string written on one platform reads back
identical on every other.
Reading a column the result set doesn’t have — a negative index, or one past the last column — raises an IOException. It’s never reported as a null value, because SQLite’s own C interface
answers an out-of-range index with SQL NULL, and passing that on would make a mistyped index
impossible to tell apart from stored data.
42.4.6. Cursor performance
Iterating forward with next() costs the same everywhere. Seeking backwards or to an absolute row
is cheap on Android, which keeps a window of rows, and costs time proportional to the distance from
the start elsewhere, because a SQLite statement only steps forward and seeking back means rewinding
and stepping again. Prefer next() for large result sets.
One consequence is worth knowing: because a backward seek re-runs the statement, a cursor is a repeatable read only inside a transaction. Outside one, another thread can write between the two passes, changing what the second pass sees.
There’s a limit on Android that follows from the same mechanism. A statement that changes the
database and returns rows — INSERT … RETURNING and its relatives — runs once, and Android
reads its rows through a window it can only refill by running the statement again. The rows that
fit in the first window are therefore readable and the rest aren’t: reaching them would apply the
insert a second time. Codename One refuses that rather than doing it, and says so in the error,
including that the changes are already applied and the statement must not be retried. If the
result set may be large, run the statement with execute() and query for what you need
afterward. Every other port steps through such a statement once and has no such limit.
42.4.7. Compatibility with the previous behaviour
This API predates the portable contract, and its behaviour used to differ between platforms. If your
application depends on the old behaviour, set the db.legacy build hint, or call
Database.setLegacyBehavior(true) before opening any database. It restores each platform’s previous
behaviour exactly.
What your project gets by default
An Ant project that uses com.codename1.db is built in compatibility mode automatically. Ant
projects predate the portable contract, so a rebuild shouldn’t change how their queries behave
unless you ask for it. A Maven project gets the portable contract, which is the documented default everywhere else
in this section.
The build server decides this from the project itself, and says so in the build log when it turns
compatibility mode on. It only applies when your application actually references
com.codename1.db; an Ant project with no database is unaffected.
The build hint always wins, in either direction:
db.legacy | Ant project | Maven project |
|---|---|---|
unset | compatibility mode | portable contract |
| portable contract | portable contract |
| compatibility mode | compatibility mode |
An Ant project can therefore opt in to the portable contract by setting db.legacy=false, and a
Maven project can pin compatibility mode with db.legacy=true. Setting it explicitly is worth doing once
you’ve decided, because it makes the choice visible in the project rather than inferred from how
it’s built. If you migrate an Ant project to Maven without setting the hint, the default flips, so
set it before you migrate if you want the behaviour to stay put.
The hint works in the simulator too, so you can test either mode without a device.
| Restored behaviour | Platforms |
|---|---|
| iOS |
| Simulator |
| Android, iOS |
Parameters bind as text rather than by type | iOS |
| Android, Simulator |
The parameterized methods discard statements after the first, without saying so | all |
A nested | Android |
Malformed SQL surfaces from | Android |
| Simulator |
| Simulator |
| all |
| all |
| all |
| all but the browser |
The flag doesn’t cover defects, nor capabilities that used to throw and now work:
last(), prev() and position(int) on iOS and the simulator, reading blobs on iOS, blob query
parameters, binding null inside a String[], the existence of a database at all on the native
Windows and Linux ports, or seeking backwards through a statement that writes, which used to run
that statement a second time and repeat what it wrote. No application can depend on those.
42.4.8. Two settings the contract can’t reach
Everything above is behaviour Codename One implements, so it can be made the same everywhere. Two things are decided when the SQLite engine itself is compiled, and Codename One only compiles one of those engines — Android uses the platform’s, the simulator uses the JDBC driver’s, and iOS uses Apple’s unless the application encrypts:
Double-quoted string literals.
SELECT "value"isn’t valid SQL — the double quotes make it an identifier — but SQLite has a compatibility mode that turns an unknown identifier into a string, and that mode is fixed when the engine is compiled, with no pragma to change it. The Android and Apple engines accept it; the simulator’s driver rejects it with a message that tells you to use single quotes. Write string literals in single quotes and the question never arises. The engine Codename One bundles for Windows, Linux and encrypted iOS keeps SQLite’s default, so switching encryption on never changes what a statement means.Foreign keys. SQLite ignores declared foreign keys unless asked, and one driver enables them on its own. Codename One puts every port on SQLite’s default so a violation behaves the same in the simulator as on a device; run
PRAGMA foreign_keys = ONafter opening if you want them enforced, which works everywhere.
Both are easy to settle for yourself: SELECT "value" either returns the string or reports an
error, and PRAGMA foreign_keys reports whether they’re on. Codename One’s own port conformance
run reports both for every platform it covers.
42.5. Network manager & connection request
One of the more common problems in Network programming is spawning a new thread to handle the network operations. In Codename One this is done seamlessly and becomes unessential thanks to the NetworkManager.
NetworkManager effectively alleviates the need for managing network threads by managing the complexity of network threading. The connection request class can be used to ease web service requests when coupled with the JSON/XML parsing capabilities.
To open a connection one needs to use a ConnectionRequest object, which has some similarities to the networking mechanism in JavaScript but is obviously somewhat more elaborate.
You can send a get request to a URL using something like:
Notice that you can also implement the same thing and much more by avoiding the response listener code and instead overriding the methods of the ConnectionRequest class which offers many points to override for example:
Notice that overriding buildRequestBody(OutputStream) will work for POST requests and will replace writing the arguments |
| You don’t need to close the output/input streams passed to the request methods. They’re implicitly cleaned up. |
NetworkManager also supports synchronous requests which work in a similar way to Dialog through the invokeAndBlock call and thus don’t block the EDT [8] illegally. For example: you can do something like this:
Notice that in this case the addToQueueAndWait method returned after the connection completed. Also notice that this was totally legal to do on the EDT!
42.5.1. Timeouts & retries
Each request can override the global timeout using setTimeout(int), which
expects a duration in milliseconds. This is useful when you’re
talking to endpoints that occasionally need a longer window than the default
NetworkManager setting. You can also configure how many times Codename One
should retry a failing call by using setSilentRetryCount(int). When
the silent retry limit is reached the standard error handling kicks in (for example:
listeners fire, fail dialogs show, etc.).
42.5.2. Threading
By default the NetworkManager launches with a single network thread. This is enough for simple applications that don’t do too much networking but if you need to fetch many images concurrently and perform web services in parallel this might be an issue.
| Once you increase the thread count there is no guarantee of order for your requests. Requests might not execute in the order with which you added them to the queue! |
To update the number of threads use:
NetworkManager.getInstance().updateThreadCount(4);All the callbacks in the ConnectionRequest occur on the network thread and not on the EDT!
One exception to this rule exists: the postResponse() method, designed to update the UI after the networking code completes.
Never change the UI from a ConnectionRequest callback. You can either use a listener on the ConnectionRequest, use postResponse() (which is the exception to this rule) or wrap your UI code with callSerially. |
42.5.3. VPN detection (best effort)
NetworkManager includes two APIs for querying VPN state:
NetworkManager nm = NetworkManager.getInstance();
if (nm.isVPNDetectionSupported()) {
boolean vpnActive = nm.isVPNActive();
}| This is a heuristic signal, not a security control. |
Both Android and iOS implementations rely on platform networking metadata and
interface-name patterns (for example: tun, ppp, utun, ipsec). This means the
result can be wrong in either direction:
False negatives: Some VPNs may hide or avoid these patterns.
False positives: Other virtual/tunnel interfaces may look like VPNs.
Use this API for UX or diagnostics (for example: warnings, telemetry, or logging), not for access control or fraud prevention by itself.
42.5.4. Arguments, headers & methods
HTTP/S is a complex protocol that expects complex encoded data for its requests. Codename One tries to simplify and abstract most of these complexities behind common sense APIs while still providing the full low-level access you would expect from such an API.
Arguments
HTTP supports many "request methods," most commonly GET & POST but also a few others such as HEAD, PUT, DELETE etc.
Arguments in HTTP are passed differently between GET and POST methods. That’s what the setPost method in Codename One determines, whether arguments added to the request should be placed using the GET semantics or the POST semantics.
If you continue your example from above you can do something like this:
This will implicitly add a get argument with the content of value. Notice that you don’t care what value is. It’s implicitly HTTP encoded based on the get/post semantics. In this case it will use the get encoding since you passed false to the constructor.
A simpler implementation could do something like this:
This would be almost identical but doesn’t provide the convenience for switching back and forth between GET/POST and it isn’t as fluent.
You can skip the encoding in complex cases where server code expects illegal HTTP characters (this happens) using the addArgumentNoEncoding method. You can also add many arguments with the same key using addArgumentArray.
Methods
As you explained above, the setPost() method allows you to manipulate the get/post semantics of a request. This implicitly changes the POST or GET method submitted to the server.
For example, if you wish to have finer grained control over the submission process for example: for making a HEAD request you can do this with code like:
Headers
When communicating with HTTP servers you often pass data within headers for authentication/authorization but also to convey various properties.
Some headers are built-in as direct APIs for example: content type is directly exposed within the API since it’s a pretty common use case. You can set the content kind of post request using:
You can also add any arbitrary header type you want, for example: a common use case is basic authorization where the authorization header includes the Base64 encoded user/password combination as such:
This can be tedious to do if you want all requests from your app to use this header. For this use case you can use:
Server headers
Server returned headers are a bit trickier to read. You need to subclass the connection request and override the readHeaders method for example:
Here you can extract the headers one by one to handle complex headers such as cookies, authentication etc.
Error handling
As you noticed above practically all the methods in the ConectionRequest throw IOException. This allows you to avoid the try/catch semantics and let the error propagate up the chain so it can be handled uniformly by the application.
There are two distinct places where you can handle a networking error:
The
ConnectionRequest- by overriding callback methodsThe
NetworkManagererror handler
Notice that the NetworkManager error handler takes precedence thus allowing you to define a global policy for network error handling by consuming errors.
For example: to block all network errors from showing anything to the user you could do something like this:
The error listener is invoked first with the NetworkEvent matching the error. Consuming the event prevents it from propagating further down the chain into the ConnectionRequest callbacks.
You can also override the error callbacks of the various types in the request for example: for a server error code you can do:
| The error callback is triggered in the network thread! As a result it can’t access the UI to show a Dialog or anything like that. |
Another approach is to use the setFailSilently(true) method on the ConnectionRequest. This will prevent the ConnectionRequest from displaying any errors to the user. It’s a powerful strategy if you use the synchronous version of the APIs for example:
| This code will work with the synchronous "AndWait" version of the method since the response code will take a while to return for the non-wait version. |
Error stream
When you get an error code that isn’t 200/300 you ignore the result. This is problematic as the result might contain information you need. For example: many webservices provide further XML/JSON based details describing the reason for the error code.
Calling setReadResponseForErrors(true) will trigger a mode where even errors will receive the readResponse callback with the error stream. This also means that APIs like getData and the listener APIs will also work in case of error.
42.5.5. GZIP
Gzip is a common compression format based on the lz algorithm, it’s used by web servers around the world to compress data.
Codename One supports GZipInputStream and GZipOutputStream, which allow you to compress data seamlessly into a stream and extract compressed data from a stream. This is useful and can be applied to every arbitrary stream.
Codename One also features a GZConnectionRequest, which will automatically unzip an HTTP response if it’s indeed gzipped. Notice that some devices (iOS) always request gzip’ed data and always decompress it for you, but for iOS it doesn’t remove the gziped header. The GZConnectionRequest is aware of such behaviors so it’s better to use that when connecting to the network (if applicable).
By default GZConnectionRequest doesn’t request gzipped data ( unzips it when its received) but its pretty easy to do so add the HTTP header Accept-Encoding: gzip for example:
Do the rest as usual and you should have smaller responses from the servers.
42.5.6. File upload
MultipartRequest tries to simplify the process of uploading a file from the local device to a remote server.
You can always submit data in the buildRequestBody but this is flaky and has some limitations in devices/size allowed. HTTP standardized file upload capabilities through the multipart request protocol, this is implemented by countless servers and is well documented. Codename One supports this out of the box:
MultipartRequest is a ConnectionRequest most stuff you expect from there should work. Even addArgument etc. |
Since you assume most developers reading this will be familiar with Java here is the way to implement the multipart upload in the servlet API:
42.5.7. Parsing
Codename One has many built in parsers for JSON, XML, CSV & Properties formats. You can use those parsers to read data from the Internet or data that’s shipping with your product. For example: use the CSV data to setup default values for your application.
All your parsers are designed with simplicity and small distribution size; they don’t check and will fail in odd ways when faced with broken data. The main logic behind this is that validation takes up CPU time on the device where CPU is a precious resource.
Parsing CSV
CSV is probably the easiest to use, the "Comma Separated Values" format is a list of values separated by commas (or some other character) with new lines to show another row in the table. These map well to an Excel spreadsheet or database table and are supported by default in all spreadsheets.
To parse a CSV use the CSVParser class as such:

The data contains a two-dimensional array of the CSV content. You can change the delimiter character by using the CSVParser constructor that accepts a character.
Notice that you used CharArrayReader from the com.codename1.io package for this sample. You would want to use java.util.InputStreamReader for real world data. |
JSON
The JSON ("JavaScript Object Notation") format is popular on the web for passing values to/from webservices since it works so well with JavaScript. Parsing JSON is as easy but has two different variations. You can use the JSONParser class to build a tree of the JSON data as such:
The response is a Map containing a nested hierarchy of Collection (java.util.List), Strings and numbers to represent the content of the submitted JSON. To extract the data from a specific path iterate the Map keys and recurs into it.
The sample below uses results from an API of ice and fire that queries structured data about the "Song Of Ice & Fire" book series. Here is a sample result returned from the API for the query http://www.anapioficeandfire.com/api/characters?page=5&pageSize=3 :
[
{
"url": "http://www.anapioficeandfire.com/api/characters/13",
"name": "Chayle",
"culture": "",
"born": "",
"died": "In 299 AC, at Winterfell",
"titles": [
"Septon"
],
"aliases": [],
"father": "",
"mother": "",
"spouse": "",
"allegiances": [],
"books": [
"http://www.anapioficeandfire.com/api/books/1",
"http://www.anapioficeandfire.com/api/books/2",
"http://www.anapioficeandfire.com/api/books/3"
],
"povBooks": [],
"tvSeries": [],
"playedBy": []
},
{
"url": "http://www.anapioficeandfire.com/api/characters/14",
"name": "Gillam",
"culture": "",
"born": "",
"died": "",
"titles": [
"Brother"
],
"aliases": [],
"father": "",
"mother": "",
"spouse": "",
"allegiances": [],
"books": [
"http://www.anapioficeandfire.com/api/books/5"
],
"povBooks": [],
"tvSeries": [],
"playedBy": []
},
{
"url": "http://www.anapioficeandfire.com/api/characters/15",
"name": "High Septon",
"culture": "",
"born": "",
"died": "",
"titles": [
"High Septon",
"His High Holiness",
"Father of the Faithful",
"Voice of the Seven on Earth"
],
"aliases": [
"The High Sparrow"
],
"father": "",
"mother": "",
"spouse": "",
"allegiances": [],
"books": [
"http://www.anapioficeandfire.com/api/books/5",
"http://www.anapioficeandfire.com/api/books/8"
],
"povBooks": [],
"tvSeries": [
"Season 5"
],
"playedBy": [
"Jonathan Pryce"
]
}
]You will place that into a file named "anapioficeandfire.json" in the src directory to make the next sample simpler:
Form hi = new Form("JSON Parsing", new BoxLayout(BoxLayout.Y_AXIS));
JSONParser json = new JSONParser();
try(Reader r = new InputStreamReader(Display.getInstance().getResourceAsStream(getClass(), "/anapioficeandfire.json"), "UTF-8");) {
Map<String, Object> data = json.parseJSON(r);
java.util.List<Map<String, Object>> content = (java.util.List<Map<String, Object>>)data.get("root"); (1)
for(Map<String, Object> obj : content) { (2)
String url = (String)obj.get("url");
String name = (String)obj.get("name");
java.util.List<String> titles = (java.util.List<String>)obj.get("titles"); (3)
if(name == null || name.length() == 0) {
java.util.List<String> aliases = (java.util.List<String>)obj.get("aliases");
if(aliases != null && aliases.size() > 0) {
name = aliases.get(0);
}
}
MultiButton mb = new MultiButton(name);
if(titles != null && titles.size() > 0) {
mb.setTextLine2(titles.get(0));
}
mb.addActionListener((e) -> Display.getInstance().execute(url));
hi.add(mb);
}
} catch(IOException err) {
Log.e(err);
}
hi.show();| 1 | The JSONParser returns a Map which is great if the root object is a Map but sometimes its a list of elements (as is the case above). In this case a special case "root" element is created to contain the actual list of elements. |
| 2 | You rely that the entries are all maps, this might not be the case for every API type. |
| 3 | Notice that the "titles" and "aliases" entries are both lists of elements. You use java.util.List to avoid a clash with com.codename1.ui.List. |

| The structure of the returned map is sometimes unintuitive when looking at the raw JSON. The easiest thing to do is set a breakpoint on the method and use the inspect variables capability of your IDE to inspect the returned element hierarchy while writing the code to extract that data |
An alternative approach is to use the static data parse() method of the JSONParser class and implement a callback parser for example:
JSONParser.parse(reader, callback);
Notice that a static version of the method is used! The callback object is an instance of the JSONParseCallback interface, which includes many methods. These methods are invoked by the parser to show internal parser states, this is like the way traditional XML SAX event parsers work.
Writing JSON — JSONWriter
For typed DTO serialization use the @Mapped annotation framework
(see JSON / XML Object Mapping) plus Mappers.toJson(…). For ad-hoc
maps / lists where a build-time Mapper would be overkill, the
com.codename1.io.JSONWriter class is the complement of JSONParser:
For tiny request bodies the fluent builders are usually faster to read
than a Map literal:
Strings are double-quoted with the standard backslash escapes for ",
\, \n, \r, \t, \b, \f, and control chars below 0x20 are
emitted as \u00xx. The writer doesn’t pretty-print; if you need
indented output, run the result through an external formatter at debug
time.
XML parsing
The XMLParser started its life as an HTML parser built for displaying mobile HTML. That usage has since been deprecated but the parser can still parse many HTML pages and is "loose" in verification. This is both good and bad as the parser will work with invalid data without complaining.
The simplest usage of XMLParser looks a bit like this:
The Element contains children and attributes. It represents a tag within the XML document and even the root document itself. You can iterate over the XML tree to extract the data from within the XML file.
You’ve had a great sample of working with XMLParser in the
Tree Section of this guide.
XMLParser has the complimentary XMLWriter class which can generate XML from the Element hierarchy. This allows developers to mutate (change) the elements and save them to a writer stream.
XPath processing
The Result class provides a subset of
XPath, but it isn’t limited to XML documents, it can also work with JSON documents, and even with raw Map objects.
Start by demonstrating how to process a response from the Google Reverse Geocoder API. Start with this XML snippet:
<?xml version="1.0" encoding="UTF-8"?>
<GeocodeResponse>
<status>OK</status>
<result> <!-- (irrelevant content removed) -->
<address_component>
<long_name>London</long_name>
<short_name>London</short_name>
<type>locality</type>
<type>political</type>
</address_component>
<!-- (irrelevant content removed) -->
<address_component>
<long_name>Ontario</long_name>
<short_name>ON</short_name>
<type>administrative_area_level_1</type>
<type>political</type>
</address_component>
<address_component>
<long_name>Canada</long_name>
<short_name>CA</short_name>
<type>country</type>
<type>political</type>
</address_component>
</result>
</GeocodeResponse>You want to extract some data above into simpler string results. You can do this using:
If you’re at all familiar with processing responses from webservices, you will notice that what would require many lines of code of selecting and testing nodes in regular java can now be done in a single line using the new path expressions.
In the code above, input can be any of:
InputStreamdirectly fromConnectionRequest.readResponse(java.io.InputStream).XML or JSON document in the form of a {@code String}</li>
JSON DOM
Mapreturned from JSONParser
To use the expression processor when calling a webservice, you could use something like the following to parse JSON (notice this is interchangeable between JSON and XML):
Form hi = new Form("Location", new BoxLayout(BoxLayout.Y_AXIS));
hi.add("Pinpointing Location");
Display.getInstance().callSerially(() -> {
Location l = Display.getInstance().getLocationManager().getCurrentLocationSync();
ConnectionRequest request = new ConnectionRequest("http://maps.googleapis.com/maps/api/geocode/json", false) {
private String country;
private String region;
private String city;
private String json;
@Override
protected void readResponse(InputStream input) throws IOException {
Result result = Result.fromContent(input, Result.JSON);
country = result.getAsString("/results/address_components[types='country']/long_name");
region = result.getAsString("/results/address_components[types='administrative_area_level_1']/long_name");
city = result.getAsString("/results/address_components[types='locality']/long_name");
json = result.toString();
}
@Override
protected void postResponse() {
hi.removeAll();
hi.add(country);
hi.add(region);
hi.add(city);
hi.add(new SpanLabel(json));
hi.revalidate();
}
};
request.setContentType("application/json");
request.addRequestHeader("Accept", "application/json");
request.addArgument("sensor", "true");
request.addArgument("latlng", l.getLatitude() + "," + l.getLongitude());
NetworkManager.getInstance().addToQueue(request);
});
hi.show();
/* omitted */The returned JSON looks something like this (notice it’s snipped because the data is too long):
{
"status": "OK",
"results": [
{
"place_id": "ChIJJ5T9-iFawokRTPGaOginEO4",
"formatted_address": "280 Broadway, New York, NY 10007, USA",
"address_components": [
{
"short_name": "280",
"types": ["street_number"],
"long_name": "280"
},
{
"short_name": "Broadway",
"types": ["route"],
"long_name": "Broadway"
},
{
"short_name": "Lower Manhattan",
"types": [
"neighborhood",
"political"
],
"long_name": "Lower Manhattan"
},
{
"short_name": "Manhattan",
"types": [
"sublocality_level_1",
"sublocality",
"political"
],
"long_name": "Manhattan"
},
{
"short_name": "New York",
"types": [
"locality",
"political"
],
"long_name": "New York"
},
{
"short_name": "New York County",
"types": [
"administrative_area_level_2",
"political"
],
"long_name": "New York County"
},
{
"short_name": "NY",
"types": [
"administrative_area_level_1",
"political"
],
"long_name": "New York"
},
{
"short_name": "US",
"types": [
"country",
"political"
],
"long_name": "United States"
},
{
"short_name": "10007",
"types": ["postal_code"],
"long_name": "10007"
},
{
"short_name": "1868",
"types": ["postal_code_suffix"],
"long_name": "1868"
}
],
"types": ["street_address"],
"geometry": {
"viewport": {
"northeast": {
"lng": -74.0044642197085,
"lat": 40.7156470802915
},
"southwest": {
"lng": -74.0071621802915,
"lat": 40.7129491197085
}
},
"location_type": "ROOFTOP",
"location": {
"lng": -74.00581319999999,
"lat": 40.7142981
}
}
}
/* SNIPED the rest */
]
}
The XML processor handles global selections by using a double slash anywhere within the expression, for example:
| Notice that Google’s JSON webservice uses plural form for each of the node names in that API (ie. results, address_components, and types) where they don’t in the XML services (that’s result, address_component etc.) |
Second example
It’s also possible to do some more complex expressions. You’ll use the following XML fragment for the next batch of examples:
<rankings type="aus" gender="male" date="2011-12-31">
<player id="1036" coretennisid="6752" rank="1"
delta="0" singlespoints="485000" doublespoints="675"
deductedpoints="0" totalpoints="485675">
<firstname>Bernard</firstname>
<lastname>Tomic</lastname>
<town>SOUTHPORT</town>
<state>QLD</state>
<dob>1992-10-21</dob>
</player>
<player id="2585" coretennisid="1500" rank="2"
delta="0" singlespoints="313500" doublespoints="12630"
deductedpoints="0" totalpoints="326130">
<firstname>Mathew</firstname>
<lastname>Ebden</lastname>
<town>CHURCHLANDS</town>
<state>WA</state>
<dob>1987-11-26</dob>
</player>
<player id="6457" coretennisid="287" rank="3"
delta="0" singlespoints="132500" doublespoints="1500"
deductedpoints="0" totalpoints="134000">
<firstname>Lleyton</firstname>
<lastname>Hewitt</lastname>
<town>EXETER</town>
<state>SA</state>
<dob>1981-02-24</dob>
</player>
<!-- ... etc ... -->
</rankings>Above, if you want to select the IDs of all players that are ranked in the top 2, you can use an expression like:
| Notice above that the expression is using an attribute for selecting both rank and id. In JSON documents, if you try to select an attribute, it will look for a child node under the attribute name you ask for) |
If a document is ordered, you might want to select nodes by their position, for example:
It’s also possible to select parent nodes, by using the .. expression. For example:
Above, you globally find a lastname element with a value of ‘Hewitt’, then grab the parent node of lastname which happens to be the player node, then grab the ID attribute from the player node. Or, you could get the same result from the following simpler statement:
It’s also possible to nest expressions, for example:
In the above example, if the player node had an address object, you’d be selecting all players from Canada. This is a simple example of a nested expression, but they can get much more complex, which will be required as the documents themselves get more complex.
Moving on, to select a node based on the existence of an attribute:
Above, you selected the IDs of all ranked players. Conversely, you can select the non-ranked players like this:
| Logical not (!) operators aren’t implemented) |
You can also select by the existence of a child node
Above, you selected all players that have a middle name.<br/> Keep in mind that the Codename One path expression language isn’t a full implementation of XPath 1.0, but does already handle many of the most useful features of the specification.
Properties files
Properties files are standard key/value pairs encoded into a text file. This file format is familiar to Java developers and the Codename One specific version tries to be as close as possible to the original Java implementation.
Notice that properties file both in Java proper and in Codename One don’t support non-ascii characters. To encode Unicode values into the properties file format you should use the native2ascii tool that ships with the JDK.
One major difference between standard Java properties and the ones in Codename One is that Codename One sorts properties alphabetically when saving. Java uses random order based on the Hashtable natural ordering.
This was done to provide consistency for saved files.
42.6. Debugging network connections

Codename One includes a Network Monitor tool which you can access through the simulator menu option. This tool reflects all the requests made through the connection requests and displays them in the left pane. This allows you to track issues in your code/web service and see everything the is "going through the wire."
This is a useful tool for optimizing and for figuring out what’s happening with your server connection logic.
42.6.1. Simpler downloads
A common task is file download to storage or filesystem.
The Util class has simple utility methods:
downloadUrlToFileSystemInBackground, downloadUrlToStorageInBackground, downloadUrlToFile & downloadUrlToStorage.
These all delegate to a feature in ConnectionRequest:
ConnectionRequest.setDestinationStorage(fileName) &
ConnectionRequest.setDestinationFile(fileName);
Both of which simplify the whole process of downloading a file.
Downloading images
Codename One has many ways to download an image and the general recommendation is the URLImage.
For example, the URLImage assumes that you know the size of the image in advance or that you’re willing to resize it. In that regard it works great for some use cases but not so much for others.
The download methods mentioned above are great alternatives but they’re a bit verbose when working with images and don’t provide fine grained control over the ConnectionRequest for example: making a POST request to get an image.
| Adding global headers is another use case but you can use addDefaultHeader to add those. |
To make this process simpler there is a set of helper methods in ConnectionRequest that downloads images directly.
These methods complement the Util methods but go a bit further and feature terse syntax for example: you can
download a ConnectionRequest to Storage using code like this:
This effectively maps the ConnectionRequest directly to a SuccessCallback for further processing.
URLImage caching
URLImage is great. It changed the way you do some things in Codename One.
For example, when you introduced it you didn’t have support for the cache filesystem or for the JavaScript port. The cache filesystem is probably the best place for images of URLImage so supporting that as a target is an obvious choice, but JavaScript seems to work so why would it need a special case?
JavaScript already knows how to download and cache images from the web. URLImage is actually a step back from the things a good browser can do so why not use the native abilities of the browser when you’re running there and fallback to using the cache filesystem if it’s available and as a last resort go to storage…
That’s what the new method of URLImage does:
A few important things you need to notice about this method:
It returns Image and not URLImage. This is crucial. Down casting to `URLImage* will work on the simulator but might fail in some platforms (for example: JavaScript) so don’t do that!
Since this is implemented natively in JavaScript you need a different abstraction for that platform.It doesn’t support image adapters and instead uses a simplified resize rule. Image adapters work on
URLImagesince you have a lot of control in that class. For example, in the browser your control is limited and so an adapter won’t work.
If you do use this approach it would be far more efficient when running in the JavaScript port and will make better use of caching in most OSes.
42.7. Rest API
The Rest API makes it easy to invoke a RESTful webservice without many of the nuances of ConnectionRequest. You can use it to define the HTTP method and start building based on that. To get a parsed JSON result from a URL you could do:
For a lot of REST requests this will fail because you need to add an HTTP header indicating that you accept JSON results. You have a special case support for that:
POST requests use the same builder pattern:
Notice the usage of post and the body builder method. MANY methods exist in the builder class that cover pretty much everything you would expect and then some when it comes to the needs of rest services.
Some highlights that are easy to miss:
.priority(byte)lets you change the underlyingConnectionRequestpriority when you need certain calls to jump the queue..cookiesEnabled(boolean)controls whether cookies are persisted for the request when you need stateless behavior..useBoolean(boolean)and.useLongs(boolean)toggle how the JSON parser materializes number and boolean types inside the resultingMap, which is handy when your back end is strict about data types..cacheMode(…)and.postParameters(…)expose the same knobs asConnectionRequest, keeping you in the fluent API even for advanced tweaks.
42.7.1. Top-level JSON arrays — fetchAsJsonList
When the endpoint returns a top-level JSON array (for example [{...}, {...}]),
use fetchAsJsonList rather than fetchAsJsonMap. The underlying
JSONParser wraps top-level arrays under a synthetic "root" key;
fetchAsJsonList unwraps that envelope for you so the callback receives
the array directly:
There is no separate builder for the ambiguous "object or array" case:
when the response shape isn’t known up-front, use fetchAsJsonMap and
branch on data.get("root") instanceof List.
42.7.2. Typed responses — fetchAsMapped and fetchAsMappedList
Rest.fetchAsJsonMap returns a generic Map<String, Object> that the caller
casts and inspects key by key. Once your DTOs are @Mapped-annotated
(see JSON / XML Object Mapping), fetchAsMapped returns the typed object
directly:
For endpoints that return a list of DTOs, use fetchAsMappedList:
Both builders fall back to the untyped fetchAsJsonMap / fetchAsJsonList
path internally and then route every map element through the build-time
mapper that the @Mapped annotation processor generated. If a mapper isn’t
registered for the requested class (typical cause: the
process-annotations Mojo didn’t run on the class, or the class isn’t
@Mapped-annotated), the callback completes with null data — so always
inspect response.getResponseCode() rather than response.getResponseData()
to differentiate a server error response from the missing-mapper case.
The code in the kitchen sink webservice sample was updated to use this API. The result is shorter and more readable without sacrificing anything.
42.7.3. Rest in practice - twilio
The best way to explain the usage of this API is through a concrete "real world" example. Twilio provides many great telephony-oriented webservices to developers. One of those is an SMS sending webservice which can be useful for things such as "device activation."
To get started you would need to sign up to Twilio and have the following 3 variable values:
String accountSID = "----------------";
String authToken = "---------------";
String fromPhone = "your Twilio phone number here";| You can open a trial Twilio account and it tags all your SMS’s. Notice you would need to use a You based number if you don’t want to pay |
You can now send hello world as an SMS to the end user. Once this is in place sending an SMS through REST is a matter of using the Rest API:
Notice that this is equivalent of this "curl" command:
curl 'https://api.twilio.com/2010-04-01/Accounts/[accountSID]/Messages.json' -X POST \ --data-urlencode 'To=[destinationPhone]' \ --data-urlencode 'From=[fromPhone]' \ --data-urlencode 'Body=Hello World' \ -u [accountSID]:[AuthToken]
That’s pretty cool as the curl command maps almost directly to the Rest API call!
What you do here is actually pretty trivial, you open a connection the api messages URL. You add arguments to the body of the post request and define the basic authentication data.
The result is in JSON form you ignore it since it isn’t that important but it might be useful for error handling. This is a sample response (redacted keys):
{
"sid": "[sid value]",
"date_created": "Sat, 09 Sep 2017 19:47:30 +0000",
"date_updated": "Sat, 09 Sep 2017 19:47:30 +0000",
"date_sent": null,
"account_sid": "[sid value]",
"to": "[to phone number]",
"from": "[from phone number]",
"messaging_service_sid": null,
"body": "Sent from your Twilio trial account - Hello World",
"status": "queued",
"num_segments": "1",
"num_media": "0",
"direction": "outbound-api",
"api_version": "2010-04-01",
"price": null,
"price_unit": "USD",
"error_code": null,
"error_message": null,
"uri": "/2010-04-01/Accounts/[sid value]/Messages/SMe802d86b9f2246989c7c66e74b2d84ef.json",
"subresource_uris": {
"media": "/2010-04-01/Accounts/[sid value]/Messages/[message value]/Media.json"
}
}Notice the error message entry which is null meaning there was no error, if there was an error you’d have a message there or an error code that isn’t in the 200-210 range.
This should display an error message to the user if there was a problem sending the SMS:
42.8. Webservice wizard
The Webservice Wizard can be invoked directly from the plugin. It generates stubs for the client side that allow performing simple method invocations on the server. It also generates a servlet that can be installed on any servlet container to intercept client side calls.
The types of values that can be passed through the webservice wizard protocol have limits, but it’s highly efficient since it’s a binary protocol and extensible through object externalization. All methods are provided both as asynchronous and synchronous calls for the convenience of the developer.


You should have a server setup locally. The example uses Tomcat since it’s trivial and the requirements are modest, but many great Java webservers exist and this should work with all them!





The types of arguments are pretty limited but you can pass an arbitrary Externalizable object which can be "anything" |


You can now open the GameOfThronesServiceServer.java file in the server and it looks like this:
public class GameOfThronesServiceServer {
public static String[] getBookNames() {
// your code goes herenull
return null;
}
public static String[] getBookPovCharacters(String bookName) {
// your code goes herenull
return null;
}
}All you need to do is fill in the code, for this example you will implement the first method for simplicity:
public class GameOfThronesServiceServer {
public static String[] getBookNames() {
return new String[] {
"A Game of Thrones", "A Clash Of Kings", "A Storm Of Swords", "A Feast For Crows",
"A Dance With Dragons", "The Winds of Winter", "A Dream of Spring"
};
}
public static String[] getBookPovCharacters(String bookName) {
// your code goes herenull
return null;
}
}Now lets open the client side code, in the GameOfThronesService.java file you see this
The destination URL needs to point at the actual server which you will recall from the new project creation should include HelloWebServiceWizard. You can fix the URL to:
private static final String DESTINATION_URL = "http://localhost:8080/HelloWebServiceWizard/cn1proxy";You would need to update the host name of the server for running on a device otherwise the device would need to live within your internal network and point to your IP address.
It’s now time to write the actual client code that calls this. Every method you defined above is now defined as a static method within the GameOfThronesService class with two permutations. One is a synchronous permutation that behaves as expected. It blocks the calling thread while calling the server and might throw an IOException if something failed.
This kind of method (synchronous method) is easy to work with since it’s legal to call it from the event dispatch thread and it’s easy to map it to application logic flow.
The second kind of method uses the async JavaScript style callbacks and accepts the callback interface. It returns and doesn’t throw any exception. It will call onSuccess/onError based on the server result.
You can pick either one of these approaches based on your personal preferences. Here you show both uses with the server API:

42.9. Connection request caching
Caching server data locally is a huge part of the advantage a native app has over a web app. This is non-trivial as it requires a delicate balance if you want to test the server resource for changes.
HTTP provides two ways to do that the ETag and Last-Modified. While both are great they’re non-trivial to use and by no definition seamless.
You added an experimental feature to connection request that allows you to set the caching mode to one of 4 states either globally or per connection request:
OFF is the default meaning no caching.
SMART means all get requests are cached intelligently and caching is "mostly" seamless
MANUAL means that the developer handles the actual caching but the system won’t do a request on a resource that’s already "fresh"
OFFLINE will fetch data from the cache and won’t try to go to the server. It will generate a 404 error if data isn’t available
You can toggle these in the specific request by using setCacheMode(CachingMode) and set the global
default using setDefaultCacheMode(CachingMode).
Caching applies to GET operations, it won’t work for POST or other methods |
There are many methods of interest to keep an eye for:
42.9.1. getCachedData()
This returns the cached data. This is invoked to implement readResponse(InputStream) when running offline
or when you detect that the local cache isn’t stale.
The smart mode implements this and will fetch the right data. For example, the manual mode doesn’t store the data and relies on you to do so. In that case you need to return the data you stored at this point and must implement this method for manual mode.
42.9.2. Cacheunmodified()
This is a callback that’s invoked to show a cache hit, meaning that you already have the data.
The default implementation still tries to call all the pieces for compatibility (for example: readResponse).
For example, if this is unnecessary you can override that method with a custom implementation or even a blank
implementation to block such a case.
42.9.3. Purgecache & purgeCacheDirectory
These methods are pretty self-explanatory. Notice one caveat though…
When you download a file or a storage element you don’t cache them and rely on the file/storage element to be present and serve as "cache." When purging you won’t delete a file or storage element you downloaded and thus these might remain.
For example, you do remove the ETag and Last-Modified data so the files might get refreshed the next time around.
42.10. Cached data service
The CachedDataService allows caching data and updating it if the data changed on the server. The download APIs won’t check for update if there is a local cache of the data (for example: URLImage always uses the local copy). This isn’t a bad thing, it’s pretty efficient.
For example, it might be important to update the image if it changed but you still want caching.
The CachedDataService will fetch data if it isn’t cached locally and cache it. When you "refresh" it will send a special HTTP request that will send back the data if it has been updated since the last refresh:
42.11. Externalizable objects
Codename One provides the Externalizable interface, which is like the Java SE Externalizable interface.
This interface allows an object to declare itself as Externalizable for serialization (so an object can be stored in a
file/storage or sent over the network). For example, due to the lack of reflection and use of obfuscation these objects
must be registered with the Util class.
Codename One doesn’t support the Java SE Serialization API due to the size issues and complexities related to obfuscation.
The major objects that are supported by default in the Codename One Externalizable are:
String, Collection, Map, ArrayList, HashMap, Vector, Hashtable, Integer, Double, Float, Byte, Short, Long, Character, Boolean, Object[],
byte[], int[], float[], long[], double[].
Externalizing an object such as h below should work fine:
Map<String, Object> h = new HashMap<>();
h.put("Hi","World");
h.put("data", new byte[] {(byte)1});
Storage.getInstance().writeObject("Test", h);For example, notice that some things aren’t polymorphic for example: if you will externalize a String[] you will get back an Object[]
since String arrays aren’t detected by the implementation.
| The externalization process caches objects so the app will seem to work and fail on restart! |
Implementing the Externalizable interface is important when you want to store a proprietary object. In this case you must register the object with the com.codename1.io.Util class so the externalization algorithm will be able to recognize it by name by invoking:
You should do this early on in the app for example: in the init(Object) but you shouldn’t do it in a static initializer within the object as that might never be invoked! |
An Externalizable object must have a default public constructor and must implement the following 4 methods:
The getVersion() method returns the current version of the object allowing the stored data to change its structure in the future (the version is then passed when internalizing the object). The object ID is a String uniquely representing the object;
it corresponds to the class name (in the example above the Unique Name should be MyClass).
It’s a common mistake to use getClass().getName() to implement getObjectId() and it would seem to work in the simulator. This isn’t the case though!Since devices obfuscate the class names this becomes a problem as data is stored in a random name that changes with every release. |
Developers need to write the data of the object in the externalize method using the methods in the data output stream and read the data of the object in the internalize method for example:
Since strings might be null sometimes you also included convenience methods to implement such externalization. This effectively writes a boolean before writing the UTF to show whether the string is null:
Assuming you added a new date field to the object you can do the following. Notice that a Date is a long value in Java that can be null. For completeness the full class is presented below:
Notice that you need to check for compatibility during the reading process as the writing process always writes the latest version of the data.
42.12. UI bindings & utilities
Codename One provides many tools to simplify the path between networking/IO & GUI. A common task of showing a wait dialog or progress sign while fetching network data can be simplified by using the InfiniteProgress class for example:
The process of showing a progress bar for a long IO operation such as downloading is automatically mapped to the IO stream in Codename One using the SliderBridge class.
| You can simulate network delays and disconnected network in the Simulator menu |
The SliderBridge class can bind a ConnectionRequest to a Slider and effectively show the progress of the download. For example:
Form hi = new Form("Download Progress", new BorderLayout());
Slider progress = new Slider();
Button download = new Button("Download");
download.addActionListener((e) -> {
ConnectionRequest cr = new ConnectionRequest("https://www.codenameone.com/img/blog/new_icon.png", false);
SliderBridge.bindProgress(cr, progress);
NetworkManager.getInstance().addToQueueAndWait(cr);
if(cr.getResponseCode() == 200) {
hi.add(BorderLayout.CENTER, new ScaleImageLabel(EncodedImage.create(cr.getResponseData())));
hi.revalidate();
}
});
hi.add(BorderLayout.SOUTH, progress).add(BorderLayout.NORTH, download);
hi.show();
42.13. Logging & crash protection
Codename One includes a Log API that allows developers to invoke Log.p(String) or Log.e(Throwable) to log information to storage.
As part of the premium cloud features it’s possible to invoke Log.sendLog() to email a log directly to the developer account. Codename One can do that seamlessly based on changes printed into the log or based on exceptions that are uncaught or logged for example:
This code will send a log every 2 minutes to your email if anything was changed. You can place it within the init(Object) method of your application.
For a production application you can use Log.REPORTING_PRODUCTION which will email the log on exception.
42.14. Sockets
At this moment Codename One supports TCP sockets. Server socket (listen/accept) is available on Android and the simulator but not on iOS.
You can check if Sockets are supported using the Socket.isSupported(). You can test for server socket support using Socket.isServerSocketSupported().
To use sockets you can use the Socket.connect(String host, int port, SocketConnection eventCallback) method.
To listen on sockets you can use the Socket.listen(int port, Class scClass) method which will instantiate a
SocketConnection instance (scClass is expected to be a subclass of SocketConnection) for every incoming
connection.
This simple example allows you to create a server and a client assuming the device supports both:
42.15. Properties
In standard Java you have a POJO (Plain Old Java Object) which has getters/setters for example: you can have a
simple Meeting class like this:
public class Meeting {
private Date when;
private String subject;
private int attendance;
public Date getWhen() {
return when;
}
public String getSubject() {
return subject;
}
public int getAttendance() {
return attendance;
}
public void setWhen(Date when) {
this.when = when;
}
public void setSubject(String subject) {
this.subject = subject;
}
public void setAttendance(int attendance) {
this.attendance = attendance;
}
}That’s a classic POJO and it’s the force that underlies JavaBeans and a few tools in Java.
The properties are effectively the getters/setters for example: subject, when etc. But properties have many features
that are crucial:
They can be manipulated in runtime by a tool that had no knowledge of them during compile time
They’re observable - a tool can monitor changes to a value of a property
They can have meta-data associated with them
These features are crucial since properties allow you all kinds of magic for example: hibernate/ORM uses properties to bind Java objects to a database representation, jaxb does it to parse XML directly into Java objects and GUI builders use them to customize UI’s visually.
POJO’s don’t support most of that so pretty much all Java based tools use a lot of reflection & bytecode manipulation. This works but has a lot of downsides for example: say you want to map an object both to the Database and to XML/JSON.
Would the bytecode manipulation collide?
Would it result in duplicate efforts?
And how do you write custom generic code that uses such abilities? Do you need to manipulate the VM?
42.15.1. Properties in Java
These are all abstract ideas, lets look at how you think properties should look in Java and how you can gain from this moving forward.
This is the same class as the one above written with properties:
public class Meeting implements PropertyBusinessObject {
public final Property<Date,Meeting> when = new Property<>("when");
public final Property<String,Meeting> subject = new Property<>("subject");
public final Property<Integer,Meeting> attendance = new Property<>("attendance");
private final PropertyIndex idx = new PropertyIndex(this, "Meeting", when, subject, attendance);
@Override
public PropertyIndex getPropertyIndex() {
return idx;
}
}This looks a bit like a handful, so start with usage which might clarify a few things, then dig into the class itself.
When you used a POJO you did this:
With properties you do this:
Encapsulation
At first glance it looks like you created public fields (which you did) but if you will look at the declaration
you will notice the final keyword:
This means that this code won’t compile:
All setting/getting must happen through the set/get methods and they can be replaced. For example: this is valid syntax that prevents setting the property to null and defaults it to an empty string:
You will discuss the reason for returning the Meeting instance below |
Introspection & observability
Since Property is a common class it’s pretty easy for introspective code to manipulate properties. For example,
it can’t detect properties in an object without reflection.
That’s why you have the index object and the PropertyBusinessObject interface (which defines getPropertyIndex).
The PropertyIndex class provides metadata for the surrounding class including the list of the properties within.
It allows enumerating the properties and iterating over them making them accessible to all tools.
Furthermore all properties are observable with the property change listener. You can write this to instantly print out any change made to the property:
42.15.2. The cool stuff
That’s the simple stuff that can be done with properties, but they can do much more!
For starters all the common methods of Object can be implemented with almost no code:
This is easy thanks to introspection…
You already have some simple code that can convert an object to/from JSON Maps for example: this can fill the property values from parsed JSON:
And vice versa:
You also have a simple ORM solution that maps values to table columns and can create tables. It’s no hibernate but sqlite isn’t big iron so it might be good enough.
Constructors
One of the problematic issues with constructors is that any change starts propagating everywhere. If you have fields in the constructor and you add a new field later you need to keep the old constructor for compatibility.
You added a new syntax:
That’s why every property in the definition needed the Meeting generic and the set method returns the Meeting
instance…
You’re pretty conflicted on this feature and are thinking about removing it.
Without this feature the code would look like this:
Seamless serialization
Suppose you have an object called Contacts which includes contact information for example:
public class Contact implements PropertyBusinessObject {
public final IntProperty<Contact> id = new IntProperty<>("id");
public final Property<String, Contact> name = new Property<>("name");
public final Property<String, Contact> email = new Property<>("email");
public final Property<String, Contact> phone = new Property<>("phone");
public final Property<Date, Contact> dateOfBirth = new Property<>("dateOfBirth", Date.class);
public final Property<String, Contact> gender = new Property<>("gender");
public final IntProperty<Contact> rank = new IntProperty<>("rank");
public final PropertyIndex idx = new PropertyIndex(this, "Contact", id, name, email, phone, dateOfBirth, gender, rank);
@Override
public PropertyIndex getPropertyIndex() {
return idx;
}
public Contact() {
name.setLabel("Name");
email.setLabel("E-Mail");
phone.setLabel("Phone");
dateOfBirth.setLabel("Date Of Birth");
gender.setLabel("Gender");
rank.setLabel("Rank");
}
}Standard Java Objects can be serialized in Codename One by implementing the Codename One Externalizable interface. You also need to register the Externalizable object so the implementation will be aware of it. Codename One business objects are seamlessly Externalizable and you need to register them.
For example: you can do something like this in your init(Object) method:
After you do that once you can write/read contacts from storage if you so want:
This will obviously also work for things like List<Contact> etc.
Seamless SQL storage
Writing SQL code can be tedious. Which is why SQLMap is such an important API for some of you. SQLMap allows CRUD (Create, Read, Update, Delete) operations on the built-in SQLite database using property objects.
If you continue the example from above to show persistence to the SQL database you can do something like this:
In the above code you do the following:
Notice that now altering a created table isn’t possible so if you add a new property you might need to detect that and do an alter call manually |
You can then add entries to the contact table using:
You can update an entry using:
And delete an entry using:
Listing the entries is more interesting:
The arguments for the select method are:
The object type
The attribute by which you want to sort the result (can be null)
Whether sort is ascending
Number of elements to fetch
Page to start with - in this case if you have more than 1000 elements you can fetch the next page using
sm.select(c, c.name, true, 1000, 1)
There are many more configurations where you can fine tune how a specific property maps to a column etc.
What’s still missing
The SQLMap API is simplistic and doesn’t try to be Hibernate/JPA for mobile. Basic things aren’t available now and won’t work. This isn’t necessarily a problem as mobile databases don’t need to be as powerful as server databases.
Relational Mappings/JOIN
Right now you can’t map an object to another object in the database with the typical one-many, one-one etc. relationships that you could do with JPA. The SQLMap API is simplistic and isn’t suited for that level of mapping now.
If there is demand for this it’s something you might add moving forward but your goal isn’t to re-invent hibernate.
Threading
SQLite is sensitive to threading issues on iOS. You ignored the issue of threading and issue all calls in process. This can be a problem for larger data sets as the calls would go on the EDT.
This is something you might want to fix for the generic SQLite API so low-level SQL queries will work with your mapping in a sensible way.
Alter
Right now you don’t support table altering to support updated schemas. This is doable and shouldn’t be too hard to implement so if there is demand for doing it you will probably add support for this.
Complex SQL/Transactions
You ignored functions, joins, transactions and a lot of other SQL capabilities.
You can use SQL directly to use all these capabilities for example: if you begin a transaction before inserting/updating or deleting this will work as advertised but if a rollback occurs your mapping will be unaware of that so you will need to re-fetch the data.
You will notice you mapped autoincrement so you will try to map things that make sense for various use cases, if you’ve such a use case you’d appreciate pull requests and feedback on the implementation.
Caching/Collision
As mentioned above, you don’t cache anything and there might be a collision if you select the same object twice you will get two separate instances that might collide if you update both (one will "win").
That means you need to pay attention to the way you cache objects to avoid a case of a modified version of an object kept with an older version.
Preferences binding
Some objects make sense as global objects, you can use the Preferences API to store that data directly but then you don’t have the type safety that property objects bring to the table. That’s where the binding of property objects to preferences makes sense. For example: say you have a global Settings property object you can bind it to preferences using:
If settings has a property called companyName it would bind into Preferences under the Settings.companyName entry.
You can do some more elaborate bindings such as:
This would customize all entry keys to start with MySettings- instead of Settings.. This would also set the company name entry to company so in this case instead of Settings.companyName you’d have MySettings-company.
UI binding
One of the bigger features of properties are their ability to bind UI to a property. For example: if you continue the sample above with the Contact class, say you have a text field on the form and you want the property (which you mapped to the database) to have the value of the text field. You could do something like this:
That would work but what if you changed the property value, that wouldn’t be reflected in the text field?
Also that works for text field but what about other types for example: numbers, check boxes, pickers etc. This becomes a bit more tedious with those.
Binding makes this all seamless. For example: the code above can be written as:
The cool thing is that this works with many component types and property types almost magically. Binding works by using an adapter class to convert the data to/from the component. The adapter itself works with a generic converter for example: this code:
Seems like the one above but it takes a String that’s returned by the text field and seamlessly converts it to the integer needed by rank. This also works in the other direction…
You can build a UI that would allow you to edit the Contact property in memory:

Binding object & auto commit
You skipped a couple of fact about the bind() method. It has an additional version that accepts a ComponentAdapter which allows you to adapt the binding to any custom 3rd party component. That’s a bit advanced for now but I might discuss this later.
For example, the big thing "skipped" earlier was the return value… bind returns a UiBinding.Binding object when performing the bind. This object allows you to manipulate aspects of the binding specifically unbind a component and also manipulate auto commit for a specific binding.
Auto commit determines if a property is changed instantly or on commit. This is useful for a case where you have an "OK" button and want the changes to the UI to update the properties when "OK" is pressed (this might not matter if you keep different instances of the object). When autocommit is on (the default which you can change through setAutoCommit in the UiBinding) changes reflect instantly, when it’s off you need to explicitly call commit() or rollback() on the Binding class.
commit() applies the changes in the UI to the properties, rollback() restores the UI to the values from the properties object (useful for a "reset changes" button).
Binding also includes the ability to "unbind" this is important if you have a global object that’s bound to a UI that’s discarded. Binding might hold a hard reference to the UI and the property object might create a memory leak.
By using the disconnect() method in Binding you can separate the UI from the object and allow the GC to clean up.
UI generation
Up until now this was pretty cool but if you looked at the UI construction code above you would see that it’s pretty full of boilerplate code. The thing about boilerplate is that it shows where automation can be applied, that’s the exact idea behind the magical "InstantUI" class. This means that the UI above can be generated using this code:
This still carries most of the flexibilities of the regular binding for example: you can still get a binding object using:
You might not have noticed this but in the previous verbose code you had lines like:
You might be surprised to know that this will still work seamlessly without doing anything, as would the picker component used to pick a date…
The picker component implicitly works for date type properties, numeric constraints and numbers are implicitly used for number properties and check boxes are used for booleans.
However, how do you know to use an email constraint for the email property?
You’ve some special case defaults for some common property names, so if your property is named email it will use an email constraint by default. If it’s named url or password etc. It will do the "right thing" unless you explicitly state otherwise. You can customize the constraint for a specific property using something like:
This will override the defaults you’ve in place. The goal of this tool is to have sensible "magical" defaults that "work."
43. Push notifications
Codename One push uses a typed message envelope and an explicit client binding. Your main application class doesn’t implement a push interface. The same application code receives messages from Android, iOS, Huawei devices, and supported web browsers.
You can use the managed BuildCloud service or install an adapter for custom native push. A custom-provider adapter is a low-level escape hatch: it bypasses BuildCloud registration and delivery completely, so your server owns tokens, credentials, targeting, retries, and provider errors.
43.1. Create and configure an application
Open the Codename One Console and select Push. Create one Push application for each logical application and environment. For example, keep production and staging separate so credentials, audiences, and analytics remain isolated.
The Overview page displays the client binding key and one readiness card for every supported provider. Copy the key into PushClient.builder(). Select any readiness card, including a green Ready card, to open Settings on that provider’s tab.

Complete the provider setup tabs you need:
Android / FCM: upload the Firebase service-account JSON file. The server uses the FCM HTTP v1 API.
iOS / APNs: save the Apple team ID, key ID, bundle ID, and
.p8signing key. Token authentication replaces expiring push certificates.Huawei: save the AppGallery Connect application ID and client secret. Add
agconnect-services.jsonto the project.Windows / WNS: save the Package SID and client secret associated with the Store identity.
Web Push: save the VAPID public and private keys and subject.
The managed backend includes WNS delivery for explicit Windows targets. It doesn’t revive or generate bindings for the unsupported UWP port.
Credentials are encrypted in the BuildCloud secrets vault and are write-only. The setup UI shows whether each provider is configured but never reads a secret back. Rotate a credential by saving its replacement.
Cloud builds detect PushClient usage and generate the typed native bootstrap automatically. On Android, include google-services.json, agconnect-services.json, or both. A build with both configurations uses FCM when Google Play Services are available on the device and falls back to Huawei Push Kit otherwise. No provider-selection build hint is required. The android.messagingService=fcm and android.messagingService=huawei hints remain available only when an application intentionally needs to force one provider.
iOS enables push support automatically when PushClient is referenced; set ios.includePush=false only when an installed custom-provider adapter intentionally owns registration.
The Console displays an application key. This key identifies an application during device registration; it isn’t a server API key and doesn’t authorize sending messages. Keep send API keys on your server.

43.2. Bind the client
Create one PushClient in init(), retain it in a field on the main application class, and call register() from start() after showing any permission rationale required by your UX:
private PushClient push;
public void init(Object context) {
push = PushClient.builder("cn1_push_application_key")
.listener(new PushListener() {
@Override
public void onRegistration(PushSubscription subscription) {
Log.p("Push ready on " + subscription.getTransportId());
}
@Override
public void onMessage(PushMessage message) {
if (message.getDeepLink() != null) {
Log.p("Route to " + message.getDeepLink());
}
}
@Override
public void onError(PushError error) {
Log.p(error.getCode() + ": " + error.getMessage());
}
})
.build();
}
public void start() {
push.register();
}
public void stop() {
// Keep the subscription and listener active while the app is paused.
}
public void disableNotifications() {
// Use only for an explicit user opt-out.
push.unregister();
}start() can run more than once during one process lifetime. register() is idempotent, so the example can call it on every start without creating duplicate native registrations. Don’t call unregister() from stop(): it removes the device subscription. Call it only for an explicit user opt-out or account-removal workflow.
Registration is asynchronous. With managed delivery, the framework registers the native token with BuildCloud automatically. PushSubscription exposes the transport identifier, opaque native token, platform, installation ID, expiry, and capability list for diagnostics. Application code shouldn’t parse the token or use it as a user identity.
On Android, the native bootstrap can obtain and persist an FCM or Huawei token before start() installs the PushClient callback. register() replays that persisted token after activating the listener and then asks the provider to refresh it, so the documented init()/start() lifecycle doesn’t lose early registration.
43.2.1. Listener lifecycle and early messages
PushClient.Builder.listener() is mandatory, and build() fails immediately if it’s missing. The client retains that listener until deregistration completes. Codename One doesn’t locate listeners with reflection or Class.forName(): the application must build, retain, and register the client explicitly. Only one PushClient can be active in a process; a second client reports an active_client error instead of replacing the first listener.
Every PushListener and PushRegistrationSink callback runs on the Codename One EDT:
onRegistration()runs after initial native registration and can run again when a provider rotates its token. Replace the previous server-side token for that installation.onMessage()receives one parsed schema-3 envelope. A foreground notification can arrive immediately. A visible background notification normally arrives after the user opens it.onError()reports registration and envelope errors. UsePushError.getCode()for decisions; diagnostic text isn’t a stable contract.
Native ports preserve a cold-start notification until the runtime can deliver it. If the runtime starts before the application calls register(), PushClient keeps a bounded process-local queue and replays it after activation. If the application never registers its client, it has provided no listener and can’t expect application callbacks. Silent/background execution remains subject to each OS’s power and scheduling rules, so refresh authoritative state whenever the application resumes.
43.3. Build a message
PushMessage is the canonical message model on both sides of the wire:
PushMessage message = PushMessage.builder()
.title("Order shipped")
.body("Order 4815 is on its way")
.deepLink("myapp://orders/4815")
.imageUrl("https://example.com/orders/4815.png")
.collapseKey("order-4815")
.ttlSeconds(3600)
.data("orderId", "4815")
.build();Common fields have consistent meanings on every provider. Add provider-specific settings under the platform object only when the common model isn’t sufficient. Unknown settings are ignored by unrelated providers.
{
"schema": 3,
"title": "Order shipped",
"body": "Order 4815 is on its way",
"deepLink": "myapp://orders/4815",
"collapseKey": "order-4815",
"ttl": 3600,
"data": { "orderId": "4815" },
"platform": {
"apns": { "badge": 3, "sound": "default", "interruptionLevel": "time-sensitive" },
"fcm": { "channelId": "orders", "priority": "high" },
"huawei": { "channelId": "orders", "importance": "HIGH" },
"wns": { "type": "toast" },
"web": { "urgency": "high" }
}
}Don’t place secrets or irreplaceable data in a notification. Providers, operating systems, and lock-screen UI may retain or expose payloads.
43.4. Send from a server
Create an API key with the push scope in the Console. Submit a typed message and one or more provider targets to POST /api/v3/push/messages:
curl -X POST https://cloud.codenameone.com/api/v3/push/messages \
-H 'Authorization: Bearer YOUR_SERVER_API_KEY' \
-H 'Content-Type: application/json' \
-d '{
"appId": "APPLICATION_ID",
"targets": [
{"provider":"fcm", "token":"OPAQUE_DEVICE_TOKEN"},
{"provider":"apns", "token":"OPAQUE_DEVICE_TOKEN"}
],
"message": {
"schema":3,
"title":"Order shipped",
"body":"Order 4815 is on its way",
"data":{"orderId":"4815"}
}
}'A successful admission returns HTTP 202 with durable delivery IDs. Invalid targets are deactivated when the provider identifies them as permanent failures.
The complete request, response, authentication, error, target, and message schemas are in the Push sending OpenAPI 3.0 specification. Import that file into Swagger UI, an OpenAPI code generator, or an API client instead of reproducing DTOs from this chapter.
Use the Console for operator-driven messages, stored audiences, campaigns, analytics, and automations.
43.5. Build audiences in the Console
Managed audiences are application-scoped. They don’t contain copied device tokens. A saved segment stores a dynamic filter, and BuildCloud resolves that filter against active subscriptions when a campaign launches.
Your authenticated server assigns an external user ID and tags to an installation with PUT /api/v3/push/apps/{appId}/installations/{installationId}. Tags should be stable application facts such as subscription=active, region=emea, role=technician, or testUser=true. Don’t let an untrusted client grant itself a privileged tag.
{
"externalUserId": "customer-4815",
"tags": {
"subscription": "active",
"region": "emea",
"testUser": "false"
}
}Open Push > Audience. The tag and value pickers contain values discovered from current active subscriptions for the selected application. Choose an optional platform, choose one tag rule, enter a segment name, and select Save segment. The new segment appears immediately under Saved segments with its current recipient estimate. It also becomes available in the Messages recipient picker.

Segments are evaluated at send time. Changing a subscription’s tags changes future membership without editing the segment. A count is an estimate of the current state; registrations, subscription removals, and tag updates can change it before admission.
For a safe rollout, tag internal devices with testUser=true, create a test-user segment, and send the message there first. Create the production segment only from server-controlled tags.
43.6. Send a message from the Console
Open Push > Messages and complete the three numbered sections:
Audience: choose All subscribed devices or a saved segment. The Console displays the current recipient estimate. Individual provider tokens aren’t entered in this workflow.
Message: enter a notification title and message. A visible notification requires message text. For a silent notification, enable Silent / data-only notification and provide an additional-data key and value. The Console builds valid JSON; operators don’t paste JSON into the primary composer.
Delivery: choose how long providers may retain an undelivered message. Console messages use safe cross-platform defaults and enter the durable queue immediately.

Select Queue message only after checking the audience name and estimate. BuildCloud creates the campaign, resolves the segment, and admits the recipients to the durable delivery queue. The provider may accept a notification that the device never displays, so inspect Push > Analytics for provider acceptance and failures without treating acceptance as device delivery.
43.7. Event automations
An automation is an enabled rule containing trigger.event, a schema-3 message, an optional audience, and an optional delaySeconds. If no audience is stored in the rule, the event must identify an externalUserId or installationId. Text fields in the message can insert event properties with ${event.propertyName}.
{
"enabled": true,
"trigger": {"event": "order.ready"},
"delaySeconds": 0,
"message": {
"schema": 3,
"title": "Order update",
"body": "Order ${event.orderId} is ready"
}
}Your server triggers enabled rules with POST /api/v3/push/apps/{appId}/events using a push-scoped API key:
{
"name": "order.ready",
"externalUserId": "customer-4815",
"properties": {"orderId": "4815"}
}Immediate matches enter the durable delivery queue. Delayed matches become scheduled campaigns, so restarts don’t lose them. Automations are intentionally push rules, not a general-purpose customer journey or analytics product.
43.8. Widgets and live surfaces
A push can publish widget content or update a live activity before the regular listener receives the message. The surface object uses one of these operations:
{
"schema": 3,
"silent": true,
"surface": {
"operation": "widget",
"kind": "order-status",
"timeline": "{...serialized widget timeline...}"
}
}For a live activity use live-update or live-end with id, serialized state, and optional dismissImmediately. Unsupported surfaces are ignored. A surface command runs when the Codename One runtime receives the envelope. On platforms that don’t start application code for a background push, the native queue preserves the command and applies it on the next start or resume. Applications must therefore refresh stale surface state during foreground activation too.
43.9. Use an application-owned push server
A custom server is a low-level alternative to managed push; it doesn’t reuse the BuildCloud protocol at a different endpoint. A CN1Lib implements PushTransport around the private provider’s native SDK. It obtains native registration material, reports token rotation, and forwards incoming data as the canonical schema-3 JSON envelope. A matching PushRegistrationSink stores and removes the subscription on your server:
// companyTransport is supplied by the native CN1Lib.
// listener is the application's normal, non-null PushListener.
PushClient client = PushClient.builder("private-app-id")
.transport(companyTransport)
.registrationSink(new PushRegistrationSink() {
@Override
public void registered(PushSubscription value) {
Log.p("Send the subscription to the company server");
}
@Override
public void unregistered(PushSubscription value) {
Log.p("Remove the subscription from the company server");
}
})
.listener(listener)
.build();When a PushTransport implementation is present, PushClient never contacts BuildCloud. Your implementation owns these responsibilities:
getId()returns a stable provider ID that your server understands.isSupported()checks whether the SDK can operate on this device.register()invokesCallback.registered()with aPushSubscription, then reports later token rotations through the same callback.unregister()removes the provider subscription and invokesCallback.unregistered()when complete.Incoming native messages call
Callback.message()with one complete schema-3 envelope. Don’t call the application listener directly and don’t invent a second payload format.Registration or transport failures call
Callback.failed(). The callback is thread-safe;PushClientmoves application-facing callbacks to the EDT.
The registration sink should asynchronously insert or update the subscription by installationId on your server and replace its token when it rotates. The server then sends through your provider’s native API. It must preserve the schema-3 envelope so the same PushListener, deep-link handling, and surface commands work in managed and custom-server modes.
The application still follows the normal lifecycle: retain one client, call register() from start(), and reserve unregister() for an actual opt-out. This custom integration doesn’t introduce reflection or automatic listener discovery.
43.10. Testing delivery behavior
Hosted CI has no installed application, OS push daemon, permission state, or physical device, so it can’t prove provider-to-device delivery. Codename One tests at the lowest controllable boundary instead. PushClientTransportTest injects a fake native transport and covers:
foreground, background, force-stopped, and cold-start delivery;
notification tap, action, dismissal, and deep-link routing;
permission granted, denied, and later changed in system settings;
token rotation, reinstall, expiry, logout, and multiple installations per user;
silent delivery and simulated constrained-state replay;
collapse keys, TTL expiry, Unicode, maximum payloads, images, and provider errors;
queued widget and live-activity updates replayed at the native/runtime seam;
retry idempotency and dead-letter behavior.
The JavaScript contract executes the real service-worker source with mocked browser clients and notification APIs. BuildCloud has a separate local suite using mocked provider HTTP responses for compatibility translation, credentials, durable queue behavior, retries, and automations. Physical-device sends are optional release diagnostics rather than a CI or nightly requirement. Provider acceptance isn’t proof of device delivery.
44. Notifications and Background Execution
Codename One exposes a cross-platform API for rich local notifications, runtime notification permission, notification channels, constraint-aware background work, foreground services, deferrable background processing, receiving content shared from other apps, and push topic subscriptions. Each capability degrades on platforms that can’t support it — calls become documented no-ops rather than errors — and the JavaSE simulator implements them so you can exercise the flows without a device.
Because these features build on platform-specific behavior, every section below lists the support per platform. In the matrices: Yes = fully supported, Partial = supported with documented limitations, No-op = the call is accepted but does nothing, Sim = exercised in the simulator.
44.1. Notification permission
On iOS, and on Android 13+ (POST_NOTIFICATIONS), an app must obtain permission before
its notifications are shown. Request it through Display:
NotificationPermissionRequest req = new NotificationPermissionRequest()
.provisional(true) // iOS: deliver quietly without an explicit prompt
.timeSensitive(true); // iOS: allow the time-sensitive interruption level
Display.getInstance().requestNotificationPermission(req, result -> {
if (result.isGranted()) {
// schedule notifications
}
AuthorizationLevel level = result.getAuthorizationLevel();
});NotificationPermissionResult.getAuthorizationLevel() returns an AuthorizationLevel
enum (NOT_DETERMINED, DENIED, AUTHORIZED, PROVISIONAL, EPHEMERAL). The values
are ordered from least to most permissive, so isGranted() is "more permissive than
DENIED." The callback is delivered on the EDT.
| Request option | iOS | Android | Simulator |
|---|---|---|---|
alert / sound / badge | Yes | Implied by POST_NOTIFICATIONS | Granted |
provisional | Yes (iOS 12+) | No-op | Granted |
timeSensitive | Yes (iOS 15+, needs entitlement) | No-op | Granted |
critical | Yes (needs Apple entitlement) | No-op | Granted |
carPlay / announcement | Yes | No-op | Granted |
The timeSensitive and critical options require an Apple capability on the App ID.
Enable injection of the matching entitlement with the ios.timeSensitiveNotifications=true
and ios.criticalAlerts=true build hints (they’re opt-in because an entitlement the
provisioning profile doesn’t carry breaks code signing).
44.2. Local notifications
LocalNotification is scheduled through Display.scheduleLocalNotification(…) as
before; the bean has been extended with fluent, backward-compatible setters:
When the user taps an action, the selected action id (and any quick-reply text) are
delivered through com.codename1.push.PushContent — getActionId(), getActionTitle()
and getTextResponse() — before your LocalNotificationCallback.localNotificationReceived(id)
runs, so push and local notification actions are handled identically.
| Capability | iOS | Android | Simulator |
|---|---|---|---|
title / body / badge / sound | Yes | Yes | Sim (panel) |
image attachment | Yes (UNNotificationAttachment) | Yes (BigPicture) | Sim (thumbnail) |
action buttons | Yes (UNNotificationAction) | Yes | Sim (buttons) |
quick-reply input action | Yes (UNTextInputNotificationAction) | Yes (RemoteInput) | Sim (text field) |
grouping | Yes (thread identifier) | Yes (group + summary) | Partial |
progress (ongoing) | No-op | Yes | Sim (progress bar) |
full-screen intent | No-op | Yes (needs permission, see hints) | No-op |
time-sensitive | Yes (iOS 15+) | Approximated (category + priority) | Sim |
messaging / conversation style | Partial | Yes (MessagingStyle) | Sim |
custom view | Notification content extension | RemoteViews | Sim (render) |
44.2.1. Resource names for sound, image and action icons
These string parameters are platform resource names, not numeric ids (Codename One has
no R.drawable constants). They’re resolved at runtime per platform:
| Parameter | What to provide | Android resolution | iOS resolution |
|---|---|---|---|
| a file whose name starts with |
|
|
| image path placed in the app root | loaded from |
|
| a drawable name bundled in |
| not displayed |
The file extension is optional for the action icon and is ignored. iOS notification action buttons don’t render icons, so the icon value is ignored there.
44.3. Notification channels (Android O+)
Channels let the user control importance, sound, vibration, lights, lock screen
visibility and badge display for a group of notifications. Build and register one at startup,
then reference it from a notification with setChannelId(…):
Channels are an Android concept. On iOS and the simulator register() is a no-op (the
simulator stores the channel so its name can be shown in the notification panel); the
channel id you assign is still carried so the notification behaves consistently.
44.4. Constraint-aware background work
BackgroundWork schedules deferrable work that the OS runs when its constraints are met.
Implement BackgroundWorker in a class with a public no-argument constructor (it’s
reconstructed after a cold launch — pass state through the input data, not fields):
| iOS | Android | Simulator | |
|---|---|---|---|
backend | BGTaskScheduler (iOS 13+) | JobScheduler | Timer |
requiresNetwork / unmetered | Yes | Yes | Toggle in Simulate menu |
requiresCharging | Yes (requiresExternalPower) | Yes | Toggle |
requiresIdle / batteryNotLow | No-op | Yes | Toggle |
periodic | Approximated (resubmit) | Yes (>= 15 min) | Yes |
BackgroundTask.scheduleProcessing(id, earliestBeginDate, requiresNetwork, requiresPower,
runnable) is a one-shot variant for occasional maintenance work. On iOS the identifiers
must be declared via the ios.backgroundProcessingIds build hint (comma separated,
default <packageName>.processing); the build also adds the processing UIBackgroundMode
and links BackgroundTasks.framework automatically.
44.5. Foreground service (Android)
ForegroundService runs a long task while a persistent notification is shown:
| Android | iOS | Simulator | |
|---|---|---|---|
persistent-notification service | Yes | No (best-effort background window + notification) | Sim (status indicator) |
When the app references ForegroundService the build registers the service and injects
FOREGROUND_SERVICE plus the per-type FOREGROUND_SERVICE_<TYPE> permission (Android 14).
Override the type with the android.foregroundServiceType build hint (default dataSync).
44.6. Receiving shared content
Override onReceivedSharedContent(SharedContent) on your Lifecycle subclass to receive
text, URLs, files or images shared into your app from other apps:
| Android | iOS | Simulator | |
|---|---|---|---|
receive shared content | Yes (SEND / SEND_MULTIPLE) | Yes (share extension + App Group) | Sim ("Send shared content") |
On Android, declare the accepted MIME types with the android.shareFilter build hint
(comma separated, for example text/plain,image/*); the build registers the share-receiver
activity. On iOS this reuses the share-extension authoring pipeline; set the
ios.shareAppGroup build hint to the App Group the extension writes to. File and image
items are copied into Codename One FileSystemStorage so your code is platform neutral.
44.7. Push topics
Push.subscribeToTopic("news") / unsubscribeFromTopic("news") subscribe the device to a
fan-out topic.
| Android | iOS | |
|---|---|---|
topic subscribe / unsubscribe | Yes (Firebase Cloud Messaging) | No-op (raw APNs has no topics; fan out server-side) |
Server-side topic delivery is handled by the Codename One push server.
44.8. Simulator
The JavaSE simulator implements all the above so you can develop without a device. Use the Simulate → Notifications and Background menu to toggle the background constraints (network / charging / idle / battery), run scheduled work immediately, inspect registered channels, and inject shared content. Posted notifications appear in a panel at the top right; tapping an action (or submitting a quick-reply) routes back through your callback exactly as on device.
45. Calendar integration
The com.codename1.calendar package provides scheduling rather than just an
"add event" shortcut. It represents calendars, events, task/reminders,
recurrence, attendees, alarms, free/busy intervals, attachments, conference
links, paging, incremental synchronization, and explicit edit conflicts.
The API is capability based. Don’t branch on the platform name. Ask the source what it can do:
LocalCalendarSource local = LocalCalendarSource.getInstance();
CalendarCapabilities capabilities = local.getCapabilities();
if (capabilities.supports(CalendarCapability.READ_EVENTS)) {
local.requestAuthorization(CalendarAccess.EVENTS_READ_ONLY).ready(status -> {
if (status == CalendarAuthorizationStatus.FULL) {
local.queryEvents(new CalendarQuery()
.setCalendarId("primary")
.setStartTime(Instant.now()))
.ready(page -> page.getItems().forEach(System.out::println));
}
});
}LocalCalendarSource is implemented with Android’s Calendar Provider and
Apple EventKit on iOS and Mac Catalyst. The simulator supplies an isolated,
in-memory source so tests never modify the developer’s real calendar. A port
that has no local calendar service returns an empty capability set. Online
sources and .ics import/export remain available on every port, including
JavaScript and Linux.
| Target | Built-in local source | Portable alternatives |
|---|---|---|
Android | Calendar Provider events | Google, Microsoft, CalDAV, and |
iOS and Mac Catalyst | EventKit events and reminders | Google, Microsoft, CalDAV, and |
Codename One simulator | Isolated in-memory source | Google, Microsoft, CalDAV, and |
Win32, native macOS desktop, Linux, and JavaScript | No built-in local source; the capability set is empty | Google, Microsoft, CalDAV, and |
This API is a clean replacement for the old CN1Calendar integration. New
code shouldn’t mix objects or identifiers from the two APIs.
45.1. Creating an event
All-day values use CalendarDateTime.allDay(LocalDate). Timed values use
ZonedDateTime (or the Instant and ZoneId convenience factory). Alarms use
Duration, and query ranges and absolute timestamps use Instant. The API
uses java.time instead of defining parallel date, time-zone, or duration
types. Keeping all-day and timed values separate avoids shifting an
all-day event when it crosses a time-zone boundary.
CalendarEvent event = new CalendarEvent()
.setCalendarId(calendarId)
.setTitle("Architecture review")
.setStart(CalendarDateTime.instant(start, ZoneId.of("Europe/Paris")))
.setEnd(CalendarDateTime.instant(end, ZoneId.of("Europe/Paris")))
.setRecurrence(new CalendarRecurrenceRule()
.setFrequency(CalendarRecurrenceRule.Frequency.WEEKLY)
.addDayOfWeek(2))
.addAttendee(new CalendarAttendee()
.setName("Ari")
.setEmail("[email protected]"))
.addAlarm(new CalendarAlarm().setTimeBefore(Duration.ofMinutes(15)));
local.saveEvent(event, CalendarMutationScope.ALL).ready(saved -> {
Log.p("Created " + saved.getId());
});The version returned by a source is an optimistic-concurrency token. Pass
the returned object to saveEvent() or its version to a delete method.
A stale token produces CalendarError.CONFLICT instead of overwriting a
newer server edit.
45.2. Online sources
Online sources work on all ports and use the application’s OAuth client. They never embed a client secret and never persist credentials implicitly.
OidcClient.discover("https://accounts.google.com").ready(oidc -> {
oidc.setClientId(clientId)
.setRedirectUri(redirectUri)
.setScopes(GoogleCalendarSource.SCOPE_CALENDAR,
GoogleCalendarSource.SCOPE_TASKS)
.authorize().ready(tokens -> {
CalendarSource google = new GoogleCalendarSource(
new OidcCalendarTokenProvider(oidc, tokens));
CalendarManager.getInstance().registerSource(google);
});
});GoogleCalendarSource covers Google Calendar and Google Tasks.
MicrosoftCalendarSource covers Microsoft Graph calendars and Microsoft To
Do. Both expose provider paging and delta tokens through CalendarPage and
retry once with a refreshed token after HTTP 401.
For CalDAV, pass the account’s calendar-home URL and an authentication strategy:
CalendarSource caldav = new CalDavCalendarSource(
"work", "Work CalDAV", calendarHomeUrl,
CalDavAuthentication.digest(username, password));CalDavAuthentication.basic(), bearer(), and digest() are supported.
Prefer Bearer or Digest over Basic unless Basic is protected by HTTPS. Calendar
discovery filters collections by their advertised VEVENT and VTODO
component support. Check the result of each asynchronous operation as servers
can restrict individual collections further.
45.3. Import and export
ICalendarCodec reads and writes RFC 5545 VEVENT, VTODO, VALARM,
attendees, recurrence rules, URI attachments, conference URIs, all-day values,
and time zones. Unknown X- properties are retained in provider data.
String ics = ICalendarCodec.writeEvent(event);
CalendarEvent imported = ICalendarCodec.readEvent(ics);45.4. Change notifications and offline synchronization
The cross-platform guarantee is intentionally pull based:
Local sources can emit
CalendarChangethroughaddChangeListener()when the operating system reports a local store change.Online providers return a sync/delta token. Store it and pass it in the next
CalendarQuery. The API doesn’t register provider webhooks.
Listeners run on the Codename One EDT. Treat a RESET change as an instruction
to query again; it doesn’t promise one callback per underlying OS edit.
Offline mutation storage is opt-in. Supply a CalendarCache to
CalendarSyncEngine, queue edits, and call sync() yourself or from the
platform’s background-work callback. StorageCalendarCache stores calendar
data and pending mutations, never credentials. Conflicts remain paused until
the application chooses KEEP_LOCAL, KEEP_REMOTE, or MERGED.
CalendarSyncEngine sync = new CalendarSyncEngine(
google, new StorageCalendarCache("google-account-1"));
sync.queueEventSave(event, CalendarMutationScope.ALL);
sync.sync().ready(result -> {
for (CalendarConflict conflict : result.getConflicts()) {
// Present both versions, then call resolveConflict(...).
}
});45.5. Permissions and build hints
Calling LocalCalendarSource.getInstance(),
CalendarManager.getLocalSource(), CalendarManager.getSources(), or
Display.getLocalCalendarSource() is the builder signal for local calendar
integration. Android builds add
READ_CALENDAR and WRITE_CALENDAR; iOS and Mac Catalyst builds add EventKit
and calendar/reminder privacy strings. You can replace the default user-facing
strings with:
ios.NSCalendarsFullAccessUsageDescription=Explain why events are needed ios.NSCalendarsWriteOnlyAccessUsageDescription=Explain why creating events is needed ios.NSRemindersFullAccessUsageDescription=Explain why reminders are needed
The built-in Win32 source currently reports unavailable. An
application-supplied native integration can explicitly opt into the standard
MSIX uap:appointments capability with:
windows.msix=true windows.calendar.restrictedCapability=true
Always check getCapabilities() and getAuthorizationStatus() at runtime.
Manifest declarations make a request possible; they don’t mean the user or
provider granted it.
46. External Surfaces: Widgets and Live Activities
Home-screen widgets and live activities answer the same developer question: how to keep a live piece of information outside the app. Codename One models both as one concept — an external surface — under the com.codename1.surfaces package. A widget is persistent, user-placed and content-driven: the weather, the next meeting, the delivery status on the home screen. A live activity is transient, app-started and progress-driven: the delivery that’s out right now, a running timer, a live score on the iOS lock screen and Dynamic Island, an ongoing Android notification, a floating desktop pill. Both share the same layout model, serialization, state mechanism, and action model.
The simulator renders every surface you publish in a dedicated preview window, so the full loop runs on your desktop with no device:

46.1. The dead-process rule
Surfaces render while your app process may not be running. Everything you hand this API is therefore turned into plain data at publish time: layouts serialize to a compact JSON descriptor, images are encoded to named PNG blobs, and "callbacks" are string action ids that open the app and reach your handler on the EDT. Layout text embeds ${key} placeholders resolved from a per-entry state map, so a content change is a cheap re-publish of data, not a new layout.
This rule explains everything unusual about the API. You can’t attach a listener to a widget — the process that renders it may have nothing to call back into. You can’t hand it a Component — there is no Codename One renderer on the other side. What you can do is describe the surface declaratively and let each platform’s native renderer (SwiftUI on iOS, RemoteViews on Android, a rasterizer on desktop) draw it.
46.2. Getting started
The build injects the native plumbing (a WidgetKit extension and App Group on iOS, widget receivers on Android) when your bytecode references com.codename1.surfaces. Apps that never touch the package get none of it, and on ports without surface support every entry point is an inert no-op.
Platform widget galleries are compiled into the native app, so widget kinds must be known at build time. Declare them in a surfaces.json resource (in src/main/resources of a Maven project, next to your icons):
{
"liveActivities": true,
"kinds": [
{
"id": "delivery_status",
"name": "Delivery",
"description": "Track your order",
"iosFamilies": ["systemSmall", "systemMedium"],
"androidMinWidthDp": 180,
"androidMinHeightDp": 60
},
{
"id": "analog_clock",
"name": "Analog Clock",
"description": "A vector clock face",
"iosFamilies": ["systemSmall"],
"androidMinWidthDp": 110,
"androidMinHeightDp": 110
}
]
}The id values must match [a-z][a-z0-9_]*. The iosFamilies list accepts both the portable names (small, medium, large, lockscreen) and the WidgetKit spellings (systemSmall, systemMedium, systemLarge, accessoryRectangular); when omitted, all three home-screen sizes are offered. The androidMinWidthDp / androidMinHeightDp / androidResizeMode fields fill the Android provider metadata. An optional top-level appGroup pins the iOS App Group id, and "liveActivities": true enables the live activity plumbing.
At runtime, mirror the manifest by registering each kind in your app’s init():
Surfaces.registerWidgetKind(new WidgetKind("delivery_status")
.setDisplayName("Delivery")
.setDescription("Track your order")
.addSupportedSize(WidgetSize.SMALL)
.addSupportedSize(WidgetSize.MEDIUM));A widget renders a timeline: a shared layout plus dated entries whose state maps fill the layout’s ${key} placeholders. The OS flips entries on schedule without waking your app. This publishes a delivery tracker that advances through four states:
long now = System.currentTimeMillis();
long eta = now + 4 * 60000L;
WidgetTimeline timeline = new WidgetTimeline()
.setContent(buildDeliveryLayout())
.addEntry(new Date(now), deliveryState("Preparing your order", eta, 0.1f))
.addEntry(new Date(now + 60000L), deliveryState("Out for delivery", eta, 0.4f))
.addEntry(new Date(now + 3 * 60000L), deliveryState("Arriving now", eta, 0.9f))
.addEntry(new Date(eta), deliveryState("Delivered", eta, 1f))
.setReloadPolicy(WidgetTimeline.RELOAD_AT_END);
Surfaces.publish("delivery_status", timeline);The layout itself is a small tree of nodes with shared styling (padding, background, corner radius, alignment, weight, size, action):
private SurfaceNode buildDeliveryLayout() {
Map<String, Object> params = new HashMap<>();
params.put("orderId", "CN1-12345");
return new SurfaceColumn().setSpacing(6).setPadding(12)
.add(new SurfaceRow().setSpacing(10)
.add(new SurfaceImage(courierAvatar)
.setSize(40, 40).setCornerRadius(20))
.add(new SurfaceColumn().setSpacing(2).setWeight(1)
.add(new SurfaceText("${status}")
.setFontSize(15)
.setFontWeight(SurfaceFontWeight.SEMIBOLD)
.setMaxLines(1))
.add(new SurfaceDynamicText(
SurfaceDynamicText.STYLE_TIMER_DOWN, "eta")
.setFontSize(24)
.setFontWeight(SurfaceFontWeight.BOLD)
.setColor(SurfaceColor.ACCENT))))
.add(new SurfaceProgress(SurfaceProgress.STYLE_LINEAR)
.setValueState("progress")
.setColor(SurfaceColor.rgb(ACCENT_COLOR)))
.setAction("open_order", params);
}
private Map<String, Object> deliveryState(String status, long eta, float progress) {
Map<String, Object> state = new HashMap<>();
state.put("status", status);
state.put("eta", eta);
state.put("progress", progress);
return state;
}Three things in this layout carry the model’s weight. SurfaceText renders ${status} from the entry state, so updates ship a tiny state map instead of a layout. SurfaceDynamicText with STYLE_TIMER_DOWN is a countdown the OS animates on its own clock — the ETA ticks every second with zero app wake-ups. SurfaceProgress reads its value from the progress state key. The setAction call at the root makes a tap anywhere on the widget open the app and deliver the open_order action.
Surfaces.publish(…) is callable from any thread and never blocks on the EDT, which matters for background refresh later in this chapter.
A complete runnable example lives in Samples/samples/SurfacesSample together with its surfaces.json:

46.2.1. Previewing in the simulator
Open Widgets > Widgets Preview in the simulator. The window lists your registered kinds, renders the published timeline of the selected kind at any size in light or dark mode, flips timeline entries on schedule, and ticks countdowns exactly as a home-screen widget would. The mock Dynamic Island at the bottom renders running live activities. Clicks map through to your action handler, and a desktop (non-simulator) build renders the same publishes as floating widget windows pinned from a tray icon.
46.3. The node catalog
The catalog is kept small: a set of nodes every platform can render natively. Android app widgets (RemoteViews) are the constrained platform, so the catalog is designed to that floor and degrades as follows:
| Node | iOS (SwiftUI) | Android (RemoteViews) | Notes |
|---|---|---|---|
|
|
| Weight maps to |
|
|
| Child alignment via a 9-way enum |
|
|
| Android maps light/regular/medium weights to regular, semibold/bold to bold |
|
|
| Ticks natively on both |
|
|
| Native on both |
| Native | Static text | Android refreshes it on the next update only |
|
|
| Named PNG blobs, content-hash dedup |
|
|
| Value 0..1 or a state key |
|
| Falls back to linear | Android widgets lack determinate circular progress |
| Native animation | Frozen at each refresh | iOS-only nicety |
| SwiftUI | Bitmap rendered in-process | Large vector nodes cost bitmap budget on Android |
|
| Weighted | Flexible gap |
Corner radius |
| Background drawable | May render square below Android 12 |
Node action |
|
| Small iOS widgets honor only the root action |
Descriptors are limited to 8 nesting levels. Keep payloads (JSON plus images) comfortably under 200kb — the iOS widget extension runs in about 30mb of memory, and Android parcels rendered widgets over a 1mb binder transaction.
46.4. Vector widgets
SurfaceVector covers the widgets the template catalog can’t express — clocks, gauges, dials — with a retained list of vector drawing operations (fills, strokes, lines, arcs, text, rotation groups) replayed natively by every renderer. Rotation groups can read their angle from a state key, which turns a static drawing into a data-driven one.
The classic example is an analog clock. The face is resolution independent — the 200x200 view box scales to whatever size the widget gets:
private SurfaceNode buildClockFace() {
SurfaceVector face = new SurfaceVector(200, 200)
.fillEllipse(100, 100, 96, 96, SurfaceColor.rgb(0xfffafafa, 0xff1c1c1e))
.strokeEllipse(100, 100, 96, 96, 4, SurfaceColor.rgb(ACCENT_COLOR));
for (int hour = 0; hour < 12; hour++) {
boolean quarter = hour % 3 == 0;
face.beginRotation(hour * 30f, 100, 100)
.line(100, 10, 100, quarter ? 24 : 18, quarter ? 5 : 3, SurfaceColor.LABEL)
.endRotation();
}
face.beginRotation("hourAngle", 100, 100)
.line(100, 100, 100, 52, 8, SurfaceColor.LABEL)
.endRotation()
.beginRotation("minuteAngle", 100, 100)
.line(100, 100, 100, 26, 5, SurfaceColor.rgb(ACCENT_COLOR))
.endRotation()
.fillEllipse(100, 100, 6, 6, SurfaceColor.rgb(ACCENT_COLOR));
return face;
}Angles use the clock convention: degrees, 0 at 12 o’clock, clockwise positive. The face publishes once; 60 per-minute timeline entries carry only the two angle values, and the OS flips them on schedule. The clock stays correct for an hour with zero app wake-ups:
WidgetTimeline timeline = new WidgetTimeline()
.setContent(buildClockFace())
.setReloadPolicy(WidgetTimeline.RELOAD_AT_END);
Calendar c = Calendar.getInstance();
c.set(Calendar.SECOND, 0);
c.set(Calendar.MILLISECOND, 0);
long minuteStart = c.getTimeInMillis();
int baseMinutes = c.get(Calendar.HOUR_OF_DAY) * 60 + c.get(Calendar.MINUTE);
for (int m = 0; m < 60; m++) {
int totalMinutes = baseMinutes + m;
Map<String, Object> state = new HashMap<>();
// clock convention: degrees, 0 = 12 o'clock, clockwise positive
state.put("minuteAngle", totalMinutes % 60 * 6f);
state.put("hourAngle", totalMinutes % 720 * 0.5f);
timeline.addEntry(new Date(minuteStart + m * 60000L), state);
}
Surfaces.publish("analog_clock", timeline);
46.5. Live activities
A live activity is started explicitly from the app and updated by pushing fresh state. The descriptor carries the main content (the lock screen presentation on iOS, the notification layout on Android) plus the Dynamic Island regions: setCompactLeading / setCompactTrailing for the pill shown around the camera cutout, setMinimal for the detached circle when several activities run, and setExpandedLeading / setExpandedTrailing / setExpandedCenter / setExpandedBottom for the long-press expanded card.
long eta = System.currentTimeMillis() + 4 * 60000L;
LiveActivityDescriptor descriptor = new LiveActivityDescriptor("delivery")
.setContent(buildDeliveryLayout())
.setCompactLeading(new SurfaceImage(courierAvatar)
.setSize(24, 24).setCornerRadius(12))
.setCompactTrailing(new SurfaceDynamicText(
SurfaceDynamicText.STYLE_TIMER_DOWN, "eta")
.setFontSize(14).setColor(SurfaceColor.ACCENT))
.setExpandedCenter(new SurfaceText("${status}")
.setFontSize(16).setFontWeight(SurfaceFontWeight.SEMIBOLD))
.setExpandedBottom(new SurfaceProgress(SurfaceProgress.STYLE_LINEAR)
.setValueState("progress")
.setColor(SurfaceColor.rgb(ACCENT_COLOR)))
.setTint(SurfaceColor.rgb(ACCENT_COLOR));
activity = LiveActivity.start(descriptor,
deliveryState("Out for delivery", eta, 0.25f));The returned handle is inert (isActive() returns false) on platforms without live activity support, so no platform checks are needed. Updates and the final state are plain state maps interpolated into the descriptor persisted at start time:
activity.update(deliveryState("Arriving now", eta, 0.9f));
// ... and when the delivery completes:
activity.end(deliveryState("Delivered", System.currentTimeMillis(), 1f));The simulator preview renders the running activity as a mock Dynamic Island pill plus the expanded card:

On iOS the activity appears on the lock screen and, on supported devices, inside the Dynamic Island (ActivityKit requires iOS 16.1 or newer). On Android it lowers to an ongoing notification that renders the same content; on Android 13 and newer the first start(…) prompts for the notification permission, which the build declares for you, and isSupported() reports false once the user has turned that prompt down twice or has switched notifications off for the app. On desktop it appears in the simulator preview or as a floating window.
46.6. Actions and cold start
Every interactive node carries a string action id plus an optional parameter map, set with setAction(id, params). Tapping the surface opens the app and delivers a SurfaceActionEvent to the single handler registered with Surfaces.setActionHandler(…):
Surfaces.setActionHandler(evt -> {
if ("open_order".equals(evt.getActionId())) {
String orderId = (String) evt.getParams().get("orderId");
showOrderForm(orderId);
} else {
Dialog.show("Surface Action", "Action " + evt.getActionId()
+ " from " + evt.getSource()
+ ", cold start: " + evt.isColdStart(), "OK", null);
}
});Actions are delivered on the EDT. When the tap launches a dead app, the event is queued across the cold start and delivered once your handler registers — which is why the registration belongs in init(). SurfaceActionEvent.isColdStart() tells you which path you are on, getSource() identifies the surface (widget kind or activity type), and getParams() returns the parameter map serialized with the action.
46.7. Updating from the background
Surfaces are updated from the running app in this release; push-driven updates are planned. Three mechanisms keep content fresh without keeping the app open:
Timelines carry the future with them. Publish entries covering the hours ahead and the OS flips them on schedule — the clock above stays correct for an hour without a single wake-up. WidgetTimeline.RELOAD_AT_END (the default) asks the platform to request fresh content when the entries run out.
Background fetch re-publishes data. Implement com.codename1.background.BackgroundFetch, register with Display.setPreferredBackgroundFetchInterval(int), and re-publish inside the callback — publishing is data-only file IO, safe from any thread and from a UI-less process:
public void performBackgroundFetch(long deadline, Callback<Boolean> onComplete) {
// fetch fresh data, then re-publish the timeline
publishDeliveryTimeline();
onComplete.onSucess(Boolean.TRUE);
}The completion callback must be invoked, or iOS stops granting fetch time. On iOS, background fetch also needs the fetch background mode:
codename1.arg.ios.background_modes=fetchOn Android, the widget pulls the app. When a provider renders an exhausted RELOAD_AT_END timeline (or no timeline at all) it starts the background fetch service directly — throttled to once per 15 minutes per kind, and only when the app declares background fetch. The iOS widget extension can’t wake the app arbitrarily: an exhausted timeline makes WidgetKit re-read the persisted document, so publish timelines with enough future entries to bridge the gap between fetches. The simulator simulates background fetch with a timer that fires while the app is paused (Simulate > Pause App).
46.8. Per-platform notes
46.8.1. iOS
The build generates a CN1Widgets WidgetKit extension target into the Xcode project and shares published timelines with it through an App Group container. The App Group id defaults to group.<your package name>; override it with the appGroup field in surfaces.json or the ios.surfaces.appGroup build hint. The extension’s deployment target defaults to 16.1 (ActivityKit’s floor) without raising your app’s own deployment target — on older iOS versions the extension never runs and Surfaces.areWidgetsSupported() returns false.
Signing follows the generic app extension rules: the extension needs its own App ID (<your package>.CN1Widgets) with the App Groups capability and, for cloud device builds with manual signing, its own provisioning profile. Either place the .mobileprovision under common/src/main/resources or supply a URL with the ios.appext.CN1Widgets.provisioningURL build hint. With automatic (managed) signing and in local ios-source builds no extra configuration is needed — Xcode provisions the extension target as usual.
Like the app itself (codename1.ios.debug.provision / codename1.ios.release.provision), the extension needs a development profile for debug device builds and a distribution profile for release builds. Qualify any extension provisioning key with debug or release after the ios. segment and the build picks the variant matching the build target, falling back to the unqualified key when no matching variant is set:
Build hints:
codename1.arg.ios.debug.appext.CN1Widgets.provisioningURLandcodename1.arg.ios.release.appext.CN1Widgets.provisioningURLLocal profile paths in
codenameone_settings.properties:codename1.ios.debug.appext.CN1Widgets.provisionandcodename1.ios.release.appext.CN1Widgets.provision
The Certificate Wizard populates both provision variants automatically when it sets up widget extension signing (the development profile requires at least one registered device). An unqualified key alone still works and is used for both build types.
Widget taps deep link back into the app through the cn1surface:// URL scheme, which the build registers automatically.
46.8.2. Android
Widgets are rendered through RemoteViews by generated per-kind providers; no Android-specific build hints are needed, and the per-kind sizing metadata comes from surfaces.json. Timeline entry flips are scheduled with inexact alarms (a 30-second window) to avoid the exact-alarm permission by default; apps that need to-the-second flips can opt in with the android.surfaces.exactAlarms build hint. Second-precision countdowns still tick natively through Chronometer. Live activities lower to ongoing notifications, which on Android 13 and newer require the POST_NOTIFICATIONS runtime permission: the build declares it for you when surfaces.json sets "liveActivities": true, and the first LiveActivity.start(…) raises the system prompt, blocking the calling thread until the user answers. Codename One raises it at most twice across an install — Android stops showing the dialog after two refusals anyway — and spends an attempt only on a request it managed to issue. Android reports a dismissed dialog exactly as it reports a refusal, so dismissing one does cost an attempt, but one rather than the whole budget. Start the first activity while your app is in the foreground: there is no UI to prompt from in a background service or push handler, so a start from one before the permission is granted is refused without spending an attempt. LiveActivity.isSupported() is the programmatic signal once the answer has settled — a spent budget or, for an app that never declared the permission, a missing manifest entry — and adb logcat -s CN1Surfaces explains every refusal, reporting each settled reason once. A grant from anywhere counts — these prompts, push registration, Display.requestNotificationPermission(…) or the system settings — because the live permission state is always checked first. The approximations listed in the node catalog table apply: font weights collapse to regular/bold, circular progress falls back to linear, relative dates refresh only on entry flips, and vector nodes render as bitmaps.
46.8.3. Desktop, Windows, and Linux
In a desktop build the app shows a tray icon whose menu pins a floating widget per kind: a frameless, always-on-top window rendering the published timeline, with clicks dispatched to your action handler. Window positions and the pinned set persist across runs, and a running live activity docks a pill window at the top of the primary screen. Desktop widgets are process-bound in this release — they exist while the app process runs. On Windows the plain signed executable ships these layered floating widgets with zero packaging; setting windows.msix=true additionally wraps the build in an MSIX package that declares a Windows 11 Widgets Board provider, so your kinds appear in the Win+W board rendered as Adaptive Cards. The MSIX channel is opt-in because it has real distribution prerequisites: a certificate the target machine trusts, the Windows App Runtime redistributable on the target machine, and Windows 11 for the board itself. On Linux the widgets are frameless GTK applet windows; on Wayland compositors that support the layer-shell protocol (KDE Plasma, Sway and the rest of the wlroots family) a runtime-loaded gtk-layer-shell places widgets above the wallpaper as real desktop applets with persistent positions and drag-to-move, and on GNOME Wayland they degrade to plain floating windows because the compositor controls global positioning and keep-above.
46.9. Build hints
| Hint | Default | Purpose |
|---|---|---|
|
| Set to |
|
| The shared App Group id; the |
|
| Deployment target of the widget extension (the host app is unaffected) |
|
| Adds |
| URL of the extension’s provisioning profile for cloud manual-signing builds; used for both debug and release builds unless a qualified variant is set | |
| Build-type-specific variants: the URL of the development profile used by debug device builds and the URL of the distribution profile used by release builds. The variant matching the build target overrides the unqualified hint | |
| Add | |
|
| Schedule widget timeline entry flips with exact alarms; declares |
|
| Wrap the Windows build in an MSIX package with a Widgets Board provider |
| package name | MSIX package identity name |
|
| MSIX identity publisher; must match the signing certificate subject |
|
| MSIX package version |
| executable signing configuration | Certificate used to sign the MSIX package |
46.10. Current limitations
Updates originate from the app (timelines, background fetch, live activity updates). Server-pushed widget content and ActivityKit push tokens are planned; the wire format already accommodates them.
The node catalog is intentionally the lowest common denominator — there is no arbitrary per-pixel drawing beyond
SurfaceVector, and no embedding of regular Codename One components.WidgetSize.LOCKSCREENmaps to the iOSaccessoryRectangularfamily and is ignored on Android in this release.The Widgets Board provider requires the
windows.msixopt-in and its distribution prerequisites; without it, Windows desktop widgets are floating windows.
47. Maps
Codename One ships a modern mapping API in the com.codename1.maps package built around two components:
MapView— a pure-vector map drawn entirely through the Codename OneGraphicspipeline. It never embeds a native peer, so it composes cleanly with the rest of your UI (dialogs, lists and overlays draw over it) and behaves identically on every platform, including the simulator and the web.NativeMap— a map backed by a native provider (Apple MapKit, Google Maps, …) when one is wired into the build, and which transparently falls back to aMapViewwhen no provider is available (the simulator, devices without the selected provider, or builds that didn’t opt in).
Both components implement the same MapSurface interface, so application code is identical regardless of which one — or which provider — is backing the map.
The legacy tile-based MapComponent and the external codenameone-google-maps cn1lib are deprecated in favor of this API. |
47.1. A first map
The pure-vector MapView renders real maps with zero configuration and no API key — by default it shows the free, keyless OpenFreeMap vector basemap (real OpenStreetMap data):
MapView map = new MapView();
map.moveCamera(new LatLng(37.7749, -122.4194), 12);
form.add(BorderLayout.CENTER, map);LatLng is the immutable WGS84 coordinate value type used throughout the API. The camera is described by a center LatLng and a fractional zoom level (the standard slippy-map scale where each whole increment doubles the scale).

47.2. The MapSurface API
Every map — vector or native — exposes the same operations through MapSurface:
Marker icons are supplied as EncodedImage and anchored in normalized (u, v) image space (0.5, 1.0 puts the pin tip on the location). When no icon is given, a marker draws the standard Material Design map pin. Polygon and circle fills accept an 0xAARRGGBB color so you can make them translucent.

47.3. Routes that follow the road
A polyline joins the coordinates you hand it with straight lines — it knows nothing about roads. Passing two endpoints to addPolyline therefore draws a single straight segment across the map, which is seldom what a navigation screen wants. Working out the road geometry between two points is a separate job, done by a routing service, and that’s what the com.codename1.maps.routing package is for:
MapView map = new MapView();
form.add(BorderLayout.CENTER, map);
// Draws the driving route along the actual roads and frames it.
Routing.showRoute(map, origin, destination);Routing.showRoute(…) fetches the route, draws it and moves the camera to frame it. Like the keyless OpenFreeMap basemap, it works with no API key and no signup: routing runs over OpenStreetMap data through the built-in OsrmRouteService.
Routing is asynchronous — the call returns immediately and the line appears when the service answers. Use Routing.findRoute(…) when you want the result itself, for example to style the line or show the distance and the estimated time:
RouteRequest request = new RouteRequest(origin, destination)
.addWaypoint(new LatLng(38.8899, -77.0091))
.setTravelMode(TravelMode.DRIVING);
Routing.findRoute(request, new RouteCallback() {
@Override
public void routesFound(java.util.List routes) {
Route best = (Route)routes.get(0);
map.addPolyline(best.toPolyline().setStrokeColor(0xff5722).setStrokeWidth(6));
map.fitBounds(best.getBounds(), CN.convertToPixels(4));
label.setText((int)(best.getDistanceMeters() / 1000) + " km, "
+ (int)(best.getDurationSeconds() / 60) + " min");
}
@Override
public void routeFailed(String message, Throwable error) {
label.setText(message);
}
});A Route carries the drawable geometry (toPolyline()), the bounds to frame it with, the total distance and duration, and the RouteLeg/RouteStep breakdown behind a turn-by-turn list. A RouteRequest adds waypoints and a TravelMode (DRIVING, WALKING, CYCLING).
| The default endpoint is OSRM’s public demo server. It exists for development and demos: no SLA, rate limited, and it hosts the car profile, so walking and cycling requests are routed over driving data there. Before shipping, point the service at your own OSRM instance (or any OSRM-compatible endpoint) — nothing else in your code changes: |
// Your own OSRM instance, or any OSRM-compatible endpoint.
Routing.setService(new OsrmRouteService("https://osrm.example.com"));To route through a different provider entirely — Google Directions, Mapbox Directions, GraphHopper, your own server — implement RouteService and install it the same way. Every provider of that kind returns the route as an encoded polyline, which Polyline.fromEncoded(geometry) turns straight into something drawable (PolylineCodec also handles the polyline6 variant used by Valhalla).
47.4. Tile sources and styles (MapView)
MapView pulls its tiles from a pluggable com.codename1.maps.vector.TileSource:
MvtTileSource— networked Mapbox Vector Tiles (.pbf/.mvt).MvtTileSource.openFreeMap()is the free, keyless OpenStreetMap-based default (its tile URLs are versioned, so it resolves them from OpenFreeMap’s TileJSON automatically). Most other hosted vector basemaps require an API key supplied viasetApiKey(…)and referenced as{key}in the URL template; a TileJSON endpoint (a URL with no{z}token) is resolved automatically.RasterTileSource— networked XYZ image tiles.RasterTileSource.openStreetMap()is a keyless raster alternative.BundledTileSource— tiles bundled into the app as resources, for fully offline maps. The screenshot tests in this repo use this against a small fixture set so the renders are deterministic and network-free; it’s not how you ship a real map.DemoTileSource— a self-contained synthetic tile set (no network), handy for demos and deterministic tests.
47.4.1. Connecting to real map data
For a real app you point MapView at a hosted tile service. The simplest keyless option is OpenFreeMap (OpenStreetMap-based vector tiles); for branded styles or higher quotas use a keyed provider such as MapTiler or your own self-hosted Protomaps/TileServer GL endpoint:
If the URL has no {z} token it’s treated as a TileJSON document and the real tile-URL template (and min/max zoom) are resolved from it automatically, so you can paste a provider’s TileJSON URL directly.
To bundle your own offline tiles instead, drop .mvt/.pbf files into the app’s resources under a {z}/{x}/{y} layout and point BundledTileSource at them — that’s exactly what the test fixtures do.
Vector tiles are painted according to a MapStyle. The built-in MapStyle.light() and MapStyle.dark() cover a usable basemap; MapStyle.fromJson(json) parses a subset of the MapLibre GL style specification (background/fill/line/symbol layers, zoom-stop interpolation, simple ["==", key, value] filters).

47.5. Native maps and providers
NativeMap renders through a native map SDK when the build wires one in:
NativeMap map = new NativeMap(new LatLng(37.7749, -122.4194), 12);
map.addMarker(new MarkerOptions(new LatLng(37.7749, -122.4194)).title("San Francisco"));
form.add(BorderLayout.CENTER, map);
if (!map.isNativeMap()) {
// Running on the simulator (or a build without a provider) -> vector fallback.
}
Which provider (if any) backs the map is decided entirely by build hints — the public API never names a provider, so unused providers add nothing to your app’s size. Select one with the maps.provider build hint (or the per-platform ios.maps.provider / android.maps.provider):
# iOS uses Apple MapKit (a free system framework, no API key, no pod):
codename1.arg.ios.maps.provider=apple
# Android uses Google Maps (pulls Google Play Services Maps):
codename1.arg.android.maps.provider=google
# ...or Huawei Map Kit, for devices without Google Play Services (HMS Core).
# The build pulls com.huawei.hms:maps from Huawei's Maven repo automatically;
# your app still needs the usual HMS onboarding (agconnect-services.json / key):
codename1.arg.android.maps.provider=huaweiThe built-in providers are Apple MapKit (iOS), Google Maps (Android) and Huawei Map Kit (Android). Huawei Map Kit runs on any Android device with HMS Core installed — not only Huawei hardware — so it’s the natural choice for the Android market without Google Play Services. Each reports isAvailable() at runtime (Google checks Play Services, Huawei checks HMS Core), and when the selected provider is unavailable NativeMap falls back to the pure-vector MapView.
When a provider is selected the build server injects that provider’s implementation into your app and wires it in; with no provider selected (or when the provider is unavailable at runtime, for example when Google Play Services is missing) NativeMap simply renders the vector MapView fallback. You can configure the fallback basemap explicitly:
47.5.1. Provider API keys
Apple MapKit needs no key. Google Maps requires the usual keys, supplied as build hints:
codename1.arg.android.xapplication=<meta-data android:name="com.google.android.maps.v2.API_KEY" android:value="YOUR_ANDROID_API_KEY"/>
codename1.arg.ios.afterFinishLaunching=[GMSServices provideAPIKey:@"YOUR_IOS_API_KEY"];47.5.2. Cross-platform web maps
A native provider only renders on the platforms that ship its SDK. To show a provider’s map everywhere — including platforms with no native SDK for it — register a WebMapProvider, which hosts the provider’s JavaScript SDK inside a BrowserComponent:
Because it needs only a web view, the web provider (id web) is the natural last step before the pure-vector fallback in a provider chain. The order is fully customizable from code, so you can express per-platform preferences — for example "try the native Google SDK, then the web map, then the vector `MapView`":

47.6. Choosing between MapView and NativeMap
Use MapView when you want a lightweight, dependency-free map that looks the same everywhere and composes with CN1 components. Use NativeMap when you want the platform’s native map look, gestures and performance, and are willing to opt a provider in through build hints — with the guarantee that it still works (as a vector map) where the provider is unavailable.
48. In-Car Experiences (CarPlay & Android Auto)
Codename One can project a driver-safe UI onto Apple CarPlay and Google Android Auto from a single portable API under the com.codename1.car package. You describe the screens once with a small set of cross-platform templates; Codename One renders them as native CPTemplate`s on CarPlay and `androidx.car.app templates on Android Auto.
CarPlay and Android Auto are template-based UI systems. Unlike the phone, tablet, or even Apple TV/Android TV (which reuse the normal Codename One renderer), the car platforms don’t let an app draw arbitrary pixels or show a regular Codename One |
This API is zero cost when unused: simply referencing com.codename1.car is what tells the build to wire the native plumbing (the CarPlay scene + entitlement on iOS, the androidx.car.app dependency + CarAppService on Android). Apps that never touch the package get none of it.
48.1. Quick start
Register a single CarApplication from your app’s init() — before a head unit connects — and return a root CarScreen that builds a template:
That single description renders natively on both platforms:

On the simulator and on any port without in-car projection there is no head unit, so the whole API is an inert no-op and CN.isCarConnected() returns false — your code never needs platform if statements.
48.2. Templates
A CarScreen returns exactly one CarTemplate. The catalogue mirrors what the head units allow:
| Template | Use for | CarPlay | Android Auto |
|---|---|---|---|
| Sectioned scrolling list of rows (browse, settings) |
|
|
| Image-forward grid (categories, presets, artwork) |
|
|
| Detail pane: label/value rows + up to two actions |
|
|
| Short message + actions (errors, prompts, messaging) |
|
|
| Turn-by-turn surface with a drawable map |
|
|
| System now-playing surface for audio apps |
| media now-playing |
Rows (CarRow), grid items (CarGridItem) and actions (CarAction) carry a title, optional secondary text, an optional com.codename1.ui.Image icon and a CarActionListener invoked on the EDT when the element is selected. Mark a row setBrowsable(true) when selecting it drills into a deeper screen.

Head units enforce a hard cap on the number of rows/items they display (driver-distraction rules). Query it and trim accordingly:
48.3. Screen stack & lifecycle
CarContext manages a back stack, mirroring androidx.car.app’s `ScreenManager and CarPlay’s CPInterfaceController:
CarScreen exposes optional lifecycle hooks — onCreate(), onResume(), onPause(), onDestroy() — and CarApplication is notified of connection changes via onCarConnected(CarContext) / onCarDisconnected(). You can also observe connection globally:
48.4. Now-playing (audio apps)
For audio apps the track metadata, artwork, scrubber and transport controls are driven by the platform media session (the Android background audio service / MPNowPlayingInfoCenter on iOS), so CarNowPlayingTemplate carries no metadata of its own — it routes the head unit to the now-playing surface and lets you add a couple of app-specific buttons (shuffle, like).

48.5. Build configuration
Native wiring is added automatically when your bytecode references com.codename1.car. Apple grants CarPlay entitlements — and Android Auto surfaces categories — per app category, so declare the categories you ship with these build hints:
| Category | iOS hint | Android hint | Notes |
|---|---|---|---|
Audio |
| (media browser service) | Default CarPlay entitlement when none specified |
Communication |
|
| Read-aloud / voice reply |
Navigation |
|
| Adds the drawable map surface + |
Point of interest |
|
| Browse/POI list apps |
Optional: android.carAppVersion pins the androidx.car.app version; android.androidAuto.minCarApiLevel sets the minimum car API level.
CarPlay and the restricted Android Auto categories require approval from Apple/Google before they will run outside the simulator/Desktop Head Unit. The build wiring is automatic, but shipping to real cars still needs the relevant CarPlay entitlement on your Apple App ID (request it at developer.apple.com) and acceptance into the Android Auto programme. |
48.6. Debugging in the simulator
The fastest way to build and debug an in-car experience is the Codename One simulator. Run your app as usual, then use the Car menu:
Car > Connect CarPlay or Car > Connect Android Auto opens a simulated head-unit window that renders your registered
CarApplicationin the matching style. Click rows, grid items and actions to drive navigation (pushScreen/popScreen) exactly as a real head unit would; the Back button pops the stack.Car > Disconnect (or closing the window) ends the session and fires
onCarDisconnected().
This needs no iOS/Android toolchain, no entitlement and no head unit — it exercises the same portable template tree and the same CarActionListener callbacks (on the EDT) that ship to the device, so you can iterate on your screens in seconds. If you haven’t called Car.setApplication(…) the menu tells you so. The simulated head unit approximates the two platform styles and the driver-distraction row caps; it’s a debugging aid, not a pixel-accurate emulation.

Selecting a browsable row pushes the next screen, just as it would in the car — here a CarGridTemplate, reachable via the Back button:

48.7. Testing on the real platforms
iOS: run the app in the iOS Simulator, then I/O > External Displays > CarPlay to open the CarPlay window.
Android: install the Desktop Head Unit (DHU) from the Android SDK and connect a device/emulator running Android Auto.
A complete runnable example lives in Samples/samples/CarSample.
48.8. Limitations
The navigation map surface (
CarSurfaceCallback) is scaffolded; live map drawing onto the head-unit surface is a work in progress — the navigation template’s controls, header and ETA strip are wired.Android Auto media browsing is driven by the standard media session;
CarNowPlayingTemplateroutes to it.You can’t show arbitrary Codename One forms on the head unit — use the template catalogue above.
49. Motion Sensors
The com.codename1.sensors package exposes the device motion hardware through a single entry point, MotionSensorManager, and layers high-level gesture detection on top of the raw sensor stream. The raw sensors are the accelerometer, the gyroscope and the magnetometer. From those readings the framework derives the gravity vector, the linear acceleration and the device orientation, and it recognizes a set of common gestures: shake, flip, tilt, pick up and free fall.
Gesture detection lives in the core rather than in each platform port. Any platform that reports an accelerometer therefore gets the full gesture set, with no per-device work.
49.1. Reading a sensor
MotionSensorManager.getInstance() always returns a manager. On a device without motion hardware every sensor reports as unsupported, so application code can call the API without a null check on the manager itself. getSensor(int) returns null when the requested sensor isn’t available on the current device:
Callbacks arrive on the EDT, so the listener can update the UI directly. Sampling is reference counted: the hardware sensor draws power only while at least one listener is registered. Remove the listener once the screen is no longer visible, typically from the form’s removeNotify, so the sensor powers down:
49.2. Sensor types
Each sensor is identified by a TYPE_* constant on MotionSensorManager. The three hardware sensors map directly to the device. The gravity, linear acceleration and orientation values are derived in the core from the accelerometer (and the magnetometer, for the compass azimuth) when the platform doesn’t report them on its own.
| Constant | Reading |
|---|---|
| Acceleration including gravity, in meters per second squared. |
| Acceleration with gravity removed, in meters per second squared. |
| The gravity vector on its own, in meters per second squared. |
| Rate of rotation around each axis, in radians per second. |
| The ambient magnetic field, in microtesla. |
| Azimuth, pitch and roll, in radians. |
Readings use a single convention across every port: the x-axis points to the right, the y-axis points up, and the z-axis points out of the screen toward the user, with the device held upright in portrait. At rest, face up, the accelerometer reports about +9.81 on the z-axis.
49.3. Detecting gestures
Register a GestureListener for one of the GestureEvent.TYPE_* gestures. The accelerometer powers on for the duration that a gesture listener stays registered:
The recognized gestures are:
TYPE_SHAKE— the device was shaken back and forth.TYPE_FLIP_FACE_DOWNandTYPE_FLIP_FACE_UP— the device was turned screen down or screen up.TYPE_TILT_LEFT,TYPE_TILT_RIGHT,TYPE_TILT_FORWARDandTYPE_TILT_BACKWARD— the device crossed a tilt angle on the roll or pitch axis.TYPE_PICK_UP— the device was lifted from a resting position.TYPE_FREE_FALL— the device is falling (near weightlessness was detected).
The detection thresholds suit most apps as shipped, and you can tune them when a gesture needs to be more or less sensitive:
A smaller sampling interval makes gestures more responsive at a higher battery cost. The value is clamped to the range 10ms through 1000ms.
49.4. Device orientation
TYPE_ORIENTATION is a derived sensor. Its event carries the azimuth, pitch and roll in radians, available through getAzimuth(), getPitch() and getRoll() on MotionEvent. Pitch and roll come from the gravity vector and need only the accelerometer. The azimuth is a compass heading and needs the magnetometer; on a device without one the azimuth stays at zero.
49.5. Platform notes
Android — backed by
android.hardware.SensorManager. Android already reports its readings in the units and axis convention this API documents, so no conversion takes place.iOS — backed by CoreMotion (
CMMotionManager). Add the build hintios.NSMotionUsageDescriptionwith a short sentence describing why the app reads motion data; iOS denies access to the motion hardware without it. The iOS Simulator doesn’t expose an accelerometer, so the sensors report as unsupported there. Test motion features on a real device.Other ports — a port that doesn’t implement the sensors returns an unsupported manager, so the API stays safe to call everywhere.
49.6. Testing in the simulator
The simulator can stand in for real hardware. Open Simulate > Motion / Gesture Simulation to show a small control window. The two sliders set the simulated device orientation, which the accelerometer reflects, and the buttons inject the motion needed to fire the shake, flip, pick up and free fall gestures. This lets you wire up and debug a gesture handler on the desktop before deploying to a device.
50. Miscellaneous features
50.1. Phone functions
Most of the low-level phone functionality is accessible in the Display class. Think of it as a global class that covers access to the "system."
50.1.1. SMS
Codename One supports sending SMS messages but not receiving them as this functionality isn’t portable. You can send an SMS using either the Display singleton or the static helper methods on CN. Both APIs throw IOException, which you should handle in case the native layer reports a failure:
try {
Display.getInstance().sendSMS("+999999999", "My SMS Message");
// Or: CN.sendSMS("+999999999", "My SMS Message");
} catch(IOException err) {
Log.e(err);
Dialog.show("SMS Failed", "Unable to send the SMS", "OK", null);
}Android supports sending SMS messages in the background without any UI. iOS doesn’t provide that ability, so the best it can offer is to launch the native SMS app with your message composed for the user to send. Android supports that interactive flow as well (launching the OS native SMS app).
The default sendSMS API ignores that difference and works interactively on iOS while sending
in the background for Android when the platform allows it.
The getSMSSupport API returns one of the following options:
SMS_NOT_SUPPORTED - for desktop, tablet etc.
SMS_SEAMLESS -
sendSMSwon’t show a UI and will send in the backgroundSMS_INTERACTIVE -
sendSMSwill show an SMS sending UISMS_BOTH -
sendSMScan support both seamless and interactive mode, this works on Android
The sendSMS can accept an interactive argument: sendSMS(String phoneNumber, String message, boolean interactive)
The last argument will be ignored unless SMS_BOTH is returned from getSMSSupport at which point you
would be able to choose one way or the other. The default behavior (when not using that flag) is the background
sending which is the current behavior on Android.
A typical use of this API would be something like this:
50.1.2. Dialing
Dialing the phone is pretty trivial. This should open the dialer UI without physically dialing the phone, as that’s discouraged by device vendors.
You can dial the phone by using:
Display.getInstance().dial("+999999999");50.1.3. Call detection
Codename One includes a generic call detection API through Display.isCallDetectionSupported() and Display.isInCall().
This API is intentionally best effort and should be used as a UX hint (for example, to defer a non-critical animation while the app is interrupted).
On iOS, isInCall() is inferred from app interruption lifecycle events, which means it can report true for non-call interruptions (for example: Control Center, app switching, permission sheets), and some call flows may still be missed.
Because iOS toggles this flag during app lifecycle transitions, polling it with a UITimer can miss the interruption window entirely (timers are paused while the app is inactive, and the flag is reset when the app becomes active again). If you need to react, check it from lifecycle callbacks such as your app’s stop()/start() flow instead of periodic polling.
On Android, call detection is unsupported because robust detection would require invasive telephony permissions that are intentionally avoided:
Display display = Display.getInstance();
if (display.isCallDetectionSupported() && display.isInCall()) {
Log.p("Call interruption is currently active (heuristic)");
}50.1.4. E-Mail
You can send an email through the platforms native email client with code such as this:
Message m = new Message("Body of message");
Display.getInstance().sendMessage(new String[] {"[email protected]"}, "Subject of message", m);You can add one attachment by using setAttachment and setAttachmentMimeType.
You need to use files from FileSystemStorage and NOT Storage files! |
You can add more than one attachment by putting them directly into the attachment map for example:
| Some features such as attachments etc. Don’t work in the simulator but should work on iOS/Android |
50.2. Larger text accessibility
Codename One can adapt to the operating system’s larger text accessibility setting. The Display APIs expose two signals: isLargerTextEnabled() indicates whether the user has enabled larger text, and getLargerTextScale() returns the scale factor that should be applied to fonts.
If you want the theme system to automatically scale its fonts when larger text is enabled, enable the UIManager setting:
UIManager.getInstance().setUseLargerTextScale(true);You can also enable this behavior in the theme by setting the useLargerTextScaleBool theme constant to true.
If you need to apply the scale manually for custom fonts or layout calculations, read the values directly:
50.2.1. How the scale is computed per platform
iOS: the scale is the ratio between the body text size at the user’s current Dynamic Type setting and the iOS standard 17pt body size, that is,
[UIFont preferredFontForTextStyle:UIFontTextStyleBody].pointSize / [UIFont systemFontSize]. Scales for the standard slider stops range from0.82×(Extra Small) through1.00×(Large, default) up to1.35×(Extra Extra Large). When the user enables Larger Accessibility Sizes in Settings → Accessibility → Display & Text Size → Larger Text, the slider extends with five more stops whose scales reach as high as3.12×. These values match what every native iOS app sees fromUIFontMetrics.Android: the scale is
Configuration.fontScale, which is bucketed by Android (typically0.85,1.0,1.15,1.30).
Because the scale is multiplicative, a base font size that’s already larger than the platform default will compound. For example, a defaultFontSizeInt: 18 in your CSS is 6% larger than iOS’s 17pt body, so at iOS Dynamic Type Extra Extra Large (1.35×) your text will render at 24.3pt versus a native iOS app’s 23pt. If you intentionally use a base size larger than the platform default and you also enable useLargerTextScaleBool, expect the absolute size at high accessibility settings to be visibly larger than typical native apps. Many native iOS apps cap Dynamic Type via UIFontMetrics maximumPointSize: for non-text-heavy UIs to avoid layout breakage. |
50.2.2. Previewing in the simulator
The JavaSE simulator includes a Simulate → Larger Text menu that lets you preview every iOS Dynamic Type stop (Extra Small through Accessibility 5) without leaving your desktop. The simulator returns the same scale factor that the corresponding iOS device would report, so this is the recommended way to verify how your UI behaves at each setting before testing on hardware. The selected stop is persisted across simulator restarts.
If your app looks correct in the simulator at Large (default) but fonts appear oversized on your iPhone with the Display & Brightness slider near the middle, check whether Settings → Accessibility → Display & Text Size → Larger Text → Larger Accessibility Sizes is enabled on the device. When that toggle is on, the system reports the larger Accessibility size categories whose scales begin at 1.65× and exceed what the standard slider can reach. |
50.3. Contacts API
The contacts API provides you with the means to query the phone’s address book, delete elements from it and create new entries into it. To get the platform specific list of contacts you can use
String[] contacts = ContactsManager.getAllContacts();
Notice that on some platforms this will prompt the user for permissions and the user might choose not to grant that permission. To detect whether this is the case you can invoke isContactsPermissionGranted() after invoking getAllContacts(). This can help you adapt your error message to the user.
Once you have a Contact you can use the getContactById method, but the default method is a bit slow if you want to pull a large batch of contacts. The solution for this is to extract the data that you need through
Here you can specify true for the attributes that actually matter to you.
Another capability of the contacts API is the ability to extract all the contacts. This isn’t supported on all platforms but platforms such as Android can get a boost from this API as extracting the contacts one by one is slow on Android.
You can check if a platform supports the extraction of all the contacts through ContactsManager.isAllContactsFast().
| When retrieving all the contacts, notice that you should probably not retrieve all the data and should set some fields to false to perform a more efficient query |
You can then extract all the contacts using code that looks a bit like this, notice that you use a thread so the UI won’t be blocked!

Notice that you didn’t fetch the image of the contact as the performance of loading these images might be prohibitive. You can enhance the code above to include images by using slightly more complex code such as this:
The scheduleBackgroundTask method is like new Thread() in some regards. It places elements in a queue instead of opening too many threads so it can be good for non-urgent tasks |

Notice that the code above uses callSerially & scheduleBackgroundTask in a liberal nested way. This is important to avoid an EDT violation |
You can use createContact(String firstName, String familyName, String officePhone, String homePhone, String cellPhone, String email) to add a new contact and deleteContact(String id) to delete a contact.
50.4. Localization & internationalization (L10N & I18N)
Localization (l10n) means adapting to a locale which is more than translating to a specific language but also to a specific language within environment for example: en_US!= en_UK.
Internationalization (i18n) is the process of creating one application that adapts to all locales and regional requirements.
Codename One supports automatic localization and seamless internationalization of an application using Java properties bundles.
Place locale-specific properties files inside an l10n directory directly under your module’s main directory (for example: common/src/main/l10n).
Each file inside this directory is treated as a resource bundle and will be packaged automatically with your app, allowing you to version translations alongside the rest of your source code.
When you’re iterating on translations you can also use the simulator to capture bundles automatically. Open the Simulator menu and enable Auto Update Default Bundle so that running your app in the Codename One simulator will create any missing resource bundles on the fly as you interact with the UI, which makes it simple to populate keys without manually editing files during development. You can install the bundle using code like this:
The device language (as an ISO 639 two-letter code) could be retrieved with this:
String local = L10NManager.getInstance().getLanguage();Once installed a resource bundle takes over the UI and every string set to a label (and label like components) will be automatically localized based on the bundle. You can also use the localize method of UIManager to perform localization on your own:
UIManager.getInstance().localize( "KeyInBundle", "DefaultValue");The list of available languages in the resource bundle could be retrieved like this. Notice that this a list that was set by you and doesn’t need to confirm to the ISO language code standards:
An exception for localization is the TextField/TextArea components both of which contain user data, in those cases the text won’t be localized to avoid accidental localization of user input.
| You can export and import resource bundles as standard Java properties files, CSV and XML. The formats are pretty standard for most localization shops, the XML format Codename One supports is the one used by Android’s string bundles which means most localization specialists should localize it |
The resource bundle is a map between keys and values for example: the code below displays "This Label is localized" on the Label with the hardcoded resource bundle. It would work the same with a resource bundle loaded from a resource file:
Form hi = new Form("L10N", new BoxLayout(BoxLayout.Y_AXIS));
HashMap<String, String> resourceBudle = new HashMap<String, String>();
resourceBudle.put("Localize", "This Label is localized");
UIManager.getInstance().setBundle(resourceBudle);
hi.add(new Label("Localize"));
hi.show();
50.4.1. Localization manager
The L10NManager class includes a multitude of features useful for common localization tasks.
It allows formatting numbers/dates & time based on platform locale. It also provides a great deal of the information you need such as the language/locale information you need to pick the proper resource bundle:

50.4.2. RTL/Bidi
RTL stands for right to left, in the world of internationalization it refers to languages that are written from right to left (Arabic, Hebrew, Syriac, Thaana).
Most western languages are written from left to right (LTR), but some languages are written from right to left (RTL) speakers of these languages expect the UI to flow in the opposite direction otherwise it seems weird like reading this word would be to most English speakers: "drieW."
The problem posed by RTL languages is known as BiDi (Bi-directional) and not as RTL since the "true" problem isn’t the reversal of the writing/UI but rather the mixing of RTL and LTR together. For example: numbers are always written from left to right ( like in English) so in an RTL language the direction is from right to left and once you reach a number or English text embedded in the middle of the sentence (such as a name) the direction switches for a duration and is later restored.
The main issue in the Codename One world is in the layouts, which need to reverse on the fly. Codename One supports this through an RTL flag on all components that’s derived from the global RTL flag in UIManager.
Resource bundles can also include special case constant @rtl, which indicates if a language is written from right to left. This allows everything to automatically reverse.
When in RTL mode the UI will be the exact mirror so WEST will become EAST, RIGHT will become LEFT and this would be true for paddings/margins as well.
If you have a special case where you don’t want this behavior you will need to wrap it with an isRTL check. You can also use setRTL on a per Component basis to disable RTL behavior for a specific Component.
Most UI APIs have special cases for BiDi instead of applying it globally for example: AWT introduced constants such as LEADING instead of making WEST mean the opposite direction. You think that was a mistake since the cases where you wouldn’t want the behavior of automatic reversal are rare. |
Codename One’s support for bidi includes the following components:
Bidi algorithm - allows converting between logical to visual representation for rendering
Global RTL flag - default flag for the entire application indicating the UI should flow from right to left
Individual RTL flag - flag indicating that the specific component/container should be presented as an RTL/LTR component (for example: for displaying English elements within an RTL UI).
RTL text field input
Most of Codename One’s RTL support is under the hood, the LookAndFeel global RTL flag can be enabled using:
UIManager.getInstance().getLookAndFeel().setRTL(true);
Once RTL is activated all positions in Codename One become reversed and the UI becomes a mirror of itself. For example: Adding a Toolbar command to the left will actually make it appear on the right. Padding on the left becomes padding on the right. The scroll moves to the left etc.
This applies to the layout managers (except for group layout) and most components. Bidi is seamless in Codename One but a developer still needs to be aware that his UI might be mirrored for these cases.
50.4.3. Localizing native iOS strings
Some strings in iOS need to be localized using iOS’s native mechanisms - namely providing *.lproj directories with .strings files. For example, if you want the app to have a different bundle display name for each language, or you want to translate the "UsageDescription" strings of your Info.plist into many languages, you would need to use iOS' native localization facilities.
Example: Localizing the app name
The app name, as it’s displayed to the user, is defined in using the CFBundleDisplayName key of the app’s Info.plist file., this will be automatically set to your app’s display name, as defined in your codenameone_settings.properties file. This works fine if your app will have the same name in every locale, but suppose you want your app to take on a different name in French than in English. For example: You want your app to be called "Hello App" for English-speaking users, and "Bonjour App" for French-speaking users.
In this case, you need to add iOS localization bundles "en.lproj" and fr.lproj, each with a file named InfoPlist.strings. If you’re using Maven, then you can add these directly inside the ios/src/main/strings directory of your project.
| You will need to create the strings directory manually, if it doesn’t exist yet. |

"CFBundleDisplayName"="Hello App";"CFBundleDisplayName"="Bonjour App";The strings format is like the properties file format, except that both the "key" and the "value" must be wrapped in quotes. And if there are many strings, then they must be delimited by a semi-colon |
Example: Localization app usage description strings
iOS requires you to supply usage descriptions for many features that will be displayed to the user when the app requests permission to use the feature. For example, the NSCameraUsageDescription string must be provided if your app needs to use the camera. You can specify these values as build hints using the pattern ios.NSXXXUsageDescription=This feature is needed blah blah. In the NSCameraUsageDescription case, you might include the build hint:
ios.NSCameraUsageDescription=This app needs to use your camera to scan bar codesThese descriptions are embedded in your app’s Info.plist file, so they can be localized the same way you localize other Info.plist values - in the localized InfoPlist.strings file.
See the above example for instructions on localizing values in the Info.plist file. Then add translations to the InfoPlist.strings file for your usage descriptions.
"CFBundleDisplayName"="Hello App";
"NSCameraUsageDescription"="This app needs to use your camera to scan bar codes";"CFBundleDisplayName"="Bonjour App";
"NSCameraUsageDescription"="Cette application doit utiliser votre appareil photo pour scanner les codes à barres";50.4.4. Localizing the app icon
Codename One can ship a different launcher icon per locale on iOS and Android by detecting specially named PNG files during the build. Drop your per-locale artwork into common/src/main/resources using the convention:
cn1_icon_<lang>[_<country>].png<lang> is a two-letter ISO 639-1 language code and the optional <country> is a two-letter ISO 3166-1 country code. Language is treated as case-insensitive; the country component is normalized to uppercase. A few valid examples:
cn1_icon_fr.png: French (any region)cn1_icon_en_GB.png: British Englishcn1_icon_es_MX.png: Mexican Spanish
Supply a square source image at least 432×432 pixels (the largest size emitted for Android adaptive icons; 1024×1024 is recommended, matching the main app icon); the build resizes it to every target density. A smaller source would be upscaled and look blurry, so the build now fails with a clear error when it detects an undersized localized icon rather than shipping a soft one. The default app icon continues to be controlled by your codenameone_settings.properties file and is used whenever the device locale doesn’t match any of the localized variants.
These icons live under src/main/resources and Maven copies them into target/classes incrementally — it doesn’t delete the copy when you remove or rename the source file. If you replace a localized icon and still see the old (often blurry) one, run mvn clean to clear the stale resource from target/classes before rebuilding. The build also fails when it finds an undersized cn1_icon_*.png in the compiled output that’s about to be bundled and sent to the build server. |
At runtime the builders look for a <lang>_<COUNTRY> match first, then fall back to a bare <lang> match. Providing both (for example cn1_icon_en.png plus cn1_icon_en_GB.png) lets you give British users a country-specific icon while every other English locale still receives the generic English icon.
Android behavior
On Android the build generates locale-qualified drawable resources at every density so the platform picks the right icon automatically based on the device’s current locale:
drawable-<lang>[-r<COUNTRY>][-<dpi>]/icon.pngat 36, 48, 72, 96, 128, 144 and 192 pixels for legacy launchers.When
android.enableAdaptiveIcons=truethe same variants are also written asmipmap-<lang>[-r<COUNTRY>]-<dpi>/ic_launcher.pngandic_launcher_foreground.png. The default adaptive background and themipmap-anydpi-v26/ic_launcher.xmldefinition are reused as-is.
No code changes are required—Android’s resource framework switches icons when the locale changes.
When you supply a region-qualified icon (such as cn1_icon_ar_AE.png) without a matching language-only variant, the build also emits the default (non-localized) icon into drawable-<lang>/ and the matching mipmap-*-<lang>/ directories. This barrier is required because Android’s resource resolver (API 24+) walks every child of the parent locale when it can’t find an exact or parent-language match, and would otherwise pick ar-rAE for, say, an ar-PK device. The barrier short-circuits that lookup so only devices whose region matches the supplied variant receive the localized icon. If you also ship a language-only file (for example cn1_icon_ar.png) it’s used as the barrier instead, so you keep full control of the fallback icon for Arabic speakers outside AE.
iOS behavior
iOS doesn’t localize launcher icons natively, so Codename One wires up alternate app icons for you:
For each detected locale the build generates an
AppIcon_<lang>_<COUNTRY>.appiconsetinsideImages.xcassetscontaining the 120×120, 180×180, 152×152 and 167×167 (iPad Pro) PNGs along with a matchingContents.json.The build adds the matching
ASSETCATALOG_COMPILER_ALTERNATE_APPICON_NAMESXcode build setting soactoolemits a coherent partialInfo.plistcovering bothCFBundlePrimaryIconandCFBundleAlternateIcons. The user’sInfo.plistis left untouched; injectingCFBundleIconsmanually would be dropped during the actool merge and is therefore avoided.The
CodenameOne_GLAppDelegateis patched to call-[UIApplication setAlternateIconName:completionHandler:]at launch. The delegate reads[NSLocale preferredLanguages], tries the full<lang>_<COUNTRY>key first, then falls back to the language-only key, and clears the alternate icon (reverting to the default) if no variant matches.The injection is idempotent and runs before the
ios.afterFinishLaunchinghook, so any custom code you supply via that build hint is unaffected.
| IOS displays a system alert the first time an app switches to an alternate icon. This is platform-standard behavior—Codename One can’t suppress it. |
Tips and troubleshooting
File names are matched case-insensitively.
cn1_icon_EN_uk.pngis treated the same ascn1_icon_en_UK.png.Names that don’t fit the
<2-letter lang>[_<2-letter country>]pattern are logged and skipped; the rest of the build continues.The original
cn1_icon_*.pngfiles are removed after processing so they aren’t shipped as stray bundle resources.To override the default (non-localized) icon, keep using the
Iconsetting incodenameone_settings.propertiesor theiconimage inCN1Resource.res. This feature only adds alternate icons for specific locales.
50.5. Location - GPS
The Location API allows you to track changes in device location or the current user position.
| The Simulator includes a Location Simulation tool that you can launch to determine the current position of the simulator and debug location events |
The most basic usage for the API allows you to fetch a device Location, notice that this API is blocking and can take a while to return:
Location position = LocationManager.getLocationManager().getCurrentLocationSync();In order for location to work on iOS you MUST define the build hint ios.locationUsageDescription and describe why your application needs access to location. Otherwise you won’t get location updates! |
The getCurrentLocationSync() method is good for cases where you need to fetch a current location once and not repeatedly query location. It activates the GPS then turns it off to avoid excessive battery usage. For example, if an application needs to track motion or position over time it should use the location listener API to track location as such:
Notice that there is a method called getCurrentLocation() which will return the current state and might not be right for some cases: |
class MyListener implements LocationListener {
public void locationUpdated(Location location) {
// update UI etc.
}
public void providerStateChanged(int newState) {
// handle status changes/errors appropriately
}
}
LocationManager.getLocationManager().setLocationListener(new MyListener());| On Android location maps to low-level APIs if you disable the usage of Google Play Services. By default location should perform well if you leave the Google Play Services on |
50.5.1. Location in the background - geofencing
Polling location is expensive and requires a special permission on iOS. Its also implemented rather differently both in iOS and Android. Both platforms place restrictions on the location API usage in the background.
Because of the nature of background location the API is non-trivial. It starts with the venerable LocationManager but instead of using the standard API you need to use setBackgroundLocationListener.
Instead of passing a LocationListener instance you need to pass a Class object instance. This is important because background location might be invoked when the app isn’t running and an object would need to be allocated.
Notice that you shouldn’t perform long operations in the background listener callback. IOS wake-up time is limited to about 10 seconds and the app could get killed if it exceeds that time slice.
Notice that the listener can also send events when the app is in the foreground, so it’s recommended to check the app state before deciding how to process this event. You can use Display.isMinimized() to determine if the app is running or in the background.
When implementing this make sure that:
The class passed to the API is a public class in the global scope. Not an inner class or anything like that!
The class has a public no-argument constructor
You need to pass it as a class literal for example:
MyClassName.class. Don’t useClass.forName("my.package.MyClassName")!
Class names are problematic since device builds are obfuscated, you should use literals which the obfuscator detects and handles.
The following code demonstrates usage of the GeoFence API:
Android background location permissions (API 30+)
On Android 11 (API level 30) and higher, requesting background location permission requires a two-step process. First, foreground location permissions must be granted. Then, the app must request background location access, which will direct the user to the system settings to select Allow all the time. Codename One handles this flow automatically when you use LocationManager.
For Android 11+ (API 30+), Codename One detects if background location is needed and presents a dialog explaining the need before redirecting the user to the app settings. You can customize the permission prompt message using the localization key android.permission.ACCESS_BACKGROUND_LOCATION:
50.6. Background music playback
Codename One supports playing music in the background (for example: when the app is minimized) which is useful for developers building a music player style application.
This support isn’t totally portable since the Android and iOS approaches for background music playback differ a great deal. To get this to work on Android you need to use the API: MediaManager.createBackgroundMedia().
You should use that API when you want to create a media stream that will work even when your app is minimized.
For iOS you will need to use a special build hint: ios.background_modes=music.
Which should allow background playback of music on iOS and would work with the createBackgroundMedia() method.
50.7. Capture - photos, video, audio
The capture API allows you to use the camera to capture photographs or the microphone to capture audio. It even includes an API for video capture.
The API itself couldn’t be simpler:
String filePath = Capture.capturePhoto();Just captures and returns a path to a photo you can either open it using the Image class or save it somewhere.
The returned file is a temporary file, you shouldn’t store a reference to it and instead copy it locally or work with the Image object |
For example: you can copy the Image to Storage using:
When running on the simulator the Capture API opens a file chooser API instead of physically capturing the data. This makes debugging device or situation specific issues simpler |
You can capture an image from the camera using an API like this:
Form hi = new Form("Capture", new BorderLayout());
hi.setToolbar(new Toolbar());
Style s = UIManager.getInstance().getComponentStyle("Title");
FontImage icon = FontImage.createMaterial(FontImage.MATERIAL_CAMERA, s);
ImageViewer iv = new ImageViewer(icon);
hi.getToolbar().addCommandToRightBar("", icon, (ev) -> {
String filePath = Capture.capturePhoto();
if(filePath != null) {
try {
DefaultListModel<Image> m = (DefaultListModel<Image>)iv.getImageList();
Image img = Image.createImage(filePath);
if(m == null) {
m = new DefaultListModel<>(img);
iv.setImageList(m);
iv.setImage(img);
} else {
m.addItem(img);
}
m.setSelectedIndex(m.getSize() - 1);
} catch(IOException err) {
Log.e(err);
}
}
});
hi.add(BorderLayout.CENTER, iv);
hi.show();
You show video capture in the MediaManager section.
The sample below captures audio recordings (using the 'Capture' API) and copies them locally under unique names. It also demonstrates the storage and organization of captured audio:
Form hi = new Form("Capture", BoxLayout.y());
hi.setToolbar(new Toolbar());
Style s = UIManager.getInstance().getComponentStyle("Title");
FontImage icon = FontImage.createMaterial(FontImage.MATERIAL_MIC, s);
FileSystemStorage fs = FileSystemStorage.getInstance();
String recordingsDir = fs.getAppHomePath() + "recordings/";
fs.mkdir(recordingsDir);
try {
for(String file : fs.listFiles(recordingsDir)) {
MultiButton mb = new MultiButton(file.substring(file.lastIndexOf("/") + 1));
mb.addActionListener((e) -> {
try {
Media m = MediaManager.createMedia(recordingsDir + file, false);
m.play();
} catch(IOException err) {
Log.e(err);
}
});
hi.add(mb);
}
hi.getToolbar().addCommandToRightBar("", icon, (ev) -> {
try {
String file = Capture.captureAudio();
if(file != null) {
SimpleDateFormat sd = new SimpleDateFormat("yyyy-MMM-dd-kk-mm");
String fileName =sd.format(new Date());
String filePath = recordingsDir + fileName;
Util.copy(fs.openInputStream(file), fs.openOutputStream(filePath));
MultiButton mb = new MultiButton(fileName);
mb.addActionListener((e) -> {
try {
Media m = MediaManager.createMedia(filePath, false);
m.play();
} catch(IOException err) {
Log.e(err);
}
});
hi.add(mb);
hi.revalidate();
}
} catch(IOException err) {
Log.e(err);
}
});
} catch(IOException err) {
Log.e(err);
}
hi.show();
Or, you can use the Media, MediaManager and MediaRecorderBuilder APIs to capture audio, as a more customizable approach than using the Capture API:

50.7.1. Capture asynchronous API
The Capture API also includes a callback based API that uses the ActionListener interface to implement capture. For example: you can adapt the previous sample to use this API as such:
50.8. Gallery
The gallery API allows picking an image and/or video from the cameras gallery (camera roll).
Like the Capture API the image returned is a temporary image that should be copied locally, this is due to device restrictions that don’t allow direct modifications of the gallery |
You can adapt the Capture sample above to use the gallery as such:
Form hi = new Form("Capture", new BorderLayout());
hi.setToolbar(new Toolbar());
Style s = UIManager.getInstance().getComponentStyle("Title");
FontImage icon = FontImage.createMaterial(FontImage.MATERIAL_CAMERA, s);
ImageViewer iv = new ImageViewer(icon);
hi.getToolbar().addCommandToRightBar("", icon, (ev) -> {
Display.getInstance().openGallery((e) -> {
if(e != null && e.getSource() != null) {
try {
DefaultListModel<Image> m = (DefaultListModel<Image>)iv.getImageList();
Image img = Image.createImage((String)e.getSource());
if(m == null) {
m = new DefaultListModel<>(img);
iv.setImageList(m);
iv.setImage(img);
} else {
m.addItem(img);
}
m.setSelectedIndex(m.getSize() - 1);
} catch(IOException err) {
Log.e(err);
}
}
}, Display.GALLERY_IMAGE);
});
hi.add(BorderLayout.CENTER, iv);| No need for a screenshot as it will look identical to the capture image screenshot above |
The last value is the type of content picked which can be one of:
Display.GALLERY_ALL, Display.GALLERY_VIDEO or Display.GALLERY_IMAGE.
50.9. Analytics integration
Analytics now has its own chapter. It covers the provider SPI, consent and privacy handling, the built-in providers (the Codename One first-party service, Google Analytics 4, Matomo, Firebase and a logging provider), and how to write your own. See the Analytics chapter.
The AnalyticsService class documented here previously is deprecated but still works — it delegates to the new API. The migration table at the end of the Analytics chapter maps each old call to its replacement.
50.10. Social sign-in (Facebook, Google, …)
The legacy Facebook and Google OAuth2 sign-in flows that used to live here drove an embedded WebBrowser, which the providers no longer permit. The full sign-in stack — system-browser-based OpenID Connect for any provider, plus Facebook / Google / Microsoft / Apple / Auth0 / Firebase helpers — now lives in the Authentication and Identity chapter.
50.11. Lead Component
Codename One has two basic ways to create new components:
Subclass a
Componentoverridepaint, implement event callbacks etc.Compose many components into a new component, by subclassing a
Container.
Components such as Tabs subclass Container which make a lot of sense for that component since it’s physically a Container.
For example,
components like MultiButton, SpanButton & SpanLabel don’t necessarily seem like the right candidate for compositing but they’re all Container subclasses.
Using a Container provides you a lot of flexibility in layout & functionality for a specific component. MultiButton
is a great example of that. It’s a Container internally that’s composed of 5 labels and a Button.
Codename One makes the MultiButton "feel" like a single button through the use of setLeadComponent(Component) which
turns the button into the "leader" of the component.
When a Container hierarchy is placed under a leader all events within the hierarchy are sent to the leader, so if a label within the lead component receives a pointer pressed event this event will be sent to the leader.
For example: for the MultiButton the internal button will receive that event and send the action performed event, change the state etc.
This creates some potential issues for instance in MultiButton:
myMultiButton.addActionListener((e) -> {
if(e.getComponent() == myMultiButton) {
// this won't occur since the source component is really a button!
}
if(e.getActualComponent() == myMultiButton) {
// this will happennull
}
});The leader also determines the style state, so all the elements being lead are in the same state. For example: if the button is pressed all elements will display their pressed states, notice that they will do so with their own styles but
they will each pick the pressed version of that style so a Label UIID within a lead component in the pressed state
would return the Pressed state for a Label not for the Button.
This is convenient when you need to construct more elaborate UI’s and the cool thing about it’s that you can do this entirely in the designer which allows assembling containers and defining the lead component inside the hierarchy.
For example: the SpanButton class is like this code:
public class SpanButton extends Container {
private Button actualButton;
private TextArea text;
public SpanButton(String txt) {
setUIID("Button");
setLayout(new BorderLayout());
text = new TextArea(getUIManager().localize(txt, txt));
text.setUIID("Button");
text.setEditable(false);
text.setFocusable(false);
actualButton = new Button();
addComponent(BorderLayout.WEST, actualButton);
addComponent(BorderLayout.CENTER, text);
setLeadComponent(actualButton);
}
public void setText(String t) {
text.setText(getUIManager().localize(t, t));
}
public void setIcon(Image i) {
actualButton.setIcon(i);
}
public String getText() {
return text.getText();
}
public Image getIcon() {
return actualButton.getIcon();
}
public void addActionListener(ActionListener l) {
actualButton.addActionListener(l);
}
public void removeActionListener(ActionListener l) {
actualButton.removeActionListener(l);
}
}50.11.1. Blocking lead behavior
The Component class has two methods that allow you to exclude a component from lead behavior: setBlockLead(boolean) & isBlockLead().
Effectively when you have a Component within the lead hierarchy that you would like to treat differently from the rest you can use this method to exclude it from the lead component behavior while keeping the rest in line…
This should have no effect if the component isn’t a part of a lead component.
The sample below is based on the Accordion component which uses a lead component internally:
f.getToolbar().addMaterialCommandToRightBar("", FontImage.MATERIAL_ADD, e -> addEntry(accr));
addEntry(accr);
f.add(BorderLayout.CENTER, accr);
f.show();This allows you to add/edit entries but it also allows the delete button above to actually work. Without a call to setBlockLead(true) the delete button would cat as the rest of the accordion title.

50.12. Pull to refresh
Pull to refresh is the common UI paradigm that Twitter popularized where the user can pull down the form/container to receive an update. Adding this to Codename One couldn’t be simpler!
Just invoke addPullToRefresh(Runnable) on a scrollable container (or form) and the runnable method will be invoked when the refresh operation occurs.
Pull to refresh is implicitly implements in the InifiniteContainer |
Form hi = new Form("Pull To Refresh", BoxLayout.y());
hi.getContentPane().addPullToRefresh(() -> {
hi.add("Pulled at " + L10NManager.getInstance().formatDateTimeShort(new Date()));
});
hi.show();setPullToRefresh(Runnable) is provided as a more discoverable alias for the
same single-task slot — both names route to the same field, and a second
call replaces whatever runnable was previously registered.

50.12.1. Modern arc-spinner pull-to-refresh
The legacy pull-to-refresh visual is the classic "rotating arrow + text"
stack. Modern Material 3 / iOS apps instead show a thin circular arc
that grows as the user pulls and spins once the task fires. This is
shipped as an opt-in path via the pullToRefreshModernBool theme
constant; the iOS Modern and Android Material themes enable it by
default so apps shipping against those themes get the spec-accurate
look without any extra wiring.
To enable in a custom theme:
#Constants {
pullToRefreshModernBool: true;
pullToRefreshIndicatorDiameterMm: 8; /* 8mm circle */
pullToRefreshIndicatorStrokeMm: "0.6"; /* 0.6mm stroke thickness */
}
TabIndicator {
/* The pull-to-refresh arc shares its color with the animated tab
indicator -- both follow the brand's accent. */
color: #007aff;
background-color: transparent;
padding: 0;
margin: 0;
}Behavior:
During the pull gesture the arc sweep grows from 0° to ~330° proportional to how far the user has pulled past the threshold.
When the refresh task fires the arc rotates continuously at ~360°/sec until the task completes.
All sizing is in millimetres so the indicator stays physical-size-accurate across device densities; no rasterized images involved.
The legacy addPullToRefresh API is unchanged — the same Runnable is
invoked at the same moment; only the visual rendering differs.
50.13. Running 3rd party apps using display’s execute
The Display class’s execute method allows you to invoke a URL which is bound to a particular application.
This works rather well assuming the application is installed. For example: this list contains a set of valid URLs that can be used on iOS to run common applications and use built-in functionality.
Some URLs might not be supported if an app isn’t installed, on Android there isn’t much that can be done but iOS has a canOpenURL method for Objective-C.
On iOS you can use the Display.canExecute() method which returns a Boolean instead of a boolean which
allows you to support 3 result states:
Boolean.TRUE- the URL can be executedBoolean.FALSE- the URL isn’t supported or the app is missingnull- you’ve no idea whether the URL will work on this platform.
The sample below launches a "godfather" search on IMDB when this is sure to work ( on iOS currently). You can actually try to search for null as well but this sample plays it safe by using the http link which is sure to work:
Boolean can = Display.getInstance().canExecute("imdb:///find?q=godfather");
if(can != null && can) {
Display.getInstance().execute("imdb:///find?q=godfather");
} else {
Display.getInstance().execute("http://www.imdb.com");
}50.14. Automatic build hint configuration
You try to make Codename One "seamless," this expresses itself in small details such as the automatic detection of permissions on Android etc. The build servers go a long way in setting up the environment as intuitive. However, it isn’t enough, build hints are often confusing and obscure. It’s hard to abstract the mess that’s native mobile OSes and the odd policies from Apple/Google…
A good example for a common problem developers face is location code that doesn’t work in iOS. This is due to the ios.locationUsageDescription build hint that’s required. The reason that build hint was added is a need by Apple to provide a description for every app that uses the location service.
To solve this sort of used case you have two APIs in Display:
Both of these allow you to detect if a build hint is set and if not (or if it’s set incorrectly) set its value…
If you use the location API from the simulator and you didn’t define ios.locationUsageDescription Codename One will implicitly define a string there. The cool thing is that you will now see that string in your settings and you would be able to customize it.
For example, this gets way better than that trivial example!
The real value is for 3rd party cn1lib authors. For example: Google Maps or Parse. They can inspect the build hints in the simulator and show an error in case of a misconfiguration. They can even show a setup UI. Demos that need special keys in place can force the developer to set them up before continuing.
50.15. Easy thread
Working with threads is ranked as one of the least intuitive and painful tasks in programming. This is such an error prone task that some platforms/languages took the route of avoiding threads entirely. A typical scenario: you need to convert some code to work on a separate thread but you still want the ability to communicate and transfer data from that thread.
This is possible in Java but non-trivial, the thing is that this is easy to do in Codename One with tools such as callSerially that let arbitrary code run on the EDT. Why not offer that to any random thread?
That’s why EasyThread exists: it takes some concepts of Codename One’s threading and makes them more accessible to an arbitrary thread. This way you can move things like resource loading into a separate thread and synchronize the data back into the EDT as needed…
Easy thread can be created like this:
You can send a task to the thread using:
However, it gets better, say you want to return a value:
Lets break that down… You ran the thread with the success callback on the new thread then the callback got invoked on the EDT as a result. This code (success) → success.onSuccess(doThisOnTheThread()) ran off the EDT in the thread and when you invoked the onSuccess callback it sent it asynchronously to the EDT here: (myResult) → onEDTGotResult(myRsult).
These asynchronous calls make things a bit painful to wade through, so the API wraps them in a simplified synchronous version:
There are a few other variants like runAndWait and there is a kill() method which stops a thread and releases its resources.
50.16. Mouse cursor
Codename one can change the mouse cursor when hovering over specific areas to show resizability, movability etc. For obvious reasons this feature is available in the desktop and JavaScript ports as the other ports rely on touch interaction. The feature is off by default and needs to be enabled on a Form by using Form.setEnableCursors(true);. If you’re writing a custom component that can use cursors such as SplitPane you can use:
@Override
protected void initComponent() {
super.initComponent();
getComponentForm().setEnableCursors(true);
}Once this is enabled you can set the cursor over a specific region using cmp.setCursor() which accepts one of the cursor constants defined in Component.
50.17. Working with GIT
Working with GIT for storing Codename One projects isn’t a feature but since it’s so ubiquitous you think it’s important to have a common guideline.
When you first started committing to git you used something like this for NetBeans projects:
*.jar nbproject/private/ build/ dist/ lib/CodenameOne_SRC.zip
Removing the jars, build, private folder etc. makes a lot of sense but there are a few nuances that are missing here…
50.17.1. cn1lib’s
You will notice you excluded the jars which are stored under lib and you exclude the Codename One source zip. However, cn1libs aren’t excluded… That was an omission since the original project you committed didn’t have cn1libs. However, should you commit a binary file to git?
It’s a fair question. Git isn’t good with binaries but committing cn1libs can still make sense. In another project that did have a cn1lib the approach was this:
*.jar nbproject/private/ build/ dist/ lib/CodenameOne_SRC.zip lib/impl/ native/internal_tmp/
The important lines are lib/impl/ and native/internal_tmp/. Technically cn1libs are zips. When you run a refresh-libs operation they unzip into the right directories under lib/impl and native/internal_tmp. By excluding these directories you can remove duplicates that can result in conflicts.
50.17.2. Resource files
Committing the res file is a matter of personal choice. It’s committed in the git ignore files above but you can remove it. The res file is at risk of corruption and in that case having a history you can refer to, matters a lot.
However, the resource file is a bit of a problematic file. As a binary file if you have a team working with it the conflicts can be a major blocker. This was far worse with the old GUI builder, that was one of the big motivations of moving into the new GUI builder which works better for teams.
Still, if you want to keep an eye of every change in the resource file you can switch on the File → XML Team Mode which should be on by default. This mode creates a file hierarchy under the res directory to match the res file you opened. For example: if you have a file named src/theme.res it will create a matching res/theme.xml and also nest all the images and resources you use in the res directory.
That’s useful as you can edit the files directly and keep track of every file in git. For example, this has two big drawbacks:
It’s flaky - while this mode works it never reached the stability of the regular res file mode
It conflicts - the simulator/device are oblivious to this mode. If you fetch an update you also need to update the res file and you might still have conflicts related to that file
Both of these issues shouldn’t be a deal-breaker. Even though this mode is a bit flaky it’s better than the alternative as you can "see" the content of the resource file. You can revert and reapply your changes to the res file when merging from git, it’s tedious but again not a deal-breaker.
50.17.3. Eclipse version
Building on the gitignore you’ve for NetBeans the eclipse version should look like this:
.DS_Store *.jar build/ dist/ lib/impl/ native/internal_tmp/ .metadata bin/ tmp/ *.tmp *.bak *.swp *.zip *~.nib local.properties .settings/ .loadpath .recommenders .externalToolBuilders/ *.launch *.pydevproject .cproject .factorypath .buildpath .project .classpath
50.17.4. IntelliJ/IDEA
.DS_Store *.jar build/ dist/ lib/impl/ native/internal_tmp/ *.zip .idea/**/workspace.xml .idea/**/tasks.xml .idea/dictionaries .idea/**/dataSources/ .idea/**/dataSources.ids .idea/**/dataSources.xml .idea/**/dataSources.local.xml .idea/**/sqlDataSources.xml .idea/**/dynamic.xml .idea/**/uiDesigner.xml .idea/**/gradle.xml .idea/**/libraries *.iws /out/ atlassian-ide-plugin.xml
51. Video encoding & decoding (VideoIO)
The VideoIO API is to video what the ImageIO API is to still images, but it goes deeper. It uses the platform’s native codecs to:
Encode application rendered frames and audio into a standard video file, with deep control over dimensions, frame rate, codec, bitrate, key frame interval and the audio track.
Decode an existing clip into frame accurate RGBA frames and PCM audio.
The decode side is something the
Media player API
doesn’t provide. Media is a player: its setTime() snaps to key frames
and gives no exact frame guarantee. VideoReader, by contrast, decodes the precise frame
at a requested time, which is what you need when you want to read an imported clip (for
example a screen recording) frame by frame. |
VideoIO is supported on iOS, macOS, Android, Windows, Linux, JavaScript and the desktop
simulator. It’s not available on the TV, Watch or Car targets.
51.1. Checking for support
As with other optional platform features, always gate usage with isSupported():
if (!VideoIO.isSupported()) {
// Video encoding / decoding is not available on this platform
// (for example TV, Watch or Car), so fall back gracefully.
return;
}
VideoIO io = VideoIO.getVideoIO();On the desktop simulator VideoIO is backed by an ffmpeg/ffprobe binary. The
simulator bundles one automatically; if isSupported() returns false on the desktop,
make sure ffmpeg is on your PATH or set the ffmpeg.dir system property. |
51.2. Encoding a video
Build a VideoWriter with a
VideoWriterBuilder,
then push frames and (optionally) audio. Because every frame is an ordinary
Image that you draw into,
you have complete control over the pixels - render charts, overlays, transformed camera
frames, generated animation, anything.
String out = FileSystemStorage.getInstance().getAppHomePath() + "/generated.mp4";
int w = 640, h = 480;
float fps = 30;
VideoWriter writer = new VideoWriterBuilder()
.path(out)
.width(w).height(h).frameRate(fps)
.videoCodec(VideoIO.CODEC_H264).videoBitRate(4_000_000)
.build();
// Each frame is just an Image you fully control: draw whatever you like.
for (int i = 0; i < 90; i++) { // 3 seconds at 30fps
Image frame = Image.createImage(w, h, 0xff000000);
Graphics g = frame.getGraphics();
g.setColor(0xffffff);
g.fillRect((i * 8) % w, h / 2 - 20, 60, 40);
writer.writeFrame(frame, Math.round(i * 1000f / fps));
}
writer.close();To add an audio track, enable it on the builder (.hasAudio(true)) and push interleaved
16 bit PCM with VideoWriter.writeAudio(…), or hand it an
AudioBuffer.
51.3. Decoding a video frame by frame
VideoReader exposes the clip’s duration, dimensions and frame rate, a frame accurate
frameAt(long) and a variable-to-constant frame rate resampler readFrames(fps, callback)
that walks the whole clip emitting evenly spaced frames:
VideoReader reader = VideoIO.getVideoIO().openReader(videoPath);
System.out.println(reader.getWidth() + "x" + reader.getHeight()
+ " " + reader.getFrameRate() + "fps, "
+ reader.getDurationMillis() + "ms");
List<Image> thumbnails = new ArrayList<>();
// Frame accurate single frame (unlike Media.setTime which snaps to key frames):
VideoFrame oneSecond = reader.frameAt(1000);
if (oneSecond != null) {
thumbnails.add(oneSecond.toImage());
}
// Resample the (possibly variable frame rate) clip to a constant 10fps stream:
reader.readFrames(10, f -> {
// f.getARGB() / f.toImage() give you the decoded RGBA pixels
thumbnails.add(f.toImage());
return thumbnails.size() < 50; // stop after 50 frames
});
reader.close();The audio track, when present, is decoded to interleaved PCM:
VideoReader reader = VideoIO.getVideoIO().openReader(videoPath);
if (reader.hasAudio()) {
AudioBuffer pcm = reader.readAudio();
System.out.println("Decoded " + pcm.getSize() + " PCM samples at "
+ reader.getAudioSampleRate() + "Hz, "
+ reader.getAudioChannels() + " channels");
}
reader.close();51.4. Discovering available codecs
The set of codecs is device dependent. Enumerate it to pick the best one (and to detect hardware accelerated encoders):
VideoIO io = VideoIO.getVideoIO();
for (VideoCodec codec : io.getAvailableEncoders()) {
System.out.println(codec.getId()
+ " (" + codec.getName() + ")"
+ (codec.isHardwareAccelerated() ? " [hardware]" : ""));
}
boolean canEncodeH264 = io.isEncoderSupported(VideoIO.CODEC_H264);51.5. Platform support
| Platform | Backend |
|---|---|
iOS / macOS | AVFoundation ( |
Android |
|
JavaScript | HTML5 |
Windows | Media Foundation ( |
Linux | GStreamer ( |
Simulator |
|
TV / Watch / Car | Not supported ( |
52. Performance, size & debugging
52.1. Reducing resource file size
It’s easy to lose track of size/performance when you’re working within the comforts of a visual tool like the Codename One Designer. When optimizing resource files you need to keep in mind one thing: it’s all about image sizes.
| Images will take up 95-99% of the resource file size; everything else pales in comparison. |
Like every optimization the first rule is to reduce the size of the biggest images which will provide your biggest improvements, for this purpose Codename One provides the ability to see image sizes in kilobytes. To launch that feature use the menu item Images → Image Sizes (KB) in the designer.

This produces a list of images sorted by size with their sizes. Often the top entries will be multi-images, which include HD resolution values that can be pretty large. These high-resolution images take up a significant amount of space!
Just going to the multi-images, selecting the unnecessary resolutions & deleting these images can save significant amounts of space:

| You can see the size in KB at the top right side in the designers image viewer |
Applications using the old GUI builder can use the Images → Delete Unused Images menu option (it’s also under the Images menu). This tool allows detecting and deleting images that aren’t used within the theme/GUI.
If you have a large image that’s opaque you might want to consider converting it to JPEG and replacing the built in PNG’s. Notice that JPEGs work on all supported devices and are typically smaller.

You can use the excellent OptiPng tool to optimize image files right from the Codename One designer. To use this feature you need to install OptiPng then select Images → Launch OptiPng from the menu. Once you do that the tool will automatically optimize all your PNG’s.
When faced with size issues make sure to check the size of your res file, if your JAR file is large open it with a tool such as 7-zip and sort elements by size. Start reviewing which element justifies the size overhead.
52.2. Improving performance
As a developer you can do quite a few things to improve the performance and memory footprint of a Codename One application. This sometimes depends on specific device behaviors but some tips here are true for all devices.
The simulator contains some tools to measure performance overhead of a specific component and also detect EDT blocking logic. Other than that follow these guidelines to create more performance code:
Avoid round rect borders - they have a huge overhead on all platforms. Use image borders instead (counter intuitively they’re MUCH faster)
Avoid Gradients - they perform poorly on most OSes. Use a background image instead
Use larger images when tiling or building image borders, using a 1 pixel (or event a few pixels) wide or high image and tiling it repeatedly can be expensive
Shrink resource file sizes - Otherwise data might get collected by the garbage collector and reloading data might be expensive
Check that you don’t have too many image lock misses - this is discussed in the graphics section
On some platforms mutable images are slow - mutable images are images you can draw on (using
getGraphics()). On some platforms they perform quite badly (for example, iOS) and should be avoided. You can check if mutable images are fast in a platform usingDisplay.areMutableImagesFast()* Make components either transparent or opaque * - a translucent component must paint it’s parent every time. This can be expensive. An opaque component might have margins that would require that you paint the parent so there is often overdraw in such cases (overdraw means the same pixel being painted twice).
52.2.1. ParparVM native translation performance hints
For ParparVM-generated native code, Codename One now supports method-level optimization hints via annotations. These can provide good wins in hot code paths, but they come with tradeoffs and should be applied surgically.
Method-level codegen hints
@DisableDebugInfo
Suppresses generated line/debug metadata for the annotated method. This can reduce generated C size and remove some per-instruction debug overhead.@DisableNullChecksAndArrayBoundsChecks
Suppresses generated null and array-bounds checks for the annotated method. This can reduce branch-heavy code in tight loops.
| Use these on methods that are both performance-critical and well-covered by tests. These annotations intentionally trade runtime safety diagnostics for speed. |
Class-level concrete implementation hints
For native ParparVM output (C/Objective-C), you can also provide a class-level hint that a base type always maps to a known concrete subclass at runtime:
@Concrete(name="fully.qualified.ConcreteClassName")
Allows the translator to bypass virtual table lookup forinvokevirtualcalls on the annotated base class. The translator first attempts a direct call on the concrete class; if the method isn’t implemented there, it falls back to the annotated base class implementation.
This is useful for platform abstraction classes where one implementation is guaranteed in the native pipeline.
For example, Codename One annotates:
| This hint is intended for ParparVM native translation and doesn’t apply to the JavaScript back end. |
Fused object layout: @Fused
A class annotated @com.codename1.annotations.Fused tells the translator that
primitive arrays created in its constructors are fully encapsulated: they’re
implementation details the class never hands out. The translator then lays the
owner object and those arrays out in a single allocation block — one
allocation instead of several, one GC visit instead of several, and no
pointer indirection between the object and its buffer.
@com.codename1.annotations.Fused
class RgbImage {
private final int[] pixels; // laid out INSIDE the RgbImage allocation
private final byte[] flags;
RgbImage(int w, int h) {
pixels = new int[w * h]; // computed sizes (w * h) fuse too
flags = new byte[16];
}
}The contract you accept by annotating:
The fused arrays must never be stored into another object’s field, a static, or an array — their lifetime is the owner’s lifetime. Reading them, iterating them, and passing them as transient call arguments is fine.
Keep the fields private and never return them from a getter. If the class hands its buffer out, don’t annotate it.
Everything else stays automatic and safe: constructors that compute non-constant sizes, reflective instantiation, delegating constructors and oversized arrays (bigger than the small-object allocator handles) all fall back to ordinary separate allocations with identical semantics.
java.lang.String and java.lang.StringBuilder are fused this way
internally — a typical string is one allocation, not two.
Optimizations you get without annotations
Several ParparVM optimizations are applied automatically when the translator can prove they’re safe; knowing they exist helps you write code that benefits from them:
Stack-allocated string building. Every string concatenation the compiler lowers to a
StringBuilderchain — and any builder the translator can prove never escapes its method — is allocated on the C stack, including its initial character buffer. A typical"a" + x + "b"allocates nothing on the heap except the resultingString. This is proven per call site by escape analysis; passing the builder to another method or storing it in a field simply keeps that site on the ordinary heap path.Tagged integers. On 64-bit targets,
Integer.valueOfreturns a tagged immediate pointer instead of allocating — boxing anintfor a map key is free. 32-bit-pointer targets (including Apple Watch) fall back to heap boxing automatically.Closed-world devirtualization. A virtual call with no reachable override compiles to a direct C call, which link-time optimization can then inline.
finalclasses and methods make this trivially provable.Compact collections.
HashMap/LinkedHashMapuse open addressing over parallel arrays — no entry objects, no allocation onput,clear()is three array wipes.Bounds-check elimination. The canonical
for (int i = 0; i < arr.length; i++)loop shape is proven safe and compiled without per-access checks — prefer it over manual index juggling.
The benchmark and correctness suite that gates these optimizations lives in
vm/benchmarks in the repository, with run instructions in its README; every
optimization must produce output bit-identical to a host JVM there before it
ships.
Fast method-stack path
The translator can emit a fast method-stack prologue/epilogue (DEFINE_METHOD_STACK_FAST_* and CN1_FAST_RETURN_RELEASE) for methods that meet strict safety criteria. Methods that qualify for the stricter frameless form (no try/catch, no synchronization) skip the VM frame entirely — their locals become plain C locals the optimizer keeps in registers.
In practice, this tends to help for:
Small, hot methods.
Methods without monitor usage / exception-heavy flow.
Methods with straightforward control flow and low instruction complexity.
Tradeoffs:
Overly broad fast-path eligibility can regress performance if extra branches or memory writes are introduced.
Primitive- fast-frame variants may not always outperform a straightforward full clear on all targets/compilers.
| Benchmark representative workloads after enabling fast-stack behavior. Keep eligibility conservative and expand where measurement shows consistent gains. |
Base64-style hot-loop guidelines
For low-level loops (for example, Base64 encode/decode):
Prefer simple loop bodies with predictable branches.
Cache decode/lookup tables in primitive arrays (
int[]lookup tables can reduce per-iteration conversion overhead).Avoid adding “defensive” branches in the inner-most loop unless they’re required for correctness in production inputs.
Build configuration matters
When benchmarking translator output, ensure native projects are compiled with optimization enabled (for example, CMake Release builds). Debug/default builds can hide improvements or produce misleading regressions.
If you’re using the integration test harness, make sure CMake is configured with:
-DCMAKE_BUILD_TYPE=ReleaseWithout this setting, comparison between Java and ParparVM native output is often noisy and can lead to wrong optimization conclusions.
52.3. SIMD: Data-Parallel primitives
SIMD stands for Single Instruction, Multiple Data. It’s a family of CPU
instructions that apply the same arithmetic or logical operation to several
values at once, packed together into a single wide register. On a 128-bit
NEON or SSE register you can hold sixteen bytes, eight 16-bit integers, four
32-bit integers, or four 32-bit floats, and a single instruction such as
VADD or PADDD then operates on every lane in parallel. For data-parallel
workloads—Base64 encode/decode, pixel blending, alpha-mask compositing,
color-channel manipulation, table lookups—SIMD typically delivers a 3× to
10× speedup over scalar code.
Modern mobile and desktop CPUs expose several SIMD instruction sets:
x86/x64—MMX, SSE, SSE2/3/4, AVX, AVX2, AVX-512
ARM/ARM64—NEON (Advanced SIMD) and SVE
Codename One exposes those primitives as portable Java method calls on
com.codename1.util.Simd.
On ParparVM (iOS) the translator lowers them to NEON intrinsics; on Android
and the JavaSE simulator a pure-Java fallback in JavaSESimd provides the
same semantics so code written against Simd runs everywhere and simply
performs better where native SIMD is available.
52.3.1. When to use SIMD
SIMD is worth reaching for when all the following hold:
You are processing a buffer of at least dozens of elements at a time.
The operation per element is simple (add, min, blend, table lookup, interleave/unpack) and identical across elements.
Control flow is regular—no per-element early exit, no data-dependent branches that differ across lanes.
Data is contiguous in a primitive array (
byte[],int[],float[]).
Classic fits are image pixel passes, codecs (Base64, UTF-8 validation, hex encoding), checksums, audio mixing, and vector arithmetic. Poor fits are tight loops with pointer chasing, per-element branching on complex state, or buffers smaller than a single SIMD register.
If you aren’t sure whether your platform has a vectorized implementation
available, call Simd.get().isSupported(). The fallback path still returns
correct results; isSupported() only tells you whether you will see the
speedup.
52.3.2. Getting an instance
Simd is accessed as a singleton:
The returned object is safe to cache in a field as long as the cache is refreshed across simulator restarts (the simulator may swap the backing implementation).
52.3.3. Allocation: Alignment and provenance
SIMD load/store instructions prefer—and on some architectures require—
that the memory address they read from or write to be a multiple of the
register width (16 bytes on NEON and SSE). Misaligned access either throws
a hardware fault on strict platforms or costs extra cycles because
the CPU has to split the transaction across two cache lines. A JVM offers
no guarantee that new byte[64] is aligned to anything beyond the
platform’s object-header convention, so the framework forbids passing
arbitrary new-allocated arrays to Simd primitives.
Every buffer used with a Simd primitive must so come from one of
the allocation helpers on Simd:
All three methods enforce a minimum size of 16 elements and throw
IllegalArgumentException for anything smaller; the minimum keeps each
buffer large enough to hold a full SIMD register and leaves room for
alignment padding.
Don’t construct SIMD buffers with new byte[64] and pass them
to Simd. The simulator enforces this at runtime (see Simulator
Tracking below) and the iOS native path assumes alignment. Passing an
unregistered array yields either an IllegalArgumentException in the
simulator or undefined results on device. |
52.3.4. A minimal End-to-End example
All Simd ops take explicit offset / length pairs so callers can
chunk a large buffer through a small scratch array without reallocating.
Many methods have interleaved variants—unpackBytesInterleaved3/4,
packBytesInterleaved3/4—designed for packed pixel formats (RGB, RGBA)
and fused operations like blendByMaskTestNonzero and
replaceTopByteFromUnsignedBytes that collapse common three- or
four-pass pixel pipelines into a single vector pass.
52.3.5. Scratch allocations: alloca*
A SIMD primitive often needs a short-lived working buffer: somewhere to
stage intermediate lanes, hold a temporary mask, or accumulate partial
results. Allocating a new byte[] per call via allocByte would dominate
the runtime of the primitive it was trying to accelerate—heap
allocation, zero-fill, and eventual GC reclamation all add up. The natural
solution is to let the compiler place these buffers on the call stack
where they cost nothing to create and are reclaimed automatically when the
method returns. This is what the alloca* family exposes:
On the simulator (and on Android) these behave like heap allocations with
registration. On ParparVM the translator intercepts each alloca* call
and rewrites it into a C-level __builtin_alloca that carves a faux
JavaArrayPrototype out of the current C stack frame. The resulting
pointer masquerades as an ordinary Java array for the lifetime of the
enclosing method and is reclaimed on return.
The distinction between allocByte and allocaByte mirrors the
distinction between new byte[N] and C’s alloca(N):
alloc* (heap) | alloca* (stack on ParparVM) | |
|---|---|---|
Cost to assign | object header + zero fill + GC bookkeeping | register adjust, essentially free |
Lifetime | until last reference dropped | until enclosing method returns |
Can be stored in a field | yes | no—use-after-free on device |
Can be returned from the method | yes | no |
Can be passed to non- | yes | no |
Initial contents | zero | undefined (use |
Size limit | heap | bounded by remaining stack |
alloca* memory, like any stack memory, starts out containing
whatever the previous frame left behind. Callers that require predictable
initial contents should use allocaByteZeroed / allocaIntZeroed /
allocaFloatZeroed, or the *Filled variants that accept an explicit
initial value, rather than rolling their own loop. |
52.3.6. Rules for alloca* scratch arrays
Because alloca* memory can’t outlive its defining method on
ParparVM, the array it returns must be treated as method-local.
The framework enforces four rules at build and run time:
Don’t return an
alloca*array from the method that allocated it.Don’t store an
alloca*array in an instance or static field, or into an object array.Don’t pass an
alloca*array to a method whose owner isn’tSimd,IOSSimd, orJavaSESimd. Helper methods outside the SIMD package might themselves violate one of the other rules.Don’t pass an
alloca*array throughinvokedynamic; dynamic dispatch can’t be analyzed statically.
Inside the defining method you are free to pass the array to any number
of Simd primitives, copy values into and out of it, combine it with
other buffers, etc.
52.3.7. Build-Time verification
The Maven plugin ships a bytecode-compliance goal (compliance-check)
that walks every method in the application’s compiled classes and
performs a dataflow pass whose only job is to track whether each value
on the operand stack or in a local variable was produced by an alloca*
call. The pass is an ASM BasicInterpreter subclass that taints every
value returned from a method on Simd, IOSSimd, or JavaSESimd whose
name begins with alloca followed by an upper-case letter. The taint
propagates through DUP, ASTORE/ALOAD, CHECKCAST, and every
control-flow merge, so a value keeps its provenance through any amount
of local plumbing.
The verifier fails the build if a tainted value reaches any of:
ARETURN—"SIMD alloca value returned from method"PUTFIELD/PUTSTATIC—"SIMD alloca value stored into instance/static field"AASTORE—"SIMD alloca value stored into object array"INVOKE*whose owner isn’tSimd,IOSSimd, orJavaSESimdINVOKEDYNAMIC: refused unconditionally
Every violation is reported with the offending class, method, and the hint "Keep SIMD alloca scratch arrays method-local and only pass them to SIMD methods." Because this is wired into the Maven build, code that would dereference freed stack memory on device can’t ship.
A complementary guard lives inside the translator itself:
CustomInvoke.appendSimdAllocaExpression only performs stack lowering
when the length argument is a compile-time constant. A call like
simd.allocaByte(n) with a variable n falls through to the default
codegen and becomes a normal heap allocation, which avoids both
unbounded stack growth and an alloca whose size the translator can’t
inspect.
52.3.8. Simulator tracking of aligned arrays
The JavaSE simulator runs on the desktop where there is no NEON, no
__builtin_alloca, and no guarantee that a given byte[] is 16-byte
aligned. To keep developer bugs from hiding on the desktop and
reappearing only on device, the simulator takes a strict stance: only
arrays obtained from Simd.alloc / Simd.alloca* are accepted as
inputs to SIMD primitives.*
Internally this is an identity-based registry. Every allocation helper
routes its result through a registration call that stores the array’s
System.identityHashCode—the JVM’s per-object identity hash, stable
for the object’s lifetime regardless of GC movement. Every SIMD entry
point validates its array arguments against the same set and throws
IllegalArgumentException if a caller hands it a plain new byte[64]:
java.lang.IllegalArgumentException: SIMD array argument was not
allocated using Simd.alloc*(). objectId=…Combined with the build-time verifier, both static analysis and dynamic execution refuse to accept arrays that would not be 16-byte aligned on device. On the device itself no such validation occurs—by that point the build has already proved the invariant.
52.3.9. Built-In SIMD paths
You gain from SIMD without touching the API directly.
com.codename1.util.Base64 detects Simd.isSupported() at encode/decode
entry points and routes the hot loop through unpackLookupBytesInterleaved4,
lookupBytes, or, and shl with cached per-call constant tables; the
bodies of Image.applyMask, Image.modifyAlpha, and Image.removeColor
use fused primitives like replaceTopByteFromUnsignedBytes and
blendByMaskTestNonzero to collapse multi-pass pixel pipelines into a
single vector loop.
If you are writing your own hot loop on a primitive buffer and the data
is already contiguous and aligned in a Simd.alloc* array, reach for the
Simd API before optimizing further with the ParparVM annotations
described above—vectorization and annotation hints compose, but
vectorization is the larger win.
52.4. Performance monitor
The Performance Monitor tool can be accessible via the Simulator → Performance Monitor menu option in the simulator. This launches the following UI that can help you improve application performance:

The first tab of the performance monitor includes a table of the drawn components. Each entry includes the number of times it was drawn and the slowest/fastest and average drawing time. The toolbar across the top includes Pause/Continue buttons so you can freeze the counters while you inspect the current snapshot, a "Clear Data" action to reset the tables, and a "GC" button that invokes the simulator’s garbage collector so you can see how memory usage changes.
This is useful if a Form is slow. You might be able to pinpoint it to a specific component using this tool.
The Log on the bottom includes debug related information. For example, it warns about the usage of mutable images which might be slow on some platforms. This also displays warnings when an unlocked image is drawn etc. A live "Image Memory Overhead" meter summarizes how much native image memory the current form consumes so you can correlate spikes with your drawing code.

The rendering tree view allows you to inspect the hierarchy painting. You can press the refresh button which will trigger the painting of the current Form. Every graphics operation is logged and so is the stack to it.
You can then inspect the hierarchy and see what was drawn by the various components. You can click the "stack" buttons to see the specific stack trace that lead to that specific drawing operation.
This is a powerful debugging tool as you can see "overdraw" within this tool. E.g if you see fillRect or similar APIs invoked in the parent and then again and again in the children this could show a problem.
| Android devices have a nice overdraw debugging tool |
52.5. Network speed

This feature is actually more useful for general debugging but it’s sometimes useful to simulate a slow/disconnected network to see how this affects performance.
For this purpose the Codename One simulator allows you to slow down networking or even fake a disconnected network to see how your application handles such cases.
52.6. Debugging Codename One sources
When you debug your app with your source code you can place breakpoints deep within Codename One and gain unique insight. You can also use the profilers and profile into Codename One to gain similar performance specific insight.
When you run into a bug or a missing feature you can push that feature/fix back to Codename One using a pull request. GitHub makes that process trivial and in this new video and slides below you show you how. The steps to use the code are:
Signup for GitHub
Fork http://github.com/codenameone/CodenameOne and http://github.com/codenameone/codenameone-skins (also star and watch the projects for good measure).
Clone the git URLs from the projects into the IDE using the Team → Git → Clone menu option. Notice that you must deselect projects in the IDE for the menu to appear.
Download the cn1-binaries project from GitHub here.
Unzip the cn1-binaries project and make sure the directory has the name cn1-binaries. Verify that cn1-binaries, CodenameOne and codenameone-skins are within the same parent directory. .In your own project remove the jars both in the build & run libraries section. Replace the build libraries with the
CodenameOne/CodenameOneproject. Replace the runtime libraries with theCodenameOne/Ports/JavaSEPortproject.
This allows you to run the existing Codename One project with the Codename One source code and debug into Codename One. You can now also commit, push and send a pull request with the changes.
52.7. Device testing Framework/Unit testing
Codename One includes a built in testing framework and test recorder tool as part of the simulator. This allows developers to build both functional and unit test execution on top of Codename One. It even enables sending tests for execution on the device (pro-feature).
To get started with the testing framework, launch the application and open the test recorder in the simulator menu.

Once you press record a test will be generated for you as you use the application.

You can build tests using the Codename One testing package to manipulate the Codename One UI programmatically and perform various assertions.
Unlike frameworks such as JUnit which assign a method per test, the Codename One test framework uses a class per test. This allows the framework to avoid reflection and thus allows it to work on the device.
52.8. EDT error handler and sendlog
Handling errors or exceptions in a deployed product is pretty difficult, most users would throw away your app and some would give it a negative rating without providing you with the opportunity to actually fix the bug that might have happened.

Google improved on this a bit by allowing users to submit stack traces for failures on Android devices but this requires the users approval for sending personal data which you might not need if you want to receive the stack trace and maybe some basic application state (without violating user privacy).
For quite some time Codename One had a powerful feature that allows you to both catch and report such errors, the error reporting feature uses the Codename One cloud which is exclusive for pro/enterprise users. In Codename One you catch all exceptions on the EDT (which is where most exceptions occur) and display an error to the user as you can see in the picture. This isn’t helpful to you as developers who want to see the stack; furthermore you might prefer the user doesn’t see an error message at all!
Codename One allows you to grab all exceptions that occur on the EDT and handle them using the method addEdtErrorHandler in the Display class. Adding this to the Log’s ability to report errors directly to you and you can get a powerful tool that will send you an email with information when a crash occurs!
This can be accomplished with a single line of code:
Log.bindCrashProtection(true);You place this in the init(Object) method so all future on-device errors are emailed to you. Internally this method uses the Display.getInstance().addEdtErrorHandler() API to bind error listeners to the EDT. When an exception is thrown there it’s swallowed (using ActionEvent.consume()). The Log data is then sent using Log.sendLog().
If your crash handler runs while networking is unavailable or you want to avoid
blocking the EDT, use Log.sendLogAsync() instead. It performs the upload in a
background thread and is what Codename One’s lifecycle helper falls back to when
regular error reporting fails.
You can also plug in your own crash reporting pipeline by calling
Display.getInstance().setCrashReporter(CrashReport). The
CrashReport
callback will receive the exception, device information, and log payload so you
can forward it to services like Firebase Crashlytics or your in-house tools.
To truly gain from this feature you need to use the Log class for all logging and exception handling instead of APIs such as System.out.
To log standard printouts you can use the Log.p(String) method and to log exceptions with their stack trace you can use Log.e(Throwable).
52.9. Kitchen sink case study
Performance is one of those vague subjects that’s often taught by example.
While debugging the contacts demo (part of the new kitchen sink demo), its performance appeared sub-par. The initial assumption was that this was due to the implementation of getAllContacts and that there was nothing to do. Later, while debugging an unrelated issue, an anomaly was noticed during the loading of the contacts.
This led to the discovery that you’re loading the same resource file over and over again for every single contact in the list!
In the new Contacts demo you have a share button for each contact, the code for constructing a ShareButton looks like this:
This seems reasonable until you realize that the constructors for SMSShare, EmailShare & FacebookShare load the icons for each of those…
These icons are in a shared resource file that you load and don’t cache. The initial workaround was to cache this resource but a better solution was to convert this code:
Into this code:
@Override
public Image getIcon() {
Image i = super.getIcon();
if(i == null) {
i = Resources.getSystemResource().getImage("sms.png");
setIcon(i);
}
return i;
}This way the resource uses lazy loading as needed.
This small change boosted the loading performance and probably the general performance due to less memory fragmentation.
The lesson that you should learn every day is to never assume about performance…
52.9.1. Scroll performance - threads aren’t magic
Another performance pitfall in this same demo came during scrolling. Scrolling was janky (uneven/unsmooth) right after loading finished would recover after a couple of minutes.
This relates to the images of the contacts.
To hasten the loading of contacts you load them all without images. You then launch a thread that iterates the contacts and loads an individual image for a contact. Then sets that image to the contact and replaces the placeholder image.
This performed well in the simulator but didn’t do too well even on powerful mobile phones. You assumed this wouldn’t be a problem because you used Util.sleep() to yield CPU time but that wasn’t enough.
Often when you see performance penalty the response is: "move it to a separate thread." The problem is that this separate thread needs to compete for the same system resources and merge its changes back into the EDT. When you perform something intensive you need to make sure that the CPU isn’t needed right now…
In this and past cases you solved this using a class member indicating the last time a user interacted with the UI.
Here you defined:
private long lastScroll;Then you did this within the background loading thread:
This effectively sleeps when the user interacts with the UI and loads the images if the user hasn’t touched the UI in a while.
Notice that you also check if the scroll changes, this allows you to notice cases like the animation of scroll winding down.
All you need to do now is update the lastScroll variable whenever user interaction is in place. This works for user touches:
This works for general scrolling:
| Due to technical constraints you can’t use a lambda in this specific case… |
53. Testing with JUnit 5
Codename One ships two compatible test frameworks. com.codename1.testing.AbstractTest, driven by the cn1:test Maven goal, is the only way to run tests on a physical iOS or Android device — JUnit Jupiter isn’t available on ParparVM. The JavaSE simulator also exposes a standard JUnit 5 integration so you can write tests that run through Surefire and your IDE’s native test runner; those tests run only in the simulator JVM but in exchange give you reflection, mocking libraries, and the rest of the standard Java testing ecosystem.
Both styles coexist in the same project under common/src/test/java. You pick per test class. This chapter explains when to reach for which, walks through the JUnit annotations, and shows how the two frameworks compare side by side.
53.1. When to use JUnit versus AbstractTest
| Framework | Use it for | Don’t use it for |
|---|---|---|
| Tests that must execute on a real device ( | Tests that need reflection, Mockito, AssertJ, parameterized data sets, |
| Simulator-only tests. Anything that wants a full JVM at test time — reflection, mocking libraries, parameterized tests, IDE green-bar integration, | Anything that must also run on a device — JUnit Jupiter isn’t available on ParparVM. |
The two runners discover disjoint sets of test classes (cn1:test looks for com.codename1.testing.UnitTest implementers; Surefire looks for @Test-annotated methods), so a project can mix both. mvn install runs Surefire during the test phase and cn1:test from the javase module’s test profile in the same phase — you don’t lose either test pass.
53.2. Dependencies
The cn1app archetype generates a common/pom.xml and javase/pom.xml that already pull in junit-jupiter and codenameone-javase at test scope. If your project predates that wiring, add these dependency blocks yourself:
<dependencies>
<dependency>
<groupId>com.codenameone</groupId>
<artifactId>codenameone-javase</artifactId>
<scope>test</scope>
</dependency>
<dependency>
<groupId>org.junit.jupiter</groupId>
<artifactId>junit-jupiter</artifactId>
<version>5.9.3</version>
<scope>test</scope>
</dependency>
</dependencies><dependency>
<groupId>org.junit.jupiter</groupId>
<artifactId>junit-jupiter</artifactId>
<version>5.9.3</version>
<scope>test</scope>
</dependency>Tests live in common/src/test/java. Surefire only runs from the javase module — the common module keeps Surefire skipped (<skipTests>true</skipTests>) to avoid running each test twice, since javase/pom.xml mounts the same sources via <testSourceDirectory>${project.basedir}/../common/src/test/java</testSourceDirectory>.
53.3. A minimal JUnit test
Run with:
mvn -pl javase test # all JUnit + cn1:test
mvn -pl javase test -Dtest=GreetingFormTest # one class
mvn -pl javase test -Dtest=GreetingFormTest#formShowsExpectedTitle # one method53.4. @CodenameOneTest
A class-level meta-annotation equivalent to @ExtendWith(CodenameOneExtension.class). The extension does four things:
If
GraphicsEnvironment.isHeadless()is true, throwTestAbortedExceptionfrom@BeforeAll. JUnit reports the class as skipped rather than failed, and the Display singleton is never left half-initialized — so subsequent test classes in the same JVM aren’t poisoned. This makes JUnit-style Codename One tests safe to run on a headless CI runner; they simply skip.Boot
Displayonce per JVM viaDisplay.init(null). The call is idempotent, so multiple@CodenameOneTestclasses share one Display instance for the rest of the test run.Apply any visual-config annotations (
@Theme,@DarkMode,@LargerText,@Orientation,@RTL,@SimulatorProperty) on the EDT in one batch before each test, followed by a single theme refresh.Dispatch
@RunOnEdttest methods throughCN.callSeriallyand rethrow their exceptions on the JUnit thread so stack traces stay clickable in IDEs.
53.5. @RunOnEdt
Place on a method (or on the class for all tests) when the body mutates UI state.
Class-level @RunOnEdt also routes @BeforeEach/@AfterEach methods through the EDT. Method-level @RunOnEdt is scoped to that one @Test.
Tests that only exercise pure model or utility code can omit @RunOnEdt and run on the JUnit worker thread — they’re faster because nothing pumps the EDT.
53.6. @SimulatorProperty / @SimulatorProperties
Set a property visible to the simulator before the test runs.
The scope field selects where the value lands:
| Scope | Where | When applied |
|---|---|---|
|
| After Display init. Use for properties your app reads via |
|
| Before Display init (class-level only). Use for things the simulator reads at startup, for example |
The JavaSE port compiles at source 1.7, which predates @Repeatable. To set more than one property on the same target, wrap multiple @SimulatorProperty entries inside @SimulatorProperties({…}) rather than repeating the annotation directly.
53.7. @Theme
Loads a base theme resource and installs it through UIManager.setThemeProps, then triggers a refresh. The annotation accepts either of two mutually exclusive inputs.
By native theme. Use the NativeTheme enum for the themes bundled into the simulator jar — the same set the simulator’s Simulate > Native Theme menu offers:
The enum carries the resource path (NativeTheme.IOS_MODERN.resourcePath() returns /iOSModernTheme.res) and the simulator-menu label (displayName()), so test reports can render the same name a user sees in the simulator UI.
By resource path. For app themes shipped under src/main/resources or src/test/resources, point value at the .res file with a leading slash:
If both nativeTheme and value are set, nativeTheme wins. If neither is set, the annotation is a no-op.
53.8. @DarkMode
Toggles dark/light mode via Display.setDarkMode(Boolean) and refreshes the active form.
53.9. @LargerText
Sets the accessibility text-scale multiplier — the same knob exposed by the simulator’s Simulate → Larger Text submenu. Useful for catching layout regressions at accessibility font sizes.
scale = 1.0f restores the default size; common values mirror the menu’s 1.3f / 1.6f / 2.0f presets.
53.10. @Orientation
Forces the simulator into portrait or landscape for the test.
This calls a non-persisting setter on JavaSEPort and sets an explicit-portrait flag honored by Display.isPortrait() — so unit-test JVMs (where the canvas inherits the host window’s full size and would otherwise read landscape on every wide screen) get the expected orientation back.
53.11. @RTL
Flips the look-and-feel into right-to-left mode (Arabic, Hebrew) via UIManager.getInstance().getLookAndFeel().setRTL(…). The active form is revalidated so existing layouts reflow before the test body asserts.
53.12. Annotation resolution
When the same annotation appears at both the class and the method level, method wins. Annotations the method doesn’t override are inherited from the class. Annotations that appear on neither leave Display state alone — the extension never resets a knob the caller didn’t ask for. Use @AfterEach for cross-test cleanup if a class must leave the simulator pristine for the next one.
53.13. EDT semantics
@RunOnEdt dispatches the test body through CN.callSerially(…) and uses a latch with wait/notify to block the JUnit worker thread until the EDT-side runnable finishes or timeoutMillis elapses. Throwables from inside the EDT runnable are captured and rethrown on the JUnit thread so the assertion stack trace lands in the IDE as if the test had been invoked directly.
Without @RunOnEdt, the test body runs on the Surefire worker thread — fine for pure model assertions, broken for UI mutation. Forms, components, and UIManager are EDT-confined; touch them off the EDT and you get sporadic deadlocks and rendering glitches.
53.14. Headless behavior
Display.init(null) eventually calls JavaSEPort.init(null), which constructs a javax.swing.JFrame to host the simulator canvas. JFrame construction in a headless JVM throws HeadlessException immediately. Therefore:
Local dev (macOS / Windows / Linux desktop): works out of the box.
CI with an X server or Xvfb: works — wrap your build with
xvfb-run mvn testif the runner is otherwise headless.CI without DISPLAY, or with explicit
-Djava.awt.headless=true: every@CodenameOneTestclass aborts viaTestAbortedExceptionfrom@BeforeAll. JUnit reports the class as skipped, not failed, and crucially the Display singleton is never left half-initialized — so subsequent test classes in the same JVM aren’t poisoned.
This is why the framework’s internal CodenameOneExtensionTest (in the Codename One sources) carries @DisabledIfSystemProperty(named = "java.awt.headless", matches = "true"). The extension catches the headless case AWT detects automatically (Linux without DISPLAY); the annotation catches the explicit -Djava.awt.headless=true case. Together they let the test class skip cleanly on a headless runner.
Pure-logic tests (no UI, no @CodenameOneTest) can run on any headless runner without configuration.
53.15. Coexistence with cn1:test
The two runners discover disjoint sets of classes:
cn1:testlooks for classes thatimplements com.codename1.testing.UnitTest(whichAbstractTestextends).Surefire (JUnit Jupiter) looks for
@Test-annotated methods.
They don’t trip over each other. mvn install runs Surefire during the test phase, then the cn1:test execution bound in the javase/pom.xml test profile runs in the same phase. To target just one runner:
mvn -pl javase test # both runners
mvn -pl javase test -DskipTests # skip Surefire, cn1:test still runs
mvn -pl javase test -Dtest=NoMatch # filter Surefire to nothing,
# cn1:test still runs53.16. Side-by-side example
The same "sign in, assert Home is shown" check, written both ways:
The UI driving (TestUtils.*) is identical — TestUtils is independent of the runner. What changes is the lifecycle plumbing: shouldExecuteOnEDT() + runTest() returns boolean becomes @RunOnEdt + @Test void + a standard assertion library.
53.17. Cross-reference
For the
AbstractTestframework’s full API surface (TestUtilshelpers,screenshotTesttolerance algorithm, baseline management), see Screenshot Testing in the performance chapter.For the
cn1:testMaven goal, see the test goal appendix.
54. Advertising
Codename One provides a pluggable advertising API under com.codename1.ads. The
framework defines the formats, the consent flow and the app/UI lifecycle
integration; an ad network is supplied by a separate library that implements the
provider interface. The reference implementation is the Google AdMob library
(cn1-admob), but the design is network agnostic - AdMob, AppLovin MAX, Unity
LevelPlay or a custom mediation layer all plug in the same way, with no changes
to the framework or the build.
The supported formats are:
Banner - a small inline ad that lives in the component hierarchy (
com.codename1.ads.BannerAd).Interstitial - a full screen ad shown at a natural break, such as between game levels (
com.codename1.ads.InterstitialAd).Rewarded - an opt-in full screen ad that grants a reward for watching (
com.codename1.ads.RewardedAd).Rewarded interstitial - an incentivized transition ad (
com.codename1.ads.RewardedInterstitialAd).App open - shown when the app is brought to the foreground (
com.codename1.ads.AppOpenAd).Native - assets you render with your own components (
com.codename1.ads.NativeAd).
The screenshot below is the advertising sample running in the simulator against
the deterministic mock provider (cn1-ads-mock): a news feed with an in-feed
native ad (the "Sponsored" row, rendered with the app’s own components) and an
anchored banner at the bottom.

54.1. Ad provider cn1libs
Several provider libraries ship with the framework. They’re released to Maven
Central together with the core and the AI cn1libs, sharing the same version
(${cn1.version}), so you never mix versions. Each declares its own native SDK
dependencies (Pods / Gradle dependencies / permissions), applied automatically
when the library is on the classpath; you don’t edit build hints by hand,
except for the per-app id described under Section 54.9, “Configuring the AdMob application id”.
| cn1lib | Provider class | Provides |
|---|---|---|
|
| Google AdMob on the Google Mobile Ads SDK (banner, interstitial, rewarded, rewarded interstitial, app open), with AdMob mediation behind it. |
|
| AppLovin MAX mediation (banner, interstitial, rewarded, app open). |
|
| Unity LevelPlay (ironSource) mediation (banner, interstitial, rewarded). |
|
| A deterministic, network-free provider that renders fixed labelled ads - for unit tests, screenshot tests and trying the API in the simulator. |
Add the matching dependency to your project’s common/pom.xml. The provider
libraries use a -lib aggregator with <type>pom</type> so Maven pulls in the
per-platform classifier jars:
<dependency>
<groupId>com.codenameone</groupId>
<artifactId>cn1-admob-lib</artifactId>
<version>${cn1.version}</version>
<type>pom</type>
</dependency>cn1-ads-mock is a single cross-platform jar, so it needs no classifier:
<dependency>
<groupId>com.codenameone</groupId>
<artifactId>cn1-ads-mock</artifactId>
<version>${cn1.version}</version>
</dependency>54.2. Enabling a provider
Enable a provider once at startup. Each library exposes a static install()
method that registers its provider with AdManager:
That single call binds the provider; the rest of your code uses only the
framework API in com.codename1.ads. If no provider is registered the API
stays safe: format support reports false and loads fail with
AdError.CODE_UNSUPPORTED instead of throwing, so a build without an ad library
still runs.
54.3. Initialization and consent
Collecting privacy consent is mandatory on modern platforms before personalized ads can be served: in the EEA/UK the GDPR consent form must be shown (providers wrap Google’s User Messaging Platform or an equivalent), and on iOS the App Tracking Transparency prompt must be presented to access the advertising identifier. The recommended order is to initialize, gather consent, then load:
AdConfig also carries the global compliance flags every network requires:
test mode, test device ids, child directed treatment, under-age-of-consent
treatment and a maximum ad content rating.
Never ship a release build with testMode on, and never click live ads
during development - both violate ad network program policies. Use the test ad
unit ids while developing. |
54.4. Banner ads
BannerAd is a regular Codename One component. Add it to a form (typically
anchored at the top or bottom) and call load():
The default SIZE_ADAPTIVE requests an anchored adaptive banner sized to the
available width, which is the recommended modern banner type.
54.5. Interstitial ads
Interstitials are event driven - load, then show when loaded, and preload the next one when the current ad is dismissed:
You can also let Codename One show an interstitial automatically on screen transitions, no more often than a given interval:
54.6. Rewarded and rewarded interstitial ads
Register a reward listener and grant the reward when it fires. For valuable rewards, verify server side rather than trusting the client:
RewardedInterstitialAd has the same API but is shown on a transition rather
than opt-in.
54.7. App open ads
App open ads are shown while the app is brought to the foreground. Let the manager and provider handle the foreground hook and freshness window for you:
54.8. Native ads
Native ads let you render the advertiser’s assets with your own components, so the ad matches the look and feel of the surrounding content. This is the format to reach for in content driven apps - a news or social feed, a store listing, a chat or a search results screen - where a banner feels bolted on but a row styled like the others fits in. The ad must still be clearly labelled (for example "Sponsored"):
NativeAd exposes the headline, body, call-to-action, advertiser and rating
that you bind to your own components. Native ad support is an optional provider
capability; when the active provider doesn’t support it, NativeAdLoader
reports the format as unsupported.
54.9. Configuring the AdMob application id
The GMA SDK requires your per-app AdMob application id in the native project.
Because it differs per app it’s not baked into the library; set it with the
standard build hints in your project’s codenameone_settings.properties:
codename1.arg.android.xapplication=<meta-data android:name="com.google.android.gms.ads.APPLICATION_ID" android:value="ca-app-pub-XXXXXXXX~YYYYYYYY"/>
codename1.arg.ios.plistInject=<key>GADApplicationIdentifier</key><string>ca-app-pub-XXXXXXXX~YYYYYYYY</string>The SDK dependencies themselves (the GMA pod / Gradle dependency and the
INTERNET permission) are declared by the cn1-admob library, so they’re added
automatically when the library is on the classpath.
54.10. Implementing a provider
Third party networks plug in by implementing com.codename1.ads.spi.AdProvider
(and the optional NativeAdProvider capability) and calling
AdManager.registerProvider(…) - conventionally from a static install()
method. No framework or build-tool changes are required.
For tests and screenshots the framework ships a deterministic, network-free
provider, MockAdProvider (in cn1-ads-mock), that renders fixed, labelled ads
with stable sizes and colours.
55. Crash Protection
Crash Protection is an opt-in service that captures uncaught exceptions in your shipping app and files them as deduplicated issues on your GitHub repository. Symbolicated stack traces, scrubbed messages, and a per-bug counter are all recorded server-side; you triage from GitHub Issues like any other bug.
The service is available on the Pro and Enterprise subscription tiers. See the pricing page for current limits.
55.1. What gets stored where
Three things move when you opt in:
Symbol bundles (ProGuard
mapping.txton Android, dSYM on iOS, debug-info-bearing binaries on Mac/Linux/Win32). Uploaded by the Codename One build server after each successful release build. Stored compressed; subject to per-tier storage quota.Crash reports (one per device occurrence). Sent by the app at runtime via
CrashProtection.capture(t)or the automatic EDT error handler. Scrubbed on the device before transmission (see Privacy below).GitHub issues — the actual triage surface. One issue per unique crash fingerprint. Subsequent occurrences of the same fingerprint bump a counter on the issue body rather than filing duplicates.
Codename One never reads or persists the unscrubbed message body. The crash data store is the issue tracker on your repository, not a separate database. The service keeps only the minimum lookup state needed to find the right issue on the next occurrence.
55.2. Opting in
Add this line to your app’s codenameone_settings.properties:
codename1.arg.crashProtection.enabled=trueThe codename1.arg. prefix marks it as a build hint — when the property reaches the Codename One build server, it tells the build to upload the symbol bundle (PDB / dSYM / .debug / mapping.txt) to the crash-protection service alongside the normal release artifact.
55.2.1. Runtime hook
In your Lifecycle.init:
install() registers the EDT error handler and (on Android) wires Thread.UncaughtExceptionHandler. It’s idempotent and a no-op on the simulator. setEnabled(boolean) controls whether captured crashes actually get sent to the server — the captured payload is always persisted locally first, so setEnabled(true) after the fact drains the buffer.
You can also report a caught-but-noteworthy exception with CrashProtection.capture(e).
55.3. Per-platform opt-out
Sometimes one platform’s symbols are noisy or you don’t ship that target. Disable a platform with:
codename1.arg.crashProtection.and.enabled=false
codename1.arg.crashProtection.ios.enabled=false
codename1.arg.crashProtection.mac.enabled=false
codename1.arg.crashProtection.linux.enabled=false
codename1.arg.crashProtection.win.enabled=falseSetting one of these to false makes CrashProtection.install() a no-op at runtime on that platform AND skips the build-time symbol upload for it. Setting to true (or leaving unset) keeps the platform enabled.
The runtime check uses Display.getInstance().getPlatformName(). Supported values: and, ios, mac, linux, win, javascript, javase.
55.4. Tier limits
| Tier | Storage quota | Symbol retention |
|---|---|---|
Pro | 100 MB compressed | 3 weeks |
Enterprise | 500 MB compressed | 6 weeks |
Symbol bundles are gzipped before storage. mapping.txt files typically compress ~10x; dSYMs ~2x. The quota admits several recent builds per app for a typical developer.
When a new symbol upload would push you over the quota, the build’s symbol step is rejected with HTTP 413 (the build itself succeeds). You can free space from the Tracked apps tab in the console — delete an old build’s symbols or remove a whole app’s enrollment.
55.5. Privacy
55.5.1. What’s PII
PII is short for personally identifiable information: any field in a crash payload that could be traced back to a specific user. The pieces of a Java exception message that are typically PII are email addresses, account numbers, phone numbers, IP addresses, full URLs to authenticated endpoints (with session tokens in the query string), and the contents of user input fields that ended up in the message via string concatenation. Stack trace frames are class / method / file / line — they describe code paths, not users, so they’re not PII.
The Codename One crash-protection client runs incoming messages through a scrubber before transmission. The scrubber can be replaced with a stricter rule set if your application’s exception messages routinely carry data you don’t want to leave the device.
55.5.2. What gets sent
CrashReportPayload carries these fields. The marked one goes through PiiScrubber before transmission.
eventId(UUID, used for idempotent dedup)buildKey(anti-spoofing token; matched against the uploaded symbol bundle)packageName,appVersion,platform,osVersion,localeexceptionClassmessageScrubbed— scrubbedframes[]— class / method / file / line /nativeflag per framerawStack— the pre-rendered Java stack captured viaprintStackTrace, including the cause chain and any verbatim platform formatting. It complements the structuredframes(whichgetStackTrace()now populates on every port) and is the readable trace on the JavaScript port, where the JavaScript engine’s stack has no structured framestraceFormat— how the server should readrawStack:structured,parparvm-text,js-error, ornone. Derived, never guessedmappingId— the id of the obfuscation mapping a hardened build shipped with, so a report ties to the exact mapping even if a rebuild reused the build key; empty for unhardened buildshardenLevel— the hardening level of the build, so the server can give a specific reason for an unretraceable reportclientTs
55.6. Crash reports from a hardened build
When a build is hardened (see Chapter 64, App Hardening), the build server retains the cross-platform obfuscation mapping and symbolicates incoming reports against it, so a hardened build’s crashes still land as readable, correctly lined issues. Two things follow from how the mapping is retained: a report whose mapping has aged out of retention can no longer be retraced, and a locally hardened build — whose mapping never reached the server — can’t be symbolicated at all. The ParparVM ports (iOS, tvOS, watchOS, mac-native, Windows, Linux) report structured frames, and also carry the pre-rendered trace in rawStack; the JavaScript port has no structured frames, so its report relies on the rawStack JavaScript engine stack (js-error), symbolicated best-effort through the source map.
55.6.1. Default scrubber rules
PiiScrubber applies these by default:
Email addresses: redacted to the first 3 characters of the local part.
[email protected]becomesjoe***@example.com(the full domain is preserved so the issue still tells you which provider was involved).Long digit runs: any run of 6 or more consecutive digits collapses to
[num]. Catches phone numbers, order IDs, account numbers, ZIP+suffix, etc.URLs aren’t scrubbed by default. Override the scrubber if your app’s URLs carry session tokens.
Override scrubMessage(String) or scrubFrame(String, String) on a PiiScrubber subclass and register via CrashProtection.setScrubber(myScrubber) if you need stricter rules.
55.7. Mapping packages to repositories
In the console at https://cloud.codenameone.com/console/index.html, open Repo mappings:

Click Add mapping and supply:
Package name — the exact value from
codenameone_settings.properties.Installation — which authorized GitHub App installation should file the issue. Only shown if you have more than one installation linked.
Repository — pick from the dropdown of the installation’s repos.
You must have authorized the Codename One Crash Protection GitHub App for at least one of your repositories first. The mapping page renders a button labeled Connect on GitHub that opens the App install flow on github.com. The post-install redirect brings you back to the same page with the installation already loaded; if you already have one installation and want to add another (for example a second GitHub org), the Connect another GitHub org card lets you link an additional one without disturbing the existing mapping.
55.8. Setup checklist
Pro or Enterprise subscription.
Add
codename1.arg.crashProtection.enabled=truetocodenameone_settings.properties.Call
CrashProtection.install()inLifecycle.init. CallCrashProtection.setEnabled(true)once you have the user’s consent.Build your app for release. The Codename One build server uploads the symbol bundle automatically.
Open the console, go to Repo mappings, click Connect on GitHub, and install the App on the repo you want crashes to land in.
Add a mapping for your package → repo.
Crashes from your release builds will now appear as GitHub issues on the mapped repo.
56. Analytics
The analytics API records how your application is used in the field. It’s built around a small provider SPI: you register one or more providers with the Analytics entry point, then report screen views, events, user properties and crashes. The Analytics class fans every call out to all registered providers, but only after the matching consent has been granted. Consent is central to this API and is explained in Consent and privacy below.
Codename One ships several providers: a first-party service that reports into the Codename One cloud (with capabilities gated by your subscription tier), Google Analytics 4, Matomo (a privacy-first, self-hostable option), Firebase, and a logging provider for the simulator and tests. You can also write your own provider for any other backend.
The older AnalyticsService class still works but is deprecated. It now delegates to the API described here. See Migrating from AnalyticsService at the end of this chapter. |
56.1. Registering providers
Register providers once, early in your app’s lifecycle. Providers are plain objects — there is no reflection or service lookup, which keeps the mechanism safe under the obfuscation applied to release builds.
Once at least one provider is registered, report usage from anywhere in your app:
Analytics.crash emits a lightweight exception event (for example GA4’s app_exception) to whichever analytics backends you have registered, so exception counts appear next to your usage metrics. It’s separate from Codename One Crash Protection (com.codename1.crash.CrashProtection), which is a dedicated pipeline that records full, symbolicated stack traces to the build cloud crash console for debugging. The two are independent: use Crash Protection to diagnose crashes, use Analytics.crash when you also want exception events in your analytics, and enable either or both.
56.2. Consent and privacy
The API is designed to help you comply with privacy regulations such as GDPR and CCPA. A ConsentMode controls what happens before the user makes an explicit choice. The default is OPT_IN: nothing is collected or transmitted until the application records consent.
AnalyticsConsent.all() grants every category and AnalyticsConsent.none() denies every category. The older granted() and denied() methods remain as aliases.
Consent is broken down by category, so you can honor granular choices — for example allowing crash reporting while declining behavioral analytics:
The consent choice is persisted, so it survives restarts. Screen views and events require the analytics category, crash reports require crashReporting, and setUserId requires personalization. Calls made without the matching consent are dropped.
56.2.1. Consent you already hold
If your application has already obtained consent through its own mechanism — a custom prompt, a third-party consent-management platform, an enterprise device-management policy, or a jurisdiction where you have determined consent isn’t required — record it once at startup so reporting flows without a second prompt:
You can also seed every category and then revoke just one with the builder, for example to allow analytics but not ad storage:
If you would rather not gate at all, switch the default so collection is active unless the user withdraws it. This places the compliance responsibility on you as the integrator:
Note that the service records pseudonymous data rather than anonymous data. The client id described below is a persistent identifier stored on the device; it isn’t tied to a real-world identity and the server discards full IP addresses, but storing and reading such an identifier for usage tracking is often treated as consent-requiring under GDPR and similar regimes. That’s why opt-in is the safe default. Relax it only when you are confident the change fits your use.
56.2.2. Client identity and erasure
Each device is identified by a pseudonymous client id. It’s generated on first use and stored locally — it isn’t derived from any hardware identifier. To honor an erasure request ("right to be forgotten"), reset it:
For the first-party service this can be paired with a server-side deletion of the previous id’s data.
56.3. Automatic events
Codename One emits a few events for you, so the common funnels work without any wiring. Like every report these are consent-gated and do nothing until a provider is registered, so they’re always safe.
| Event | When it fires |
|---|---|
|
|
| A purchase completes and its receipt is posted. The gap between this and |
| A social login ( |
| A social login fails, with the provider in |
| The native share sheet is invoked. |
You can add your own events at any time with Analytics.event(…); these built-ins simply save you the boilerplate for the most common funnels.
56.4. Built-in providers
56.4.1. Codename One first-party service
CodenameOneAnalyticsProvider batches events and posts them to the Codename One cloud, which aggregates them into the reports shown in the developer console. App identity is read from the build-injected properties, so no API key is embedded in your app.
The capabilities you actually get — screen views, custom events, user properties, retention window, raw export — are gated server-side by your subscription tier. Higher tiers retain data longer and unlock richer reporting.
56.4.2. Google Analytics 4
GoogleAnalyticsProvider uses the GA4 Measurement Protocol. Create it with a measurement id (G-XXXXXXXX) and a Measurement Protocol API secret from the GA4 admin console:
Screen views are sent as the GA4 screen_view event and crashes as app_exception.
56.4.3. Matomo
MatomoAnalyticsProvider targets Matomo (formerly Piwik) through its HTTP tracking API. Matomo can be self-hosted and supports IP anonymization, which makes it a good fit for privacy-sensitive deployments:
56.4.4. Firebase
FirebaseAnalyticsProvider forwards to the native Firebase Analytics SDK on Android and iOS. Register it like any other provider:
Firebase reports only from a native Android or iOS build, and only when two things are in place. Without both, FirebaseAnalyticsProvider does nothing — which is why it’s always safe to register, including in the Codename One simulator and the desktop build, where it’s a no-op.
First, add the Firebase configuration file for your app (downloaded from the Firebase console) to the matching platform module’s resources:
Android:
android/src/main/resources/google-services.jsoniOS:
ios/src/main/resources/GoogleService-Info.plist
These are Maven project paths. The native/android and native/ios directories from the old Ant projects no longer apply.
Second, enable the SDK with build hints:
codename1.arg.android.firebaseAnalytics=true
codename1.arg.ios.firebaseAnalytics=trueThese hints add the Firebase Analytics Gradle dependency (Android) and the Firebase/Analytics pod (iOS), and make the build generate the native bridge that FirebaseAnalyticsProvider talks to.
| You need both the configuration file and the matching build hint. If either is missing the provider stays a no-op and no events are sent. Firebase events never show up in the Codename One simulator or a desktop run — verify on a real device (or a platform emulator/simulator) with the Firebase project configured for the build. |
56.4.5. Logging provider
LoggingAnalyticsProvider logs every call instead of sending it anywhere. It’s the recommended default in the simulator and is used as the backing provider in tests.
56.5. Writing your own provider
Implement AnalyticsProvider, or extend AbstractAnalyticsProvider and override only the calls you support. The Analytics class handles consent gating and fan-out for you, so a provider just forwards the data to its backend.
The init(AnalyticsContext) callback hands you the app name, version, platform, locale and the pseudonymous client id. onConsentChanged(AnalyticsConsent) lets a provider reconfigure when the user updates consent. supports(AnalyticsCapability) lets tooling introspect which features a provider offers.
56.6. Migrating from AnalyticsService
The deprecated AnalyticsService continues to compile and now routes through this API. To preserve its historical always-on behavior — which predates the consent model — AnalyticsService.init switches the default consent mode to OPT_OUT. New code should migrate to Analytics and manage consent explicitly:
| Deprecated call | Replacement |
|---|---|
|
|
|
|
|
|
subclassing | implement |
57. Commerce
Commerce is an optional service that validates your in-app purchases and subscriptions server-side and gives your app a single, store-agnostic question to ask: does this user have this entitlement right now? It wraps the existing Purchase API (see the Monetization chapter) — purchases still go through the platform store — and adds cloud receipt validation, a normalized subscription state machine across Apple and Google, lifecycle webhooks to your backend, and a revenue console.
Codename One doesn’t process payments and never touches your money — the stores (and, for physical goods, your own payment processor) do. Commerce is infrastructure that sits beside the money flow, exactly like the third-party services it replaces.
57.1. Entitlements, not SKUs
The core idea is the entitlement: an abstract access right such as pro or remove_ads. You map one or more store products to an entitlement, and your code only ever checks the entitlement:
An entitlement is active when any of its granting products is active. This matters: a promotional grant and a paid subscription, or a sandbox and a production purchase, can both map to pro without one hiding the other. Access is decided by a single authoritative rule — the latest expiry over the active grants, evaluated against a server timestamp — so a tampered device clock can’t extend it. Everything else (will-renew, billing stage, period type, family sharing) is advisory and never removes access on its own.
57.2. Client usage
In your Lifecycle.init (or wherever you set up purchases):
Drive purchases through the manager (these delegate to the Purchase API):
After a purchase, or on app start, validate the device’s receipts with the cloud and refresh the entitlement cache. refresh() makes a blocking network call, so run it off the EDT:
isEntitled returns the last cloud-validated answer when one is available, and otherwise falls back to the platform’s own receipt (treating the entitlement id as a subscription SKU) so a paying user is never locked out while the network is down.
57.3. How the app finds the service
Commerce reuses the standard build_key that every Codename One cloud build already carries, the same token the analytics provider sends — so there is nothing to wire into the build. CommerceManager.isCloudEnabled() is true on any cloud build and false in the simulator or a local build (where every call defers to Purchase). Two optional build hints tune it:
| Build hint | Default | Description |
|---|---|---|
|
| Set to |
| (Codename One cloud) | Base URL of the commerce service. Override only if you self-host. |
57.4. Server notifications
For the entitlement state to stay correct after the initial purchase — renewals, cancellations, refunds, billing retries, grace periods, holds — point the stores' server notifications at the service:
Apple — in App Store Connect, set the App Store Server Notifications V2 URL to
https://cloud.codenameone.com/api/v2/commerce/notifications/apple.Google — in the Play Console, set Real-time developer notifications and route the Pub/Sub topic to
https://cloud.codenameone.com/api/v2/commerce/notifications/google.
Notifications are idempotent (deduplicated on Apple’s notificationUUID / Google’s Pub/Sub messageId), so a redelivery never double-counts.
57.5. Server-side validation (connect your store credentials)
By default the service validates the store-signed receipt the device presents — enough to gate features, and it works with no setup. For server-authoritative validation — where the service calls Apple’s and Google’s own server APIs to confirm the real subscription state — provide your store credentials in the console Secrets page:
Apple — an App Store Connect API key, as three secrets:
commerce.apple.keyId,commerce.apple.issuerId, andcommerce.apple.privateKey(the contents of the.p8file).Google — a service account with Android Publisher access, as
commerce.google.serviceAccountJson(the full JSON key).
Secrets are stored AES-256-GCM encrypted in the BuildCloud vault; they’re decrypted only server-side at call time and are never shown in the console again. Once set:
Entitlements are confirmed against Apple’s
Get All Subscription Statusesand Google’ssubscriptionsv2.get, so a grant is server-verified rather than device-trusted, andSubscription renewals signalled by store notifications are recorded at their real amount (the renewal price lives only in the store’s server response).
Without credentials the service stays in device-trusted mode — everything still works, you just don’t get the server cross-check or accurate renewal revenue.
57.6. Lifecycle webhooks to your backend
Commerce can forward every normalized state change to your own backend. Configure a URL and a signing secret on the Commerce page of the console. Each event is HMAC-SHA256 signed (header CN1-Commerce-Signature) and carries:
A per-customer monotonic
sequence— so your consumer can reject stale events and never has to reorder defensively,The grant’s
state_version— reconcile against this,An always-present
effective_expiration_at, andThe event
idfor idempotent dedup.
Delivery is at-least-once, in sequence order per customer, with retries that back off exponentially. Event types mirror the familiar set: INITIAL_PURCHASE, RENEWAL, CANCELLATION, UNCANCELLATION, EXPIRATION, BILLING_ISSUE, PRODUCT_CHANGE, SUBSCRIPTION_PAUSED, REFUND_REVERSED, TRANSFER.
57.7. The console
The Commerce section in the console at https://cloud.codenameone.com/console/index.html is account-level by default, with an app filter to narrow to one app:
Overview — the subscription dashboard: headline KPIs (MRR, ARR, ARPU, active subscriptions, active trials, churn, trial conversion, customers) and trend charts for MRR, active subscriptions and revenue.
Insights — MRR movement (new vs churned), MRR forecast, realized-LTV curve, active subscriptions by store and by product, cohort-retention, and period-over-period MRR.
Customers — each app user and their active entitlements.
Transactions — the recent validated-event ledger.
Webhook — your delivery endpoint and signing secret.
57.8. Analytics
Commerce normalizes every active subscription to a monthly figure (MRR) and reconstructs the trends from the subscription history, so the dashboard matches what dedicated subscription-analytics tools provide:
MRR / ARR / ARPU — normalized recurring revenue, annualized, and per active subscription.
Churn and trial conversion rates, refund rate.
Cohort retention — monthly acquisition cohorts and the percentage still active each subsequent month.
Realized LTV — average cumulative revenue per paying customer by months since acquisition.
Forecast — projected MRR for the coming months from the current run-rate and recent growth.
Breakdowns by store and by product, and period-over-period comparison.
Every chart pairs a graph with its underlying data table (one tab-flip away) for export-friendly inspection. All money is shown in your reporting currency; transactions in other currencies are normalized to USD via daily exchange rates.
57.9. Privacy
Commerce stores entitlement state and transaction metadata (store, product id, event type, amount, validation state) keyed by your app-user id. It never stores card numbers or payment credentials — those stay with Apple, Google, or your processor. Family shared purchases grant access but are excluded from revenue. The minimum lookup state needed to resolve the next notification is kept; grants are retained as the durable record, while the high-churn ledger and delivered webhook rows are purged on a rolling window.
57.10. Setup checklist
Map your store products to entitlements in the console.
In the app, call
CommerceManager.getInstance().subscribe(…)/.purchase(…), then.refresh()off the EDT, and gate features with.isEntitled(…).Point Apple App Store Server Notifications V2 and Google RTDN at the service notification URLs.
(Optional) Set a webhook URL + secret on the Commerce console page to receive lifecycle events on your backend.
58. Monetization
Codename One integrates many built-in monetization options such as in-app purchases and subscriptions. Advertising is covered in its own chapter; see Advertising.
Many monetization options are available as third-party cn1libs that you can install through the Codename One website.
58.1. In-app purchase
In-app purchase is a helpful way to make app development profitable. Codename One supports in-app purchases of consumable and non-consumable products on Android and iOS. It also supports subscriptions. Even though the concept is simple, in-app purchase involves many moving parts, for subscriptions.
58.1.1. The SKU
In-app purchase support centers around the set of SKUs you want to sell. Each product, whether it’s a one-month subscription, an upgrade to the "Pro" version, or "10 disco credits," has a SKU (stock-keeping unit). Ideally, you can use the same SKU across every store that sells your app.
58.1.2. Types of products
Four classifications for products exist:
Non-consumable Product - This is a product that the user purchases once to "own." They can’t re-buy it. One example is a product that upgrades your app to a "Pro" version.
Consumable Product - This is a product that the user can buy more than once. For example, you might have a product for "10 Credits" that lets the user buy items in a game.
Non-Renewable Subscription - A subscription that you buy once, and won’t be "auto-renewed" by the app store. These are almost identical to consumable products, except that subscriptions need to be transferable across all the user’s devices. This means that non-renewable subscriptions require that you have a server that keeps track of the subscriptions.
Renewable Subscriptions - A subscription that the app store manages. The user will be automatically billed when the subscription period ends, and the subscription will renew.
| These subscription categories may not be explicitly supported by a given store, or they may use different names. You can integrate each product type in a cross-platform way using Codename One. For example, Google Play doesn’t distinguish between consumable products and non-renewable subscriptions, but iTunes does. |
58.1.3. The "hello world" of in-app purchase
Start with a simple example of an app that sells Worlds. First, pick the SKU for the product. Here you use com.codename1.world:
public static final String SKU_WORLD = "com.codename1.world";Although this example uses the package-name convention for a SKU, you can use any name you want, for example UA8879. |
Next, the app’s main class needs to implement the PurchaseCallback interface
Using these callbacks, the app receives notifications whenever a purchase changes. For this simple app, only itemPurchased() and itemPurchaseError() matter. The legacy itemRefunded(), subscriptionStarted(), and subscriptionCanceled() hooks are deprecated in the core API and are no longer dispatched by the stores. Instead of relying on callbacks for long-term entitlement state, query the current receipts at runtime with helpers such as Purchase.wasPurchased(…), Purchase.isSubscribed(…), or Purchase.getReceipts(). That keeps the UI aligned with the latest data from the underlying store.
Now in the start() method, add a button that lets the user buy the world:
At this point, the app can track the sale of the world. To make it more useful, add ToastBar feedback for purchase completion:
| You can test out this code in the simulator without doing any more setup and it will work. If you want the code to work on Android and iOS, you’ll need to set up the app and in-app purchase settings in the Google Play and iTunes stores respectively as explained below |
When the app first opens you see your button:

In the simulator, clicking on the "Buy World" button will bring up a prompt to ask you if you want to approve the purchase.

Now if you try to buy the product again, it pops up the dialog to let you know that you already own it.

58.1.4. Making it consumable
In the "Buy World" example above, the "world" product was non-consumable, since you could only buy the world once. You could change it to a consumable product by disregarding whether it was purchased before & keeping track of how many times it had been purchased.
You’ll use storage to keep track of the number of worlds that the user purchased. You need two methods to manage this count. One method gets the number of worlds that you own, and another adds a world to this count:
private static final String NUM_WORLDS_KEY = "NUM_WORLDS.dat";
public int getNumWorlds() {
synchronized (NUM_WORLDS_KEY) {
Storage s = Storage.getInstance();
if (s.exists(NUM_WORLDS_KEY)) {
return (Integer)s.readObject(NUM_WORLDS_KEY);
} else {
return 0;
}
}
}
public void addWorld() {
synchronized (NUM_WORLDS_KEY) {
Storage s = Storage.getInstance();
int count = 0;
if (s.exists(NUM_WORLDS_KEY)) {
count = (Integer)s.readObject(NUM_WORLDS_KEY);
}
count++;
s.writeObject(NUM_WORLDS_KEY, new Integer(count));
}
}Now you’ll change your buy code as follows:
And your itemPurchased() callback will need to add a world:
| When you set up the products in the iTunes store you will need to mark the product as a consumable product or iTunes will prevent you from purchasing it more than once |
58.1.5. Non-Renewable subscriptions
As you discussed before, there are two types of subscriptions:
Non-renewable
Auto-renewable
Non-renewable subscriptions are the same as consumable products, except that they’re shareable across devices. Auto-renewable subscriptions will continue as long as the user doesn’t cancel the subscription. They will be re-billed automatically by the appropriate app-store when the chosen period expires, and the app-store handles the management details itself.
| The concept of an "Non-renewable" subscription is unique to iTunes. Google Play has no formal similar option. To create a non-renewable subscription SKU that behaves the same in your iOS and Android apps you would create it as a regular product in Google play, and a Non-renewable subscription in the iTunes store. You’ll learn more about that in a later post when you go into the specifics of app store setup. |
The Purchase class includes both a purchase() method and a subscribe() method. On some platforms it makes no difference which one you use, but on Android it matters. If the product is set up as a subscription in Google Play, then you must use subscribe() to buy the product. If it’s set up as a regular product, then you must use purchase(). Since you enter "Non-renewable" subscriptions as regular products in the play store, you would use the purchase() method. |
58.1.6. Promotional offers (iOS)
Apple allows you to present discounted introductory pricing to existing subscribers via promotional offers. Codename One surfaces this capability through overloads of both Purchase.purchase(String, PromotionalOffer) and Purchase.subscribe(String, PromotionalOffer), which forward the promotional context to StoreKit when you start the transaction. Promotional offers are only honoured by iOS, so the overloads fall back to the regular buy flow on other platforms.
To build the signed discount payload required by Apple you can use the ApplePromotionalOffer helper:
Apple generates the signature and timestamp from your App Store Connect server notifications endpoint; Codename One passes them to the native StoreKit APIs. For one-time products you can call purchase(sku, offer) instead of subscribe(…).
58.1.7. Restoring purchases and managing subscriptions
Both Apple and Google provide built-in user interfaces for restoring past purchases and managing subscription billing preferences. Codename One exposes these entry points so you can surface the native flows without reimplementing them yourself.
Restores: Call
Purchase.isRestoreSupported()before presenting a "Restore purchases" button. When supported (iOS implements this natively), invokePurchase.restore()to prompt the operating system to re-deliver past transactions. Your app should implementRestoreCallback(like how you implementPurchaseCallback) so you can respond to individualitemRestored(…)events and to the completion or failure of the restore request.Subscription management: Use
Purchase.isManageSubscriptionsSupported()to detect whether the platform can show the subscription management UI. When it returnstrue, callingPurchase.manageSubscriptions(null)opens the store-specific settings screen (Apple’s subscription center on iOS and Google Play’s subscription management activity on Android). On Android you can optionally pass a SKU to deep-link directly to the plan the user should manage.
Because these flows are handled by the underlying store your UI doesn’t need to rebuild any billing screens. Gate the buttons on the capability checks above so that iOS and Android users get the familiar restore/manage dialogs while other platforms can fall back to your own help copy.
58.1.8. The Server-Side
Since a subscription purchased on one user device needs to be available across the user’s devices (Apple’s rules for non-renewable subscriptions), your app will need to have a server-component. In this section, you’ll gloss over that & "mock" the server interface. You’ll go into the specifics of the server-side below.
The receipts API
Subscriptions, in Codename One use the "Receipts" API. It’s up to you to register a receipt store with the in-app purchase instance, which allows Codename one to load receipts (from your server), and submit new receipts to your server. A Receipt includes information such as:
Store code (since you may be dealing with receipts from itunes, google play & Microsoft)
SKU
Transaction ID (store specific)
Expiry Date
Cancellation date
Buy date
Order Data (that you can use on the server-side to verify the receipt and load receipt details directly from the store it originated from).
The Purchase provides a set of methods for interacting with the receipt store, such as:
isSubscribed([skus])- Checks to see if the user is subscribed to any of the provided skus.getExpiryDate([skus])- Checks the expiry date for a set of skus.synchronizeReceipts()- Synchronizes the receipts with the receipt store. This will try to submit any pending purchase receipts to the receipt store, and the reload receipts from the receipt store.
In order for any of this to work, you must implement the ReceiptStore interface, and register it with the Buy instance. Your receipt store must implement two methods:
fetchReceipts(SuccessCallback<Receipt[]> callback)- Loads all the receipts from your receipt store for the current user.submitReceipt(Receipt receipt, SuccessCallback<Boolean> callback)- Submits a receipt to your receipt store. This gives you an opportunity to add details to the receipt such as an expiry date.
58.1.9. The "hello world" of Non-Renewable subscriptions
You’ll expand on the theme of "Buying" the world for this app, except, this time you will "Rent" the world for a period of time. You’ll have two products:
A 1-month subscription
A 1-year subscription
Notice that you create two separate SKUs for the 1 month and 1-year subscription. Each subscription period must have its own SKU. The example uses an array (PRODUCTS) that contains both of the SKUs. This is handy, as you’ll see in the examples ahead, because the APIs for checking status and expiry date of a subscription take the SKUs in a "subscription group" as input.
| Different SKUs that sell the same service/product but for different periods form a "subscription group." Conceptually, customers aren’t subscribing to a particular SKU, they’re subscribing to the subscription group of which that SKU is a member. As an example, if a user purchases 1-month subscription to "the world," they’re actually subscribing to "the world" subscription group. |
It’s up to you to know the grouping of your SKUs. Any methods in the Purchase class that check subscription status or expiry date of a SKU should be passed all SKUs of that subscription group. For example, If you want to know if the user is subscribed to the SKU_WORLD_1_MONTH subscription, it would not be enough to call iap.isSubscribed(SKU_WORLD_1_MONTH), because that wouldn’t consider if the user had purchased 1-year subscription. The correct way is to always call iap.isSubscribed(SKU_WORLD_1_MONTH, SKU_WORLD_1_YEAR), or iap.isSubscribed(PRODUCTS) since you have placed both SKUs into your PRODUCTS array.
Implementing the receipt store
| The receipt store is intended to interface with a server so that the subscriptions can be synced with multiple devices, as required by Apple’s guidelines. For this post you’ll just store your receipts on device using internal storage. Moving the logic to a server is a simple matter that this guide covers in a future post when you cover the server-side. |

A basic receipt store needs to implement just two methods:
fetchReceiptssubmitReceipt
You’ll register it in your app’s init() method so that it’s always available:
These methods are designed to be asynchronous since real-world apps will always be connecting to some sort of network service. Instead of returning a value, both of these methods are passed instances of the SuccessCallback class. It’s important to make sure to call callback.onSuccess() ALWAYS when the methods have completed, even if there is an error, or the Buy class will just assume that you’re taking a long time to complete the task, and will continue to wait for you to finish.
Once implemented, your fetchReceipts() method will look like:
This is straight forward. You’re checking to see if you already have a list of receipts stored. If so you return that list to the callback. If not you return an empty array of receipts.
Receipt implements Externalizable so you are able to write instances directly to Storage. |
The submitReceipt() method is a little more complex, as it needs to calculate the new expiry date for your subscription:
The main logic of this method involves iterating through all the existing receipts to find the latest current expiry date, so that when the user purchases a subscription, it’s added onto the end of the current subscription (if one exists) rather than going from today’s date. This enables users to renew their subscription before the subscription has expired.
In the real-world, you would implement this logic on the server-side.
The iTunes store and Play store have no knowledge of your subscription durations. This is why it’s up to you to set the expiry date in the submitReceipt method. Non-renewable subscriptions are essentially no different than regular consumable products. It’s up to you to manage the subscription logic - and Apple, in particular, requires you to do so using a server. |
Synchronizing receipts
In order for your app to provide you with current data about the user’s subscriptions and expiry dates, you need to synchronize the receipts with your receipt store. Purchase provides a set of methods for doing this. You’ll call one of them inside the start() method, and you may resynchronize at other strategic times if you suspect that the information may have changed.
The following methods can be used for synchronization:
synchronizeReceipts()- Asynchronously synchronizes receipts in the background. You won’t be notified when it’s complete.synchronizeReceipts(final long ifOlderThanMs, final SuccessCallback<Boolean> callback)- Asynchronously synchronizes receipts, but only if they haven’t been synchronized in the specified time. For example, In your start() method you might decide that you only want to synchronize receipts once per day. This also includes a callback that will be called when synchronization is complete.synchronizeReceiptsSync(long ifOlderThanMs)- Synchronously synchronizes receipts, blocking until it’s complete, and will only refetch if data is older than the given time (pass0to always refetch). This is safe to use on the EDT as it employsinvokeAndBlockunder the covers.
In your hello world app you synchronize the subscriptions in a few places.
At the end of the start() method:
And you also provide a button to allow the user to manually synchronize the receipts:
Expiry dates and subscription status
Now that you have a receipt store registered, and you have synchronized your receipts, you can query the Purchase instance to see if a SKU or set of SKUs is subscribed. Three useful methods in this realm:
boolean isSubscribed(String… skus)- Checks to see if the user is subscribed to any of the provided SKUs.Date getExpiryDate(String… skus)- Gets the latest expiry date of a set of SKUs.Receipt getFirstReceiptExpiringAfter(Date dt, String… skus)- This method will return the earliest receipt with an expiry date after the given date. This is needed in cases where you need to decide if the user should have access to some content based on its publication date. For example, If you published an issue of your e-zine on March 1, and the user purchased a subscription on March 15th, then they should get access to the March 1st issue even though it doesn’t necessarily fall in the subscription period. Being able to fetch the first receipt after a given date makes it easier to determine if a particular issue should be covered by a subscription.
If you need to know more information about subscriptions, you can always just call getReceipts() to get a list of all the current receipts and determine for yourself what the user should have access to.
In the hello world app you’ll use this information in a few different places. On your main form you’ll include a label to show the current expiry date, and you allow the user to press a button to synchronize receipts manually if they think the value is out of date:
Allowing the user to purchase the subscription
You should now have all the background required to implement the Hello World Subscription app. You’ll return to the code and see how the user purchases a subscription.
In the main form, you want two buttons to subscribe to the World, for one month and one year respectively. They look like:
58.1.10. Subscribe() vs purchase()
The Purchase class includes two methods for initiating a purchase:
purchase(sku)subscribe(sku)
Which one you use depends on the type of product that’s being purchased. If your product is set up as a subscription in the Google Play Store, then you should use subscribe(sku). Otherwise, you should use purchase(sku).
Handling purchase callbacks
The buy callbacks are like the ones implemented in the regular in-app purchase examples:
Notice that, in itemPurchased() you don’t need to explicitly create any receipts or submit anything to the receipt store. This is handled for you automatically. You do make a call to synchronizeReceiptsSync(0) but this is just to ensure that your toast message has the new expiry date loaded already.
58.1.11. Screenshots




58.1.12. Summary
This section demonstrated how to set up an app to use non-renewable subscriptions using in-app purchase. Non-renewable subscriptions are the same as regular consumable products except for the fact that they’re shared by all the user’s devices, and thus, require a server component. The app store has no knowledge of the duration of your non-renewable subscriptions. It’s up to you to specify the expiry date of purchased subscriptions on their receipts when they’re submitted. Google play doesn’t formally have a "non-renewable" subscription product type. To implement them in Google play, you would just set up a regular product. It’s how you handle it internally that makes it a subscription, and not just a regular product.
Codename One uses the Receipt class as the foundation for its subscriptions infrastructure. You, as the developer, are responsible for implementing the ReceiptStore interface to provide the receipts. The Purchase instance will load receipts from your ReceiptStore, and use them to determine whether the user is subscribed to a subscription, and when the subscription expires.
58.1.13. Auto-Renewable subscriptions
Auto-renewable subscriptions provide, arguably, an easier path to recurring revenue than non-renewable subscriptions because all the subscription stuff is handled by the app store. You defer almost entirely to the app store (iTunes for iOS, and Play for Android) for billing and management.
If there is a down-side, it would be that you are also subject to the rules of each app store - and they take their cut of the revenue.
For more information about Apple’s auto-renewable subscription features and rules see this document.
For more information about subscriptions in Google play, see this document.
58.1.14. Auto-Renewable vs Non-Renewable: Choosing between them
When deciding between auto-renewable and non-renewable subscriptions, as always, the answer will depend on your needs and preferences. Auto-renewables are nice because it takes the process out of your hands. You just get paid. On the other hand, there are valid reasons to want to use non-renewables. For example, You can’t cancel an auto-renewable subscription for a user. They have to do that themselves. You may also want more control over the subscription and renewal process, in which case a non-renewable might make more sense.
| Some developers are opposed to auto-renewable subscriptions. There isn’t enough information to make a solid recommendation on this matter. |
On a practical level, if you are using auto-renewable subscriptions (and so subscription products in the Google Play Store) you must use the Purchase.subscribe(sku) method for initiating the purchase workflow. For non-renewable subscriptions (and so regular products in the Google Play Store), you must use the Purchase.purchase(sku) method.
58.1.15. Learning by example
In this section you’ll describe the general workflow of subscription management on the server. You also show how use Apple’s and Google’s web services to check receipts and stay informed of important events (such as when users cancel or renew their subscriptions).
58.1.16. Building the IAP demo project
To aid in this process, Codename One provides a fully functional in-app purchase demo project that includes both a client app and a server app.
Setting up the client project
Create a new Codename One project in Netbeans, and choose the
Bare-bones Hello World Template. You should make your package name something unique so that you are able to create real corresponding apps in both Google Play and iTunes connect.Once the project is created, copy this source file contents into your main class file. Then change the package name, and class name in the file to match your project settings. For example, change
package ca.weblite.iapdemo;topackage <your.package.name.here>;andclass IAPDemo implements PurchaseCallbacktoclass YourClassName implements PurchaseCallback.Add the Generic Web Service Client library to your project by going to "Codename Settings" >
Extensions, finding that library, and clickDownload. Then "Refresh CN1 libs" as it suggests.Change the
localHostproperty to point to your local machine’s network address. Using "http://localhost" isn’t going to cut it here because when the app is running on a phone, it needs to be able to connect to your web server over the network. This address will be your local network address (for example, 192.168.0.9, or something like that).private static final String localHost = "http://10.0.1.32";Add the
ios.plistInjectbuild hint to your project with the value<key>NSAppTransportSecurity</key> <dict> <key>NSAllowsArbitraryLoads</key> <true/> </dict>. This is so that you can use http urls in iOS. Since you don’t intend to fully publish this app, you can cut corners like this. If you were creating a real app, you would use proper secure URLs.
Setting up the server project
Download the CN1-IAP-Server demo project from GitHub, and run its "install-deps" ANT task to download and install its dependencies to your local Maven repo.
| For the following commands to work, make sure you have "ant," "mvn," and "git" in your environment PATH. |
$ git clone https://github.com/shannah/cn1-iap-demo-server $ cd cn1-iap-demo-server $ ant install-deps
Open the project in Netbeans
Setting up the database
Create a new database in your preferred DBMS. Call it anything you like.
Create a new table named "RECEIPTS" in this database with the following structure:
create TABLE RECEIPTS ( TRANSACTION_ID VARCHAR(128) not null, USERNAME VARCHAR(64) not null, SKU VARCHAR(128) not null, ORDER_DATA VARCHAR(32000), PURCHASE_DATE BIGINT, EXPIRY_DATE BIGINT, CANCELLATION_DATE BIGINT, LAST_VALIDATED BIGINT, STORE_CODE VARCHAR(20) default '' not null, primary key (TRANSACTION_ID, STORE_CODE) )Open the "persistence.xml" file in the server NetBeans project.

Change the data source to the database you just created.

If you’re not sure how to create a data source, see your previous tutorial on connecting to a MySQL database.
Testing the project
At this point you should be able to test out the project in the Codename One simulator to make sure it’s working.
Build and Run the server project in Netbeans. You may need to tell it which application server you wish to run it on. This example runs on the Glassfish 4.1 that comes bundled with Netbeans.
Build and run the client project in Netbeans. This should open the Codename One simulator.
When the app first opens you’ll see a screen as follows:

This screen is for testing consumable products, so you won’t be making use of this right now.
Open the hamburger menu and select Subscriptions. You should see something like this:

Click on the "Subscribe 1 Month No Ads" button. You will be prompted to accept the purchase:

Upon completion, the app will submit the purchase to your server, and if all went well, it will retrieve the updated list of receipts from your server also, and update the label on this form to say "No Ads. Expires <some date>":

| This project is set up to use an expedited expiry date schedule for purchases from the simulator. 1 month = 5 minutes. 3 months = 15 minutes. This helps for testing. That’s why your expiry date may be different than expected. |
Just to verify that the receipt was inserted, you should check the contents of your "RECEIPTS" table in your database. In Netbeans, you can do this from the "Services" pane. Expand the database connection down to the RECEIPTS table, right click "RECEIPTS" and select View Data. This will open a data table similar the following:


A few things to mention here:
The "username" was provided by the client. It’s hard-coded to "admin," but the idea is that you would have the user log in and you would have access to their real username.
All dates are stored as unix timestamps in milliseconds.
If you delete the receipt from your database, then press the "Synchronize Receipts" button in your app, the app will again say "No subscriptions." Similarly if you wait 5 minutes and hit "Synchronize receipts" the app will say no subscriptions found, and the "ads" will be back.
Troubleshooting
Don’t pretend that everything worked on the first try. There’s a lot that could go wrong here. If you make a purchase and nothing appears to happen, the first thing you should do is check the Network Monitor in the simulator ("Simulate" > "Network" > "Network Monitor"). You should see a list of network requests. Some will be GET requests and there will be at least one POST request. Check the response of these requests to see if they succeeded.
Also check the Glassfish server log to see if there is an exception.
Common problems would be that the URL you have set in the client app for endpointURL is wrong, or that there is a database connection problem.
58.1.17. Looking at the source of the app
Now that you’ve set up and built the app, take a look at the source code so you can see how it all works.
Client side
The example uses the Generic Webservice Client Library from inside your ReceiptStore implementation to load receipts from the web service, and insert new receipts to the database.
The source for your ReceiptStore is as follows:
Notice that you aren’t doing any calculation of expiry dates in your client app, as you did in the previous post (on non-renewable receipts). Since you are using a server now, it makes sense to move all that logic over to the server.
The createRESTClient() method shown there creates a RESTfulWebServiceClient and configuring it to use basic authentication with a username and password. The idea is that your user would have logged into your app at some point, and you would have a username and password on hand to pass back to the web service with the receipt data so that you can connect the subscription to a user account. The source of that method is listed here:
Server-Side
On the server-side, your REST controller is a standard JAX-RS REST interface. The Netbeans web service wizard generated it and then it was modified to suit the purposes here. The methods of the ReceiptsFacadeREST class for the REST API are shown here:
The magic happens inside that validateAndSaveReceipt() method, which You’ll cover in detail soon.
Notifications
It’s important to note that you won’t be notified by apple or google when changes are made to subscriptions. It’s up to you to periodically "poll" their web service to find if any changes have been made. Changes you would be interested in are primarily renewals and cancellations. Set up a method to run periodically (once per day might be enough), using the scheduling mechanism on your server stack.
That method finds all the receipts in the database that haven’t been validated in some period of time, and validates it. Again, the magic happens inside the validateAndSaveReceipt() method which you cover later.
| This example only checks receipts from the iTunes and Play stores because those are the only stores that support auto-renewing subscriptions in Codename One. |
58.1.18. The CN1-IAP-Validator library
For this tutorial, the example uses a purpose-built library to handle receipt validation in a way that hides as much of the complexity as possible. It supports both Google Play receipts and iTunes receipts.
The general usage is as follows:
As you can see from this snippet, the complexity of receipt validation has been reduced to entering three configuration strings:
APPLE_SECRET- This is a "secret" string that you will get from iTunes connect when you set up your in-app products.GOOGLE_DEVELOPER_API_CLIENT_ID- A client ID that you’ll get from the Google developer API console when you set up your API service credentials.GOOGLE_DEVELOPER_PRIVATE_KEY- A PKCS8 encoded string with an RSA private key that you’ll receive at the same time as theGOOGLE_DEVELOPER_API_CLIENT_ID.
The next section walks through the steps to get these values.
58.1.19. The validateAndSaveReceipt() method
You are now ready to see the full magic of the validateAndSaveReceipt() method in all its glory:
In many of the code snippets for the Server-side code, you’ll see references to both a Receipts class and a Receipt class. This is slightly confusing. The Receipts class is a JPA entity the encapsulates a row from the "receipts" table of your SQL database. The Receipt class is com.codename1.payment.Receipt. It’s used to interface with the IAP validation library. |
58.1.20. Google play setup
Creating the app in Google play
To test out in-app purchase on an Android device, you’ll need to create an app the Google Play Developer Console. This section doesn’t describe the process, but plenty of information around the internet covers how to do this. Some useful references for this include:
Getting Started With Publishing - If you don’t already have an account with Google to publish your apps.
Graphics, icons, etc
You are required to upload some screenshots and feature graphics. Don’t waste time making these perfect. For the screenshots, you can just use the "Screenshot" option in the simulator. (Use the Nexus 5 skin). For the feature graphics, this example uses this site that will generate the graphics in the correct dimensions for Google Play. You can also just leave the icon as the default Codename One icon.
Creating test accounts
| You can’t buy in-app products from your app using your publisher account. You need to set up at least one test account for testing the app. |
To test your app, you need to set up a test account. A test account must be associated with a real gmail email address. If you have a domain that’s managed by Google apps, then you can also use an address from that domain.
The full process for testing in-app billing can be found in this Google document; the documentation is dense and can be difficult to follow.
For your purposes, you’ll need to set up a tester list in Google Play. Choose "Settings" > Tester Lists. Then create a list with all the email address that you want to have treated as test accounts. Any purchases made by these email addresses will be treated as "Sandbox" purchases, and won’t require real money to change hands.
Alpha channel distribution
To test in-app purchase on Android, you must first publish your app. You can’t just build and install your app manually. The app needs to be published on the Play store, and it must be installed through the play store for in-app purchase to work. You can publish to an Alpha channel so that your app won’t be publicly available.
For more information about setting up alpha testing on Google play see this Google support document on the subject.
Once you have set your app up for alpha testing, you can send an invitation link to your test accounts. You can find the link in the Google Play console under the APK section, under the "Alpha" tab (and assuming you’ve enabled alpha testing.

The format of the link is https://play.google.com/apps/testing/your-app-id in case you can’t find it. You can email this to your alpha testers. Make sure that you have added all testers to your tester lists so that their purchases will be made in the sandbox environment.
Also, before proceeding with testing in-app purchases, you need to add the in-app products in Google Play.
Adding In-App products
After you have published your APK to the alpha channel, you can create the products. For the purposes of this tutorial, you’ll just add two products:
iapdemo.noads.month.auto - The 1-month subscription.
iapdemo.noads.3month.auto - The 3-month subscription.
Since you will be adding products as "Subscriptions" in the pay store, your app must use the Purchase.subscribe(sku) method for initiating a purchase on these products, and not the Purchase.purchase(sku) method. If you use purchase() to buy a subscription on Android, the payment will go through, but your buy callback will receive an error. |
Adding 1 month Subscription
Open Google Play Developer Console, and navigate to your app.
Click on "In-app Products" in the menu. Then click the "Add New Product" button.
Select
Subscription, and enter "iapdemo.noads.month.auto" for the Product ID. Then click "Continue"

Now fill in the form. You can choose your own price and name for the product. The following is a screenshot of the options selected for this example.

Adding 3 month Subscription
Follow the same process as for the 1-month subscription except use "iapdemo.noads.3month.auto" for the product ID, and select "3 months" for the billing period instead of Monthly.
Testing the app
At this point you should be ready to test your app. Assuming you’ve installed the app using the invite link you sent yourself from Google play, as a test account that’s listed on your testers list, you should be good to go.
Open the app, click on Subscriptions, and try to buy a 1-month subscription. If all goes well, it should insert the subscription into your database. But with no expiry date, since you haven’t yet implemented receipt validation yet. You’ll do that next.
Creating Google play receipt validation credentials
Google play receipt validation is accomplished via the android-publisher Purchases: get API. The CN1-IAP-Validation library shields you from most of the complexities of using this API, but you still need to get a "private key" and a "client ID" to access this API. Both of these are provided when you set up an OAuth2 Service Account for your app.
| The following steps assume that you have already created your app in Google play and have published it to at least the alpha channel. See your previous post on this topic here (Link to be provided). |
Steps:
Open the Google API Developer Console, and select your App from the menu.
Click on the "Library" menu item in the left menu, and then click the "Google Play Developer API" link.
Figure 305. Google Play Developer API LinkClick on the button that says
Enable. (If you already have it enabled, then just proceed to the next step).
Figure 306. Enable API buttonClick on the "Credentials" menu item in the left menu.
In the "Credentials" drop-down menu, select the "Service Account Key" option.
Figure 307. Credentials dropdownYou will be presented with a new form. In the "Service Account" drop-down, select
New Service Account. This will give you some more options.
Figure 308. Create service account keyEnter anything you like for the
Service account name. For the role, you’ll select "Project" > "Owner" for now just so you don’t run into permissions issues. You’ll probably want to investigate further to fine a more limited role that only allows receipt verification, but for now, avoid any unnecessary road blocks for getting this to work. You’re probably going to run into "permission denied" errors at first anyway, so the fewer reasons for this, the better.It will autogenerate an account ID for you. 9., for the
Key type, selectJSON. Then click the "Create" button.
This should prompt the download of a JSON file that will have contents like the following:
{
"type": "service_account",
"project_id": "iapdemo-152500",
"private_key_id": "1b1d39************7d839826b8a",
"private_key": "-----BEGIN PRIVATE KEY-----... Some private key string -----END PRIVATE KEY-----\n",
"client_email": "[email protected]",
"client_id": "117601572633333082772",
"auth_uri": "https://accounts.google.com/o/oauth2/auth",
"token_uri": "https://accounts.google.com/o/oauth2/token",
"auth_provider_x509_cert_url": "https://www.googleapis.com/oauth2/v1/certs",
"client_x509_cert_url": "https://www.googleapis.com/robot/v1/metadata/x509/iapdemo%40iapdemo-152500.iam.gserviceaccount.com"
}This is where you get the information you’re looking for. The "client_email" is what you’ll use for your googleClientId, and the "private_key" is what you’ll use for the googlePrivateKey.
| Use the "client_email" value as your client ID, not the "client_id" value as you might be tempted to do. |
You’ll set these in your constants:
NOT DONE YET
Before you can use these credentials to verify receipts for your app, you need to link your app to this new service account from within Google Play.
Steps:
Open the Google Play Developer Console, then click on "Settings" >
API Access.You should see your app listed on this page. Click the "Link" button next to your app.
Figure 309. Link to APIThis should reveal some more options on the page. You should see a "Service Accounts" section with a list of all the service accounts that you have created. Find the one you just created, and click the "Grant Access" button in its row.
Figure 310. Grant accessThis will open a dialog titled
Add New User. Leave everything default, except change the "Role" toAdministrator. This provides "ALL" permissions to this account, which probably isn’t a good idea for production. Later on, after everything is working, you can circle back and try to refine permissions. For this tutorial, the goal is to remove all potential road blocks.
Figure 311. New UserPress the "Add User" button.
At this point, the service account should be active so you can try to check receipts.
Testing receipt validation
The ReceiptsFacadeREST class includes a flag to enable/disable play store validation. By default it’s disabled. Enable it:
public static final boolean DISABLE_PLAY_STORE_VALIDATION=true;Change this to false.
Then build and run the server app. The validateSubscriptionsCron() method is set to run once per minute, so you just need to wait for the timer to come up and it should try to check all the play store receipts.
| You’re assuming you’ve already added a receipt in the previous test that you did. If necessary, you should buy the subscription again in your app. |
After a minute or so, you should see "----------- VALIDATING RECEIPTS ---------" written in the Glassfish log, and it will check your receipts. If it works, your receipt’s expiry date will get populated in the database, and you can press "Synchronize Receipts" in your app to see this reflected. If it fails, there will likely be a big ugly stack trace and exception readout with some clues about what went wrong.
Realistically, your first try will fail for some reason. Use the error codes and stack traces to help lead you to the problem. And feel free to post questions here.
58.1.21. iTunes connect setup
The process for setting up and testing your app on iOS is much simpler than on Android (IMHO). It took you a couple of hours to get the iTunes version working, vs a couple of days on the Google Play side of things. One notable difference that makes things simpler is that you don’t need to actually upload your app to the store to test in-app purchase. You can just use your debug build on your device. It’s also much easier to roll a bunch of test accounts than on Google Play. You don’t need to set up an alpha program, you just create a few "test accounts" (and this is easy to do) in your iTunes connect account, and then make sure to use one of these accounts when making a purchase. You can switch accounts on your device from the "Settings" app, where you can just log out of the iTunes store - which will cause you to be prompted in your app the next time you make a purchase.
Setting up In-App products
The process to add products in iTunes connect is outlined in this Apple developer document. You’ll add your two SKUs:
iapdemo.noads.month.auto - The 1-month subscription.
iapdemo.noads.3month.auto - The 3-month subscription.
Just make sure you add them as auto-renewable subscriptions, and that you specify the appropriate renewal periods. Use the SKU as the product ID. Both of these products will be added to the same subscription group. Call the group whatever you like.
Creating test accounts
To test purchases, you need to create some test accounts. See this apple document for details on how to create these test accounts. Don’t worry, the process is much simpler than for Android. It should take you under 5 minutes.
Once you have the test accounts created, you should be set to test the app.
Make sure your server is running.
Log out from the app store. The process is described here.
Open your app.
Try to buy a 1-month subscription
If all went well, you should see the receipt listed in the RECEIPTS table of your database. But the expiry date will be null. You need to set up receipt verification in order for this to work.
Setting up receipt verification
In order for receipt verification to work you need to generate a shared secret in iTunes connect. The process is described here.
Once you have a shared secret, update the ReceiptsFacadeREST class with the value:
public static final String APPLE_SECRET = "your-shared-secret-here";And enable iTunes store validation:
public static final boolean DISABLE_ITUNES_STORE_VALIDATION=true;Change this to false.
If you rebuild and run the server project, and wait for the validateSubscriptionsCron() method to run, it should check the receipt. After about a minute (or less), you’ll see the text "----------- VALIDATING RECEIPTS ---------" written to the Glassfish log file, followed by some output from connecting to the iTunes validation service. If all went well, you should see your receipt expiration date updated in the database. If not, you’ll likely see some exception stack traces in the Glassfish log.
| Sandbox receipts in the iTunes store are set to run on an accelerated schedule. A 1-month subscription is actually 5 minutes, 3 months is 15 minutes etc. Also sandbox subscriptions don’t seem to persist in perpetuity until the user has cancelled it. In practice they renew only 4 or 5 times before they’re allowed to lapse by Apple. |
59. App Review & Feedback
Both Apple and Google provide an in-app review prompt that lets the user rate your app without leaving it. Asking for a review at the right moment is one of the most effective ways to improve your store rating. Codename One exposes this through the com.codename1.appreview.AppReview API, which uses the native review sheet (SKStoreReviewController on iOS, the Play In-App Review API on Android) when it’s available and falls back to a Codename One drawn rating widget everywhere else (the simulator, desktop, the web target and older OS versions).
The native prompt is the store-sanctioned way to ask for a review, so prefer it over a hand-rolled dialog: the operating system controls how often it appears and throttles excessive prompts, which keeps your app within store policy.
59.1. Asking for a review
The simplest usage is a single call at a moment that makes sense in your app — typically right after the user completed something rewarding (finished a level, saved a document, completed an order):
requestReview() shows the native review sheet when the platform supports it. On platforms without a native prompt it shows the built-in rating widget instead. You decide the timing.
59.2. The engagement scheduler
Rather than picking the moment yourself, you can let AppReview decide based on simple engagement heuristics: how many times the app was launched, how long ago it was installed, and how long since it last asked. Configure it once (for example in your app’s init or start method) and call registerSession() on every launch:
registerSession() records the launch and, once the thresholds are met and the user hasn’t already rated or opted out, prompts. The bookkeeping (launch count, install date, last-prompt time and a completion flag) is stored in Preferences so it survives restarts. Once the user rates the app or chooses to stop, AppReview stops prompting. Call reset() to clear this state.
You can combine both styles — use registerSession() for the automatic cadence and still call requestReview() from a "Rate this app" menu item. |
59.3. Smart feedback split
The fallback widget is presented as a bottom sheet, so the user can swipe it away instead of dismissing a blocking dialog. It asks for a star rating and then routes the user based on the result. A high rating (at or above the threshold set by setHighRatingThreshold(int), four stars by default) sends the user to your store listing. A low rating opens a private feedback step instead, so unhappy users reach you directly rather than posting a one-star public review.

By default the low-rating feedback is collected through an e-mail to the address passed to setSupportEmail(String). To deliver feedback through your own backend, register a FeedbackListener:
59.4. How the platform decides
AppReview checks CN.isNativeInAppReviewSupported() to choose between the native prompt and the fallback sheet. On Android the native path is active only when the app references the app-review API — the build adds the Play In-App Review library in that case, so apps that never ask for a review carry no extra dependency. On iOS the StoreKit review controller is linked the same way, only when the API is used.
The native prompts are drawn by the operating system, so this guide can’t show them as Codename One screenshots. On iOS the prompt is the StoreKit rating panel: a star selector the system overlays on your app, submitted without leaving it. On Android it’s the Play In-App Review card that slides up from the bottom. Both are styled and rate-limited by the OS — you can’t theme them, force them to appear, or read the outcome, which is why the fallback sheet shown above renders on every other platform.
| The native review controllers hide whether the user submitted a rating, and may decline to show the prompt at all based on their own quotas. Treat a review request as best-effort; never block your UI waiting for a result. |
60. Apple Wallet Extension
Card issuers (banks, fintechs) can let users add a payment card to Apple Wallet from inside the Wallet app itself. The user opens Wallet, taps the add button and sees the issuer’s cards listed under "From apps on your iPhone" - without ever launching the issuer’s app. Apple implements this through a pair of app extensions called issuer provisioning extensions, and Codename One can generate them for you from build hints with no native code in your project.
This is distinct from the in-app flow where your app shows an "Add to Apple Wallet" button. The extension flow starts inside the Wallet app, runs in a separate process and usually runs while your app isn’t running at all.
60.1. How the extension works
Apple defines two extension points:
A non-UI extension that Wallet queries for status and the list of available cards, and that produces the encrypted provisioning payload when the user adds a card. Wallet gives it 100ms to answer the status query, so it can’t perform network calls or heavy work there.
An optional authorization UI extension that presents a login screen inside Wallet when the non-UI extension reports that authentication is required.
Because the extensions run in a separate process, they can’t call into your Java code. The Codename One integration bridges this in two ways:
Your app pre-publishes the card list, card art and an auth token through
com.codename1.payment.WalletExtension. The data lands in a shared App Group container where the generated extension reads it instantly.The one step that genuinely needs the issuer’s backend - producing
encryptedPassDatafrom the certificates and nonce that Apple hands the extension - is performed by an HTTPS endpoint you host. The generated extension POSTs the request there and relays the response to Wallet.
60.2. Prerequisites from Apple
Before any of this works you need approvals that only Apple and your card network can grant:
The
com.apple.developer.payment-pass-provisioningentitlement is restricted. Apple grants it per app on request (see the In-App Provisioning documentation on the Apple developer site). After approval, enable it under the App ID’s Additional Capabilities tab for the app and for each extension App ID.Each extension needs its own App ID (for example
com.mybank.app.WalletNonUIExtension) and its own provisioning profile carrying the entitlement.The card network/PNO pass metadata must list the extension App IDs in
associatedApplicationIdentifiers, otherwise Wallet never invokes the extensions.The extensions require iOS 14. The generated extension targets set their own deployment target, so your app can still target an older iOS version.
60.3. Mode 1: Generate the extensions from build hints
Add these build hints to the iOS build:
codename1.arg.ios.wallet.extension=true
codename1.arg.ios.wallet.appGroup=group.com.mybank.app
codename1.arg.ios.wallet.issuerEndpoint=https://api.mybank.com/wallet/provisionThat generates the non-UI extension, wires it into the Xcode project as an embedded extension target and injects the App Group into the app and extension entitlements. To also generate the login UI extension add:
codename1.arg.ios.wallet.includeUI=true
codename1.arg.ios.wallet.authEndpoint=https://api.mybank.com/wallet/loginIn Java, publish the user’s cards whenever they change (typically after login) and keep a fresh token published so Wallet can skip the login screen:
Call WalletExtension.clear() on logout. The card art must be a PNG without personally identifiable information (Apple requires square corners and no full card number). The extension automatically filters out cards that are already provisioned on the device or the paired watch.
60.3.1. The issuer endpoint
When the user adds a card, the generated extension POSTs JSON to the ios.wallet.issuerEndpoint URL:
{
"certificates": ["base64...", "base64..."],
"nonce": "base64...",
"nonceSignature": "base64...",
"cardIdentifier": "the WalletPassEntry identifier",
"authToken": "the token published via setAuthToken"
}The token is also sent as an Authorization: Bearer header. Your backend performs the network-specific encryption (this always happens server side - the keys never live on the device) and responds with:
{
"activationData": "base64...",
"encryptedPassData": "base64...",
"ephemeralPublicKey": "base64..."
}For the RSA_V2 scheme return wrappedKey instead of ephemeralPublicKey.
60.3.2. The login UI extension
When you can’t guarantee a fresh token, report setRequiresAuthentication(true) and enable the UI extension. It shows a minimal username/password form inside Wallet, POSTs {"username", "password"} to the ios.wallet.authEndpoint URL, expects {"token"} back and stores it where the non-UI extension picks it up. If the generated form doesn’t fit your brand or login model, use the injection hints below or bring your own extension (Mode 2).
60.3.3. Customizing the generated code
The generated Objective-C contains marker comments at every interesting point, and each marker has a matching build hint that injects your snippet there: ios.wallet.nonuiImportsInject, ios.wallet.statusInject, ios.wallet.passEntriesInject, ios.wallet.remotePassEntriesInject, ios.wallet.generateRequestInject (runs before the POST - the mutable payload dictionary is in scope, so you can add fields your backend expects), ios.wallet.generateResponseInject, ios.wallet.uiImportsInject, ios.wallet.uiViewDidLoadInject, ios.wallet.uiAuthRequestInject and ios.wallet.uiAuthResponseInject.
Xcode build settings of the extension targets can be overridden with ios.wallet.nonui.buildSettings.SETTING=value and ios.wallet.ui.buildSettings.SETTING=value - useful in local builds for DEVELOPMENT_TEAM or CODE_SIGN_STYLE.
60.3.4. Provisioning profiles for cloud builds
Cloud device builds sign each extension with its own profile. Either place the .mobileprovision files under common/src/main/resources and name them in build hints:
codename1.arg.ios.wallet.nonuiProvisioningProfile=WalletNonUI.mobileprovision
codename1.arg.ios.wallet.uiProvisioningProfile=WalletUI.mobileprovisionAlternatively, host them at URLs the build server can reach and supply ios.wallet.nonuiProvisioningURL / ios.wallet.uiProvisioningURL instead. Profiles contain no private keys, so bundling them in resources is safe; the build keeps them out of the final app bundle. The build validates that each profile matches your distribution certificate and actually carries the payment-pass-provisioning entitlement, and fails with an actionable message when it doesn’t.
In local builds ("ios-source" target) no profile hints are needed - you sign the generated Xcode project in Xcode as usual.
60.4. Mode 2: Bring your own extension
If you already have Xcode extension targets - from an issuer SDK vendor or an existing native app - skip the ios.wallet.* hints and drop each extension into the generic app extension mechanism instead. Create ios/app_extensions/MyWalletExtension/ in your project containing:
The extension’s source files (
.m,.h,.swift)Info.plistwith theNSExtensiondictionaryMyWalletExtension.entitlementsOptional
buildSettings.propertieswith Xcode build settings, one per line (setIPHONEOS_DEPLOYMENT_TARGET=14.0for Wallet extensions)The extension’s own
.mobileprovisionfor cloud device builds - see below
Each folder becomes an embedded extension target with bundle id <your package>.<folder name>. This mechanism isn’t Wallet-specific - it embeds any iOS app extension type.
60.4.1. Signing a brought-in extension
Apple signs an app extension against its own App ID. The app’s provisioning profile covers the app’s bundle id and nothing beneath it, so every extension needs its own App ID and its own profile - two extra of each for a Wallet pair. Supply none and the extension target inherits the app’s profile, and Xcode fails the build with:
Provisioning profile "MyApp_Distribution" has app ID "com.mybank.app", which does not match the bundle ID "com.mybank.app.WalletNonUIExtension"
Codename One refuses that build before it’s sent, naming the extension and the bundle id its App ID has to match. To fix it, create an App ID for <your package>.<folder name> in the Apple Developer portal - for a Wallet extension with the com.apple.developer.payment-pass-provisioning entitlement Apple grants on request, and with the same App Group as the app - generate a provisioning profile for it against the same certificate as the app, and supply it in one of three ways:
Place the
.mobileprovisionfile insideios/app_extensions/MyWalletExtension/. It’s picked up automatically and kept out of the app bundle. Profiles carry no private keys, so committing one is safe.Point at it from
codenameone_settings.properties, which suits a profile that lives outside the repository:codename1.ios.debug.appext.MyWalletExtension.provision=${user.home}/certs/MyWalletExtension_dev.mobileprovision codename1.ios.release.appext.MyWalletExtension.provision=${user.home}/certs/MyWalletExtension_dist.mobileprovisionThe unqualified
codename1.ios.appext.MyWalletExtension.provisionis the fallback for both build types.Host it and name the URL in
ios.appext.MyWalletExtension.provisioningURL(or theios.debug.appext…/ios.release.appext…variants).
The build validates the profile it’s given: it must match the app’s signing certificate, cover the extension’s bundle id, be current, and grant the App Groups and the payment-pass-provisioning entitlement the extension’s .entitlements asks for. Each of those fails with a message naming the extension, rather than as an Xcode code signing error minutes into the build.
A wildcard App ID (com.mybank.*) is the one case that needs no extra profile - it’s already covering the extension bundle ids, and the build lets it through. Wallet extensions can’t use one: the payment-pass-provisioning entitlement is granted per explicit App ID.
Local "ios-source" builds need none of this - you sign the generated Xcode project in Xcode as usual.
60.5. Testing
Wallet extensions can’t be exercised in the iOS simulator’s Wallet app; testing the full flow requires a device, a provisioning profile with the entitlement and a card network sandbox. What you can verify earlier:
A local "ios-source" build with the hints produces the
WalletNonUIExtension/WalletUIExtensiontargets - open the generated Xcode project and build.WalletExtension.isSupported()returnsfalsein the simulator and on other platforms, and all publish calls are safe no-ops there, so the Java code needs no platform guards beyond the one shown above.
61. Advanced topics/under the hood
61.1. Sending arguments to the build server
When you send a build to the server, you can provide more parameters. The server incorporates those parameters into the build process as build hints.
These hints are often called "build hints" or "build arguments." They behave like compiler flags that tune the build server’s behavior. That makes them useful for fast iteration on new functionality without rebuilding plugin UI for every change. They’re also useful when you need to expose low-level behavior such as customizing the Android manifest XML or the iOS plist.
Launch Codename One Settings from the Maven project root, then select Hints in the left navigation rail. The hints use the key=value style.
mvn cn1:settings
You can also set the build hints directly in the codenameone_settings.properties file. When you do that, each setting must start with the codename1.arg. prefix. For example, android.debug=true becomes codename1.arg.android.debug=true.
Application code can read a custom build argument through Display.getProperty():
class AppArgSnippet {
public void readArgument() {
String arg = Display.getInstance().getProperty("AppArg", null);
}
}Here is the current list of supported arguments. Build hints change over time, so consult the discussion forum if you don’t find what you need here:
| Name | Description |
|---|---|
build.cn1Version | Pro/Enterprise only. Pins the cloud build to a specific released Codename One version using the Maven release scheme (for example |
android.debug | true/false defaults to true - indicates whether to include the debug version in the build |
android.release | true/false defaults to true - indicates whether to include the release version in the build |
android.onDeviceDebug | Boolean true/false defaults to false. When |
android.installLocation | Maps to android:installLocation manifest entry defaults to auto. Can also be set to internalOnly or preferExternal. |
android.xapplication | defaults to an empty string. Allows developers of native Android code to add text within the application block to define things such as widgets, services etc. |
android.permission.PERMISSION_NAME | true/false Whether to include a particular permission. Use of these build hints is preferred to |
android.permission.PERMISSION_NAME.maxSdkVersion | Will be translated to the |
android.permission.PERMISSION_NAME.required | true/false Will be translated to the |
android.xpermissions | more permissions for the Android manifest |
android.xintent_filter | Allows adding an intent filter to the main android activity |
android.tv | true/false (defaults to false). Marks the build as an Android TV / Google TV app. Adds the |
android.activity.launchMode | Allows explicitly setting the |
android.licenseKey | The license key for the Android app, this is required if you use in-app purchase on Android |
android.signingV1 | true/false Default true. See https://source.android.com/docs/security/features/apksigning |
android.signingV2 | true/false Default true. See https://source.android.com/docs/security/features/apksigning |
android.signingV3 | true/false Default true. See https://source.android.com/docs/security/features/apksigning |
android.signingV4 | true/false Default true. See https://source.android.com/docs/security/features/apksigning |
android.stack_size | Size in bytes for the Android stack thread |
android.statusbar_hidden | true/false defaults to false. When set to true hides the status bar on Android devices. |
android.facebook_permissions | Permissions for Facebook used in the Android build target, applicable only if Facebook native integration is used. |
android.googleAdUnitId | Allows integrating admob/google play ads, this is effectively identical to google.adUnitId but only applies to Android |
android.googleAdUnitTestDevice | Device key used to mark a specific Android device as a test device for Google Play ads defaults to C6783E2486F0931D9D09FABC65094FDF |
android.includeGPlayServices | Deprecated, please android.playService.*! Indicates whether Google Play Services should be included into the build, defaults to false but that might change based on the functionality of the application and other build hints. Adding Google Play Services support allows you to use a more refined location implementation and invoke some Google specific functionality from native code. |
android.playService.plus, android.playService.auth, android.playService.base, android.playService.identity, android.playService.indexing, android.playService.appInvite, android.playService.analytics, android.playService.cast, android.playService.gcm, android.playService.drive, android.playService.fitness, android.playService.location, android.playService.maps, android.playService.ads, android.playService.vision, android.playService.nearby, android.playService.panorama, android.playService.games, android.playService.safetynet, android.playService.wallet, android.playService.wearable | Allows including only a specific play services library portion. Notice that this setting conflicts with the deprecated If none of the services are defined to true then plus, auth, base, analytics, gcm, location, maps & ads will be set to true. If one or more of the |
android.playServicesVersion | The version number of play services to build against. Experimental. Use with caution as building against versions other than the server default may introduce incompatibilities with some Codename One APIs. |
xxx.minPlayServicesVersion | This is a special case build hint. You can use any prefix to the build hint and the convention is to use your cn1lib name. It’s identical to |
android.multidex | Boolean true/false defaults to false. Multidex allows Android binaries to reference more than 65536 methods. This slows builds a bit so you have it off by default but if you get a build error mentioning this limit you should turn this on. |
android.headphoneCallback | Boolean true/false defaults to false. When set to true it assumes the main class has two methods: |
android.gpsPermission | Indicates whether the GPS permission should be requested, it’s autodetected by default if you use the location API. But, some code might want to explicitly define it |
android.asyncPaint | Boolean true/false defaults to true. Toggles the Android pipeline between the legacy pipeline (false) and new pipeline (true) |
android.stringsXml | Allows injecting more entries into the strings.xml file using a value that includes something like this |
android.supportV4 | Boolean true/false defaults to false but that can change based on usage (for example, push implicitly activates this). Indicates whether the android support v4 library should be included in the build |
android.style | Allows injecting more data into the |
android.enableAdaptiveIcons | Boolean true/false defaults to false. Enables Android adaptive icon generation in Android Gradle builds. When enabled, Codename One generates |
android.adaptiveIconBackground | Background color to use for adaptive icons when |
android.adaptiveIconBackgroundImage | Optional path (relative to the root of the native Android project) to an image file to use as the adaptive icon background when |
android.cusom_layout1 | Applies to any number of layouts as long as they’re in sequence (for example, android.cusom_layout2, android.cusom_layout3 etc.). Will write the content of the argument as a layout XML file and give it the name |
android.keyboardOpen | Boolean true/false defaults to true. Toggles the new async keyboard mode that leaves the keyboard open while you move between text components |
android.versionCode | Allows overriding the auto generated version number with a custom internal version number specifically used for the XML attribute |
android.captureRecord | Indicates whether the |
android.nonconsumable | Comma delimited string of items that are non-consumable in the in-app purchase API |
android.removeBasePermissions | Boolean true/false defaults to false. Disables the built-in permissions specifically |
android.blockExternalStoragePermission | Boolean true/false defaults to false. Disables the external storage (SD card) permission |
android.blockReadMediaPermissions | Boolean true/false, defaults to the value of |
android.requestReadMediaPermissions | Boolean true/false defaults to false. Declares |
android.min_sdk_version | The least SDK required to run this app, the default value changes based on functionality but can be as low as 7. This corresponds to the XML attribute |
android.manifest.queries | Embeds XML content into the <queries> section of the Android manifest file. This is required in Android 11 for package visibility. See queries element Android documentation. |
android.mockLocation | Boolean true/false defaults to true. Toggles the mock location permission which is on by default, this allows easier debugging of Android device location based services |
android.smallScreens | Boolean true/false defaults to true. Corresponds to the |
android.xapplication_attr | Allows injecting more attributes into the |
android.xactivity | Allows injecting more attributes into the |
android.streamMode | The mode in which the volume key should behave, defaults to OS default. Allows setting it to |
android.pushVibratePattern | Comma delimited long values to describe the push pattern of vibrate used for the |
android.enableProguard | Boolean true/false defaults to true. Allows disabling the proguard obfuscation even on release builds, notice that this isn’t recommended |
android.proguardKeep | Arguments for the keep option in proguard allowing you to keep a pattern of files for example, |
android.shrinkResources | Boolean true/false defaults to false. Used only in conjunction with android.enableProguard. Strips out unused resources to reduce apk size. Since 7.0 |
android.sharedUserId | Allows adding a manifest attribute for the sharedUserId option |
android.sharedUserLabel | Allows adding a manifest attribute for the sharedUserLabel option |
android.targetSDKVersion | Indicates the Android SDK used to compile the Android build defaults to 21. Notice that not all targets will work since the source might have some limitations and not all SDK targets are installed on the build servers. |
android.useAndroidX | Use Android X instead of support libraries. This will also run a find/replace on all source files to replace support libraries and artifacts with AndroidX equivalents. |
android.rootCheck | Boolean true/false defaults to false. Indicates whether the app should check for root access on the device. If root access is detected, the app will exit. |
android.tapjackingGuard | Boolean true/false defaults to false. Switches on tapjacking / screen-overlay protection at launch, so touches that arrive while another app’s window covers this one are detected and dropped. See the security chapter. |
android.tapjackingGuard.mode |
|
android.tapjackingGuard.hideOverlays | Boolean true/false defaults to true. Also asks Android 12+ to hide overlay windows drawn over the app, which is the only mitigation that covers native peer components, and declares the |
android.hideOverlayWindows | Boolean true/false defaults to false. Declares the |
android.fridaDetection | Boolean true/false defaults to false. Indicates whether the app should check for the presence of the Frida dynamic instrumentation toolkit on the device. If Frida is detected, the app will exit. This uses the [frida-blocker](https://github.com/shannah/frida-blocker) library to perform the frida detection. |
android.fridaVersion | x.y.z The version of [frida-blocker](https://github.com/shannah/frida-blocker) to use to perform frida detection. This is only relevant if |
android.fridaDebugLogging | Boolean true/false defaults to false. If true, it will add verbose debug logs during frida detection to show which check if fails on. |
android.theme | Light or Dark defaults to Light. On Android 4+ the default Holo theme is used to render the native widgets sometimes and this indicates whether holo light or holo dark is used. This doesn’t affect the Codename One theme but that might change in the future. |
android.web_loading_hidden | true/false defaults to false - set to true to hide the progress indicator that appears when loading a web page on Android. |
block_server_registration | true/false flag defaults to false. By default Codename One applications register with the Codename One server. Setting this to true blocks them from sending information to the Codename One cloud, which is kept for statistical purposes and may be used to provide more installation stats in the future. |
facebook.appId | The application ID for an app that requires native Facebook login integration, this defaults to null which means native Facebook support shouldn’t be in the app |
facebook.clientToken | The client token for an app that requires native Facebook login integration, this is required if the facebook.appId is set. |
gcm.sender_id | The Android/chrome push identifier, see the push section for more details |
android.background_push_handling | Deliver push messages on Android when the app is minimized by setting this to "true." Default behaviour is to deliver the message only if the app is in the foreground when received, or after the user taps on the notification to open the app, if the app was in the background when the message was received. |
desktop.mac.plist.PLISTKEY | Set the key |
desktop.mac.plistInject | Injects raw XML into the Info.plist file for desktop builds. For example, |
windows.arch | Native Windows ( |
windows.debug | Native Windows target: |
windows.signing.pkcs12 / windows.signing.password / windows.signing.timestampUrl / windows.signing.digest / windows.signing.name / windows.signing.url | Native Windows Authenticode signing of the produced |
linux.arch | Native Linux ( |
linux.debug | Native Linux target: |
linux.libc | Native Linux target: |
ios.associatedDomains | Comma-delimited list of domains associated with this app. Each domain should be prefixed by a supported prefix. For example, "applinks:" or "webcredentials:." See Apple’s documentation on Associated domains for more information. |
ios.bitcode | true/false defaults to false. Enables bitcode support for the build. |
ios.debug.archs | Can be set to "armv7" to force iOS debug builds to be 32 bit. By default, debug builds are 64 bit only. |
ios.release.archs | Can be set to "arm64" to only build iOS release builds for 64 bit. By default, release builds are both 32 and 64 bit. |
ios.distributionMethod | Specifies distribution type for debug iOS builds. This is used for enterprise or ad-hoc builds (using values "enterprise" and "ad-hoc" respectively). |
ios.debug.distributionMethod | Specifies distribution type for debug iOS builds only. This is used for enterprise or ad-hoc builds (using values "enterprise" and "ad-hoc" respectively). |
ios.release.distributionMethod | Specifies distribution type for release iOS builds only. This is used for enterprise or ad-hoc builds (using values "enterprise" and "ad-hoc" respectively). |
ios.keyboardOpen | Flips between iOS keyboard open mode and autofold keyboard mode. Defaults to true which means the keyboard will remain open and not fold automatically when editing moves to another field. |
ios.uiscene | true/false (defaults to true). Enables iOS UIScene lifecycle support. UIScene lets iOS manage one or more app UI sessions independently, improving lifecycle handling in modern iOS versions. Apple has indicated UIScene will be required starting with iOS 27, so this is now on by default; set the flag to |
ios.urlScheme | Allows intercepting a URL call using the syntax |
ios.useAVKit | Use AVKit for video components on iOS rather than |
ios.teamId | Specifies the team ID associated with the iOS provisioning profile and certificate. Use |
ios.debug.teamId | Specifies the team ID associated with the iOS debug provisioning profile and certificate. |
ios.release.teamId | Specifies the team ID associated with the iOS release provisioning profile and certificate. |
ios.project_type | one of ios, ipad, iphone (defaults to ios). Indicates whether the resulting binary is targeted to the iphone only or ipad only. Notice that the IDE plugin has a "Project Type" combo box you should use under the iOS section. |
ios.rpmalloc |
|
ios.statusbar_hidden | true/false defaults to false. Hides the iOS status bar if set to true. |
ios.newStorageLocation | true/false defaults to false but defined on new projects as true by default. This changes the storage directory on iOS from using caches to using the documents directory which is the recommended location but might break compatibility. This is described in this issue |
ios.prerendered_icon | true/false defaults to false. The iOS build process adapts the submitted icon for iOS conventions (adding an overlay) that might not be appropriate on some icons. Setting this to true leaves the icon unchanged (only scaled). |
ios.app_groups | Space-delimited list of app groups that this app belongs to as described in Apple’s documentation. These are added to the entitlements file with key |
ios.keychainAccessGroup | Space-delimited list of keychain access groups that this app has access to as described in Apple’s documentation. These are added to the entitlements file with the key |
ios.application_exits | true/false (defaults to false). Indicates whether the application should exit on home button press. The default is to exit, leaving the application running is only tested at the moment. |
ios.blockScreenshotsOnEnterBackground | true/false (defaults to false). Indicates that app should prevent iOS from taking screenshots when app enters background. Described here. |
ios.detectJailbreak | true/false (defaults to false). When true, the iOS app will exit on launch if it detects that it’s running on a jailbroken device. |
ios.notificationPermissionAtLaunch | true/false (defaults to false). Backward-compatibility flag for the pre-issue-#4876 behavior. By default, the iOS notification permission prompt is deferred until the app calls |
ios.applicationQueriesSchemes | Comma separated list of url schemes that |
ios.themeMode |
|
and.themeMode |
|
nativeTheme |
|
ios.interface_orientation | UIInterfaceOrientationPortrait by default. Indicates the orientation, one or more of (separated by colon :): |
ios.xcode_version | The version of Xcode used on the server. Defaults to 4.5; accepts 5.0 as an option and nothing else. |
ios.multitasking | Set to true to enable iOS multitasking and split-screen support. This only works if |
java.version | Valid values include 5 or 8. Indicates the JVM version that should be used for server compilation, this is defined by default for newly created apps based on the Java 8 mode selection |
javascript.inject_proxy | true/false (defaults to |
javascript.inject.beforeHead | Content to be injected into the index.html file at the beginning of the |
javascript.inject.afterHead | Content to be injected into the index.html file at the end of the |
javascript.minifying | true/false (defaults to |
javascript.port |
|
javascript.proxy.allowedTargets | Comma-separated target origins, host names, or wildcard subdomains that a generated proxy may access, for example |
javascript.proxy.target | The generated ParparVM proxy deployment platform. Supported values are |
javascript.proxy.url | The URL of an existing proxy to use for network requests. Setting it suppresses generated proxy packaging unless |
javascript.sourceFilesCopied | true/false (defaults to |
javascript.stopOnErrors | true/false (defaults to |
javascript.teavm.version | (Optional) The version of TeaVM to use for the build. Use caution, only use this property if you know what you’re doing! |
google.adUnitId | Allows integrating Admob/Google Play ads into the application see this |
ios.entitlementsInject | Content to inject into the iOS entitlements file. This should be in the Plist XML format. See Apple Entitlements Documentation. |
ios.plistInject | entries to inject into the iOS plist file during build. |
ios.includePush | true/false (defaults to false). Whether to include the push capabilities in the iOS build. Notice that the IDE plugin has an "Include Push" check box you should use under the iOS section. |
ios.newPipeline | Boolean true/false defaults to true. Allows toggling the OpenGL ES 2.0 drawing pipeline off to the older OGL ES 1.0 pipeline. |
ios.headphoneCallback | Boolean true/false defaults to false. When set to true it assumes the main class has two methods: |
ios.facebook_permissions | Permissions for Facebook used in the Android build target, applicable only if Facebook native integration is used. |
ios.applicationDidEnterBackground | Objective-C code that can be injected into the iOS callback method (message) |
ios.enableAutoplayVideo | Boolean true/false defaults to false. Makes videos "autoplay" when loaded on iOS |
ios.googleAdUnitId | Allows integrating admob/google play ads, this is effectively identical to google.adUnitId but only applies to iOS |
ios.viewDidLoad | Objective-C code that can be injected into the iOS callback method (message) |
ios.googleAdUnitIdPadding | Indicates the amount of padding to pass to the Google Ads placed at the bottom of the screen with |
ios.enableBadgeClear | Boolean true/false defaults to true. Clears the badge value with every load of the app, this is useful if the app doesn’t manually keep track of number values for the badge |
ios.glAppDelegateHeader | Objective-C code that can be injected into the iOS app delegate at the top of the file. For example, if you need to include headers or make special imports for other injected code |
ios.glAppDelegateBody | Objective-C code that can be injected into the iOS app delegate within the body of the file before the end. This only makes sence for methods that aren’t already declared in the class |
ios.beforeFinishLaunching | Objective-C code that can be injected into the iOS app delegate at the top of the body of the didFinishLaunchingWithOptions callback method |
ios.afterFinishLaunching | Objective-C code that can be injected into the iOS app delegate at the bottom of the body of the didFinishLaunchingWithOptions callback method |
ios.locationUsageDescription | This flag is required for iOS 8 and newer if you’re using the location API. It needs to include a description of the reason for which you need access to the users location |
ios.NSXXXUsageDescription | iOS privacy flags for using certain APIs. Starting with Xcode 8, you’re required to add usage description strings for certain APIs. Find a full list of the available keys in Apple’s docs. Some relevant ones include |
ios.add_libs | A semicolon separated list of libraries that should be linked to the app to build it |
ios.pods | A comma separated list of Cocoa Pods that should be linked to the app to build it. For example, |
ios.pods.platform | Sets the Cocoapods 'platform' for the Cocoapods. Some Cocoapods require a minimum platform level. For example, |
ios.deployment_target | Sets the deployment target for iOS builds. This is the minimum version of iOS required by a device to install the app. For example, |
ios.bundleVersion | Indicates the version number of the bundle, this is useful if you want to create a minor version number change for the beta testing support |
ios.objC | Added the |
ios.testFlight | Boolean true/false defaults to false and works only for pro accounts. Enables the testflight support in the release binaries for easy beta testing. Notice that the IDE plugin has a "Test Flight" check box you should use under the iOS section. |
ios.metal | Boolean true/false defaults to true. Selects the Metal rendering backend ( |
ios.metal.colorSpace | Selects the |
ios.generateSplashScreens | Boolean true/false defaults to false. Enables legacy generation of splash screen images instead of the current launch storyboards. |
ios.onDeviceDebug | Boolean true/false defaults to false. When |
ios.onDeviceDebug.proxyHost | Hostname or IP address the device-side listener dials to reach the desktop proxy. Default |
ios.onDeviceDebug.proxyPort | TCP port on |
ios.onDeviceDebug.waitForAttach | Boolean true/false defaults to false. When |
ios.wallet.extension | Boolean true/false defaults to false. Generates an Apple Wallet issuer provisioning extension (the "From apps on your iPhone" flow in the Wallet app) and embeds it in the build. Requires |
ios.wallet.appGroup | App Group id starting with |
ios.wallet.issuerEndpoint | HTTPS URL of the issuer backend endpoint that produces the encrypted provisioning payload. The generated extension POSTs Apple’s certificates/nonce plus the card identifier and auth token there as JSON. Required when |
ios.wallet.includeUI | Boolean true/false defaults to false. Also generates the Wallet authorization UI extension - a login form shown inside the Wallet app when the app reports that authentication is required. Requires |
ios.wallet.authEndpoint | HTTPS URL the generated login UI extension POSTs |
ios.wallet.nonuiExtensionName / ios.wallet.uiExtensionName | Names of the generated extension targets, also used as the bundle id suffix ( |
ios.wallet.nonuiProvisioningProfile / ios.wallet.uiProvisioningProfile | Cloud device builds only. File name of the extension’s |
ios.wallet.nonuiProvisioningURL / ios.wallet.uiProvisioningURL | Cloud device builds only. URL fallback for the extension provisioning profile when it isn’t bundled in resources, mirroring |
ios.wallet.nonui.buildSettings.SETTING / ios.wallet.ui.buildSettings.SETTING | Extra Xcode build settings applied to the generated extension targets, for example |
ios.wallet.nonuiImportsInject, ios.wallet.statusInject, ios.wallet.passEntriesInject, ios.wallet.remotePassEntriesInject, ios.wallet.generateRequestInject, ios.wallet.generateResponseInject, ios.wallet.uiImportsInject, ios.wallet.uiViewDidLoadInject, ios.wallet.uiAuthRequestInject, ios.wallet.uiAuthResponseInject | Objective-C code injected at the matching marker comment in the generated Wallet extension sources, for custom behavior at each callback (for example adding fields to the issuer endpoint payload in |
ios.appext.NAME.provisioningURL | Cloud device builds only. URL of the provisioning profile for a generic app extension dropped into |
ios.debug.appext.NAME.provisioningURL / ios.release.appext.NAME.provisioningURL | Cloud device builds only. Build-type-specific variants of |
codename1.mac.appid | Mac Native cloud builds only. The Mac bundle identifier registered in App Store Connect / Apple Developer. Distinct from |
codename1.mac.certificate | Mac Native cloud builds only. Path to the |
codename1.mac.certificatePassword | Mac Native cloud builds only. Password to unlock the P12 referenced by |
codename1.mac.provision | Mac Native cloud builds only. Path to the Mac provisioning profile ( |
macNative.distribution | Mac Native builds only. |
macNative.teamId | Mac Native builds only. Apple Developer Team ID (alphanumeric). Falls back to |
macNative.bundleId | Mac Native builds only. Used only when |
macNative.deriveBundleId | Mac Native builds only. |
macNative.minDeploymentTarget | Mac Native builds only. Minimum macOS version ( |
macNative.iosMinDeploymentTarget | Mac Native builds only. iOS deployment-target floor for the Catalyst slice ( |
macNative.appCategory | Mac Native builds only. |
macNative.copyright | Mac Native builds only. |
macNative.signing.style | Mac Native builds only. |
macNative.signingIdentity.appStore | Mac Native builds only. Signing certificate identity for the App Store channel. Default |
macNative.signingIdentity.developerID | Mac Native builds only. Signing certificate identity for the Developer ID channel. Default |
macNative.provisioningProfile.appStore | Mac Native builds only. Provisioning profile name for App Store distribution — used only when |
macNative.provisioningProfile.developerID | Mac Native builds only. Provisioning profile name for Developer ID distribution — used only when |
macNative.entitlements.appSandbox | Mac Native builds only. |
macNative.entitlements.network.client | Mac Native builds only. Toggles |
macNative.entitlements.network.server | Mac Native builds only. Toggles |
macNative.entitlements.files.userSelected | Mac Native builds only. |
macNative.entitlements.hardenedRuntime | Mac Native builds only. |
macNative.entitlements.allowJit | Mac Native builds only. |
macNative.entitlements.extra | Mac Native builds only. Free-form XML inserted verbatim inside the |
macNative.fixedWindowSize | Mac Native builds only. Opt-in. Format |
desktop.width | Width in pixels for the form in desktop builds, will be doubled for retina grade displays. Defaults to 800. |
desktop.height | Height in pixels for the form in desktop builds, will be doubled for retina grade displays. Defaults to 600. |
desktop.adaptToRetina | Boolean true/false defaults to true. When set to true some values will ve implicitly doubled to deal with retina displays and icons etc. Will use higher DPI’s |
desktop.resizable | Boolean true/false defaults to true. Indicates whether the UI in the desktop build is resizable |
desktop.fontSizes | Indicates the sizes in pixels for the system fonts as a comma delimited string containing 3 numbers for small,medium,large fonts. |
desktop.theme | Name of the theme res file (without the ".res" extension) to use as the "native" theme. By default this is native indicating iOS theme on Mac and Windows Metro on Windows. If its something else then the app will try to load the file /themeName.res (placed in native/Java SE directory). |
desktop.themeMac | Same as |
desktop.themeWin | Same as |
desktop.windowsOutput | Can be exe or msi depending on desired results |
desktop.win.cef | Whether to use CEF for media and BrowserComponent instead of JavaFX in windows desktop builds. true/false. Default value is |
desktop.mac.cef | Whetherto use CEF for media or BrowserComponent instead of JavaFX in Mac desktop builds. true/false. Default value is |
tvNative.enabled | true/false (defaults to false). Adds an Apple TV (tvOS) application target to the iOS build. The tvOS app is a separate |
tvNative.mainClass (a.k.a. codename1.tvMain) | Fully-qualified tvOS lifecycle entry class. Setting it auto enables the tvOS target. If omitted while |
tvNative.bundleId | Bundle identifier of the tvOS app. Defaults to |
tvNative.minDeploymentTarget |
|
tvNative.displayName | The tvOS app name shown on Apple TV. Defaults to the app’s display name. |
tvNative.teamId | Apple Developer Team ID used to sign the tvOS target. Falls back to the iOS team id ( |
mac.desktop-vm | The JVM the should be bundled with Mac desktop build. Mac desktop builds only. Supported values: zuluFx8, zulu11, zuluFx11 |
win.desktop-vm | The JVM that should be bundled in the Windows desktop build. Windows desktop builds only. Supported values: zulu8, zuluFx8, zulu8-32bit, zuluFx8-32bit, zulu11, zuluFx11, zulu11-32bit, zuluFx11-32bit |
windows.extensions | Historical build hint for the discontinued UWP target. It’s retained here only for legacy reference and isn’t used by current supported build targets. |
win.vm32bit | true/false (defaults to false). Forces windows desktop builds to use the Win32 JVM instead of the 64 bit VM making them compatible with older Windows Machines. This is off by default at the moment because of a bug in JDK 8 update 112 that might cause this to fail for some cases |
win.installDirName | Windows desktop builds only. Overrides the default installation folder name suggested by the installer (under |
win.shortcutName | Windows desktop builds only. Overrides the name used for the Start Menu shortcut, the Desktop shortcut and (when |
noExtraResources | true/false (defaults to false). Blocks codename one from injecting its own resources when set to true, the only effect this has is in slightly reducing archive size. This might have adverse effects on some features of Codename One so it isn’t recommended. |
windows.arch | Native Windows port only (the |
windows.debug | Native Windows port only. true/false (defaults to false). When |
windows.sdkRoot | Native Windows port only; used when building on a non-Windows host (for example a Linux build server). Path to a Windows SDK laid out by |
(signing certificate) | Native Windows port only. The code-signing certificate itself isn’t a build-hint argument; configure it through project settings as |
windows.signing.timestampUrl | Native Windows port only. RFC 3161 timestamp server used when signing, so the signature stays valid after the certificate expires. Default |
windows.signing.digest | Native Windows port only. Signature digest algorithm. Default |
windows.signing.name / windows.signing.url | Native Windows port only. The description and URL embedded in the signature (the "More info" shown by Windows). Default: the app’s display name, and no URL. |
windows.signing | Native Windows port only. |
61.2. Versioned builds
By default a cloud build always uses the current Codename One release. With a versioned build you can instead pin the build to a specific previously released framework version, so you get reproducible output over time. This helps when stabilizing a release, supporting an older app, or isolating a regression: if an app that built correctly in the past starts failing, rebuilding against the last known good version tells you whether the change came from your code or from the framework and build server.
Set the build.cn1Version build hint to the version you want to target. Versions use the standard Maven release scheme published to Maven Central, for example 7.0.182:
codename1.arg.build.cn1Version=7.0.182
The build server fetches that version’s framework artifacts from Maven Central and builds against them. To keep your simulator and local compile classpath aligned with the same release, set the matching cn1.version in your project pom.xml.
Versioned builds are a Pro and Enterprise feature, and how far back you can target depends on the subscription tier:
| Tier | Versions you can target |
|---|---|
Pro | Any version released within the last two months |
Enterprise | Any version released within the last six months |
If you request a version older than your tier’s window, a version that was never published, or you aren’t on a Pro or Enterprise plan, the build fails with an explanatory message instead of falling back to the current release.
61.2.1. Building against master
Set build.cn1Version to master to build against the current development head (the latest master of the Codename One repository) instead of a released version:
codename1.arg.build.cn1Version=master
Every push to master publishes a fresh set of framework artifacts and the build server always grabs the latest, so this is the quickest way to verify an unreleased fix or feature end to end on a device. Because master tracks active development it can be less stable than a release, so use it for verification rather than for shipping production builds. Building against master is available to Pro and Enterprise subscribers.
61.3. Android permissions
One of the annoying tasks when programming native Android applications is tuning all the required permissions to match your codes requirements, Codename One aims to simplify this. The build server automatically introspects the classes sent to it as part of the build and injects the right set of permissions required by the app.
For example, sometimes developers might find the permissions that come up a bit confusing and might not understand why a specific permission came up. This maps Android permissions to the methods/classes in Codename One that would trigger them. Notice that this list isn’t exhaustive as the API is rather large:
android.permission.WRITE_EXTERNAL_STORAGE - included by default (up to Android 13) so file APIs continue to work unless you block it with android.blockExternalStoragePermission=true.
android.permission.INTERNET - always requested because the networking stack depends on it even for offline features like local web views.
android.permission.CAMERA & android.permission.RECORD_AUDIO - required when capturing photos, video, or audio. The builder injects them automatically and the Android port prompts the user the first time the API is used.
android.permission.READ_PHONE_STATE - used by telephony-aware APIs like Display.getMsisdn() and by media integration so audio pauses on calls.
android.permission.ACCESS_FINE_LOCATION & android.permission.ACCESS_COARSE_LOCATION - requested when using com.codename1.location or embedded maps so location fixes can be delivered.
android.permission.ACCESS_BACKGROUND_LOCATION - added when background geofencing or fetch tasks are enabled; the Android port verifies the permission on Android 10+.
android.permission.POST_NOTIFICATIONS - prompted on Android 13+ for both push registration and local notifications.
package.permission.C2D_MESSAGE, com.google.android.c2dm.permission.RECEIVE, and android.permission.RECEIVE_BOOT_COMPLETED - bundled with the push subsystem so Firebase Cloud Messaging can wake the app after device restarts.
android.permission.READ_CONTACTS - requested when accessing the device address book through Display.getAllContacts() and related APIs.
android.permission.READ_MEDIA_VIDEO & android.permission.READ_MEDIA_AUDIO - added on API 33 and above when the app plays a URI through MediaManager.createMedia(String, boolean) or createMediaAsync(String, boolean, Runnable), since that URI can point at the shared media store. The InputStream overloads don’t add them: the Android port copies the stream into app private storage and reads nothing shared. Block them with android.blockReadMediaPermissions=true.
android.permission.READ_MEDIA_IMAGES - never added by media playback, because no Codename One API requests it at runtime. Declaring it alongside READ_MEDIA_VIDEO places the app under Google Play’s Photo and Video Permissions policy, so ask for it only when you need it, with android.requestReadMediaPermissions=true.
61.3.1. Permissions under Marshmallow (Android 6+)
Starting with Marshmallow (Android 6+ API level 23) Android shifted to a permissions system that prompts users for permission the first time an API is used for example: when accessing contacts the user will receive a prompt whether to allow contacts access.
| Permission can be denied and a user can later on revoke/grant a permission through external settings UI |
This is great as it allows apps to be installed with a single click and no permission prompt during install which can increase conversion rates!
Enabling permissions
By default, Codename One’s Gradle 8 based Android builder uses the highest Android SDK you’ve installed, with a minimum of API 36, for both the compile and target SDK versions. If you override the target through the android.targetSDKVersion build hint, the builder honors it while keeping the compile SDK at least as high as the target SDK. Lowering the target may disable some compatibility libraries. Keeping the target current is strongly recommended for Play Store compliance.
Permission prompts
To test this API see the following simple contacts app:
Form f = new Form("Contacts", BoxLayout.y());
f.add(new InfiniteProgress());
Display.getInstance().invokeAndBlock(() -> {
Contact[] ct = Display.getInstance().getAllContacts(true, true, false, true, true, false);
Display.getInstance().callSerially(() -> {
f.removeAll();
for (Contact c : ct) {
MultiButton mb = new MultiButton(c.getDisplayName());
mb.setTextLine2(c.getPrimaryPhoneNumber());
f.add(mb);
}
f.revalidate();
});
});
f.show();If you explicitly lower the target SDK (for example: android.targetSDKVersion=21) and install this app on an Android 6 device you will still see the legacy install prompt with all permissions listed up front:

When you keep the default target (API 36+) the installer defers to the runtime permission flow and the installation UI looks like this instead:

When you launch the UI under the old permissions system you see the contacts instantly. In the new system you’re presented with this UI:

If you accept and allow all is good and the app loads as usual but if you deny then Codename One provides the user another chance to request the permission. Notice that in this case you can customize the prompt string as explained below.

If you select don’t ask then you will get a blank screen since the contacts will return as a 0 length array. This makes sense as the user is aware he denied permission and the app will still function as expected on a device where no contacts are available. For example, if the user realizes his mistake he can double back and ask to re-prompt for permission in which case he will see this native prompt:

Notice that denying this second request won’t trigger another Codename One prompt.
Code changes
No explicit code changes needed for this functionality to "work." The respective APIs will work like they always worked and will prompt the user seamlessly for permissions.
| Some behaviors that never occurred on Android but were legal in the past might start occurring with the switch to the new API. For example: the location manager might be null and your app must always be ready to deal with such a situation |
When permission is requested a user will be seamlessly prompted/warned. You can customize the permission text through Display properties. For example: to customize the rationale text of the contacts permission:
Display.getInstance().setProperty(
"android.permission.READ_CONTACTS",
"MyCoolChatApp needs access to your contacts so we can show you which of your friends already have MyCoolChatApp installed");The Android port also checks UIManager.localize() for localized values before falling back to Display properties. You can provide localized strings for the permission body and dialog buttons/title using keys based on the permission name:
com.codename1.ui.plaf.UIManager.getInstance().setBundle(new java.util.Hashtable<String, String>() {{
put("android.permission.READ_CONTACTS", "Localized rationale for contacts");
put("android.permission.READ_CONTACTS.title", "Localized permission title");
put("android.permission.READ_CONTACTS.askAgain", "Localized ask again");
put("android.permission.READ_CONTACTS.dontAsk", "Localized don't ask");
}});For example, if the permission key is android.permission.READ_CONTACTS, you can localize these keys:
android.permission.READ_CONTACTS(dialog body)android.permission.READ_CONTACTS.titleandroid.permission.READ_CONTACTS.askAgainandroid.permission.READ_CONTACTS.dontAsk
The same pattern applies to other permissions. android.permission.ACCESS_BACKGROUND_LOCATION also supports:
android.permission.ACCESS_BACKGROUND_LOCATION.settings,
android.permission.ACCESS_BACKGROUND_LOCATION.cancel,
android.permission.ACCESS_BACKGROUND_LOCATION.explanation_title,
android.permission.ACCESS_BACKGROUND_LOCATION.explanation_body, and
android.permission.ACCESS_BACKGROUND_LOCATION.ok.
This is optional as there is a default value defined. You can define this once in the init(Object) method but for some extreme cases permission might be needed for different things for example: you might ask for this permission with one reason at one point in the app and with a different reason at another point in the app.
Simulating prompts
You can simulate permission prompts by checking that option in the simulator menu.

This will produce a dialog to the user whenever this happens in Android and will try to act in a similar way to the device. Notice that you can test it in the iOS simulator too.
AndroidNativeUtil’s checkForPermission
If you write Android native code using native interfaces you’re probably familiar with the AndroidNativeUtil class from the com.codename1.impl.android package.
This class provides access to many low-level capabilities you would need as a developer writing native code. Since native code might need to request a permission Codename One uses the same underlying logic, namely:
checkForPermission.
To get a permission you can use this code as such:
if (!AndroidNativeUtil.checkForPermission(
android.Manifest.permission.READ_PHONE_STATE,
"This should be the description shown to the user...")) {
// you didn't get the permission, you might want to return here
}
// you have the permission, do what you needThis will prompt the user with the native UI and later on with the fallback option as described above. Notice that the checkForPermission method is a blocking method and it will return when there is a final conclusion on the subject. It uses invokeAndBlock and can be invoked on the event dispatch thread without concern.
By default, fallback prompts are displayed using Codename One’s Dialog.show(…). If you’re writing native Android code and need to use your own prompt implementation, you can install a custom callback:
AndroidNativeUtil.setPermissionPromptCallback(new PermissionPromptCallback() {
@Override
public boolean showPermissionPrompt(String permission, String title, String body, String positiveButtonText, String negativeButtonText) {
return com.codename1.ui.Dialog.show(title, body, positiveButtonText, negativeButtonText);
}
@Override
public void showPermissionMessage(String permission, String title, String body, String okButtonText) {
com.codename1.ui.Dialog.show(title, body, okButtonText, null);
}
});Pass null to AndroidNativeUtil.setPermissionPromptCallback() to restore the default behavior.
61.4. On device debugging
On-device debugging now has two dedicated chapters, one per platform:
Chapter 80, On-Device Debugging (iOS) covers attaching a standard Java debugger (IntelliJ, jdb, VS Code) to an iOS app running on a device or in the native iOS simulator, as well as debugging the generated Xcode project natively.
Chapter 81, On-Device Debugging (Android) covers the equivalent adb/JDWP-based flow for Android devices and emulators, including wireless debugging and debugging the generated Gradle project from Android Studio.
61.5. Native interfaces
Sometimes you may wish to use an API that’s unsupported by Codename One or integrate with a 3rd party library/framework that isn’t supported. These are achievable tasks when writing native code and Codename One lets you encapsulate such native code using native interfaces.
61.5.1. Introduction
Notice that when you say "native" you don’t mean C/C++ always but rather the platforms "native" environment. For Android, Java or Kotlin code can be invoked with full access to the Android API. In case of iOS, Objective-C or Swift code can be invoked and so forth.
| You can still access C code under Android either by using JNI from the Android native code or by using a library |
Native interfaces are designed to allow primitive types, Strings, arrays of primitive types (single dimension ) & PeerComponent values. Any other kind of parameter/return type is prohibited. For example, once in the native layer the native code can act and query the Java layer for more information.
The reason for the limits is the disparity between the platforms. Mapping a Java Object to an Objective-C NSObject is possible but leads to odd edge cases and complexity for example: GC vs. ARC in a disparate object graph |
Furthermore, native methods should avoid features such as overloading, varargs (or any Java 5+ feature for that matter) to allow portability for languages that don’t support such features.
| Don’t rely on pass by reference/value behavior since they vary between platforms |
Implementing a native layer effectively means:
Creating an interface that extends NativeInterface and defines methods with the arguments/return values declared in the previous paragraph.
Creating the proper native implementation hierarchy based on the call conventions for every platform within the native directory
For example: to create a simple hello world interface do something like:
public interface MyNative extends NativeInterface {
String helloWorld(String hi);
}You now need to right-click the class in the IDE and select the Generate Native Access menu item:


You can now look int the native directory in the project root (in NetBeans you can see that in the Files tab) and you can see something that looks like this:

These are effectively stubs you can edit to implement the methods in native code.
| If you re-run the Generate Native Access tool you will get this dialog, if you answer yes all the files will be overwritten, if you answer no files you deleted/renamed will be recreated |

For now lets leave the stubs and come back to them soon. From the Codename One Java code you can call the implementation of this native interface using:
MyNative my = NativeLookup.create(MyNative.class);
if (my != null && my.isSupported()) {
Log.p(my.helloWorld("Hi"));
}Notice that for this to work you must implement the native code on all supported platforms.
You will start with Android which should be familiar and intuitive to many developers. The helper MyNativeImplStub class below mirrors the stub that the tooling generates under the native/android directory:
class MyNativeImplStub {
public String helloWorld(String param) {
return null;
}
public boolean isSupported() {
return false;
}
}The stub implementation always returns false, null or 0 by default. The isSupported also defaults to false thus allowing you to implement a NativeInterface on some platforms and leave the rest out without knowing anything about these platforms.
You can implement the Android version in Java or Kotlin. Here is the Java version:
public class MyNativeImpl { (2) (3)
public String helloWorld(String param) {
Log.d("MyApp", param); (1)
return "Tada";
}
public boolean isSupported() {
return true; (4)
}
}| 1 | Notice that you’re using the Android native android.util.Log class which isn’t accessible from standard Codename One code |
| 2 | The impl class doesn’t physically implement the MyNative interface!This is intentional and due to the PeerComponent functionality mentioned below. You don’t need to add an implements clause. |
| 3 | Notice that there is no constructor and the class is public. It’s crucial that the system will be able to assign the class without obstruction. You can use a constructor but it can’t have any arguments and you shouldn’t rely on semantics of construction. |
| 4 | You implemented the native method and that you set isSupported to true. |
| The IDE won’t provide completion suggestions and will claim that there are errors in the code! Codename One doesn’t include the native platforms in its bundle for example: the full Android SDK or the full Xcode Objective-C runtime. For example, since the native code is compiled on the servers (where these runtimes are present) this shouldn’t be a problem |
| When implementing a non-trivial native interface, send a server build with the "Include Source" option checked. Implement the native interface in the native IDE then copy and paste the native code back into Codename One |
The implementation of this interface is identical for Android (Java/Kotlin) & Java SE.
Swift (iOS) and Kotlin (Android) options
For iOS native interfaces you can implement the generated …Impl class in Objective-C or Swift.
For Android native interfaces you can implement the generated …Impl class in Java or Kotlin.
| Platform | Typical file locations for native interface implementations |
|---|---|
Android (Java/Kotlin) |
|
iOS (Objective-C/Swift) |
|
Native Windows (win32, C) |
|
Native Linux © |
|
JavaScript |
|
| The native Windows and native Linux ports compile your app to C (no JVM), so their native interface implementations are plain C, generated alongside the others by the "Generate Native Sources" tool. The native Mac target reuses the iOS Objective-C/Swift implementation, since it rides the same build. |
Use the Android main thread (native EDT)
iOS, Android & pretty much any modern OS has an EDT like thread that handles events etc. The problem is that they differ in their nuanced behavior. For example: Android will respect calls off of the EDT and iOS will often crash. Some OSes enforce EDT access and will throw an exception when you violate that…
You don’t need to know about these things, hidden functionality within your implementation bridges between your EDT and the native EDT to provide consistent cross-platform behavior. However, when you write native code you need awareness.
How do you access the native EDT
Within your native code in Android do something like:
com.codename1.impl.android.AndroidNativeUtil.getActivity().runOnUiThread(new Runnable() {
public void run() {
// your native code here...
}
});This will execute the block within run() asynchronously on the native Android UI thread. If you need synchronous execution you have a special method for Codename One:
com.codename1.impl.android.AndroidImplementation.runOnUiThreadAndBlock(new Runnable() {
public void run() {
// your native code here...
}
});This blocks in a way that’s OK with the Codename One EDT which is unique to your Android port.
Gradle dependencies
Integrating a native OS library isn’t hard but it sometimes requires some juggling. Most instructions target developers working with Xcode or Android Studio & you need to twist your head around them. In Android the steps for integration in most modern libraries include a Gradle dependency.
For example: you published a library that added support for Intercom. The native Android integration instructions for the library looked like this:
Add the following dependency to your app’s build.Gradle file:
dependencies {
compile 'io.intercom.android:intercom-sdk:3.+'
}Which instantly raises the question: "How do you do that in Codename One"?
Well, it’s actually pretty simple. You can add the build hint:
android.gradleDep=compile 'io.intercom.android:intercom-sdk:3.+'
This would "work" but there is a catch…
You might need to define the specific version of the Android SDK used and specific version of Google Play Services version used. Intercom is pretty sensitive about those and demanded that you also add:
android.playServices=9.8.0 android.sdkVersion=25
Once those were defined the native code for the Android implementation became trivial to write and the library was easy as there were no jars to include.
61.5.2. Objective-C and Swift (iOS)
When generating the Objective-C code the "Generate Native Sources" tool produces two files by default: com_mycompany_myapp_MyNativeImpl.h & com_mycompany_myapp_MyNativeImpl.m.
If you enable Swift stub generation in the Maven goal, it can also produce com_mycompany_myapp_MyNativeImpl.swift.
The .m files are the Objective-C equivalent of .c files and .h files contain the header/include information. In this case the com_mycompany_myapp_MyNativeImpl.h contains:
#import <Foundation/Foundation.h>
@interface com_mycompany_myapp_MyNativeImpl : NSObject {
}
-(NSString*)helloWorld:(NSString*)param;
-(BOOL)isSupported;
@endAnd com_mycompany_myapp_MyNativeImpl.m contains:
#import "com_mycompany_myapp_MyNativeImpl.h"
@implementation com_mycompany_myapp_MyNativeImpl
-(NSString*)helloWorld:(NSString*)param{
return nil;
}
-(BOOL)isSupported{
return NO;
}
@endObjective-C relies on argument names as part of the message (method) signature. -(NSString*)helloWorld:(NSString*)param isn’t the same as -(NSString*)helloWorld:(NSString*)iChangedThisName!don’t change argument names in the Objective-C native interface! |
Here is a simple implementation like above:
#import "com_mycompany_myapp_MyNativeImpl.h"
@implementation com_mycompany_myapp_MyNativeImpl
-(NSString*)helloWorld:(NSString*)param{
NSLog(@"MyApp: %@", param);
return @"Tada";
}
-(BOOL)isSupported{
return YES;
}
@endIf you prefer Swift for iOS native interfaces, keep the same class naming convention (com_mycompany_myapp_MyNativeImpl) and annotate the class with @objc(…) so the runtime can discover it.
Using the iOS main thread (native EDT)
iOS has a native thread you should use for all calls like Android. Check out the Native EDT on Android section above for reference.
On iOS this is pretty like Android (if you consider objective-c to be similar). This is used for asynchronous invocation:
dispatch_async(dispatch_get_main_queue(), ^{
// your native code here...
});You can use this for synchronous invocation, notice the lack of the a in the dispatch call:
dispatch_sync(dispatch_get_main_queue(), ^{
// your native code here...
});The problem with the synchronous call is that it will block the caller thread, if the caller thread is the EDT this can cause performance issues and even a deadlock. It’s important to be cautious with this call!
Use Cocoapods for dependencies
Cocoapods are the iOS equivalent of Gradle dependencies.
CocoaPods allow you to add a native library dependency to iOS far more than Gradle. By default you target iOS 7.0 or newer which is supported by Intercom for older versions of the library. Annoyingly CocoaPods might seem to work but some specific APIs won’t work since it fell back to an older version… To solve this you’ve to explicitly define the build hint ios.pods.platform=8.0 to force iOS 8 or newer. You might need to force it to even newer versions as some libraries force an iOS 9 least etc.
Including intercom itself required a single build hint: ios.pods=Intercom which you can obviously extend by using commas to include many libraries. You can search the CocoaPods website for supported 3rd party libraries which includes everything you would expect. One important advantage when working with CocoaPods is the faster build time as the upload to the Codename One website is smaller and the bandwidth you’ve to CocoaPods is faster. Another advantage is the ability to keep up with the latest developments from the library providers.
61.5.3. C (native Windows and native Linux)
The native Windows (win32) and native Linux ports have no JVM: the "clean" ParparVM target compiles your whole app to C and then to a native binary. A native interface on these ports is therefore implemented in plain C rather than C#/Objective-C/Java. The "Generate Native Sources" tool emits one C file per interface:
win/src/main/c/com/mycompany/myapp/MyNativeImplCodenameOne.c(native Windows)linux/src/main/c/com/mycompany/myapp/MyNativeImplCodenameOne.c(native Linux)
The two files are identical, so a native interface written once works on both ports; only the directory differs. (The native Mac target reuses the iOS Objective-C/Swift implementation, because it rides the iOS build.)
The translator emits one C function per interface method. Unlike the Objective-C
stub, the function name is the fully qualified, mangled C symbol the translated app
links against, so don’t rename the functions or change their signatures; just fill
in the bodies. Each function takes the thread state as its first argument and
JAVA_* typed parameters. For example, the interface:
public interface MyNative extends NativeInterface {
String helloWorld(String hi);
}This generates the C stub below (returning JAVA_NULL until you implement it):
#include "cn1_globals.h"
JAVA_OBJECT com_mycompany_myapp_MyNativeImplCodenameOne_helloWorld___java_lang_String_R_java_lang_String(CODENAME_ONE_THREAD_STATE, JAVA_OBJECT param1) {
return JAVA_NULL;
}Type mapping: the primitives (int, long, boolean, byte, short, char,
float, double) become their JAVA_INT/JAVA_LONG/JAVA_BOOLEAN equivalents;
String, arrays and other objects become JAVA_OBJECT; a void method returns
JAVA_VOID and omits the R suffix in its name; and a
com.codename1.ui.PeerComponent is passed and returned as a JAVA_LONG native peer
handle. Use the core helpers declared in cn1_globals.h (for example
newStringFromCString / stringToUTF8) to convert between C and Java values. As
with the other ports, you can drop additional .c/.h sources and prebuilt
libraries into the same src/main/c directory and they’re compiled into the binary.
61.5.4. JavaScript
Native interfaces in JavaScript look a little different than the other platforms since JavaScript doesn’t natively support threads or classes. The native implementation should be placed in a file with name matching the name of the package and the class name combined where the "." elements are replaced by underscores.
The default generated stubs for the JavaScript build look like this com_mycompany_myapp_MyNative:
(function(exports){
var o = {};
o.helloWorld__java_lang_String = function(param1, callback) {
callback.error(new Error("Not implemented yet"));
};
o.isSupported_ = function(callback) {
callback.complete(false);
};
exports.com_mycompany_myapp_MyNative= o;
})(cn1_get_native_interfaces());A simple implementation looks like this:
(function(exports){
var o = {};
o.helloWorld__java_lang_String = function(param1, callback) {
callback.complete("Hello World!!!");
}
o.isSupported_ = function(callback) {
callback.complete(true);
};
exports.com_my_code_MyNative = o;
})(cn1_get_native_interfaces());Notice that you use the complete() method of the provided callback to pass the return value rather than using the return statement. This is to work around the fact that JavaScript doesn’t natively support threads. The Java thread that’s calling your native interface will block until your method calls callback.complete(). This allows you to use asynchronous APIs inside your native method while still allowing Codename One to work use your native interface through a synchronous API.
Make sure you call either callback.complete() or callback.error() in your method at some point, or you will cause a deadlock in your app (code calling your native method will sit and "wait" forever for your method to return a value). |
The naming conventions for the methods themselves are modeled after the naming conventions shown in the previous examples:
<method-name>__<param-1-type>_<param-2-type>_…<param-n-type>
Where <method-name> is the name of the method in Java, and the `<param-X-type>`s are a string representing the parameter type. The general rule for these strings are:
Primitive types are mapped to their type name. (For example:
intto "int,"doubleto "double," etc.).Reference types are mapped to their fully qualified class name with '.' replaced with underscores. For example:
java.lang.Stringwould bejava_lang_String.Array parameters are marked by their scalar type name followed by an underscore and
1ARRAY. For example:int[]would be "int_1ARRAY" andString[]would bejava_lang_String_1ARRAY.
JavaScript examples
Java API:
public interface JavaScriptNativeApi {
void print(String str);
}becomes
o.print__java_lang_String = function(param1, callback) {
console.log(param1);
callback.complete();
}Java API:
interface JavaScriptNativeApiAddTwoArgs {
int add(int a, int b);
}becomes
o.add__int_int = function(param1, param2, callback) {
callback.complete(param1 + param2);
}interface JavaScriptNativeApiAddArray {
int add(int[] a);
}becomes
o.add__int_1ARRAY = function(param1, callback) {
var c = 0, len = param1.length;
for (var i =0; i<len; i++) {
c += param1[i];
}
callback.complete(c);
}61.5.5. Native GUI components
PeerComponent return values are automatically translated to the platform native peer as an expected return value. For example: for a NativeInterface method such as this:
interface NativePeerProvider {
PeerComponent createPeer();
}Android native implementation would use:
class AndroidPeerImplementation {
public View createPeer() {
return null;
}
}The iphone would need to return a pointer to a view for example:
- (UIView*)createPeer;| Not all platforms support native peers. Specifically Java SE doesn’t support them due to the way the Java SE native interfaces are mapped to their implementation. Note that this won’t limit the code from running on an unsupported platform. Only that specific method won’t work. |
JavaScript would expect a DOM Element (for example: a <div> tag to be returned.). For example:
o.createHelloComponent_ = function(callback) {
var c = jQuery('<div>Hello World</div>')
.css({'background-color' : 'yellow', 'border' : '1px solid blue'});
callback.complete(c.get(0));
};Notice that if you want to use a native library (jar,.a file etc.) places it within the appropriate native directory and it will be packaged into the final executable. You would be able to reference it from the native code and not from the Codename One code, which means you will need to build native interfaces to access it.
This is discussed further below.
61.5.6. Type mapping & rules
Several rules govern the creation of NativeInterfaces and you covered some of them.
The implementation class must have a default public constructor or no constructor at all
Native methods can’t throw exceptions, checked or otherwise
A native method can’t have the name
initas this is a reserved method in Objective-COnly the supported types listed below can be used
Native implementations can’t rely on pass by reference/value semantics as those might change between platforms
hashCode,equals&toStringare reserved and won’t be mapped to native code
| Java | Android | Java SE | Obj-C | C# |
|---|---|---|---|---|
byte | byte | byte | char | sbyte |
boolean | boolean | boolean | BOOL | bool |
char | char | char | int | char |
short | short | short | short | short |
int | int | int | int | int |
long | long | long | long | long |
float | float | float | float | float |
double | double | double | double | double |
String | String | String | NSString* | String |
byte[] | byte[] | byte[] | NSSData* | sbyte[] |
boolean[] | boolean[] | boolean[] | NSData* | bool[] |
char[] | char[] | char[] | NSData | char[] |
short[] | short[] | short[] | NSData* | short[] |
int[] | int[] | int[] | NSData* | int[] |
long[] | long[] | long[] | NSData* | long[] |
float[] | float[] | float[] | NSData* | float[] |
double[] | double[] | double[] | NSData* | double[] |
PeerComponent | android.view.View | PeerComponent | void* | FrameworkElement |
| JavaScript is excluded from the table above as it isn’t a type safe language and thus has no such type mapping |
PeerComponent on iOS is void* but UIView is expected as a result |
The examples below show the signatures for this method on all platforms:
interface AllTypesNativeApi {
void test(byte b, boolean boo, char c, short s,
int i, long l, float f, double d, String ss,
byte[] ba, boolean[] booa, char[] ca, short[] sa, int[] ia,
long[] la, float[] fa, double[] da,
PeerComponent cmp);
}class AndroidAllTypesImplementation {
public void test(byte param, boolean param1, char param2,
short param3, int param4, long param5, float param6,
double param7, String param8, byte[] param9,
boolean[] param10, char[] param11, short[] param12,
int[] param13, long[] param14, float[] param15,
double[] param16, android.view.View param17) {
}
}-(void)test:(char)param param1:(BOOL)param1
param2:(int)param2 param3:(short)param3 param4:(int)param4
param5:(long long)param5 param6:(float)param6
param7:(double)param7 param8:(NSString*)param8
param9:(NSData*)param9 param10:(NSData*)param10
param11:(NSData*)param11 param12:(NSData*)param12
param13:(NSData*)param13 param14:(NSData*)param14
param15:(NSData*)param15 param16:(NSData*)param16
param17:(void*)param17;| You had to break lines for the print version, the JavaScript version is a long method name that broke the book! |
o["test__byte_boolean_char_short_int_long_float_double_java_lang_String_byte_1ARRAY_boolean_1ARRAY_char_1ARRAY_short_1ARRAY_int_1ARRAY_long_1ARRAY_float_1ARRAY_double_1ARRAY_com_codename1_ui_PeerComponent"] = function(param1, param2, param3, param4, param5, param6, param7, param8, param9, param10, param11, param12, param13, param14, param15, param16, param17, param18, callback) {
callback.error(new Error("Not implemented yet"));
};class JavaScriptAllTypesImplementation {
public void test(byte param, boolean param1, char param2, short param3, int param4,
long param5, float param6, double param7, String param8, byte[] param9,
boolean[] param10, char[] param11, short[] param12, int[] param13,
long[] param14, float[] param15, double[] param16,
PeerComponent param17) {
}
}61.5.7. Android native permissions
Permissions in Codename One are seamless. Codename One traverses the bytecode and automatically assigns permissions to Android applications based on the API’s used by the developer.
For example, when accessing native functionality this won’t work since native code might require specialized permissions and you don’t/can’t run any serious analysis on it (it can be about anything).
If you require more permissions in your Android native code you need to define them in the build arguments using
android.permission.<PERMISSION_NAME>=true for each permission you want to include. A full list of permissions are listed in Android’s Manifest.permission documentation.
For example:
android.permission.ADD_VOICEMAIL=true android.permission.BATTERY_STATS=true ...
You can specify the maximum SDK version in which the permission is needed using the android.permission.<PERMISSION_NAME>.maxSdkVersion build hint. You can also specify whether the permission is required for the app to run using the android.permission.<PERMISSION_NAME>.required build hint.
For example:
android.permission.ADD_VOICEMAIL=true android.permission.BATTERY_STATS=true android.permission.ADD_VOICEMAIL.required=false android.permission.ADD_VOICEMAIL.maxSdkVersion=18 ...
You can or use the android.xpermissions build hint to inject <uses-permission> tags into the manifest file. For example:
android.xpermissions=<uses-permission android:name="android.permission.READ_CALENDAR" />
| You need to include the full XML snippet. You can unify many lines into a single line in the GUI as XML allows that. |
61.5.8. Native AndroidNativeUtil
If you do any native interfaces programming in Android you should be familiar with the AndroidNativeUtil class which allows you to access native device functionality more from the native code. For example: many Android APIs need access to the Activity which you can get by calling AndroidNativeUtil.getActivity().
The native util class includes a few other features such as:
runOnUiThreadAndBlock(Runnable)- this is such a common pattern that it was generalized into a public static method. Its identical toActivity.runOnUiThreadbut blocks until the runnable finishes execution.addLifecycleListener/removeLifecycleListener- These essentially provide you with a callback to lifecycle events:onCreateetc. which can be pretty useful for some cases.registerViewRenderer- PeerComponent's are shown on top of the UI since they’re rendered within their own thread outside of the EDT cycle. When you need to show a Dialog on top of the peer you grab a screenshot of the peer, hide it and then show the dialog with the image as the background (the same applies for transitions). Some components (specifically the MapView) might not render and require custom code to implement the transferal to a native Bitmap, this API allows you to do that.
You can work with AndroidNativeUtil using native code such as this:
class NativeCallsImpl {
public void nativeMethod() {
AndroidNativeUtil.getActivity().runOnUiThread(new Runnable() {
public void run() {
// ...
}
});
}
// ...
}61.5.9. Broadcast receiver
A common way to implement features in Android is the BroadcastReceiver API. This allows intercepting operating system events for common use cases.
A good example is intercepting incoming SMS which is specific to Android so you’d need a broadcast receiver to implement that. This is often confusing to developers who sometimes derive the impl class from broadcast receiver. That’s a mistake…
The solution is to place any native Android class into the native/android directory. It will get compiled with the rest of the native code and "works." You can therefore place this class under native/android/com/codename1/sms/intercept:
public class SMSListener extends BroadcastReceiver {
@Override
public void onReceive(Context cntxt, Intent intent) {
if (intent.getAction().equals("android.provider.Telephony.SMS_RECEIVED")) {
Bundle bundle = intent.getExtras();
SmsMessage[] msgs = null;
if (bundle != null) {
try {
Object[] pdus = (Object[]) bundle.get("pdus");
msgs = new SmsMessage[pdus.length];
for (int i = 0; i < msgs.length; i++) {
msgs[i] = SmsMessage.createFromPdu((byte[]) pdus[i]);
String msgBody = msgs[i].getMessageBody();
SMSCallback.smsReceived(msgBody);
}
} catch (Exception e) {
Log.e(e);
SMSCallback.smsReceiveError(e);
}
}
}
}
}The code above is pretty standard native Android code, it’s a callback in which most of the logic is like the native Android code mentioned in this stackoverflow question.
However, there is still more you need to do. To implement this natively you need to register the permission and the receiver in the manifest.xml file as explained in that question. This is how their native manifest looked:
<?xml version="1.0" encoding="utf-8"?>
<manifest xmlns:android="http://schemas.android.com/apk/res/android"
package="com.bulsy.smstalk1">
<uses-permission android:name="android.permission.RECEIVE_SMS" />
<uses-permission android:name="android.permission.READ_SMS" />
<uses-permission android:name="android.permission.SEND_SMS"/>
<uses-permission android:name="android.permission.READ_CONTACTS" />
<application
android:allowBackup="true"
android:icon="@mipmap/ic_launcher"
android:label="@string/app_name"
android:supportsRtl="true"
android:theme="@style/AppTheme">
<activity android:name=".MainActivity">
<intent-filter>
<action android:name="android.intent.action.MAIN" />
<category android:name="android.intent.category.LAUNCHER" />
</intent-filter>
</activity>
<receiver android:name="com.bulsy.smstalk1.SmsListener"
android:enabled="true"
android:permission="android.permission.BROADCAST_SMS"
android:exported="true">
<intent-filter android:priority="2147483647">//this doesnt work
<category android:name="android.intent.category.DEFAULT" />
<action android:name="android.provider.Telephony.SMS_RECEIVED" />
</intent-filter>
</receiver>
</application>
</manifest>You need the broadcast permission XML and the permission XML. Both are doable through the build hints. The former is pretty easy:
android.xpermissions=<uses-permission android:name="android.permission.RECEIVE_SMS" />The latter isn’t much harder; notice that many lines have been merged into a single line for convenience:
android.xapplication=<receiver android:name="com.codename1.sms.intercept.SMSListener" android:enabled="true" android:permission="android.permission.BROADCAST_SMS" android:exported="true"> <intent-filter android:priority="2147483647"><category android:name="android.intent.category.DEFAULT" /> <action android:name="android.provider.Telephony.SMS_RECEIVED" /> </intent-filter> </receiver>Here it’s formatted for readability:
<receiver android:name="com.codename1.sms.intercept.SMSListener"
android:enabled="true"
android:permission="android.permission.BROADCAST_SMS"
android:exported="true">
<intent-filter android:priority="2147483647">
<category android:name="android.intent.category.DEFAULT" />
<action android:name="android.provider.Telephony.SMS_RECEIVED" />
</intent-filter>
</receiver>Listening & permissions
You will notice that these don’t include the actual binding or permission prompts you would expect for something like this. To do this you need a native interface.
The native sample in stack overflow bound the listener in the activity but here you want the app code to decide when you should bind the listening:
public interface NativeSMSInterceptor extends NativeInterface {
void bindSMSListener();
void unbindSMSListener();
}That’s easy!
Notice that isSupported() returns false for all other OSes so you won’t need to ask whether this is "Android" you can use isSupported().
The implementation is pretty easy too:
public class NativeSMSInterceptorImpl {
private SMSListener smsListener;
public void bindSMSListener() {
if (AndroidNativeUtil.checkForPermission(Manifest.permission.RECEIVE_SMS, "We can automatically enter the SMS code for you")) { (1)
smsListener = new SMSListener();
IntentFilter filter = new IntentFilter();
filter.addAction("android.provider.Telephony.SMS_RECEIVED");
AndroidNativeUtil.getActivity().registerReceiver(smsListener, filter); (2)
}
}
public void unbindSMSListener() {
AndroidNativeUtil.getActivity().unregisterReceiver(smsListener);
}
public boolean isSupported() {
return true;
}
}| 1 | This will trigger the permission prompt on Android 6 and newer. Even though the permission is declared in XML this isn’t enough for 6+. Notice that even when you run on Android 6 you still need to declare permissions in XML! |
| 2 | Here you actually bind the listener, this allows you to grab one SMS and not listen in on every SMS coming through |
61.5.10. Native code callbacks
Native interfaces standardize the invocation of native code from Codename One, but it doesn’t standardize the reverse of callbacks into Codename One Java code. The reverse is more complicated since its platform specific and more error prone.
A common "trick" for calling back is to define a static method and then trigger it from native code. This works for Android & Java SE since those platforms use Java for their "native code." Mapping this to iOS requires some basic understanding of how the iOS VM works.
For this explanation lets pretend you have a class called NativeCallback in the src hierarchy under
the package com.mycompany that has the method: public static void callback():
public class NativeCallback {
public static void callback() {
// do stuff
}
public static void callback(int arg) {
// do stuff
}
public static void callback(String arg) {
// do stuff
}
public static int callbackR(int arg) {
// do stuff
return arg;
}
}If you want to call it from Android or all the Java based platforms you can write this in the "native" code:
public class NativeCallbackUsage {
public void invokeCallbacks() {
NativeCallback.callback();
NativeCallback.callback("My Arg");
}
}You can also pass an argument as you do later on:
public class NativeCallbackUsage {
public void invokeCallbacks() {
NativeCallback.callback();
NativeCallback.callback("My Arg");
}
}Accessing callbacks from Objective-C
If you want to invoke that method from Objective-C you need to do the following.
Add an include statement as such:
#include "com_mycompany_NativeCallback.h"
#include "CodenameOne_GLViewController.h"Notice that the CodenameOne_GLViewController.h include defines various macros such as CN1_THREAD_STATE_PASS_SINGLE_ARG.
Then when you want to trigger the method do:
com_mycompany_NativeCallback_callback__(CN1_THREAD_STATE_PASS_SINGLE_ARG);For most callbacks you should use the macro CN1_THREAD_GET_STATE_PASS_SINGLE_ARG instead of CN1_THREAD_STATE_PASS_SINGLE_ARG also make sure to add `#include "cn1_globals.h" in the file |
The VM passes the thread context along method calls to save on API calls (thread context is used in Java for synchronization, gc and more).
You can pass arguments like:
public static void callback(int arg) {
// do stuff
}Which maps to native as (notice the extra _ before the int):
com_mycompany_NativeCallback_callback___int(CN1_THREAD_GET_STATE_PASS_ARG intValue);Notice that there is no comma between the CN1_THREAD_GET_STATE_PASS_ARG and the value!
A common use case is passing string values to the Java side, or NSString* which is iOS equivalent. Assuming a method like this:
public static void callback(String arg) {
// do stuff
}You would need to convert the NSString* value you already have to a java.lang.String which the callback expects.
The fromNSString function also needs this special argument so you will need to change the method as such:
com_mycompany_NativeCallback_callback___java_lang_String(CN1_THREAD_GET_STATE_PASS_ARG fromNSString(CN1_THREAD_GET_STATE_PASS_ARG nsStringValue));And you might want to return a value from callback as such:
public static int callbackR(int arg) {
// do stuff
return arg;
}This is tricky since the method name changes to support covariant return types and so the signature would be:
com_mycompany_NativeCallback_callback___int_R_int(intValue);The upper case R allows you to differentiate between void callback(int,int) and int callback(int).
Covariant return types are a little known Java 5 feature. For example: the method Object getX() can be overridden by MyObject getX(). For example, in the VM level they can both exist side by side. |
Accessing callbacks from JavaScript
The mechanism for invoking static callback methods from JavaScript (for the JavaScript port ) is like Objective-C’s. The this object in your native interface method contains a property named $GLOBAL$ that provides access to static Java methods. This object will contain JavaScript mirror objects for each Java class (though the property name is mangled by replacing "." with underscores). Each mirror object contains a wrapper method for its underlying class’s static methods where the method name follows the same naming convention as is used for the JavaScript native methods themselves (and like the naming conventions used in Objective-C).
For example, the Google Maps project includes the static callback method:
class MapContainerCallbacks {
static void fireMapChangeEvent(int mapId, final int zoom, final double lat, final double lon) {
// ...
}
}It’s defined in the com.codename1.googlemaps.MapContainer class.
This method is called from JavaScript inside a native interface using the following code:
var fireMapChangeEvent = this.$GLOBAL$.com_codename1_googlemaps_MapContainer.fireMapChangeEvent__int_int_double_double;
google.maps.event.addListener(this.map, 'bounds_changed', function() {
fireMapChangeEvent(self.mapId, self.map.getZoom(), self.map.getCenter().lat(), self.map.getCenter().lng());
});In this example you first get a reference to the fireMapChangeEvent method, and then call it later. For example, you could have called it directly also.
Your code MUST contain the full string path this.$GLOBAL$.your_class_name.your_method_name or the build server won’t be able to recognize that your code requires this method. The $GLOBAL$ object is populated by the build server with those classes and methods that are used inside your native methods. If the build server doesn’t recognize that the methods are being used (through this pattern) it won’t generate the necessary wrappers for your JavaScript code to access the Java methods. |
Callbacks of the SMS receiver
The SMS Broadcast Receiver code from before also used callbacks such as this:
package com.codename1.sms.intercept; (1)
import com.codename1.util.FailureCallback;
import com.codename1.util.SuccessCallback;
import static com.codename1.ui.CN.*;
class SMSCallback {
static SuccessCallback<String> onSuccess;
static FailureCallback onFail;
public static void smsReceived(String sms) {
if (onSuccess != null) {
SuccessCallback<String> s = onSuccess;
onSuccess = null;
onFail = null;
SMSInterceptor.unbindListener();
callSerially(() -> s.onSucess(sms)); (2)
}
}
public static void smsReceiveError(Exception err) {
if (onFail != null) {
FailureCallback f = onFail;
onFail = null;
SMSInterceptor.unbindListener();
onSuccess = null;
callSerially(() -> f.onError(null, err, 1, err.toString()));
} else {
if (onSuccess != null) {
SMSInterceptor.unbindListener();
onSuccess = null;
}
}
}
}| 1 | Notice that the package is the same as the native code and the other classes. This allows the callback class to be package protected so it isn’t exposed through the API (the class doesn’t have the public modifier) |
| 2 | You wrap the callback in call serially to match the Codename One convention of using the EDT by default. The call will probably arrive on the Android native thread so it makes sense to normalize it and not expose the Android native thread to the user code |
Asynchronous callbacks & threading
One of the problematic aspects of calling back into Java from JavaScript is that JavaScript has no notion of multi-threading. If the method you’re calling uses Java’s threads at all (for example: It includes a wait(), notify(), sleep(), callSerially(), etc.) you need to call it asynchronously from JavaScript. You can call a method asynchronously by appending $async to the method name. For example: With the Google Maps example above, you would change :
to
var asyncFireMapChangeEvent = this.$GLOBAL$.com_codename1_googlemaps_MapContainer.fireMapChangeEvent__int_int_double_double$async;This will cause the call to be wrapped in the appropriate bootstrap code to work with threads - and it’s necessary in cases where the method may use threads of any kind. The side-effect of calling a method with the $async suffix is that you can’t use return values from the method.
| Usually you should use the async version of a method when calling it from your native method. Only use the synchronous (default) version if you’re sure that the method doesn’t use any threading primitives. |
61.6. Libraries - cn1lib
Support for JAR files in Codename One has been a source of confusion so its probably a good idea to revisit this subject again and clarify all the details.
The first source of confusion is changing the classpath. You should NEVER change the classpath or add an external JAR through the IDE classpath UI. The reasoning here is simple, these IDEs don’t package the JARs into the final executable and even if they did these JARs would probably use features unavailable or inappropriate for the device (for example: java.io.File etc.).

Cn1libs are Codename One’s file format for 3rd party extensions. It’s physically a zip file containing other zip files and some meta-data.
61.6.1. Why not use JAR
A jar can be compiled with usage of any Java API that might not be supported, it can be compiled with a Java target version that isn’t tested.
Jars don’t include support for writing native code; you could use JNI in jars but that doesn’t match Codename One’s needs for native support (see section above).
Jars don’t support "proper" code completion, a common developer trick is to stick source code into the jar but that prevents usage with proprietary code. Cn1libs provide full IDE code completion (with JavaDoc hints) without exposing the sources.
There are two use cases for wanting JARs and they both have different solutions:
Modularity
Working with an existing JARs
Cn1lib’s address the modularity aspect allowing you to break that down. Existing jars can sometimes be used native code settings but you would want to adapt the code to abide by Codename One restrictions.
61.6.2. How to use cn1libs
Codename One has a large repository of 3rd party cn1libs. With the Maven build tool, you consume a cn1lib the same way you consume any other Maven dependency: by adding it to the <dependencies> section of your application’s common/pom.xml file. A typical entry looks like:
<dependency>
<groupId>com.example</groupId>
<artifactId>mylib-lib</artifactId>
<version>1.0.0</version>
<type>pom</type>
</dependency>Add the dependency before the <!-- INJECT DEPENDENCIES -→ comment in common/pom.xml. The -lib suffix on the artifactId and the <type>pom</type> declaration are both important - they tell Maven to pull in the library’s "lib" aggregator module rather than a plain jar. See Section 1.5, “Codename One libraries” for the full library-consumption guide.
| Some cn1libs require additional configuration such as build hints. Always read the library author’s instructions when integrating a 3rd party library. |
61.6.3. Creating a simple cn1lib
Codename One libraries are generated from the cn1lib-archetype Maven archetype, which creates a multi-module project containing a common module for your cross-platform Java sources and one module per native platform (iOS, Android, Java SE, JavaScript) for any native interfaces. The detailed walkthrough - command-line, IntelliJ IDEA, NetBeans, and Eclipse - lives in Section 1.5, “Codename One libraries”.
The quickest path from a shell:
mvn archetype:generate \
-DarchetypeArtifactId=cn1lib-archetype \
-DarchetypeGroupId=com.codenameone \
-DarchetypeVersion=LATEST \
-DgroupId=com.example.mylib \
-DartifactId=mylib \
-Dversion=1.0-SNAPSHOT \
-DinteractiveMode=falseOnce the project is generated, add your cross-platform Java sources under common/src/main/java, CSS under common/src/main/css, and run mvn install from the project root to build. The build produces both a Maven artifact for pom-style consumption and a legacy .cn1lib file in common/target for users still on Ant.
61.6.4. Build hints in cn1libs
Some cn1libs are pretty simple to install - just add them as a Maven dependency in common/pom.xml. For example, many of the more elaborate cn1libs need some pretty complex configurations. This is the case when native code is involved where you need to add permissions or plist entries for the various native platforms to get everything to work. This makes the cn1lib’s helpful but less than seamless which is where you want to go.
Codename One cn1libs include two files that can be placed into the root: codenameone_library_required.properties & codenameone_library_appended.properties.
In these files you can write a build hint as codename1.arg.ios.plistInject=… for the various hints.
Notice the usage of the properties syntax for the build hint with the codename1.arg prefix you would also need to escape reserved characters for properties files.The best way to discover the right syntax for such build hints is to set them through the build hints GUI in a regular project and copy/paste them from codenameone_settings.properties into the cn1lib file. |
The obvious question is why do you need two files?
There are two types of build hints: required and appended.
Required build hints can be something like ios.objC=true
which you want to always work. For example: if a cn1lib defines ios.objC=true and another cn1lib defines ios.objC=false
things won’t work since one cn1lib won’t get what it needs…
In this case you’d want the build to fail so you can remove the faulty cn1lib.
If two cn1libs define ios.objC=true there will be no collision as the value would be identical |
An appended property would be something like ios.plistInject=<key>UIBackgroundModes</key><array><string>audio</string> </array>
Notice that this can still collide for example: if a different cn1lib defines its own background mode. For example, there are many valid cases where ios.plistInject can be used for other things. In this case you will append the content of the ios.plistInject into the build hint if it isn’t already there.
Keep these things in mind:
Properties are merged with every "refresh libs" call not dynamically on the server. This means it should be pretty simple for the developer to investigate issues in this process.
Changing flags is problematic - there is no "uninstall" process. Since the data is copied into the
codenameone_settings.propertiesfile. If you need to change a flag later on you might need to alert users to make changes to their properties essentially negating the value of this feature…
be careful when adding properties here.
It’s your responsibility as a library developer to decide which build hint goes into which file!
Codename One can’t automate this process as the whole process of build hints is by definition an ad hoc process.
The rule of thumb is that a build hint with a numeric or boolean value is always a required property. If an entry has a string that you can append with another string then its probably an appended entry.
These build hints are probably of the "required" type:
android.debug
android.release
android.installLocation
android.licenseKey
android.stack_size
android.statusbar_hidden
android.googleAdUnitId
android.includeGPlayServices
android.headphoneCallback
android.gpsPermission
android.asyncPaint
android.supportV4
android.theme
android.cusom_layout1
android.versionCode
android.captureRecord
android.removeBasePermissions
android.blockExternalStoragePermission
android.min_sdk_version
android.smallScreens
android.streamMode
android.enableProguard
android.targetSDKVersion
android.web_loading_hidden
facebook.appId
facebook.clientToken
ios.keyboardOpen
ios.project_type
ios.newStorageLocation
ios.prerendered_icon
ios.application_exits
ios.themeMode
ios.xcode_version
javascript.inject_proxy
javascript.minifying
javascript.proxy.url
javascript.sourceFilesCopied
javascript.teavm.version
google.adUnitId
ios.includePush
ios.headphoneCallback
ios.enableAutoplayVideo
ios.googleAdUnitId
ios.googleAdUnitIdPadding
ios.enableBadgeClear
ios.locationUsageDescription
ios.bundleVersion
ios.objC
ios.testFlight
ios.metal
desktop.width
desktop.height
desktop.adaptToRetina
desktop.resizable
desktop.fontSizes
desktop.theme
desktop.themeMac
desktop.themeWin
desktop.windowsOutput
noExtraResources
android.permission.<PERMISSION_NAME>These build hints should probably be appended:
android.xapplication
android.xpermissions
android.xintent_filter
android.facebook_permissions
android.stringsXml
android.style
android.nonconsumable
android.xapplication_attr
android.xactivity
android.pushVibratePattern
android.proguardKeep
android.sharedUserId
android.sharedUserLabel
ios.urlScheme
ios.interface_orientation
ios.plistInject
ios.facebook_permissions
ios.applicationDidEnterBackground
ios.viewDidLoad
ios.glAppDelegateHeader
ios.glAppDelegateBody
ios.beforeFinishLaunching
ios.afterFinishLaunching
ios.add_libs61.7. Integrating Android 3rd party libraries & JNI
While its pretty easy to use native interfaces to write Android native code some things aren’t necessarily as obvious. For example: if you want to integrate a 3rd party library, specifically one that includes native C JNI code this process isn’t as straightforward.
If you need to integrate such a library into your native calls you have the following options:
The first option (and the easiest one) is to place a Jar file in the native/android directory. This will link your binary with the jar file. Just place the jar under the native/android and the build server will pick it up and will add it to the classpath.
Notice that Android release apps are obfuscated by default which might cause issues with such libraries if they reference APIs that are unavailable on Android. You can work around this by adding a build hint to the proguard obfuscation code that blocs the obfuscation of the problematic classes using the build hint:android.proguardKeep=-keep class com.mypackage.ProblemClass { *; }`Another option is the
aarfile is a binary format Google introduced to represent an Android Library project (similarly to the cn1lib format). One of the problem with the Android Library projects was the fact that it required the project sources which made it difficult for 3rd party vendors to publish libraries.
As a result so android introduced theaarfile which is a binary format that represents a Library project. To learn more about arr you can read this.You can link an
aarfile by placing it under the native/android and the build server will link it to the project.Another obsolete approach exists that you’re mentioning for legacy purposes (for example: if you need to port code written with this legacy option). This predated the
aaroption from Google… Not all 3rd party tools can be packaged as a simple jar, some 3rd party tools need to declare activities add permissions, resources, assets, and/or even add native code (.sofiles).
To link a Library project to your Codename One project open the Library project in Eclipse or Android Studio and make sure the project builds, after the project was built successfully remove the bin directory from the project and zip the whole project.Rename the extension from
.zipto.andliband place the andlib file under thenative/androiddirectory. The build server will pick it up and will link it to the project.
61.8. Drag & drop
Unlike other platforms that tried to create overly generic catch all APIs Codename One tried to make things as simple as possible.
In Codename One components can be dragged and drop targets are always components. The logic of actually performing the operation indicated by the drop is the responsibility of the person implementing the drop.
| Some platforms for example: AWT allow dragging abstract concepts such as mime type elements. This allows dragging things like a text file into the app, but that use case isn’t realistic in mobile |
The code below allows you to rearrange the items based on a sensible order. Notice it relies on the default Container drop behavior:
public class RearrangeableItemsDemo {
public void show() {
Form hi = new Form("Rearrangeable Items", new BorderLayout());
String[] buttons = {"A Game of Thrones", "A Clash Of Kings", "A Storm Of Swords",
"A Feast For Crows", "A Dance With Dragons", "The Winds of Winter", "A Dream of Spring" };
Container box = new Container(BoxLayout.y());
box.setScrollableY(true);
box.setDropTarget(true);
java.util.List<String> got = Arrays.asList(buttons);
Collections.shuffle(got);
for (String current : got) {
MultiButton mb = new MultiButton(current);
box.add(mb);
mb.setDraggable(true);
}
hi.add(BorderLayout.NORTH, "Arrange The Titles").add(BorderLayout.CENTER, box);
hi.show();
}
}
To enable dragging a component it must be flagged as draggable using setDraggable(true), to allow dropping the component onto another component you must first enable the drop target with setDropTarget(true) and override some methods (more on that later).
When dragging on top of a child component of a drop target the code recursively searches for a drop target parent. Dropping a component on the child will automatically find the right drop target, hence there is no need to make "everything" into a drop target.
You can override these methods in the draggable components:
getDragImage- this generates an image preview of the component that will be dragged. This automatically generates a sensible default so you don’t need to override it.drawDraggedImage- this method will be invoked to draw the dragged image at a given location, it might be useful to override it if you want to display some drag related information such as an icon based on location etc. (for example: a move/copy icon).
In the drop target you can override the following methods:
draggingOver- returns true if a drop operation at this point is permitted. Otherwise releasing the component will have no effect.dragEnter/Exit- useful to track and cleanup state related to dragging over a specific component.drop- the logic for dropping/moving the component must be implemented here!
61.9. Android Lollipop ActionBar customization
When running on Android Lollipop (5.0 or newer) the native action bar will use the Lollipop design. This isn’t applicable if you use the Toolbar or SideMenuBar this will be used in the task switcher.
To customize the colors of the native ActionBar on Lollipop define a colors.xml file in the native/android directory
of your project. It should look like this:
<resources>
<color name="colorPrimary">#ff00ff00</color>
<color name="colorPrimaryDark">#80ff0000</color>
<color name="colorAccent">#800000ff</color>
</resources>61.10. Intercepting URLs on iOS & Android
A common trick in mobile application development, is communication between two unrelated applications.
In Android you can use intents which are pretty elaborate and can be used through Display.execute, but what if you would like to expose the functionality of your application to a different application running on the device. This would allow that application to launch your application.
This isn’t something built into Codename One, but it does expose enough of the platform capabilities to enable that functionality rather on Android.
On Android you need to define an intent filter which you can do using the android.xintent_filter build hint, this accepts the XML to filter whether a request is relevant to your application:
android.xintent_filter=<intent-filter> <action android:name="android.intent.action.VIEW" /> <category android:name="android.intent.category.DEFAULT" /> <category android:name="android.intent.category.BROWSABLE" /> <data android:scheme="myapp" /> </intent-filter>You can read more about it in this stack overflow question.
To bind the myapp:// URL to your application. As a result typing myapp://x into the Android browser will launch the application.
61.10.1. Passing launch arguments to the app
You can access the value of the URL that launched the app using:
public class RearrangeableItemsDemo {
public void show() {
Form hi = new Form("Rearrangeable Items", new BorderLayout());
String[] buttons = {"A Game of Thrones", "A Clash Of Kings", "A Storm Of Swords",
"A Feast For Crows", "A Dance With Dragons", "The Winds of Winter", "A Dream of Spring" };
Container box = new Container(BoxLayout.y());
box.setScrollableY(true);
box.setDropTarget(true);
java.util.List<String> got = Arrays.asList(buttons);
Collections.shuffle(got);
for (String current : got) {
MultiButton mb = new MultiButton(current);
box.add(mb);
mb.setDraggable(true);
}
hi.add(BorderLayout.NORTH, "Arrange The Titles").add(BorderLayout.CENTER, box);
hi.show();
}
}This value would be null if the app was launched through the icon.
61.10.2. Android App-to-App contracts (Wallet/Issuer style flows)
Some integrations (wallet provisioning, issuer verification, secure step-up) need more than a URL launch. They require:
a custom Android intent action,
caller validation,
asynchronous app logic (login/back end verification),
a native
setResult(…)response back to the caller.
In Codename One, keep this flow in two layers:
Android bridge activity for contract lifecycle and
setResult(…).Codename One app code for business logic in
start().
Why this isn’t implicitly generated by AndroidGradleBuilder
A generic bridge can’t infer:
expected caller package(s),
required result extra names,
approval/decline mapping rules,
timeout/failure policy.
Those are contract-specific, so the bridge activity is intentionally app-defined.
Registering the bridge activity
Use android.xapplication to inject a dedicated bridge activity and bind the action it should receive:
codename1.arg.android.xapplication=<activity android:name="com.example.wallet.WalletBridgeActivity" android:exported="true" android:launchMode="singleTop" android:noHistory="true" android:excludeFromRecents="true" android:theme="@android:style/Theme.Translucent.NoTitleBar"><intent-filter><action android:name="com.example.wallet.ACTION_VERIFY"/><category android:name="android.intent.category.DEFAULT"/></intent-filter></activity>Keep codename1.arg.android.activity.launchMode=singleTask on your main CN1 activity so app resume behavior is predictable.
Bridge activity responsibilities
A minimal bridge activity should:
Receive and parse the incoming intent.
Capture caller identity using
getCallingPackage().Launch or resume the CN1 app activity.
Hold contract state until CN1 completes verification.
Return
setResult(…)andfinish().
For payment/wallet trust decisions, treat only getCallingPackage() as verified identity.
Don’t rely on referrer extras for caller authentication because callers can spoof those values.
This implies the contract should be launched with startActivityForResult(…) so caller identity is available. |
Optional native Android example for certificate fingerprint verification (called from bridge/native layer before trusting caller):
public static boolean isTrustedCallerSignature(Context ctx, String packageName, Set<String> allowedSha256) {
if (ctx == null || packageName == null || packageName.isEmpty() || allowedSha256 == null || allowedSha256.isEmpty()) {
return false;
}
try {
PackageManager pm = ctx.getPackageManager();
PackageInfo info;
if (Build.VERSION.SDK_INT >= 28) {
info = pm.getPackageInfo(packageName, PackageManager.GET_SIGNING_CERTIFICATES);
Signature[] sigs = info.signingInfo != null
? info.signingInfo.getApkContentsSigners()
: null;
return hasAllowedFingerprint(sigs, allowedSha256);
} else {
info = pm.getPackageInfo(packageName, PackageManager.GET_SIGNATURES);
return hasAllowedFingerprint(info.signatures, allowedSha256);
}
} catch (PackageManager.NameNotFoundException | NoSuchAlgorithmException ex) {
return false;
}
}
private static boolean hasAllowedFingerprint(Signature[] sigs, Set<String> allowedSha256)
throws NoSuchAlgorithmException {
if (sigs == null) {
return false;
}
MessageDigest md = MessageDigest.getInstance("SHA-256");
for (Signature s : sigs) {
String fp = toHex(md.digest(s.toByteArray()));
if (allowedSha256.contains(fp)) {
return true;
}
}
return false;
}
private static String toHex(byte[] data) {
char[] digits = "0123456789ABCDEF".toCharArray();
StringBuilder out = new StringBuilder(data.length * 2);
for (byte b : data) {
int value = b & 0xff;
out.append(digits[value >>> 4]);
out.append(digits[value & 0x0f]);
}
return out.toString();
}public class WalletBridgeActivity extends Activity {
private static WeakReference<WalletBridgeActivity> active;
@Override
protected void onCreate(Bundle savedInstanceState) {
super.onCreate(savedInstanceState);
active = new WeakReference<>(this);
Intent in = getIntent();
String caller = getCallingPackage();
String payload = in == null ? null : in.getStringExtra("payload");
Intent launch = getPackageManager().getLaunchIntentForPackage(getPackageName());
if (launch == null) {
finish();
return;
}
launch.addFlags(Intent.FLAG_ACTIVITY_NEW_TASK | Intent.FLAG_ACTIVITY_CLEAR_TOP | Intent.FLAG_ACTIVITY_SINGLE_TOP);
launch.putExtra("wallet_payload", payload);
launch.putExtra("wallet_caller", caller == null ? "" : caller);
startActivity(launch);
// Do not finish yet. CN1 will finish this activity via native callback once verification completes.
}
@Override
protected void onDestroy() {
WalletBridgeActivity current = getActive();
if (current == this) {
active = null;
}
super.onDestroy();
}
public static WalletBridgeActivity getActive() {
return active == null ? null : active.get();
}
}Reading contract data in start()
Codename One exposes launch metadata through AppArg and Display properties. Read these in start():
AppArg(primary launch payload)android.intent.actionandroid.intent.dataandroid.intent.typeandroid.intent.callerandroid.intent.caller.verifiedandroid.intent.extra.<KEY>
public void start() {
Display d = Display.getInstance();
String action = d.getProperty("android.intent.action", null);
if ("com.example.wallet.ACTION_VERIFY".equals(action)) {
boolean callerVerified = "true".equals(d.getProperty("android.intent.caller.verified", "false"));
String payload = d.getProperty("android.intent.extra.wallet_payload", d.getProperty("AppArg", null));
String caller = d.getProperty("android.intent.caller", "");
if (!callerVerified || !isAllowedCaller(caller)) {
failClosed(); // return declined/canceled via bridge completion API
return;
}
verifyWalletPayload(payload, caller);
return;
}
showMainForm();
}Returning results to the wallet API
Implement a small native interface method (Android implementation) that:
gets
WalletBridgeActivity.getActive(),verifies
getActive()is non-null and fails closed if the bridge timed out/canceled,builds caller-specific result extras,
calls
setResult(Activity.RESULT_OK, resultIntent),calls
finish()on the bridge activity.
This is where you bind to the wallet contract’s exact response schema. Keep these extra names in one place so upgrades are manageable.
Foreground behavior on Android 14/15
Foreground transitions are best-effort because Android may block background launches in some states. Build for:
immediate resume when allowed,
notification fallback when blocked.
iOS is practically identical to Android with some small caveats, iOS’s equivalent of the manifest is the plist.
You can inject more data into the plist by using the ios.plistInject build hint.
The equivalent on the iOS side would be:
ios.plistInject=<key>CFBundleURLTypes</key> <array> <dict> <key>CFBundleURLName</key> <string>com.yourcompany.myapp</string> </dict> <dict> <key>CFBundleURLSchemes</key> <array> <string>myapp</string> </array> </dict> </array>For example, that can conflict with the Facebook integration if you use FacebookConnect which needs access to the schemes. To work around this you can use the build hint ios.urlScheme for example:
ios.urlScheme=<string>myapp</string>61.11. Native peer components
Many Codename One developers don’t truly grasp the reason for the separation between peer (native) components and Codename One components. This is a crucial thing you need to understand if you plan on working with native widgets for example: Web Browser, native maps, text input, media and native interfaces (which can return a PeerComponent).
Codename One draws all its widgets on its own, this is a concept which was modeled in part after Swing. This allows functionality that can’t be achieved in native widget platforms:
The Codename One GUI builder & simulator are almost identical to the device - notice that this also enables the build cloud, otherwise device specific bugs would overwhelm development and make the build cloud redundant.
Ability to override everything - paint, pointer, key events are all overridable and replaceable. Developers can also paint over everything for example: glasspane and layered pane.
Consistency - provides identical functionality on all platforms.
This all contributes to your ease of working with Codename One and maintaining Codename One. More than 95% of Codename One’s code is in Java hence its portable and pretty easy to maintain!
61.11.1. Why does Codename One need native widgets at all
You need the native device to do input, html rendering etc. These are too big and too complex tasks for Codename One to do from scratch.
They’re sometimes impossible to perform without the native platform. For example: the virtual keyboard input on the devices is tied directly to the native text input. It’s impractical to implement everything from scratch for all languages, dictionaries etc. The result would be sub-par.
A web browser can’t be implemented in this age without a JavaScript JIT and including a JIT within an iOS app is prohibited by Apple.
61.11.2. Problems with native widgets
Codename One does pretty much everything on the EDT (Event Dispatch Thread), this provides a lot of cool features for example: modal dialogs, invokeAndBlock etc.
For example native widgets have to be drawn on the devices native UI thread.
This means that drawing looks something like this:
Loop over all Codename One components and paint them.
Loop over all native peer components and paint them.
This means that all peer components are drawn on top of the Codename One components.
| This was also the case in AWT/Swing to one degree or another… |
61.11.3. Showing dialogs on top of peer components
Codename One grabs a screenshot of the peer, hide it and then you can show the screenshot. Since the screenshot is static it can be rendered through the standard UI. You can’t do that always since grabbing a screenshot is an expensive process on all platforms and must be performed on the native device thread.
61.11.4. Why can’t you combine peer component scrolling and Codename One scrolling
Since the form title/footer etc. Are drawn by Codename One the peer component might paint itself on top of them. Clipping a peer component is often pretty difficult. Furthermore, if the user drags his finger within the peer component he might trigger the native scroll within the might collide with your scrolling?
61.11.5. Native components in the first Form
Another problem might be counterintuitive. iOS has screenshot images representing the first form. If your first page is an HTML or a native map (or other peer widget) the screenshot process on the build server will show fallback code instead of the real thing thus providing sub-par behavior.
Its impractical to support something like HTML for the screenshot process since it would also look different from the web component running on the device.
| You can read more about the screenshot process here. |
61.12. Integrating 3rd party native SDKs
The following is a description of the procedure that was used to create the Codename One FreshDesk library. This process can be adapted to wrap any native SDK on Android and iOS.
61.12.1. Step 1 : Review the FreshDesk SDKs
Before you begin, you will need to review the Android and iOS SDKs.
FreshDesk Android SDK: Integration Guide | API Docs
FreshDesk iOS SDK: Integration Guide | API Docs
In reviewing the SDKs, you’re looking for answers to two questions:
What should your Codename One FreshDesk API look like?
What will be involved in integrating the native SDK in your app or lib?
61.12.2. Step 2: Designing the Codename One public API
When designing the Codename One API, you should begin by looking at the Javadocs for the native Android SDK. If the class hierarchy doesn’t look too elaborate, you may decide to model your Codename One public API on the Android API. But, if you need a small part of the SDK’s functionality, you may choose to create your abstractions around the functionality that you need.
For the FreshDesk SDK, it looks like most of the functionality is handled by one central class Mobihelp,
with a few other POJO classes for passing data to and from the service. This is a good candidate for a comprehensive
Codename One API.
Before proceeding, you also need to look at the iOS API to see if there are any features that aren’t included. While naming conventions in the iOS API are a little different than those in the Android API, it looks like they’re functionally the same.
The chosen approach therefore creates a class hierarchy and API that mirrors the Android SDK.
61.12.3. Step 3: The architecture and internal APIs
A Codename One library that wraps a native SDK, will consist of the following:
Public Java API, consisting of pure Java classes that are intended to be used by the outside world.
Native Interface(s). The Native Interface(s) act as a conduit for the public Java API to communicate to the native SDK. Parameters in native interface methods are limited to primitive types, arrays of primitive types, and Strings, as are return values.
Native code. Each platform must include an implementation of the Native Interface(s). These implementations are written in the native language of the platform (for example: Java for Android, and Objective-C for iOS).
Native dependencies. Any 3rd party libraries required for the native code to work, need to be included for each platform. On android, this may mean bundling.jar files,.aar files, or.andlib files. On iOS, this may mean bundling
.hfiles,.afiles,.framework, and.bundlefiles.Build hints. Some libraries will require you to add some extra build hints to your project. For example: On Android you may need to add permissions to the manifest, or define services in the
<Application>section of the manifest. On iOS, this may mean specifying more core frameworks for inclusion, or adding build flags for compilation.
The following diagram shows the dependencies in a native library:

In the specific case of your FreshDesk API, the public API and classes will look like:

Things to notice
The public API consists of the main class (
Mobihelp), and a few supporting classes (FeedbackRequest,FeedbackType,MobihelpConfig,MobihelpCallbackStatus), which were copied almost directly from the Android SDK.The way for the public API to communicate with the native SDK is through the
MobihelpNativeinterface.You introduced the
MobihelpNativeCallbackclass to ease native code calling back into the public API. This was necessary for a few methods that used asynchronous callbacks.
61.12.4. Step 4: Implement the public API and native interface
You’ve already looked at the final product of the public API in the previous step. Back up and walk through the process step-by-step.
The goal is to model your API around the Android API. The central class that includes all the functionality of the SDK is the com.freshdesk.mobihelp.Mobihelp class, so you begin there.
You will start by creating your own package (com.codename1.freshdesk) and your own Mobihelp class inside it.
Adapting method signatures
The Context parameter
In a first glance at the com.freshdesk.mobihelp.Mobihelp API you see that many of the methods take a parameter of type android.content.Context. This class is part of the core Android SDK, and won’t be accessible to any pure Codename One APIs. Your public API therefore can’t include any such references. You will be able to access a suitable context in the native layer, so you will omit this parameter from your public API, and inject them in your native implementation.
Hence, the method signature public static final void setUserFullName (Context context, String name) will become public static final void setUserFullName (String name) in your public API.
Non-Primitive parameters
Although your public API isn’t constrained by the same rules as your Native Interfaces about parameter and return types, you need to be cognizant of the fact that parameters you pass to your public API will be funnelled through your native interface. You should pay attention to any parameters or return types that can’t be passed directly to a native interface, and start forming a strategy for them. For example: consider the following method signature from the Android Mobihelp class:
public static final void showSolutions (Context activityContext, ArrayList<String> tags)
You’ve already decided to omit the Context parameter in your API, so that’s a non-issue. However, what about the ArrayList<String> tags parameter? Passing this to your public API is no problem, but when you implement the public API, how will you pass this ArrayList to your native interface, since native interfaces don’t allow you to arrays of strings as parameters?
One of three strategies applies in such cases:
Encode the parameter as either a single
String(for example: using JSON or some other parseable format) or a byte[] array (in some known format that can be parsed in native code).Store the parameter on the Codename One side and pass some ID or token that can be used on the native side to retrieve the value.
If the data structure can be expressed as a finite number of primitive values, then design the native interface method to take the individual values as parameters instead of a single object. For example: If there is a User class with properties
nameandphoneNumber, the native interface can havenameandphoneNumber parameters rather than a single `userparameter.
In this case, because an array of strings is such a simple data structure, the right approach is a variation on strategy number 1: Merge the array into a single string with a delimiter.
In any case, you don’t have to come up with the specifics right now, as you’re still on the public API, but it will pay dividends later if you think this through ahead of time.
Callbacks
It’s often the case that native code needs to call back into Codename One code when an event occurs. This may be connected directly to an API method call (for example: as the result of an asynchronous method invocation), or due to something initiated by the operating system or the native SDK on its own (for example: a push notification, a location event, etc.).
Native code will have access to both the Codename One API and any native APIs in your app, but on some platforms, accessing the Codename One API may be a little tricky. For example: on iOS you’ll be calling from Objective-C back into Java which requires knowledge of Codename One’s java-to-goal C conversion process. In general, the easiest way to ease callbacks is to provide abstractions that involve static Java methods (in Codename One space) that accept and return primitive types.
For your Mobihelp class, the following method hints at the need to have a "callback plan":
public static final void getUnreadCountAsync (Context context, UnreadUpdatesCallback callback)
The interface definition for UnreadUpdatesCallback is:
public interface UnreadUpdatesCallback {
//This method is called once the unread updates count is available.
void onResult(MobihelpCallbackStatus status, Integer count);
}The callback status enum is also mirrored in common code:
public enum MobihelpCallbackStatus {
SUCCESS,
FAILURE
}In other words: if you were to implement this method (planned for a later section), you need to have a way for the native code to call the callback.onResult() method of the passed parameter.
You’ve two issues that will need to be solved here:
How to pass the
callbackobject through the native interface.How to call the
callback.onResult()method from native code at the right time.
For the first issue, you will use strategy #2 that you mentioned earlier: (Store the parameter on the Codename One side and pass some ID or token that can be used on the native side to retrieve the value).
For the second issue, you will create a static method that can take the token generated to solve the first issue, and call the stored callback object’s onResult() method. You abstract both sides of this process using the MobihelpNativeCallback class:
public class MobihelpNativeCallback {
private static int nextId = 0;
private static Map<Integer, UnreadUpdatesCallback> callbacks = new HashMap<>();
static int registerUnreadUpdatesCallback(UnreadUpdatesCallback callback) {
callbacks.put(nextId, callback);
return nextId++;
}
public static void fireUnreadUpdatesCallback(int callbackId, final int status, final int count) {
final UnreadUpdatesCallback cb = callbacks.get(callbackId);
if (cb != null) {
callbacks.remove(callbackId);
Display.getInstance().callSerially(new Runnable() {
public void run() {
MobihelpCallbackStatus status2 = MobihelpCallbackStatus.values()[status];
cb.onResult(status2, count);
}
});
}
}
}Things to notice here:
This class uses a static
Map<Integer,UnreadUpdatesCallback>member to keep track of all callbacks, mapping a unique integer ID to each callback.The
registerUnreadUpdatesCallback()method takes anUnreadUpdatesCallbackobject, places it in thecallbacksmap, and returns the integer token that can be used to fire the callback later. This method would be called by the public API inside thegetUnreadCountAsync()method implementation to convert thecallbackinto an integer, which can then be passed to the native API.The
fireUnreadUpdatesCallback()method would be called later from native code. Its first parameter is the token for the callback to call.You wrap the
onResult()call inside aDisplay.callSerially()invocation to ensure that the callback is called on the EDT. This is a general convention that’s used throughout Codename One, and you’d be well-advised to follow it. Event handlers should be run on the EDT unless there is a good reason not to - and in that case your documentation and naming conventions should make this clear to avoid stepping into multithreading hell!
Initialization
Most Native SDKs include some sort of initialization method where you pass your developer and application credentials to the API. After filling in FreshDesk’s web-based form to create a new application, it generated an application ID, an app "secret," and a "domain." The SDK requires you to pass all three of these values to its init() method through the MobihelpConfig class.
public class MobihelpConfig {
private String appSecret;
private String appId;
private String domain;
private boolean autoReplyEnabled;
private boolean enhancedPrivacyModeEnabled;
private FeedbackType feedbackType;
private int launchCountForReviewPrompt;
private boolean prefetchSolutions;
public void setAppSecret(String appSecret) {
this.appSecret = appSecret;
}
public void setAppId(String appId) {
this.appId = appId;
}
public void setDomain(String domain) {
this.domain = domain;
}
public String getAppSecret() {
return appSecret;
}
public String getAppId() {
return appId;
}
public String getDomain() {
return domain;
}
public void setAutoReplyEnabled(boolean autoReplyEnabled) {
this.autoReplyEnabled = autoReplyEnabled;
}
public boolean isAutoReplyEnabled() {
return autoReplyEnabled;
}
public void setEnhancedPrivacyModeEnabled(boolean enhancedPrivacyModeEnabled) {
this.enhancedPrivacyModeEnabled = enhancedPrivacyModeEnabled;
}
public boolean isEnhancedPrivacyModeEnabled() {
return enhancedPrivacyModeEnabled;
}
public void setFeedbackType(FeedbackType feedbackType) {
this.feedbackType = feedbackType;
}
public FeedbackType getFeedbackType() {
return feedbackType;
}
public void setLaunchCountForReviewPrompt(int launchCountForReviewPrompt) {
this.launchCountForReviewPrompt = launchCountForReviewPrompt;
}
public int getLaunchCountForReviewPrompt() {
return launchCountForReviewPrompt;
}
public void setPrefetchSolutions(boolean prefetchSolutions) {
this.prefetchSolutions = prefetchSolutions;
}
public boolean isPrefetchSolutions() {
return prefetchSolutions;
}
public enum FeedbackType {
POSITIVE,
NEGATIVE
}
}Note, but, that FreshDesk (and most other service provides that have native SDKs) requires you to create different Apps for each platform. This means that your App ID and App secret will be different on iOS than they will be on Android.
Your public API therefore needs to enable you to provide many credentials in the same app, and your API needs to know to use the correct credentials depending on the device that the app is running on.
Many solutions to this problem exist, but the chosen approach provides two different init() methods:
public final static void initAndroid(MobihelpConfig config) {
if ("and".equals(Display.getInstance().getPlatformName())) {
init(config);
}
}and
public final static void initIOS(MobihelpConfig config) {
if ("ios".equals(Display.getInstance().getPlatformName())) {
init(config);
}
}Then you can set up the API with code like:
public class MobihelpUsage {
public void configure() {
MobihelpConfig config = new MobihelpConfig();
config.setAppSecret("xxxxxxx");
config.setAppId("freshdeskdemo-2-xxxxxx");
config.setDomain("codenameonetest1.freshdesk.com");
MobihelpInitMethods.initIOS(config);
config = new MobihelpConfig();
config.setAppSecret("yyyyyyyy");
config.setAppId("freshdeskdemo-1-yyyyyyyy");
config.setDomain("https://codenameonetest1.freshdesk.com");
MobihelpInitMethods.initAndroid(config);
}
}The resulting public API
public class Mobihelp {
private static char[] separators = new char[]{',','|','/','@','#','%','!','^','&','*','=','+','*','<'};
private static MobihelpNative peer;
public static boolean isSupported() {
return peer != null;
}
public static void setPeer(MobihelpNative peer) {
Mobihelp.peer = peer;
}
//Attach the given custom data (key-value pair) to the conversations/tickets.
public final static void addCustomData(String key, String value) {
// ...
}
//Attach the given custom data (key-value pair) to the conversations/tickets with the ability to flag sensitive data.
public final static void addCustomData(String key, String value, boolean isSensitive) {
// ...
}
//Clear all breadcrumb data.
public final static void clearBreadCrumbs() {
// ...
}
//Clear all custom data.
public final static void clearCustomData() {
// ...
}
//Clears User information.
public final static void clearUserData() {
// ...
}
//Retrieve the number of unread items across all the conversations for the user synchronously i.e.
public final static int getUnreadCount() {
return 0;
}
//Retrieve the number of unread items across all the conversations for the user asynchronously
public final static void getUnreadCountAsync(UnreadUpdatesCallback callback) {
// ...
}
//Initialize the Mobihelp support section with necessary app configuration.
public final static void initAndroid(MobihelpConfig config) {
// ...
}
public final static void initIOS(MobihelpConfig config) {
// ...
}
public void showSupport() {
// ...
}
}The native interface
The final native interface is identical to your public API, except in cases where the public API included non-primitive parameters:
public interface MobihelpNative extends NativeInterface {
void config_setAppId(String appId);
void config_setAppSecret(String appSecret);
void config_setAutoReplyEnabled(boolean enabled);
void config_setDomain(String domain);
void config_setEnhancedPrivacyModeEnabled(boolean enabled);
void config_setFeedbackType(int type);
void config_setLaunchCountForReviewPrompt(int count);
void config_setPrefetchSolutions(boolean prefetch);
void initNative();
void setUserFullName(String name);
void showSupportWithTags(String tags, String separator);
void getUnreadCountAsync(int callbackId);
}Notice also, that the native interface includes a set of methods with names prefixed with config__. This naming convention identifies methods that map to the MobihelpConfig class. A separate native interface for these would have been possible, but keeping all the native stuff in one class is simpler and easier to maintain.
Connecting the public API to the native interface
You’ve a public API, and you have a native interface. The idea is that the public API should be a thin wrapper around the native interface to smooth out rough edges that are likely to exist due to the strict set of rules involved in native interfaces. You will, so, use delegation inside the Mobihelp class to provide it a reference to an instance of MobihelpNative:
public class Mobihelp {
private static char[] separators = new char[]{',','|','/','@','#','%','!','^','&','*','=','+','*','<'};
private static MobihelpNative peer;
public static boolean isSupported() {
return peer != null;
}
public static void setPeer(MobihelpNative peer) {
Mobihelp.peer = peer;
}
//Attach the given custom data (key-value pair) to the conversations/tickets.
public final static void addCustomData(String key, String value) {
// ...
}
//Attach the given custom data (key-value pair) to the conversations/tickets with the ability to flag sensitive data.
public final static void addCustomData(String key, String value, boolean isSensitive) {
// ...
}
//Clear all breadcrumb data.
public final static void clearBreadCrumbs() {
// ...
}
//Clear all custom data.
public final static void clearCustomData() {
// ...
}
//Clears User information.
public final static void clearUserData() {
// ...
}
//Retrieve the number of unread items across all the conversations for the user synchronously i.e.
public final static int getUnreadCount() {
return 0;
}
//Retrieve the number of unread items across all the conversations for the user asynchronously
public final static void getUnreadCountAsync(UnreadUpdatesCallback callback) {
// ...
}
//Initialize the Mobihelp support section with necessary app configuration.
public final static void initAndroid(MobihelpConfig config) {
// ...
}
public final static void initIOS(MobihelpConfig config) {
// ...
}
public void showSupport() {
// ...
}
}You will initialize this peer inside the init() method of the Mobihelp class. Notice, though that init() is private since you’ve provided distinct abstractions for the Android and iOS apps:
class MobihelpInitMethods {
//Initialize the Mobihelp support section with necessary app configuration.
public final static void initAndroid(MobihelpConfig config) {
if ("and".equals(Display.getInstance().getPlatformName())) {
init(config);
}
}
public final static void initIOS(MobihelpConfig config) {
if ("ios".equals(Display.getInstance().getPlatformName())) {
init(config);
}
}
private static void init(MobihelpConfig config) {
MobihelpNative peer = (MobihelpNative) NativeLookup.create(MobihelpNative.class);
peer.config_setAppId(config.getAppId());
peer.config_setAppSecret(config.getAppSecret());
peer.config_setAutoReplyEnabled(config.isAutoReplyEnabled());
peer.config_setDomain(config.getDomain());
peer.config_setEnhancedPrivacyModeEnabled(config.isEnhancedPrivacyModeEnabled());
if (config.getFeedbackType() != null) {
peer.config_setFeedbackType(config.getFeedbackType().ordinal());
}
peer.config_setLaunchCountForReviewPrompt(config.getLaunchCountForReviewPrompt());
peer.config_setPrefetchSolutions(config.isPrefetchSolutions());
peer.initNative();
}
}Things to Notice:
The
initAndroid()andinitIOS()methods include a check to see if they’re running on the correct platform. They both callinit().The
init()method, uses the NativeLookup class to instantiate your native interface.
Implementing the glue between public API and native interface
For most of the methods in the Mobihelp class, you can see that the public API will be a thin wrapper around the native interface. For example: the public API implementation of setUserFullName(String) is:
public final static void setUserFullName(String name) {
peer.setUserFullName(name);
}For some other methods, the public API needs to break apart the parameters into a form that the native interface can accept. For example: the init() method, shown above, takes a MobihelpConfig object as a parameter, but it passed the properties of the config object individually into the native interface.
Another example, is the showSupport(ArrayList<String> tags) method. The corresponding native interface method that’s wraps is showSupport(String tags, `String separator)` - i.e., it needs to merge all tags into a single delimited string, and pass then to the native interface along with the delimiter used. The implementation is:
public final static void showSupport(ArrayList<String> tags) {
String separator = findUnusedSeparator(tags);
StringBuilder sb = new StringBuilder();
for (String tag : tags) {
sb.append(tag).append(separator);
}
peer.showSupportWithTags(sb.toString().substring(0, sb.length() - separator.length()), separator);
}The other non-trivial wrapper is the getUnreadCountAsync() method that you discussed before:
public final static void getUnreadCountAsync(UnreadUpdatesCallback callback) {
int callbackId = MobihelpNativeCallback.registerUnreadUpdatesCallback(callback);
peer.getUnreadCountAsync(callbackId);
}61.12.5. Step 5: Implementing the native interface in Android
Now that you’ve set up your public API and your native interface, it’s time to work on the native side of things. You can generate stubs for all platforms in your IDE (Netbeans in your case), by right clicking on the MobihelpNative class in the project explorer and selecting Generate Native Access.

This will generate a separate directory for each platform inside your project’s native directory:

Inside the android directory, this generates a com/codename1/freshdesk/MobihelpNativeImpl class with stubs for each method.
Your implementation will be a thin wrapper around the native Android SDK. See the source here.
Some highlights:
Context: The native API requires you to pass a context object as a parameter on many methods. This should be the context for the current activity. It will allow the FreshDesk API to know where to return to after it has done its thing. Codename One provides a class calledAndroidNativeUtilthat allows you to retrieve the app’s Activity (which includes the Context). You will wrap this with a convenience method in your class as follows:public final static void getUnreadCountAsync(UnreadUpdatesCallback callback) { int callbackId = MobihelpNativeCallback.registerUnreadUpdatesCallback(callback); peer.getUnreadCountAsync(callbackId); }This will enable you to wrap the freshdesk native API. For example:
private static Context context() { return AndroidNativeUtil.getActivity().getApplicationContext(); }runOnUiThread()- Many of the calls to the FreshDesk API may have been made from the Codename One EDT. For example, Android has its own event dispatch thread that should be used for interacting with native Android UI. Any API calls that look like they start some sort of native Android UI process should therefore be wrapped inside Android’srunOnUiThread()method which is like Codename One’sDisplay.callSerially()method. For example: see theshowSolutions()method:public void showSolutions() { activity().runOnUiThread(new Runnable() { public void run() { com.freshdesk.mobihelp.Mobihelp.showSolutions(context()); } }); }(Note here that the
activity()method is another convenience method to retrieve the app’s currentActivityfrom theAndroidNativeUtilclass).Callbacks. You discussed, in detail, the mechanisms you put in place to enable your native code to perform callbacks into Codename One. You can see the native side of this by viewing the
getUnreadCountAsync()method implementation:public void getUnreadCountAsync(final int callbackId) { activity().runOnUiThread(new Runnable() { public void run() { com.freshdesk.mobihelp.Mobihelp.getUnreadCountAsync(context(), new com.freshdesk.mobihelp.UnreadUpdatesCallback() { public void onResult(com.freshdesk.mobihelp.MobihelpCallbackStatus status, Integer count) { MobihelpNativeCallback.fireUnreadUpdatesCallback(callbackId, status.ordinal(), count); } }); } }); }
61.12.6. Step 6: Bundling the native SDKs
The last step (at least on the Android side) is to bundle the FreshDesk SDK. For Android, there are a few different scenarios you’ll run into for embedding SDKs:
The SDK includes Java classes - NO XML UI files, assets, or resources that aren’t included inside a simple.jar file. In this case, you can place the.jar file inside your project’s
native/androiddirectory.The SDK includes some XML UI files, resources, and assets. In this case, the SDK is distributed as an Android project folder that can be imported into an Eclipse or Android studio workspace. In general, in this case, you would need to zip the entire directory and change the extension of the resulting.zip file to
.andlib, and place this in your project’snative/androiddirectory.The SDK is distributed as an
.aarfile - In this case you can copy the.aarfile into yournative/androiddirectory.
The FreshDesk SDK
The FreshDesk (aka Mobihelp) SDK is distributed as a project folder (that’s: scenario 2 from the above list). Your procedure is therefore to download the SDK (download link), and rename it from mobihelp_sdk_android.zip to mobihelp_sdk_android.andlib, and copy it into your native/android directory.
Dependencies
In this case there is a catch. The Mobihelp SDK includes a dependency:
Mobihelp SDK depends on AppCompat-v7 (Revision 19.0+) Library. You will need to update project.properties to point to the Appcompat library.
If you look inside the project.properties file (inside the Mobihelp SDK directory--- that’s: you’d need to extract it from the zip to view its contents), you’ll see the dependency listed:
android.library.reference.1=../appcompat_v7
In other words, the Mobihelp SDK expects to find the appcompat_v7 library located in the same parent directory as the Mobihelp SDK project. After a little bit of research (if you’re not yet familiar with the Android AppCompat support library), you find that the AppCompat_v7 library is part of the Android Support library, which can installed into your local Android SDK using Android SDK Manager. Installation processed specified here.
After installing the support library, you need to retrieve it from your Android SDK. You can find that.aar file inside the ANDROID_HOME/sdk/extras/android/m2repository/com/android/support/appcompat-v7/19.1.0/ directory (for version 19.1.0). The contents of that directory on your system are:
appcompat-v7-19.1.0.aar appcompat-v7-19.1.0.pom appcompat-v7-19.1.0.aar.md5 appcompat-v7-19.1.0.pom.md5 appcompat-v7-19.1.0.aar.sha1 appcompat-v7-19.1.0.pom.sha1
There are two files of interest here:
appcompat-v7-19.1.0.aar - This is the actual library that you need to include in your project to meet the MobiSDK dependency.
appcompat-v7-19.1.0.pom - This is the Maven XML file for the library. It will show you any dependencies that the appcompat library has. You will also need to include these dependencies:
<dependencies> <dependency> <groupId>com.android.support</groupId> <artifactId>support-v4</artifactId> <version>19.1.0</version> <scope>compile</scope> </dependency> </dependencies>In other words: you need to include the
support-v4library version 19.1.0 in your project. This is also part of the Android Support library. If you back up a couple of directories to:ANDROID_HOME/sdk/extras/android/m2repository/com/android/support, you will see it listed there:appcompat-v7 palette-v7 cardview-v7 recyclerview-v7 gridlayout-v7 support-annotations leanback-v17 support-v13 mediarouter-v7 support-v4 multidex test multidex-instrumentation
+ And if you look inside the appropriate version directory of
support-v4(inANDROID_HOME/sdk/extras/android/m2repository/com/android/support/support-v4/19.1.0), you see:support-v4-19.1.0-javadoc.jar support-v4-19.1.0.jar support-v4-19.1.0-javadoc.jar.md5 support-v4-19.1.0.jar.md5 support-v4-19.1.0-javadoc.jar.sha1 support-v4-19.1.0.jar.sha1 support-v4-19.1.0-sources.jar support-v4-19.1.0.pom support-v4-19.1.0-sources.jar.md5 support-v4-19.1.0.pom.md5 support-v4-19.1.0-sources.jar.sha1 support-v4-19.1.0.pom.sha1
Looks like this library is pure Java classes, so you need to include the
support-v4-19.1.0.jarfile into your project. Checking the.pomfile you see that there are no more dependencies you need to add.
To summarize your findings, you need to include the following files in your native/android directory:
appcompat-v7-19.1.0.aar
support-v4-19.1.0.jar
And since your Mobihelp SDK lists the appcompat_v7 dependency path as "../appcompat_v7" in its project.properties file, you’re going to rename appcompat-v7-19.1.0.aar to appcompat_v7.aar.
When all is said and done, your native/android directory should contain the following:
appcompat_v7.aar mobihelp.andlib com support-v4-19.1.0.jar
61.12.7. Step 7: Injecting Android manifest and proguard config
The final step on the Android side is to inject necessary permissions and services into the project’s AndroidManifest.xml file.
You can find the manifest file injections required by opening the AndroidManifest.xml file from the MobiHelp SDK project. Its contents are as follows:
<?xml version="1.0" encoding="utf-8"?>
<manifest xmlns:android="http://schemas.android.com/apk/res/android"
package="com.freshdesk.mobihelp"
android:versionCode="1"
android:versionName="1.0" >
<uses-sdk
android:minSdkVersion="10" />
<uses-permission android:name="android.permission.INTERNET" />
<uses-permission android:name="android.permission.READ_LOGS" />
<uses-permission android:name="android.permission.ACCESS_NETWORK_STATE" />
<uses-permission android:name="android.permission.WRITE_EXTERNAL_STORAGE" />
<application>
<activity
android:name="com.freshdesk.mobihelp.activity.SolutionArticleListActivity"
android:configChanges="orientation|screenSize"
android:theme="@style/Theme.Mobihelp"
android:windowSoftInputMode="adjustPan" >
</activity>
<activity
android:name="com.freshdesk.mobihelp.activity.FeedbackActivity"
android:configChanges="keyboardHidden|orientation|screenSize"
android:theme="@style/Theme.Mobihelp"
android:windowSoftInputMode="adjustResize|stateVisible" >
</activity>
<activity
android:name="com.freshdesk.mobihelp.activity.InterstitialActivity"
android:configChanges="orientation|screenSize"
android:theme="@style/Theme.AppCompat">
</activity>
<activity
android:name="com.freshdesk.mobihelp.activity.TicketListActivity"
android:parentActivityName="com.freshdesk.mobihelp.activity.SolutionArticleListActivity"
android:theme="@style/Theme.Mobihelp" >
<!-- Parent activity meta-data to support 4.0 and lower -->
<meta-data
android:name="android.support.PARENT_ACTIVITY"
android:value="com.freshdesk.mobihelp.activity.SolutionArticleListActivity" />
</activity>
<activity
android:name="com.freshdesk.mobihelp.activity.SolutionArticleActivity"
android:parentActivityName="com.freshdesk.mobihelp.activity.SolutionArticleListActivity"
android:theme="@style/Theme.Mobihelp"
android:configChanges="orientation|screenSize|keyboard|keyboardHidden" >
<!-- Parent activity meta-data to support 4.0 and lower -->
<meta-data
android:name="android.support.PARENT_ACTIVITY"
android:value="com.freshdesk.mobihelp.activity.SolutionArticleListActivity" />
</activity>
<activity
android:name="com.freshdesk.mobihelp.activity.ConversationActivity"
android:parentActivityName="com.freshdesk.mobihelp.activity.SolutionArticleListActivity"
android:theme="@style/Theme.Mobihelp"
android:windowSoftInputMode="adjustResize|stateHidden" >
<!-- Parent activity meta-data to support 4.0 and lower -->
<meta-data
android:name="android.support.PARENT_ACTIVITY"
android:value="com.freshdesk.mobihelp.activity.SolutionArticleListActivity" />
</activity>
<activity
android:name="com.freshdesk.mobihelp.activity.AttachmentHandlerActivity"
android:configChanges="keyboardHidden|orientation|screenSize"
android:parentActivityName="com.freshdesk.mobihelp.activity.SolutionArticleListActivity"
android:theme="@style/Theme.Mobihelp" >
<!-- Parent activity meta-data to support 4.0 and lower -->
<meta-data
android:name="android.support.PARENT_ACTIVITY"
android:value="com.freshdesk.mobihelp.activity.SolutionArticleListActivity" />
</activity>
<service android:name="com.freshdesk.mobihelp.service.MobihelpService" />
<receiver android:name="com.freshdesk.mobihelp.receiver.ConnectivityReceiver" >
<intent-filter>
<action android:name="android.net.conn.CONNECTIVITY_CHANGE" />
</intent-filter>
</receiver>
</application>
</manifest>You will need to add the <uses-permission> tags and all the contents of the <application> tag to your manifest file. Codename One provides the following build hints for these:
android.xpermissions- For your<uses-permission>directives. Add a build hint with nameandroid.xpermissions, and for the value, paste the actual<uses-permission>XML tag.android.xapplication- For the contents of your<application>tag.
Proguard config
For the release build, you will also need to inject some proguard configuration so that important classes don’t get stripped out at build time. The FreshDesk SDK instructions state:
If you use Proguard, please make sure you have the following included in your project’s proguard-project.txt
-keep class android.support.v4.** { *; } -keep class android.support.v7.** { *; }
Also, if you look at the proguard-project.txt file inside the Mobihelp SDK, you’ll see the rules:
-keep public class * extends android.app.Service
-keep public class * extends android.content.BroadcastReceiver
-keep public class * extends android.app.Activity
-keep public class * extends android.preference.Preference
-keep public class com.freshdesk.mobihelp.exception.MobihelpComponentNotFoundException
-keepclassmembers class * implements android.os.Parcelable {
public static final android.os.Parcelable$Creator *;
}You will want to merge this and then paste them into the build hint android.proguardKeep of your project.
Troubleshooting Android stuff
If, after doing all this, your project fails to build, you can enable the "Include Source" option of the build server, then download the source project, open it in Eclipse or Android Studio, and debug from there.
61.13. Part 2: Implementing the iOS native code
Part 1 of this tutorial focused on the Android native integration. Now you will shift your focus to the iOS implementation.
After selecting "Generate Native Interfaces" for your "MobihelpNative" class, you’ll find a native/ios directory in your project with the following files:
These files contain stub implementations corresponding to your MobihelpNative class.
You make use of the API docs to see how the native SDK needs to be wrapped. The method names aren’t the same. For example: instead of a method showFeedback(), it has a message -presentFeedback:
You more-or-less follow the iOS integration guide for wrapping the API. Some key points include:
Remember to import the
Mobihelp.hfile in your header file:#import "Mobihelp.h"Like your use of
runOnUiThread()in Android, you will wrap all your API calls in eitherdispatch_async()ordispatch_sync()calls to ensure that you’re interacting with the Mobihelp API on the app’s main thread rather than the Codename One EDT.Some methods/messages in the Mobihelp SDK require you to pass a
UIViewControlleras a parameter. In Codename One, the entire application uses a single UIViewController:CodenameOne_GLViewController. You can get a reference to this using the[CodenameOne_GLViewController instance]message. You need to import its header file:#import "CodenameOne_GLViewController.h"
As an example, look at the
showFeedback()method:-(void)showFeedback{ dispatch_async(dispatch_get_main_queue(), ^{ [[Mobihelp sharedInstance] presentFeedback:[CodenameOne_GLViewController instance]]; }); }
61.13.1. Using the MobihelpNativeCallback
You described earlier how you created a static method on the MobihelpNativeCallback class so that native code could fire a callback method. Now take a look at how this looks from the iOS side of the fence. Here is the implementation of getUnreadCountAsync():
-(void)getUnreadCountAsync:(int)param{
dispatch_async(dispatch_get_main_queue(), ^{
[[Mobihelp sharedInstance]
unreadCountWithCompletion:^(NSInteger count){
com_codename1_freshdesk_MobihelpNativeCallback_fireUnreadUpdatesCallback___int_int_int(
CN1_THREAD_GET_STATE_PASS_ARG param, 3 /*SUCCESS*/, count);
}];
});
}In your case the iOS SDK version of this method is +unreadCountWithCompletion: which takes a block (which is like an anonymous function) as a parameter.
The callback to your Codename One function occurs on this line:
com_codename1_freshdesk_MobihelpNativeCallback_fireUnreadUpdatesCallback___int_int_int(
CN1_THREAD_GET_STATE_PASS_ARG param, 3 /*SUCCESS*/, count);Some things worth mentioning here:
The method name is the result of taking the FQN (
MobihelpNativeCallback.fireUpdateUnreadUpdatesCallback(int, int, int)in the packagecom.codename1.freshdesk) and replacing all.characters with underscores, suffixing two underscores after the end of the method name, then appending_intonce for each of theintarguments.You also need to import the header file for this class:
#import "com_codename1_freshdesk_MobihelpNativeCallback.h"
61.13.2. Bundling native iOS SDK
Now that you’ve implemented your iOS native interface, you need to bundle the Mobihelp iOS SDK into your project. A few different scenarios you may face when looking to include a native SDK:
The SDK includes
.bundleresource files. In this case, copy the.bundlefile(s) into yournative/iosdirectory.The SDK includes
.hheader files. In this case, copy the.hfile(s) into yournative/iosdirectory.The SDK includes
.afiles. In this case, copy the.afile(s) into yournative/iosdirectory.The SDK includes
.frameworkfiles. In this case, you’ll need to zip up the framework, and copy it into yournative/iosdirectory. For example: If the framework is named,MyFramework.framework, then the zip file should be named MyFramework.framework.zip, and should be located atnative/ios/MyFramework.framework.zip.
The FreshDesk SDK doesn’t include any .framework files, so you don’t need to worry about that last scenario. You download the iOS SDK, copy the libFDMobihelpSDK.a, Mobihelp.h. MHModel.bundle, MHResources.bundle, and MHLocalization/en.proj/MHLocalizable.strings into native/ios.
61.13.3. Troubleshooting iOS
If you run into problems with the build, you can select "Include Sources" in the build server to download the resulting Xcode Project. You can then debug the Xcode project locally, make changes to your iOS native implementation files, and copy them back into your project once it’s building.
61.13.4. Adding required core libraries and frameworks
The iOS integration guide for the FreshDesk SDK lists the following core frameworks as dependencies:

You can add these dependencies to your project using the ios.add_libs build hint. For example:

In short: you list the framework names separated by semicolons. Notice that your list in the above image doesn’t include all the frameworks that they list because many of the frameworks are already included by default (I obtained the default list by building the project with "include sources" checked, then looked at the frameworks that were included).
61.14. Part 3 : Packaging as a cn1lib
During the initial development, you find it easier to use a regular Codename One application project so that you can run and test as you go. However, once it’s stabilized and you want to distribute the library to other developers, transfer it over to a Codename One library project. This general process involves:
Generate a Maven cn1lib project using the
cn1lib-archetype(see Section 1.5, “Codename One libraries”).Copy the Java files from your original application project into the new library project’s
common/src/main/javadirectory.Copy any native source directories from your original project into the matching platform module (
ios/src/main/objectivec,android/src/main/java, etc.).Copy the relevant build hints from the original project’s
codenameone_settings.propertiesfile into the library project’scommon/codenameone_library_appended.propertiesfile.
For the FreshDesk.cn1lib, the original project’s build script was modified to generate and build a library project automatically. However, that’s beyond the scope of this tutorial.
61.15. Building your own Layout manager
A Layout contains all the logic for positioning Codename One components. It essentially traverses a Codename One Container and positions components based on internal logic.
When you build the layout you need to take margin into consideration and make sure to add it into the position/size calculations. Building a layout manager involves two simple methods: layoutContainer & getPreferredSize.
layoutContainer is invoked whenever Codename One decides the container needs rearranging, Codename One tries to avoid calling this method and invokes it at the last possible moment. Since this method is expensive (imagine the recursion with nested layouts). Codename One marks a flag indicating layout is "dirty" when something important changes and tries to avoid "reflows."
getPreferredSize allows the layout to determine the size desired for the container. This might be a difficult call to make for some layout managers that try to provide both flexibility and simplicity.
Most of FlowLayout bugs stem from the fact that this method is impossible to implement efficiently for all the use cases of a nested FlowLayout. The size of the final layout won’t necessarily match the requested size (it probably won’t) but the requested size is taken into consideration, when scrolling and also when sizing parent containers.
This is a layout manager that arranges components in a center column aligned to the middle. You then show the proper usage of margin to create a stair like effect with this layout manager:
class CenterLayout extends Layout {
public void layoutContainer(Container parent) {
int components = parent.getComponentCount();
Style parentStyle = parent.getStyle();
int centerPos = parent.getLayoutWidth() / 2 + parentStyle.getMargin(Component.LEFT);
int y = parentStyle.getMargin(Component.TOP);
boolean rtl = parent.isRTL();
for (int iter = 0; iter < components; iter++) {
Component current = parent.getComponentAt(iter);
Dimension d = current.getPreferredSize();
Style currentStyle = current.getStyle();
int marginRight = currentStyle.getMarginRight(rtl);
int marginLeft = currentStyle.getMarginLeft(rtl);
int marginTop = currentStyle.getMarginTop();
int marginBottom = currentStyle.getMarginBottom();
current.setSize(d);
int actualWidth = d.getWidth() + marginLeft + marginRight;
current.setX(centerPos - actualWidth / 2 + marginLeft);
y += marginTop;
current.setY(y);
y += d.getHeight() + marginBottom;
}
}
public Dimension getPreferredSize(Container parent) {
int components = parent.getComponentCount();
Style parentStyle = parent.getStyle();
int height = parentStyle.getMargin(Component.TOP) + parentStyle.getMargin(Component.BOTTOM);
int marginX = parentStyle.getMargin(Component.RIGHT) + parentStyle.getMargin(Component.LEFT);
int width = marginX;
for (int iter = 0; iter < components; iter++) {
Component current = parent.getComponentAt(iter);
Dimension d = current.getPreferredSize();
Style currentStyle = current.getStyle();
width = Math.max(d.getWidth() + marginX + currentStyle.getMargin(Component.RIGHT)
+ currentStyle.getMargin(Component.LEFT), width);
height += currentStyle.getMargin(Component.TOP) + d.getHeight()
+ currentStyle.getMargin(Component.BOTTOM);
}
Dimension size = new Dimension(width, height);
return size;
}
}
public class CenterLayoutDemo {
public static Form createForm() {
Form hi = new Form("Center Layout", new CenterLayout());
for (int iter = 1; iter < 10; iter++) {
Label l = new Label("Label: " + iter);
l.getUnselectedStyle().setMarginUnit(Style.UNIT_TYPE_DIPS);
l.getUnselectedStyle().setMarginLeft(iter * 4);
l.getUnselectedStyle().setMarginRight(0);
hi.add(l);
}
hi.add(new Label("Really Wide Label Text!!!"));
return hi;
}
public void show() {
createForm().show();
}
}
61.15.1. Porting a Swing/AWT Layout manager
The GridBagLayout was ported to Codename One considering the complexity of that specific layout manager. Here are some tips you should consider when porting a Swing/AWT layout manager:
Codename One doesn’t have
Insets, but adds some support for them to port GridBag but components in Codename One have a margin they need to consider instead of theInsets(the padding is in the preferred size and is thus hidden from the layout manager).AWT layout managers also synchronize a lot on the AWT thread. This is no longer necessary since Codename One is single threaded, like Swing.
AWT considers the top left position of the
Containerto be 0,0 whereas Codename One considers the position based on its parentContainer. The top left position in Codename One isgetX(),getY().
Other than those things it’s fixing method and import statements, which are slightly different. Pretty trivial stuff.
61.16. Port a language to Codename One
As you may have already read, you’ve added support for Kotlin in Codename One. This is something that you can achieve without the help of Codename One. You could port a 3rd party language like Scala, Ruby, Python etc. to Codename One.
61.16.1. What’s a JVM language
A JVM Language is any programming language that can be compiled to byte-codes that will run on the JVM (Java Virtual Machine). Java was the original JVM language, but many others have sprung up over the years. Kotlin, Scala, Groovy, and JRuby come to mind as well-established and mature languages, but there are many others.
61.16.2. How hard is it to port a JVM language to Codename One
The difficulty of porting a particular language to Codename One will vary depending on such factors as:
Does it require a runtime library?
How complex is the runtime library? (For example: Does it require classes that aren’t offered in Codename One’s subset of the java standard libraries?)
Does it need reflection?
Codename One doesn’t support reflection because it would result in a large application size. If a JVM language requires reflection to get off the ground then adding it to Codename one would be tricky.
Does it perform any runtime byte-code manipulation?
Some dynamic languages may perform byte-code manipulation at runtime. This is problematic on iOS (and possibly other platforms) which prohibits such runtime behavior.
Step 1: Assess the language
The more similar a language, and its build outputs are to Java, the easier it will be to port (probably). Most JVM languages have two parts:
A compiler, which compiles source files to JVM byte-code (usually as
.classfiles).A runtime library.
One language (other than Java) doesn’t require a runtime library: Mirah.
| Codename One also supports Mirah |
Assessing the Byte-Code
The first thing to do is take a look at the byte-code that’s produced by the compiler. Use javap to print out a nice version.
Consider a sample Kotlin class that extends Form, creates a Label and Button, and updates the label from the button’s listener.
Take a look at the bytecode that Kotlin produced for this class:
$ javap -v com/codename1/hellokotlin2/KotlinForm.class
Last modified 10-Jul-2017; size 1456 bytes
MD5 checksum 1cb00f6e63b918bb5a9f146ca8b0b78e
Compiled from "KotlinForm.kt"
public final class com.codename1.hellokotlin2.KotlinForm extends com.codename1.ui.Form
SourceFile: "KotlinForm.kt"
InnerClasses:
static final #31; //class com/codename1/hellokotlin2/KotlinForm$1
RuntimeVisibleAnnotations:
0: #56(#57=[I#58,I#58,I#59],#60=[I#58,I#61,I#58],#62=I#58,#63=[s#64],#65=[s#55,s#66,s#6,s#67])
minor version: 0
major version: 50
flags: ACC_PUBLIC, ACC_FINAL, ACC_SUPER
Constant pool:
#1 = Utf8 com/codename1/hellokotlin2/KotlinForm
#2 = Class #1 // com/codename1/hellokotlin2/KotlinForm
#3 = Utf8 com/codename1/ui/Form
#4 = Class #3 // com/codename1/ui/Form
#5 = Utf8 <init>
#6 = Utf8 ()V
#7 = Utf8 Hello Kotlin
#8 = String #7 // Hello Kotlin
#9 = Utf8 com/codename1/ui/layouts/BoxLayout
#10 = Class #9 // com/codename1/ui/layouts/BoxLayout
#11 = Utf8 y
#12 = Utf8 ()Lcom/codename1/ui/layouts/BoxLayout;
#13 = NameAndType #11:#12 // y:()Lcom/codename1/ui/layouts/BoxLayout;
#14 = Methodref #10.#13 // com/codename1/ui/layouts/BoxLayout.y:()Lcom/codename1/ui/layouts/BoxLayout;
#15 = Utf8 com/codename1/ui/layouts/Layout
#16 = Class #15 // com/codename1/ui/layouts/Layout
#17 = Utf8 (Ljava/lang/String;Lcom/codename1/ui/layouts/Layout;)V
#18 = NameAndType #5:#17 // "<init>":(Ljava/lang/String;Lcom/codename1/ui/layouts/Layout;)V
#19 = Methodref #4.#18 // com/codename1/ui/Form."<init>":(Ljava/lang/String;Lcom/codename1/ui/layouts/Layout;)V
#20 = Utf8 com/codename1/ui/Label
#21 = Class #20 // com/codename1/ui/Label
#22 = Utf8 (Ljava/lang/String;)V
#23 = NameAndType #5:#22 // "<init>":(Ljava/lang/String;)V
#24 = Methodref #21.#23 // com/codename1/ui/Label."<init>":(Ljava/lang/String;)V
#25 = Utf8 com/codename1/ui/Button
#26 = Class #25 // com/codename1/ui/Button
#27 = Utf8 Click Me
#28 = String #27 // Click Me
#29 = Methodref #26.#23 // com/codename1/ui/Button."<init>":(Ljava/lang/String;)V
#30 = Utf8 com/codename1/hellokotlin2/KotlinForm$1
#31 = Class #30 // com/codename1/hellokotlin2/KotlinForm$1
#32 = Utf8 (Lcom/codename1/hellokotlin2/KotlinForm;Lcom/codename1/ui/Label;)V
#33 = NameAndType #5:#32 // "<init>":(Lcom/codename1/hellokotlin2/KotlinForm;Lcom/codename1/ui/Label;)V
#34 = Methodref #31.#33 // com/codename1/hellokotlin2/KotlinForm$1."<init>":(Lcom/codename1/hellokotlin2/KotlinForm;Lcom/codename1/ui/Label;)V
#35 = Utf8 com/codename1/ui/events/ActionListener
#36 = Class #35 // com/codename1/ui/events/ActionListener
#37 = Utf8 addActionListener
#38 = Utf8 (Lcom/codename1/ui/events/ActionListener;)V
#39 = NameAndType #37:#38 // addActionListener:(Lcom/codename1/ui/events/ActionListener;)V
#40 = Methodref #26.#39 // com/codename1/ui/Button.addActionListener:(Lcom/codename1/ui/events/ActionListener;)V
#41 = Utf8 com/codename1/ui/Component
#42 = Class #41 // com/codename1/ui/Component
#43 = Utf8 add
#44 = Utf8 (Lcom/codename1/ui/Component;)Lcom/codename1/ui/Container;
#45 = NameAndType #43:#44 // add:(Lcom/codename1/ui/Component;)Lcom/codename1/ui/Container;
#46 = Methodref #2.#45 // com/codename1/hellokotlin2/KotlinForm.add:(Lcom/codename1/ui/Component;)Lcom/codename1/ui/Container;
#47 = Utf8 com/codename1/ui/Container
#48 = Class #47 // com/codename1/ui/Container
#49 = Methodref #48.#45 // com/codename1/ui/Container.add:(Lcom/codename1/ui/Component;)Lcom/codename1/ui/Container;
#50 = Utf8 clickMe
#51 = Utf8 Lcom/codename1/ui/Button;
#52 = Utf8 label
#53 = Utf8 Lcom/codename1/ui/Label;
#54 = Utf8 this
#55 = Utf8 Lcom/codename1/hellokotlin2/KotlinForm;
#56 = Utf8 Lkotlin/Metadata;
#57 = Utf8 mv
#58 = Integer 1
#59 = Integer 6
#60 = Utf8 bv
#61 = Integer 0
#62 = Utf8 k
#63 = Utf8 d1
#64 = Utf8
\n\n\20¢¨
#65 = Utf8 d2
#66 = Utf8 Lcom/codename1/ui/Form;
#67 = Utf8 HelloKotlin2
#68 = Utf8 KotlinForm.kt
#69 = Utf8 Code
#70 = Utf8 LocalVariableTable
#71 = Utf8 LineNumberTable
#72 = Utf8 SourceFile
#73 = Utf8 InnerClasses
#74 = Utf8 RuntimeVisibleAnnotations
{
public com.codename1.hellokotlin2.KotlinForm();
descriptor: ()V
flags: ACC_PUBLIC
Code:
stack=5, locals=3, args_size=1
0: aload_0
1: ldc #8 // String Hello Kotlin
3: invokestatic #14 // Method com/codename1/ui/layouts/BoxLayout.y:()Lcom/codename1/ui/layouts/BoxLayout;
6: checkcast #16 // class com/codename1/ui/layouts/Layout
9: invokespecial #19 // Method com/codename1/ui/Form."<init>":(Ljava/lang/String;Lcom/codename1/ui/layouts/Layout;)V
12: new #21 // class com/codename1/ui/Label
15: dup
16: ldc #8 // String Hello Kotlin
18: invokespecial #24 // Method com/codename1/ui/Label."<init>":(Ljava/lang/String;)V
21: astore_1
22: new #26 // class com/codename1/ui/Button
25: dup
26: ldc #28 // String Click Me
28: invokespecial #29 // Method com/codename1/ui/Button."<init>":(Ljava/lang/String;)V
31: astore_2
32: aload_2
33: new #31 // class com/codename1/hellokotlin2/KotlinForm$1
36: dup
37: aload_0
38: aload_1
39: invokespecial #34 // Method com/codename1/hellokotlin2/KotlinForm$1."<init>":(Lcom/codename1/hellokotlin2/KotlinForm;Lcom/codename1/ui/Label;)V
42: checkcast #36 // class com/codename1/ui/events/ActionListener
45: invokevirtual #40 // Method com/codename1/ui/Button.addActionListener:(Lcom/codename1/ui/events/ActionListener;)V
48: aload_0
49: aload_1
50: checkcast #42 // class com/codename1/ui/Component
53: invokevirtual #46 // Method add:(Lcom/codename1/ui/Component;)Lcom/codename1/ui/Container;
56: aload_2
57: checkcast #42 // class com/codename1/ui/Component
60: invokevirtual #49 // Method com/codename1/ui/Container.add:(Lcom/codename1/ui/Component;)Lcom/codename1/ui/Container;
63: pop
64: return
LocalVariableTable:
Start Length Slot Name Signature
32 32 2 clickMe Lcom/codename1/ui/Button;
22 42 1 label Lcom/codename1/ui/Label;
0 65 0 this Lcom/codename1/hellokotlin2/KotlinForm;
LineNumberTable:
line 13: 0
line 14: 12
line 15: 22
line 16: 32
line 21: 48
}That’s a big mess of stuff, but it’s pretty easy to pick through it when you know what you’re looking for. The layout of this output is pretty straight forward. The beginning shows that this is a class definition:
public final class KotlinForm extends Form {
//...
}Even comparing this line with the class definition from the source file you’ve learned something about the Kotlin compiler. It has made the class final by default. That observation shouldn’t affect your assessment here, but it’s kind of interesting.
After the class definition, it shows the internal classes:
InnerClasses:
static final #31; //class com/codename1/hellokotlin2/KotlinForm$1The Constant Pool
And the constants that are used in the class:
Constant pool:
#1 = Utf8 com/codename1/hellokotlin2/KotlinForm
#2 = Class #1 // com/codename1/hellokotlin2/KotlinForm
#3 = Utf8 com/codename1/ui/Form
#4 = Class #3 // com/codename1/ui/Form
#5 = Utf8 <init>
#6 = Utf8 ()V
#7 = Utf8 Hello Kotlin
#8 = String #7 // Hello Kotlin
#9 = Utf8 com/codename1/ui/layouts/BoxLayout
... etc.The constant pool will consist of class names, and strings. You’ll want to peruse this list to see if the compiler has added any classes that aren’t in the source code. In the example above, it looks like Kotlin is pretty faithful to the original source’s dependencies. It didn’t inject any classes that aren’t in the original source.
Even if the compiler does inject other dependencies into the bytecode, it might not be a problem. It’s a problem if those classes aren’t supported by Codename One. Watch for anything in the java.lang.reflect package or unsolicited use of java.net, java.nio, or any other package that aren’t part of the Codename One standard library. If you’re not sure if a class or package is available in the Codename One standard library, check the javadocs.
The ByteCode Instructions:
After the constant pool, you see each of the methods of the class written out as a list of bytecode instructions. For example:
public com.codename1.hellokotlin2.KotlinForm();
descriptor: ()V
flags: ACC_PUBLIC
Code:
stack=5, locals=3, args_size=1
0: aload_0
1: ldc #8 // String Hello Kotlin
3: invokestatic #14 // Method com/codename1/ui/layouts/BoxLayout.y:()Lcom/codename1/ui/layouts/BoxLayout;
6: checkcast #16 // class com/codename1/ui/layouts/Layout
9: invokespecial #19 // Method com/codename1/ui/Form."<init>":(Ljava/lang/String;Lcom/codename1/ui/layouts/Layout;)V
12: new #21 // class com/codename1/ui/Label
15: dup
16: ldc #8 // String Hello Kotlin
etc.In the above snippet, the first instruction is aload_0 (which adds this to the stack). The 2nd instruction is ldc, (which loads constant #8 — the string "Hello Kotlin" to the stack). The 3rd instruction is invokestatic which calls the static method define by Constant #14 from the constant pool, with the two parameters that had been added to the stack.
| You don’t need to understand what all these instructions do. You need to look for instructions that may be problematic. |
The instruction that might be problematic is "invokedynamic." All other instructions should work fine in Codename One. (It isn’t certain that invokedynamic won’t work - it might not work on some platforms.)
Summary of Byte-code Assessment
To summarize, the byte-code assessment phase, you’re basically looking to make sure that the compiler doesn’t tend to add dependencies to parts of the JDK that Codename One doesn’t support. And you want to make sure that it doesn’t use invokedynamic.
If you find that the compiler does use invokedynamic or add references to classes that Codename One doesn’t support, don’t give up yet. You might be able to create your own "porting" runtime library that will provide these dependencies at runtime.
Assessing the runtime library
The process for assessing the runtime library is pretty like the process for the bytecodes. You’ll want to get your hands on the language’s runtime library, and use javap to inspect the .class files. You’re looking for the same things as you were looking for in the compiler’s output: "invokedynamic" and classes that aren’t supported in Codename One.
Step 2: Convert the runtime library into a CN1Lib
Once you’ve assessed the language and are optimistic that it’s a good candidate for porting, you can proceed to port the runtime library into Codename One. That language’s runtime library will be distributed in.jar format. You need to convert this into a cn1lib so that it can be used in a Codename One project. If you can get your hands on the source code for the runtime library then the best approach is to paste the source files into a Maven cn1lib project generated with the cn1lib-archetype (see Section 1.5, “Codename One libraries”) and try to build it. This has the advantage that it will check the source during compile to ensure that it doesn’t depend on any classes that Codename One doesn’t support.
If you can’t find the sources of the runtime library or they don’t seem to be "buildable," then the next best thing is to get the binary distribution’s jar file and convert it to a cn1lib. This is what you did for the Kotlin runtime library.
This procedure exploits the fact that a cn1lib file is a zip file with a specific file structure inside it. The cross-platform Java .class files are all contained inside a file named main.zip, inside the zip file. This is the mandatory file that must be inside a cn1lib.
To make the library easier to use the cn1lib file can also contain a file named "stubs.zip" which includes stubs of the Java sources. When you build a cn1lib using a Maven cn1lib project, it will automatically generate stubs of the source so that the IDE will have access to nice things like Javadoc when using the library. The Kotlin distribution includes a separate jar file with the runtime sources, named kotlin-runtime-sources.jar, so you used this as the "stubs." It contains full sources, which isn’t necessary, but it also doesn’t hurt.
Now that you had your two jar files: kotlin-runtime.jar and kotlin-runtime-sources.jar, create a new empty directory and copy them inside. Rename the jars "main.zip" and "stubs.zip" respectively. Then zip up the directory and rename the zip file kotlin-runtime.cn1lib.
| Building cn1libs manually in this way is a ** bad habit, as it bypasses the API verification step that occurs when building a library project. It’s possible, even likely, that the jar files that you convert depend on classes that aren’t in the Codename One library, so your library will fail at runtime in unexpected ways. The reason you could do this with kotlin’s runtime (with some confidence) is because the bytecodes were already analyzed to ensure that they didn’t include anything problematic. |
Step 3: Hello world
For your "Hello World" test you will need to create a separate project in your JVM language and produce class files that you will manually copy into an appropriate location of your project. You will want to use the normal tools for the language and not worry about how it integrates with Codename One. For Kotlin, the steps follow the getting started tutorial on the Kotlin site to create a new Kotlin project in IntelliJ. When Steve ported Mirah, he used a text editor and the mirahc command-line compiler to create your Hello World class. The tools and process will depend on the language.
Create a minimal "hello world" class in the external language runtime you are evaluating.
After building this, the build produces a directory that contains com/mycompany/myapp/HelloKotlin.class.
It also produced a.jar file that contains this class.
The easiest way to integrate external code into a Codename One project is to wrap it as a cn1lib and consume it as a Maven dependency. Generate a cn1lib project with the cn1lib-archetype (see Section 1.5, “Codename One libraries”), drop the external class files into the common module, install it locally with mvn install, then add a pom-typed <dependency> entry to your application’s common/pom.xml. Using the same procedure as you used to create the kotlin-runtime.cn1lib, wrap your hellokotlin.jar as a cn1lib that exposes the same classes to the application project.
If you’re maintaining a legacy Ant project, you can still drop the .cn1lib file into the project’s lib directory and select "Codename One" → "Refresh CN1Libs" to pick it up - but new projects should use the Maven dependency mechanism described above. |
Finally, call your library from the start() method of your app:
public final class KotlinForm extends Form {
//...
}If you run this in the Simulator, it should print "Hello from Kotlin" in the output console. If you get an error, then you can dig in and try to figure out what went wrong using your standard debugging techniques. EXPECT an error on the first run. The error will probably be a missing import or something simple.
Step 4: A more complex hello world
For Kotlin, the hello world example app would actually run without the runtime library because it was so simple. It was necessary to add a more complex example to prove the need for the runtime library. It doesn’t matter what you do with your more complex example, as long as it doesn’t require classes that aren’t in Codename One.
If you want to use the Codename One inside your project, you should add the CodenameOne.jar (found inside any Codename One project) to your classpath so that it will compile.
Step 5: Automation and integration
At this point you already have a manual process for incorporating files built with your alternate language into a Codename One project. The process looks like:
Use standard tools for your JVM language to write your code.
Use the JVM language’s standard build tools (for example: command-line compiler, etc.) to compile your code so that you’ve`.class` files (and optionally a
.jarfile).Wrap your
.classfiles in a cn1lib by dropping them into a Maven cn1lib project generated from thecn1lib-archetype(see Section 1.5, “Codename One libraries”).Install the cn1lib locally with
mvn installand add it as apom-typed dependency to your Codename One application’scommon/pom.xml.Use your library from the Codename One project.
When Steve first developed Mirah support he automated this process using an ANT script. He also automatically generated some bootstrap code so that he could develop the whole app in Mirah and he wouldn’t have to write any Java. For example, this level of integration has limitations.
For example, with this approach alone, you couldn’t have two-way dependencies between Java source and Mirah source. Yes, Mirah code could use Java libraries (and it did depend on CodenameOne.jar), and your Java code could use your Mirah code. For example, Mirah source code couldn’t depend on the Java source code in your project. This has to do with the order in which code is compiled. It’s a bit of a chicken-and-egg issue. If you’re building a project that has Java source code and Mirah source code, you’re using two different compilers: mirahc to compile the Mirah files, and javac to compile the Java files. If you’re starting from a clean build, and you run mirahc first, then the .java files haven’t yet been compiled to .class files - and thus mirahc can’t reference them - and any mirah code that depends on those uncompiled Java classes will fail. If you compile the .java files first, then you have the opposite problem.
Steve worked around this problem in Mirah by writing your own pseudo-compiler that produced stub class files for the java source that would be referenced by mirahc when compiling the Mirah files. In this way he was able to have two-way dependencies between Java and Mirah in the same project.
Kotlin also supports two-way dependencies, probably using a similar mechanism.
How seamless can you make it
For both the Kotlin and Mirah support, you wanted integration to be seamless. You didn’t want users to have to create a separate project for their Kotlin/Mirah code. You wanted them to add a Kotlin/Mirah file into their project and have it * work*. Achieving this level of integration in Kotlin was easy, since they provide an ANT plugin that essentially allowed you to add one tag inside your <javac/> tags:
<withKotlin/>And it would automatically handle Kotlin and Java files together: Seamlessly. A few places in a Codename One’s build.xml file where you call "javac" so you needed to inject these tags in those places. This injection is performed automatically by the Codename One IntelliJ plugin.
For Mirah, Steve developed his own ANT plugins and Netbeans module that do something similar in Netbeans.
61.17. Update framework
When Codename One launched in 2012 there was a need to ship updates and fixes faster than the plugin update system, leading to the client lib update system. There was also a need to update the designer tool (resource editor), the GUI builder, and the skins, as well as the built-in builder code (CodeNameOneBuildClient.jar).
The Update Framework solves many problems in the old systems:
Download once - if you have many projects the library will download once to the
.codenameonedirectory. All the projects will update from local storageSkins update automatically - this is hugely important. When you change a theme you need to update it in the skins and if you don’t update the skin you might see a difference between the simulator and the device
Update of designer tools without an IDE plugin update - The IDE plugin update process is slow and tedious. This way a GUI builder fix can ship without a new IDE plugin release. The standalone Settings artifact is versioned with the Maven plugin instead.
This framework should be seamless. You should no longer see the "downloading" message whenever you push an update after your build client is updated. Your system would poll for a new version daily and update when new updates are available.
To force an update check, run mvn cn1:update from the project root.
61.17.1. How does it work
You can see the full code here the gist of it is simple. You create a jar called UpdateCodenameOne.jar under ~/.codenameone (~ represents the users home directory).
An update happens by running this tool with a path to a Codename One project for example:
java -jar ~/.codenameone/UpdateCodenameOne.jar path_to_my_codenameone_projectFor example:
java -jar ~/.codenameone/UpdateCodenameOne.jar ~/dev/AccordionDemo Checking: JavaSE.jar Checking: CodeNameOneBuildClient.jar Checking: CLDC11.jar Checking: CodenameOne.jar Checking: CodenameOne_SRC.jar Checking: designer_1.jar Checking: guibuilder_1.jar Updating the file: /Users/shai/dev/AccordionDemo/JavaSE.jar Updating the file: /Users/shai/dev/AccordionDemo/CodeNameOneBuildClient.jar Updating the file: /Users/shai/dev/AccordionDemo/lib/CLDC11.jar Updating the file: /Users/shai/dev/AccordionDemo/lib/CodenameOne.jar Updated project files
Notice that no download happened since the files were up-to-date. You can also force a check against the server by adding the force argument as such:
java -jar ~/.codenameone/UpdateCodenameOne.jar path_to_my_codenameone_projectThe way this works under the hood is thought a Versions.properties within your directory that lists the versions of local files. That way you know what should be updated.
Exclude Versions.properties from Git |
Under the ~/.codenameone directory you have a more detailed UpdateStatus.properties file that includes versions of the locally downloaded files. Notice you can delete this file and it will be recreated as all the jars get downloaded over again.
61.17.2. What isn’t covered
You will notice 3 big things that aren’t covered in this unified framework:
You don’t update cn1libs - whether you would like to update them automatically is unclear
Versioned builds - a lot of complexity exists in the versioned build system. This might be something you address in the future but for now the framework stays simple.
62. Security
Security is a "big word." It implies many things and that’s also true for the mobile app development so before you get started lets try to define the scope of security.
You will deal with application security and its communication mechanisms while ignoring everything beyond that scope. Start with a simple fact:
Codename One applications are secure on the devices by the nature of the mobile OS security.
For most intents and purposes this will be enough, unless you’re specifically concerned about security this section isn’t for you. Mobile OSes isolate applications from one another so it’s hard for an application to damage the OS or even damage/spy on a different app.
The restrictions laid on apps are here to make them extra secure and on top of that Codename One lays a few big advantages in security:
Codename One code is compiled (unlike for example, PhoneGap/Cordova)
Android release builds are obfuscated by default with R8, which makes the binaries harder to reverse engineer. On the other ports the shipped code is compiled or translated (the iOS/native ports go through ParparVM to C) rather than renamed. Enterprise accounts can turn on cross-platform hardening — name obfuscation, string encryption and more — for every port; see the App Hardening chapter
Codename One compiles the UI to native code too which means typical reverse engineering code will have a harder time following
Codename One disables debug flags so a hacker won’t be able to debug your production app on the device
Despite that you still need to keep in mind that the binary could still be reverse engineered and so it’s important to avoid storing keys in the client side code. For example, if you have an API key to access a service (for example, Google Cloud key) it needs to be stored in your server and not as a constant in your app!
Each section below discusses some attack vectors against applications and how they can be stopped. Pretty much all these attacks require a sophisticated attacker which will exist for high value targets (for example, bank apps, government etc.).
62.1. Constant obfuscation
One of the first things a hacker will do when compromising an app is look at it. For example, an attacker wanting to exploit a bank’s login UI would look at the label next to the login and then search for it in the decompiled code. If the UI has the String "enter username and password" they can search for that.
It won’t lead directly to a hack or exploit, but it will narrow down the area of the code where you should look and it makes the first step that much easier. Obfuscation helps as it removes descriptive method names but it can’t hide the Strings you use in constants. If an app has a secret key within obfuscating it can make a difference (albeit a slight difference).
Notice that this is a temporary roadblock as any savvy hacker would compile the app and connect a debugger eventually (although this is blocked in release builds) and would be able to inspect values of variables/flow. But the road to reverse engineering the app would be harder even with a simple xor obfuscation.
| This isn’t encoding or encryption — it’s a simple obfuscation of the data. |
There are two simple methods in the Util class:
They use a simple xor based obfuscation to make a String less readable. For example, if you’ve code like this:
private static final String SECRET = "Don't let anyone see this/* omitted */";You might be concerned about the secret, then this would make it slightly harder to find out:
// Don't let anyone see this/* omitted */Notice that this isn’t secure, if you have a crucial value that must not be found you need to store it in the server. No alternative exists because everything that’s sent to the client can be compromised by a determined hacker.
| Use the comment to help you find the string in the code |
Codename One’s built-in user-specific constants are obfuscated with this method. For example, an app built with Codename One carries some internal data such as the user who built the app, which is now obfuscated. The following small app encodes strings so you can copy and paste them into your app:
Form hi = new Form("Encoder", BoxLayout.y());
TextField bla = new TextField("", "Type Text Here", 20, TextArea.ANY);
TextArea encoded = new TextArea();
SpanLabel decoded = new SpanLabel();
hi.addAll(bla, encoded, decoded);
bla.addDataChangedListener((a, b) -> {
String s = bla.getText();
String e = Util.xorEncode(s);
encoded.setText(e);
decoded.setText(Util.xorDecode(e));
hi.getContentPane().animateLayout(100);
});
hi.show();This allows you to type in the first text field and the second text area shows the encoded result. A text area is used so copy/paste is easy.
For your convenience this app can be accessed here: https://www.codenameone.com/demos/StringEncoder/index.html
62.2. Storage encryption
Codename One had support for bouncy castle encryption for quite a while but it isn’t as intuitive as you’d like it to be. This makes securing/encrypting your app more painful than it should.
Codename One supports full encryption of the Storage (notice the distinction, Storage isn’t FileSystemStorage).
This is available by installing the bouncy castle cn1lib from the extensions menu then using one line of code
You would want that code within your init(Object) method |
Notice that you can’t use storage or preferences to store this data as it would be encrypted (Preferences uses
Storage internally). You can use a password for this key and it would make it way more secure but if a user
changes his password you might have a problem. In that case you might need the old password to migrate to
a new password.
This works through a new mechanism in storage where you can replace the storage instance with another instance using:
You can leverage that knowledge to change the encryption password on the encryption storage using pseudo-code like this:
| It isn’t a good idea to replace storage objects when an app is running so this is purely for this special case… |
If you use preferences it might be a good idea to set their built-in location to a different path using something like Preferences.setPreferencesLocation("EncryptedPreferences");.
This is useful as it prevents the encrypted preferences from colliding with the regular preferences.
62.3. Secure storage and secrets
Some values are too sensitive for Storage or Preferences, which are plaintext on disk: auth tokens, refresh tokens, and API keys. Codename One gives you two complementary tools for them.
62.3.1. SecureStorage (the platform keychain)
com.codename1.security.SecureStorage keeps small string values in the operating system’s secure keychain (iOS Keychain Services and the Android Keystore) so they’re protected by the platform’s secure enclave instead of being written to app storage. The quiet, no-prompt API is three calls:
On a platform without a keychain the base implementation returns false / null, so treat a null read as "not available" and fall back accordingly.
62.3.2. Secrets (fetched from the cloud, never shipped in the binary)
Baking an API key (for example a Google Maps key) into your app is unsafe: anyone can extract it from the binary, and rotating it means shipping a new build. com.codename1.security.Secrets solves this. You define the secret once in the Codename One Cloud vault, and the app fetches it at runtime and caches it in SecureStorage:
get returns the keychain-cached value when present, otherwise it fetches from the vault over TLS, caches it, and returns it. refresh(name) forces a fresh fetch (after you rotate the value server-side) and clear(name) drops the cached copy.
To publish a secret, open the Secrets page of the build console and add it under the app-readable namespace (the app. prefix; you reference it by its bare name from Secrets.get). Only secrets in that namespace are ever served to a device, so your server-only credentials (such as the store API keys used by commerce validation) stay in the vault and can’t be fetched from a client. Authentication uses the build key every cloud build already carries, so there’s nothing to wire up; on the simulator or a local build there’s no build key, so get returns the cached value if any and otherwise null.
| Build hint | Default | Description |
|---|---|---|
| (Codename One cloud) | Base URL of the secrets service. Override only if you self-host. |
62.4. Disabling screenshots
One of the common security features some apps expect is the ability to block a screenshot. In the past apps like snapchat required that you touch the screen to view a photo to block the ability to grab a screenshot (on iOS). This no longer works…
Blocking screenshots is implemented by classifying the app window as secure on Android. You can enable this via the build hint android.disableScreenshots=true. Once that’s added screenshots should no longer work for the app, this might impact other things as well such as the task view which will no longer show the screenshot either.
On iOS, you can’t prevent a user from taking a static screenshot, but you can block screen capture/recording while it’s active. This uses UIScreen.isCaptured and its change notification to hide the app contents while a capture session is active. Enable this behavior with the build hint ios.disableScreenshots=true.
62.5. Blocking copy & paste
Blocking copy & paste is useful for cases where a device might have spyware installed that monitors the clipboard. This also prevents a user from using a password manager (which rely on the clipboard), those managers could be compromised and thus if you’re building a secure app this might be necessary.
You can block copy & paste on Android & iOS. Blocking of copy & paste can be implemented globally or on a specific field.
To block copy & paste globally use:
Display.getInstance().setProperty("blockCopyPaste", "true");To block copy & paste on a specific field do:
Notice that the inverse of using false might not work as expected |
62.6. Blocking jailbreak
iOS & Android are walled gardens which is both a blessing and a curse. Looking at the bright side the walled garden aspect of locked down devices means the devices are more secure by nature. For example, on a PC that was compromised you can detect the banking details of a user logging into a bank. But on a phone it would be much harder due to the deep process isolation.
This isn’t true for jailbroken or rooted devices. In these devices security has often been compromised with good intentions (opening up the ecosystem) but it can also be used as a step in a serious attack on an application!
For obvious reasons it’s hard to accurately detect a jailbroken or rooted device but when possible if you have a high security app you might want to block the functionality or even raise a "silent alarm" in such a case. To detect this you can use the isJailbrokenDevice method as such:
if(Display.getInstance().isJailbrokenDevice()) {
// probably jailbroken or rooted
} else {
// probably not
}Notice that this isn’t right, you can’t be 100% sure as there are no official ways to detect jailbreak. That’s why it’s crucial to encrypt everything and assume the device was compromised to begin with when dealing with sensitive data. Still it’s worthwhile to use these APIs to make the life of an attacker a little bit harder.
62.7. Device integrity, RASP & attestation
The isJailbrokenDevice check above is a single, coarse signal. For high-security apps (banking, payments, healthcare) Codename One exposes a richer, cross-platform device-integrity API in com.codename1.security.DeviceIntegrity. It groups three families of runtime self-protection (RASP) primitives, each available both as a zero-code build hint (an automatic launch-time guard) and as a runtime API (so your app can make granular, per-transaction decisions). The build hints are wired into the build server, so enabling a feature is just a settings entry away.
| Every on-device check is bypassable on a sufficiently compromised device — that’s an industry truth, not a Codename One limitation. Use the on-device checks for defense-in-depth and UX (warn, degrade, require step-up auth), but gate genuinely sensitive server actions on the server-verified attestation token described below, never on a boolean computed on the device itself. |
62.7.1. Detecting rooted / jailbroken / tampered devices (RASP)
Codename One ships several launch-time hard gates that terminate the app on a compromised device. They’re enabled through build hints and need no code:
android.rootCheck=true— bundles the RootBeer library and exits at launch on a rooted device (subinaries, test-keys / custom ROM signals, Magisk indicators, dangerous system properties).android.fridaDetection=true— detects the Frida dynamic-instrumentation toolkit (the core RASP threat) and exits.ios.detectJailbreak=true— exits at launch on a jailbroken iOS device (MobileSubstrate / Liberty / FridaGadget dylibs, Cydia/apt paths, sandbox-escape probes).
When you’d rather respond in-app than be hard-killed — for example to block only a single risky operation, raise a silent alarm, or require additional authentication — use the non-exiting runtime report instead:
if (DeviceIntegrity.isDeviceCompromised()) {
// root / jailbreak / Frida / emulator detected -- do not hard-exit,
// instead degrade: disable the transfer button, require step-up auth, etc.
for (String reason : DeviceIntegrity.getCompromiseReasons()) {
// reason is a machine-readable code: "root", "frida", "emulator", "jailbreak"
Log.p("Device compromise signal: " + reason);
}
}isDeviceCompromised() aggregates the same root/jailbreak/Frida signals as the launch gates plus emulator heuristics, but never terminates the app. On the simulator and unsupported ports it simply returns false.
If your security policy mandates a specific commercial Mobile Threat Defense (MTD) / RASP vendor (Zimperium, Promon SHIELD, etc.), you integrate that vendor’s SDK through the standard android.gradleDep / ios.pods build hints — Codename One’s built-in checks complement, but don’t claim to replace, a dedicated MTD product. |
62.7.2. Platform attestation: Google Play Integrity & Apple App Attest
The trustworthy way to verify device and app integrity is hardware-backed attestation: Google Play Integrity on Android and Apple App Attest on iOS. Both produce a signed token that your backend verifies with Google / Apple. This is the mechanism to use when you must, for example, block an outward transfer to a newly added beneficiary on a device that fails integrity.
Enable it with a build hint, which bundles the SDK (Android) or links the entitlement (iOS):
android.playIntegrity=true— bundles the Play Integrity SDK and enables the runtime token API. Optionally addandroid.playIntegrity.verifyUrl=https://your-backend/integrityto also attest at launch on a background thread and exit if your backend rejects the token.android.playIntegrityVersionoverrides the bundled SDK version.ios.appAttest=true— enables App Attest (DeviceCheck.framework) and the runtime token API.ios.appAttest.environmentisdevelopment(debug builds) orproduction(release) by default.
The runtime API is identical on both platforms — request a token bound to a fresh server nonce, then POST it to your backend for verification:
DeviceIntegrity.isAttestationSupported() reports whether attestation is available and was bundled into this build. On the simulator, on unsupported ports, or when the build hint is off, requestIntegrityToken() completes with an error rather than throwing.
| The block-the-transfer decision lives in your backend, gated on the verified verdict. Codename One’s job is to reliably deliver the attested token; the policy enforcement — for example blocking new-beneficiary transfers when integrity fails and biometric controls aren’t enabled — is application + server logic that consumes this API. |
DeviceIntegrity hands you the raw platform blob and leaves verification, policy, replay protection, key management and rotation to you. If you’d rather not build that, Chapter 63, App Shield is the managed layer on top of exactly this API: the attestation is verified server-side against Apple and Google, evaluated against a policy you control, and turned into a short-lived signed token your backend checks with a few lines of middleware. Both remain available and this API keeps working unchanged.
62.7.3. Defending against accessibility-service abuse (Android)
A common Android malware technique is to abuse the accessibility services API for overlays, remote control, and on-screen text extraction (including reading text destined for text-to-speech). Codename One lets you detect untrusted accessibility services and lock down sensitive screens.
The android.accessibilityGuard=true build hint checks the enabled accessibility services at launch and, by default, exits when an untrusted one is active. Tune it with:
android.accessibilityGuard.allow=com.google.android.marvin.talkback,com.example.trusted— a comma-separated allow-list of accessibility-service packages the user legitimately relies on (such as a screen reader). Any enabled service outside this list trips the guard.android.accessibilityGuard.mode=exit|warn—exit(default) terminates the app;warnonly logs, leaving the decision to your runtime code.
At runtime you get the same information for granular control:
// Enumerate the enabled accessibility services (component ids "pkg/.Service").
String[] services = DeviceIntegrity.getEnabledAccessibilityServices();
// True if any enabled service is outside your trusted allow-list.
if (DeviceIntegrity.hasUntrustedAccessibilityService("com.google.android.marvin.talkback")) {
// Likely accessibility-abusing malware -- block the sensitive action.
}For the screens that actually matter (PIN entry, transfer confirmation), mark them secure so the OS blocks screenshots, screen recording, and accessibility screen scraping while they’re displayed:
// Entering a sensitive screen (Android FLAG_SECURE; no-op on iOS):
DeviceIntegrity.setSecureScreen(true);
// null leaving it:
DeviceIntegrity.setSecureScreen(false);Accessibility-service enumeration and setSecureScreen() are Android concepts; on iOS they’re no-ops (iOS has no equivalent third-party accessibility-service threat model). Use ios.disableScreenshots=true to block screen capture on iOS as described in Section 62.4, “Disabling screenshots”. |
62.7.4. Defending against tapjacking and screen overlays (Android)
Tapjacking is the other half of the same attack. Instead of driving your app through an accessibility service, a malicious app draws its own window on top of yours — a fake PIN pad, a fake confirmation button, or an invisible layer — so the user believes they’re tapping your UI while the tap is being framed, or harvested, by someone else. It’s the classic way a banking transfer gets confirmed by a user who thought they were dismissing a notice.
Android exposes this as flags on each touch event, and Codename One turns that into a policy you set once:
android.tapjackingGuard=true— switches on protection at launch with no code. By default it blocks obscured touches and asks Android 12+ to hide overlay windows.android.tapjackingGuard.mode=block|strict|report—block(default) drops any gesture that starts while another window covers the touched point.reportobserves without changing behavior, which is the safe way to measure how often this happens in your user base first.strictalso drops touches where only part of the window is covered; read the warning below before choosing it.android.tapjackingGuard.hideOverlays=true|false— whether to also callsetHideOverlayWindows(). Defaults totrue.
The runtime API gives you the same control plus a notification:
// Switch on tapjacking protection once, during startup. BLOCK drops any gesture
// that begins while another app's window covers the touched point.
DeviceIntegrity.setTapjackingProtection(TapjackingPolicy.BLOCK);
// A blocked gesture never reaches your components, so this listener is how the
// app learns the tap happened. It fires when the state changes, not per touch.
//
// Read the state off the event, not from isScreenObscured(). The callback is
// delivered on the EDT while the state is updated on the platform's input thread,
// so a busy EDT can let a later clean touch land first -- and re-reading the
// global state would then skip the warning for the event that caused it.
DeviceIntegrity.addTapjackingListener(e -> {
if (Boolean.TRUE.equals(e.getSource())) {
Dialog.show("Security warning",
"Another app is drawing over this screen. Close it before continuing.",
"OK", null);
}
});
// On a sensitive screen, remove the overlay instead of merely filtering its taps.
// This is Android 12+ only, and unlike the touch filter it also protects native
// peer components such as BrowserComponent.
if (DeviceIntegrity.isHideOverlayWindowsSupported()) {
DeviceIntegrity.setHideOverlayWindows(true);
}
DeviceIntegrity.setSecureScreen(true);Two properties of this API are worth being precise about, because getting them wrong leads to a false sense of coverage.
Detection is touch-driven, not a live window query. Android reports obscuring as a flag on a delivered MotionEvent, so isScreenObscured() means "the most recently observed touch arrived obscured." If an overlay appears and the user never touches the screen, nothing is observed. That’s a platform limitation, not an implementation gap.
A blocked gesture is dropped in full. Swallowing only the press and delivering the release would leave the framework holding half a gesture, so once a gesture starts obscured, everything through to the matching release is discarded. Your components see nothing at all — which is exactly why the listener exists, and why an app that blocks should register one rather than rely on polling.
setHideOverlayWindows(true) is the strongest of the three defenses and the only one that also covers native peer components such as BrowserComponent and native text fields, because it removes the offending window instead of filtering the touches it enables. Pair it with setSecureScreen(true) when you enter a sensitive screen and clear both on the way out.
It has two requirements, and isHideOverlayWindowsSupported() reports on both — it returns false rather than claiming a protection you aren’t getting:
Android 12 (API 31) or newer.
The
android.permission.HIDE_OVERLAY_WINDOWSmanifest permission. Without it the OS throws, so the call is skipped and logged instead.android.tapjackingGuard=truedeclares it for you; if you drive the runtime API without that hint, addandroid.hideOverlayWindows=true. It’s a normal install-time permission — no runtime prompt and no special-access screen for the user.
strict mode blocks touches where only part of the window is covered, and ordinary system UI causes that as a matter of course. On some devices this will discard taps the user intended and the app will simply feel broken, with nothing in the logs to explain it. Use it only where a missed tap is clearly preferable to a hijacked one, and test it on real hardware. |
This family is Android-only. iOS gives no application a way to draw over another app, so there is nothing to detect: isScreenObscured() is always false and the policy has no effect. Screen recording and mirroring are a different threat, covered by ios.disableScreenshots=true. In the simulator, Simulate > App Shield > Screen Overlay (Tapjacking) fakes an overlay so you can exercise your listener on the desktop. |
62.8. Strong Android certificates
When Android launched RSA1024 with SHA1 was considered strong enough for the foreseeable future, this hasn’t changed completely but the recommendation today is to use stronger ciphers for signing & encrypting as those can be compromised.
APKs are signed as part of the build process when you upload an app to the Google Play Store. This process seems redundant as you generate the signature/certificate ourselves (unlike Apple which generates it for you). But, this is a crucial step as it allows the device to verify upgrades and make sure a new update is from the same original author!
This means that if a hacker takes over your account on Google Play, he still won’t be able to ship fake updates to your apps without your certificate. That’s important since if a hacker would have access to your certificate he could create an app update that would send him all the users private information for example, if you’re a bank this could be a disaster.
Android launched with RSA1024/SHA1 as the signing certificates. This was good enough at the time and is still pretty secure. But, these algorithms are eroding and it’s conceivable that within the 10-15 year lifetime of an app they might be compromised using powerful hardware. That’s why Google introduced support for stronger cryptographic signing in newer versions of Android and you can use that.
62.8.1. The bad news
A downside exists…
Google introduced that capability in Android 4.3 so using these new keys will break compatibility with older devices. If you’re building a highly secure app this is probably a tradeoff you should accept. If not this might not be worth it for some theoretical benefit.
Furthermore, if your app is already shipping you’re out of luck. Due to the obvious security implications once you shipped an app the certificate is final. Google doesn’t provide a way to update the certificate of a shipping app. Thus this feature applies to apps that aren’t yet in the play store.
62.8.2. The good
If you’re building a new app this is pretty easy to integrate and requires no changes on your part. Just a new certificate. You can generate the new secure key using instructions in articles like this one.
If you’re using Codename One Setting you can check the box to generate an SHA512 key which will harden the security for the APK.
62.9. Certificate pinning
When you connect to HTTPS servers your networking code checks the certificate on the server. If the certificate was issued by a trusted certificate authority then the connection goes through, otherwise it fails. Imagine you’re sitting in a coffee shop connected to the local Wi-Fi, and you try to connect to Gmail to check your email. Since you use HTTPS to Google you trust the connection is secure.
| What if the coffee shop was hacked and the router is listening in on everything? |
HTTPS is encrypted and the way encryption works is through the certificate. The server sends you a certificate and you can use that to send encrypted data to it.
| What if the router grabs the server’s certificate and communicates with Google on your behalf? |
This won’t work since the data you send to the server is encrypted with the certificate from the server.
| What if the router sends its own "fake certificate"? |
That won’t work either. All certificates are signed by a "certificate authority" indicating that a google.com certificate is valid.
| What if an attacker could get a fake certificate authorized by a real certificate authority? |
That’s a problem!
It’s obviously hard to do but if someone was able to do this he could execute a "man in the middle" attack as described above. People were able to fool certificate authorities in the past and gain fake certificates using various methods so this is possible and probably doable for any government level attacker.
62.9.1. Certificate pinning
This is the attack certificate pinning (or SSL pinning) aims to prevent. You code into your app the "fingerprint" of the certificate that’s "good" and thus prevent the app from working when the certificate is changed. This might break the app if you replace the certificate at some point but that might be reasonable in such a case.
To do this you have a cn1lib. It fetches the certificate fingerprint from the server so you can check the fingerprint against a list of authorized keys. Run mvn cn1:settings, open Extensions, and install SSLCertificateFingerprint. Then use something like this to verify your server:
| Fingerprints coded into the app are the part that hurts: the certificate has to be replaced eventually, and a hardcoded pin turns that into an app store release with every un-updated install broken until it lands. Chapter 63, App Shield pins the public key rather than the whole certificate, delivers the pin set over the air with the attestation token, and refuses to publish a set that would brick the app — which is the same protection without the release cycle. |
Notice that once connection is established you don’t need to verify again for the current application run.
62.10. Cryptographic primitives
The com.codename1.security package gives you the cryptographic building blocks you need for typical mobile-app concerns — hashing, message authentication, symmetric and asymmetric encryption, digital signatures, JSON Web Tokens, and time/counter-based one-time passwords. The supporting com.codename1.components.OtpField component covers the UI side of OTP entry.
The hash and HMAC primitives are implemented in portable Java so they produce identical output on every platform without depending on any external library. Symmetric and asymmetric encryption, signing, and the secure RNG go through each platform’s native crypto provider via Codename One’s implementation layer:
The simulator (JavaSE) and Android route through the JRE’s
java.securityandjavax.crypto.iOS routes through Apple’s CommonCrypto and the Security framework (via
Ports/iOSPort/nativeSources/CN1Crypto.{h,m}and the correspondingIOSImplementationoverrides).
Application code never sees these differences — you call the same com.codename1.security classes regardless of the platform you are running on.
Cryptographic operations only throw com.codename1.security.CryptoException, an unchecked exception. You can let it bubble up or catch it; you don’t have to declare it. |
62.10.1. Hashing
com.codename1.security.Hash implements MD5, SHA-1, SHA-224, SHA-256, SHA-384, and SHA-512. SHA-256 is the recommended default for new code; MD5 and SHA-1 are exposed only for compatibility with older protocols since both are broken for collision resistance:
The algorithm identifier strings (Hash.MD5, Hash.SHA256, etc.) are also accepted with or without dashes and in any case ("sha256" and "SHA-256" are equivalent).
62.10.2. Message authentication (HMAC)
com.codename1.security.Hmac implements HMAC (RFC 2104) on top of any of the hash algorithms above. Use HMAC whenever a message authentication code is needed — API request signing, session cookie tamper detection, JWT signing with the HS family, or TOTP token generation:
When comparing authentication tags, use Hmac.constantTimeEquals(a, b) instead of Arrays.equals(a, b) — the latter short-circuits on the first mismatch and is vulnerable to timing attacks.
62.10.3. Secure random numbers
com.codename1.security.SecureRandom exposes the platform’s cryptographically secure RNG (SecRandomCopyBytes on iOS, /dev/urandom on Linux/Android, etc.). Use it for keys, nonces, salts, password reset tokens, and any other security-sensitive value. Never use java.util.Random or Math.random() for these purposes:
byte[] iv = SecureRandom.bytes(12); // 12-byte AES-GCM nonce
int pin = SecureRandom.intBelow(1_000_000); // bias-free 6-digit code
long id = SecureRandom.longBelow(1L << 53);62.10.4. Symmetric encryption (AES)
com.codename1.security.Cipher exposes AES through the platform’s native AES implementation. AES-GCM is the recommended default because it’s authenticated — a single tag-mismatch failure detects any tampering of the ciphertext or the associated data:
The Cipher class exposes the standard JCE-style transformation strings as constants: Cipher.AES_GCM, Cipher.AES_CBC_PKCS5, Cipher.AES_CBC, and Cipher.AES_ECB_PKCS5. For GCM, the 16-byte authentication tag is appended to the ciphertext (matching the JCE convention). ECB is exposed only for interop with legacy systems — it leaks structure and should never be used for new designs.
62.10.5. Asymmetric encryption and digital signatures (RSA, ECDSA)
com.codename1.security.Cipher also covers RSA encryption, and com.codename1.security.Signature covers digital signatures (RSA and ECDSA). Keys are represented by com.codename1.security.PublicKey and com.codename1.security.PrivateKey, which wrap X.509 SubjectPublicKeyInfo and PKCS#8 DER blobs respectively — the same encodings used by OpenSSL:
To use a key that was generated outside the app, feed the DER bytes to the static factory methods:
The Signature class exposes the JCE algorithm strings as constants: SHA256_WITH_RSA, SHA384_WITH_RSA, SHA512_WITH_RSA, SHA256_WITH_ECDSA, SHA384_WITH_ECDSA, and SHA512_WITH_ECDSA.
62.10.6. JSON Web Tokens
com.codename1.security.Jwt provides JWT (RFC 7519) signing and verification. The HS family (HMAC-SHA-2) is pure Java so it works on every platform; the RS family (RSA-PKCS#1 v1.5 with SHA-2) and the ES family (ECDSA with SHA-2) route through the platform’s native crypto:
Map<String, Object> claims = new LinkedHashMap<String, Object>();
claims.put("sub", "user-123");
claims.put("exp", System.currentTimeMillis() / 1000 + 3600);
// Sign with a shared secret (HS256)
String token = Jwt.signHs256(claims, "secret".getBytes("UTF-8"));
// Parse + verify
Jwt parsed = Jwt.parse(token);
if (!parsed.verifyHs256("secret".getBytes("UTF-8"))) {
throw new SecurityException("bad signature");
}
String subject = (String) parsed.getClaim("sub");For RSA-signed tokens (RS256/384/512) and ECDSA-signed tokens (ES256/384/512), pass the key to the dynamic overloads:
Jwt.parse(token) doesn’t verify the signature — you must call one of the verify* methods afterwards. Tokens with an alg header of none are rejected by verify unless you explicitly call setVerifyAllowNoneAlgorithm(true) on the parsed JWT. Accepting unsigned tokens is a critical security bug in almost every deployment, so leave it off unless you have decided that the transport is trusted. |
62.10.7. HOTP / TOTP one-time passwords
com.codename1.security.Otp implements counter-based HOTP (RFC 4226) and time-based TOTP (RFC 6238). The output is identical to standard authenticator apps (Google Authenticator, Microsoft Authenticator, 1Password, Authy, etc.) — you can use this class to generate codes inside your app, to validate codes sent by an authenticator on a sign-in flow, or for SMS-based two-factor flows.
Shared secrets are commonly distributed as Base32 strings (the format embedded in QR codes by authenticator apps). com.codename1.security.Base32 handles the encoding:
For HOTP, supply the counter explicitly and increment it after every successful authentication:
62.10.8. Walkthrough: Adding two-factor authentication to a sign-in flow
The typical TOTP-based two-factor authentication flow has two distinct phases. The first is enrolment, where the server provisions a shared secret to the user’s authenticator app; the second is verification, which happens on every subsequent sign-in.
The TOTP secret should be generated and stored on your server, not on the Codename One client. The client only ever sees the secret long enough to display the enrolment QR code, then forgets it. Verification on every subsequent sign-in is also a server-side concern (the client just sends the code the user types in). The code samples below put the cryptography on the client only to keep the example self-contained — in production, the server does the actual generation and verification. |
Phase 1 — Enrollment. When the user opts into 2FA, generate a 20-byte random secret and show it to their authenticator app as a QR code that encodes a standard otpauth://totp/… URI:
// 1. Generate (or fetch from your server) a 20-byte secret -- 160 bits is the
// de-facto standard for authenticator compatibility.
byte[] secret = SecureRandom.bytes(20);
// 2. Build the otpauth URI. The authenticator app stores the secret against
// the "Acme Bank: [email protected]" label and tags it with the issuer
// so it can show "Acme Bank" next to the rotating code.
String uri = Otp.otpauthUri("Acme Bank", "[email protected]", secret);
// 3. Render `uri` as a QR code and show it on screen for the user to scan.
// See "Rendering the QR code" below.The maximum-compatibility settings — 6 digits, 30 second step, SHA-1 — are the defaults of |
Rendering the QR code. Codename One core doesn’t currently ship a QR-code generator. Pick whichever option fits your deployment:
Server-side render (simplest). Send
urito your backend over HTTPS and have it return a PNG. The Google Charts API endpointhttps://chart.googleapis.com/chart?cht=qr&chs=300x300&chl={url-encoded-uri}and the open-sourcehttps://api.qrserver.com/v1/create-qr-code/?data={url-encoded-uri}both work; the latter doesn’t require Google API setup. Render the resulting PNG withURLImageorEncodedImage.create(bytes).Use a QR cn1lib. Community cn1libs such as
QRMakerprovide native generation. Add as a normal cn1lib dependency.Display the secret as a typed value. If you can’t render a QR code, show the user the Base32-encoded secret (the value after
secret=inuri) and ask them to type it manually into their authenticator’s "set up by hand" flow. Less convenient but works on every platform.
Phase 2 — Verification. On every sign-in after enrolment, ask the user for the current six-digit code and verify it against the stored secret. Use [com.codename1.components.OtpField] for the input:
Server-side verification. When your backend does the verification, the corresponding Java looks the same — Otp.verifyTotp(storedSecret, codeFromClient, 1). Make sure you rate-limit verification attempts (for example, lock the account after 5 wrong codes within a minute) and log failures, since the 6-digit search space is small enough to be brute-forced without that.
62.10.9. OTP input widget
com.codename1.components.OtpField is a segmented input — one box per character, that advances to the next box as the user types and steps back on backspace. This is the standard pattern for SMS confirmation and authenticator-app entry screens:
Style the boxes through the UIIDs OtpField (the container) and OtpDigit (each box). The component supports alphanumeric input via the two-argument constructor (new OtpField(8, false)), and pasting a full code into any one box distributes the characters across the remaining boxes automatically.
62.10.10. Algorithm identifier reference
The string constants exposed by these classes are listed below so you can pick them out at a glance.
| Class | Constant | Algorithm string |
|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Same as the JWT |
62.10.11. Key sizes and recommended defaults
AES: 256 bits (
KeyGenerator.aes(256)) for new code. 128 bits is also acceptable and faster; pick 192 only if you have a specific reason.RSA: 2048 bits minimum (
KeyGenerator.rsa(2048)). Use 3072 or 4096 if you need a longer security margin — key generation gets slow above 2048 so run it on a background thread.HMAC: a key at least as long as the hash output (32 bytes for HMAC-SHA-256).
KeyGenerator.hmac(256)returns a key of the requested bit length.TOTP / HOTP: 160 bits (20 bytes) is the de-facto standard for authenticator-app compatibility.
63. App Shield
The security chapter covers a lot of ground that ends at the same place: every check runs on the device, and a device the attacker fully controls is a device where every check can be patched out. Root detection returns false. The pinning code is skipped. The jailbreak probe is stubbed. None of it reaches your server, which is where the money is.
App Shield closes that loop. The app obtains a short-lived, Codename One-signed attestation token backed by a server-side verification of Apple’s App Attest and Google’s Play Integrity statements, and your own API refuses to serve a request that doesn’t carry a valid one. The statement that matters is made by a party the attacker doesn’t control, and your backend can check it in about twenty lines of middleware.
| App Shield doesn’t make an app unhackable, and no product does. What it changes is the cost: scripted abuse of your API goes from "curl in an afternoon" to "reverse-engineer a native binary, and start again after every rotation," and your backend gets a cryptographically verifiable statement it can act on. Be careful not to promise more than that, internally or in marketing. |
This is an Enterprise feature. The public API in com.codename1.security.shield ships in the open-source core and is safe to call in any build — in a build without the attestation engine it degrades to a documented no-op rather than failing — but tokens are only ever minted for entitled accounts.
63.1. How it fits together
Three parties are involved: the app, the Codename One attestation service, and your own API. A protected request goes through five steps.
The app asks the attestation service for a challenge, and the service answers with a nonce it generated. The nonce is what stops a token captured once from being replayed later.
The app asks the platform to attest itself against that nonce. Apple’s App Attest or Google’s Play Integrity produces a statement signed by hardware the app can’t forge.
The app sends that statement to the attestation service, together with any runtime signals it has collected.
The service verifies the statement with Apple or Google, applies the policy you configured, and answers with a short-lived ES256 JWT and the current certificate pin set.
The app sends that token to your API in the
X-CN1-Attestheader, and your middleware verifies its signature against the public keys the service publishes.
Steps 1 to 4 are the framework’s job and happen on the network thread. Step 5 is automatic for every ConnectionRequest to a host you registered. The decision — what to do about a device the service declined — is yours, and it belongs in step 5, on your server.
63.2. Turning it on
Two things have to be true: the account has to be entitled, and the build has to ask for it.
| Build hint | Default | Description |
|---|---|---|
|
| Master switch. The build server injects the hardening engine and wires it into the app’s startup. A build that asks for it without an Enterprise subscription, or on a server where the engine is unavailable, fails with an explanation rather than producing an unprotected app and saying nothing. |
| (service default) | The policy generation this build was compiled against. |
| (none) | The initial pin set, so the first launch on a new install is pinned before it has ever reached the service. Comma-separated base64 SHA-256 SPKI digests. |
| (none) | Pins the key that signs the tokens, so a compromised DNS answer can’t introduce a signing key the app will trust. |
| (Codename One cloud) | Override for a private deployment of the verification service. |
|
| The hardening engine’s own failure policy: |
|
| The App Attest environment written into the entitlement. |
| The engine is injected at build time and isn’t present in a source checkout, in the simulator, or in an unentitled build. That’s deliberate: the detection logic is the part an attacker most wants to read. Everything in this chapter that’s API is open source; only the engine behind it isn’t. |
63.3. Protecting hosts
Registration is the whole configuration. A host you don’t register is never touched — no header, no certificate check, no behaviour change of any kind.
AppShield.init(new ShieldConfig()
// Money moves here, so refuse the request when no token can be obtained.
.protect("api.mybank.example", HostPolicy.ENFORCED)
// Everything else under the domain gets a token when one is available.
.protect("*.mybank.example", HostPolicy.PROTECTED));
// From here on nothing changes at the call sites. A request to a protected
// host is given its token and its certificate check on the network thread.
ConnectionRequest r = new ConnectionRequest("https://api.mybank.example/transfer", true);
NetworkManager.getInstance().addToQueueAndWait(r);HostPolicy is two independent decisions plus what to do when the shield can’t deliver:
| Policy | Token | Pins | When no token can be obtained |
|---|---|---|---|
| no | no | Not applicable. This is what an unregistered host gets. |
| yes | yes | Fail open. The request goes out without a token and your backend decides. Right for most hosts. |
| yes | yes | Fail closed. |
Fail-closed is a promise that a request without a valid token never leaves the device, so it applies to the awkward cases too: a protected host reached over plain http is refused rather than handed the bearer token in clear text, and a shield that was interrupted before it finished starting refuses rather than guessing.
If most of your hosts want the same failure mode, set it once and register them the short way:
AppShield.init(new ShieldConfig()
.defaultFailureMode(FailureMode.CLOSED)
// Registered the short way, so it picks up the default above.
.protect("api.mybank.example")
// And this one opts back out, because an outage here should degrade
// rather than block the app.
.protect("images.mybank.example", HostPolicy.PROTECTED));The default failure mode is read when a host’s policy is resolved, not when it’s registered, so .protect(h).defaultFailureMode(CLOSED) and the same two calls in the other order mean the same thing. |
63.3.1. Wildcards and hosts discovered at runtime
A pattern may be an exact host or a leading . wildcard covering its subdomains — .example.com matches api.example.com and a.b.example.com, but not the apex example.com and not example.com.somewhere-else.test. The most specific rule wins, so an exact registration is never relaxed by a wildcard.
Backends the app only learns about after it starts — a regional endpoint chosen at login, a tenant-specific host — are registered the same way, with the same matching:
// Exact host or a "*." wildcard, resolved the way the configured ones are:
// the most specific rule wins, and a runtime registration beats a configured
// one for the same pattern.
AppShield.addProtectedHost(region + ".api.mybank.example", HostPolicy.ENFORCED);
AppShield.addProtectedHost("*.cdn.mybank.example", HostPolicy.PROTECTED);63.4. What happens to a request
Once init() has run, ConnectionRequest, Rest, RequestBuilder and anything else built on NetworkManager are covered without further code. For a request to a protected host, on the network thread:
It waits for initialization to finish if a cold start is still in progress, rather than treating "not ready yet" as "not protected."
Any token the shield attached earlier is taken back off before the request is reused — a redirect reuses the same request object, and a bearer token that follows a redirect off a protected host has been handed to whoever the redirect points at. A header your own
onRedirect()installed under the same name is left alone: the shield removes its token only while the value is still the token it attached.The token is added under the token header, unless the URL isn’t
https, in which case the host’s failure mode decides.The certificate chain is collected and checked against the pin set, before any request body is written.
The response side is just as narrow: the guard sees the status code and the headers it asked for, which is how a backend tells the app its token was refused as opposed to the user’s credentials.
63.4.1. The token header
The default is X-CN1-Attest. It isn’t Authorization, by design: that slot belongs to your own user authentication, and the two answer different questions — who the user is, versus whether this is a genuine unmodified app on an uncompromised device. Your backend needs both, so they have to compose.
ShieldConfig.tokenHeader(String) changes it, and refuses names that can’t carry a token rather than accepting them and failing out of sight later:
Anything that isn’t a legal HTTP field name. A name with a space or a separator in it isn’t the header you asked for by the time it reaches the server — and it also slips past every check below, because
Cookie ` isn’t `Cookie.Content-Type, whichConnectionRequestroutes to the request’s media type rather than the header map, so the token would replace the content type and survive the redirect cleanup.Your app’s cookie header, whatever it has been renamed to, because the cookie string is written after the request’s own headers and would overwrite the token after
attach()reported success.Headers the transport owns — framing, routing, and the hop-by-hop names a correctly behaving proxy consumes and doesn’t forward.
63.5. Status, and what to do about it
The most important distinction in the API is between "the shield couldn’t be reached" and "the shield looked at this device and said no." Reacting to the first the way you react to the second is how an app locks a paying customer out on a train.
| Status | Transient | Meaning |
|---|---|---|
| - | A valid token is in hand. |
| no | This build has no attestation engine. Nothing is enforced. |
| no |
|
| yes | The service couldn’t be reached. |
| yes | The service answered with an error. |
| yes | This device is being throttled. Retry after a backoff. |
| no | The service evaluated this device and declined to mint a token. |
| no | A pinned host presented a chain matching none of its pins. Nothing was sent. |
ShieldStatus is a constant object rather than an enum on purpose: the vocabulary is visible on the wire and the service must be able to add a status without breaking apps built against an older release. Compare with equals, branch on isSuccess() and isTransient(), and treat an id you don’t recognise as a non-success.
Listeners are delivered on the EDT, so they may touch the UI directly. The framework never shows a dialog and never terminates the app over a shield event — what the user sees is entirely your decision:
AppShield.addListener(new ShieldListener() {
public void statusChanged(ShieldStatus status) {
if (status.isSuccess()) {
return;
}
if (status.isTransient()) {
// The service could not be reached. This is a bad connection, not a
// bad device -- treating it like a rejection is how an app locks out
// users on a train.
Log.p("AppShield: attestation unavailable (" + status.getId() + ")");
return;
}
// REJECTED or PIN_MISMATCH: the service evaluated this device and
// declined, so degrade rather than retry.
disableTransfers();
}
public void signalRaised(ShieldSignal signal) {
// Informational. The server decides what a signal means -- an emulator
// signal is normal on a developer's machine.
Log.p("AppShield signal " + signal.getId() + " severity "
+ signal.getSeverity());
}
public void tokenRefreshed(ShieldToken token) {
}
});63.6. Getting a token yourself
For anything the guard doesn’t cover — a third-party HTTP client, a payload you sign yourself, a handshake — ask for the token directly. fetchToken() is asynchronous and returns immediately, including during a cold start:
AsyncResource<ShieldToken> pending = AppShield.fetchToken();
pending.ready(new SuccessCallback<ShieldToken>() {
public void onSucess(ShieldToken token) {
sendToMyBackend(token.getValue());
}
});
pending.except(new SuccessCallback<Throwable>() {
public void onSucess(Throwable error) {
ShieldStatus status = ((ShieldException) error).getStatus();
Log.p("AppShield: no token (" + status.getId() + ")");
}
});Pass a binding value to tie the token to one specific request, so a token lifted from it can’t be replayed onto another:
// The digest travels in the token, so a token lifted off this request and
// replayed on another one does not verify against the other one's body.
AppShield.fetchToken(sha256(payload)).ready(new SuccessCallback<ShieldToken>() {
public void onSucess(ShieldToken token) {
sendToMyBackend(token.getValue());
}
});AppShield.attach(ConnectionRequest) does the same work synchronously for a request you are about to send. It blocks on a network round trip, so it must not be called on the EDT:
ConnectionRequest r = new ConnectionRequest("https://api.mybank.example/transfer", true);
try {
// Blocks on the attestation round trip, so never on the EDT. In normal use
// the guard does this for you on the network thread.
AppShield.attach(r);
} catch (ShieldException err) {
if (ShieldStatus.PIN_MISMATCH.equals(err.getStatus())) {
// The chain presented for a pinned host matched no pin. Nothing was
// sent, and this is the one status worth surfacing to the user: it
// usually means the connection is being intercepted.
warnAboutInterception();
return;
}
// A fail-closed host with no token. Retry later if the status is transient.
Log.e(err);
return;
}
NetworkManager.getInstance().addToQueueAndWait(r);Token lifetime is measured from a monotonic clock, never from exp against the device clock, because on a rooted device the wall clock is whatever the attacker wants it to be. getCachedToken() returns the current token without any network access, and invalidateToken() discards it so the next request re-attests — which is what to call when your backend tells you the token itself was refused:
ConnectionRequest r = new ConnectionRequest("https://api.mybank.example/transfer", true) {
@Override
protected void readHeaders(Object connection) throws IOException {
// Your middleware sets this header when the ATTESTATION was the problem,
// as opposed to the user's own credentials. Without it a 401 or 403 is
// ambiguous, and an app re-attests its way through a wrong password.
if (getHeader(connection, AppShield.REJECT_HEADER) != null) {
AppShield.invalidateToken();
}
}
};
NetworkManager.getInstance().addToQueueAndWait(r);AppShield.REJECT_HEADER is X-CN1-Attest-Reject. Have your middleware set it only when the token was the problem: a protected API normally carries your own user authentication too, and an app that reads every 401 as an attestation failure re-attests its way through a wrong password. |
63.7. Certificate pinning
Pins are published by the service and refreshed with the token, so rotating a certificate is a console action rather than an app store release. They’re pinned over the subject public key info, so renewing a certificate on the same key pair doesn’t invalidate the pin, and a chain matches if any certificate in it matches any pin for the host — which is what makes it safe to pin an issuing CA as the backup.
Pinning is the one part of the shield that can take an app offline for a reason the developer can’t fix remotely, so the failure behaviour is asymmetric by design:
| Condition | Behaviour |
|---|---|
Host has no pins | Never enforced. Covers first run, a cold start with no network, and any host the service hasn’t published pins for. |
Pin fetch failed | Never fails a request. The last known set is kept. |
Set past its soft expiry | Still enforced; a refresh is attempted. |
Set past its hard expiry | Dropped, and enforcement stops. A device offline for weeks loses pinning, not the app. |
Chain matches a pin | Request proceeds. |
Host has pins, chain matches none | Fail closed. |
PinSet pins = AppShield.getPinSet();
if (!pins.isEnforcedFor("api.mybank.example")) {
// No published pins for this host yet, or the set has hard-expired on a
// long-offline device. Pinning is not enforced, and the app still works.
Log.p("AppShield: no pins in force (version " + pins.getVersion() + ")");
}A pin mismatch surfaces as an exception on the request, not as a silent empty response. If you swallow IOException at your call sites you won’t see it, and an intercepted connection is the one failure worth telling the user about. |
63.8. Runtime signals
The framework’s own detections — root, jailbreak, hooking frameworks, emulators, debuggers, repackaging, untrusted accessibility services — are reported to ShieldSignals rather than acted on locally, and ride along with the next token fetch. There is no separate beacon to block and no extra battery cost.
This is a deliberate inversion of the older exit(0) style checks. Terminating the app is trivially patched out, destroys the telemetry that makes the feature useful, and turns a detection into a crash report. The client reports; the service decides. An emulator signal is normal on a developer’s machine; ten high-severity signals from one device in an hour is a device the service can keep flagging on its next clean-looking attestation.
Your own code can report what only it can notice — a server-side consistency check that failed, a sequence of actions no human performs:
// Severity is 0-100. The service applies the policy; the client only reports.
ShieldSignals.add("serverStateMismatch", 60,
"balance disagreed with the ledger after a retry");
// The framework's own detections arrive the same way.
for (ShieldSignal s : AppShield.getSignals()) {
if (ShieldSignal.HOOK.equals(s.getId())) {
requireStepUpAuth();
}
}The bus is bounded and repeat reports of an id collapse onto the existing entry, so a detector that trips on every frame can’t exhaust memory. An identical repeat refreshes the entry without notifying listeners again; a changed severity or detail is a new observation and is announced.
63.9. Transports the guard doesn’t cover
Coverage matters more here than anywhere else in this chapter, because a gap is invisible at the call site: the code compiles, the request succeeds, and no token was ever attached.
| Transport | Coverage |
|---|---|
| Token and pinning, automatically. |
| Token via |
| The initial navigation only, through |
A native or third-party HTTP client | Nothing automatic. Use |
// BrowserComponent: the INITIAL navigation only. Requests the loaded page makes
// itself are invisible to the framework and cannot be given a token or pinned.
Hashtable headers = AppShield.headersFor("https://api.mybank.example/statement");
browser.setURL("https://api.mybank.example/statement", headers);
// WebSocket: the handshake carries the token. Emitted on Android, desktop,
// Windows and Linux; silently dropped on iOS and in the browser, whose platform
// sockets expose no way to add a header.
WebSocket.build("wss://api.mybank.example/stream")
.header("X-CN1-Attest", token)
.connect();63.10. Composing with your own network guard
NetworkManager holds exactly one guard and seals the slot after the first one is installed, so an app that needs its own interception has to delegate to the shield’s rather than displace it:
// NetworkManager holds exactly one guard and seals the slot, so an app with its
// own has to delegate rather than replace -- calling attach() by hand instead
// would restore the token and silently drop the certificate callbacks that
// enforce pinning.
final NetworkGuard shield = AppShield.getNetworkGuard();
NetworkManager.setNetworkGuard(new NetworkGuard() {
public void beforeRequest(ConnectionRequest r) throws IOException {
r.addRequestHeader("X-My-Trace", newTraceId());
shield.beforeRequest(r);
}
public boolean isCertificateCheckRequired(String url) {
return shield.isCertificateCheckRequired(url);
}
public void checkCertificates(ConnectionRequest r, SSLCertificate[] chain)
throws IOException {
shield.checkCertificates(r, chain);
}
public String[] interestingResponseHeaders() {
return shield.interestingResponseHeaders();
}
public void afterResponse(ConnectionRequest r, int code, String[] headers) {
shield.afterResponse(r, code, headers);
}
});Don’t "work around" the single slot by dropping the shield’s guard and calling attach() by hand. That restores the token and drops the certificate callbacks with no error, so pinning stops being enforced while everything still looks like it’s working — the half of the shield whose absence looks exactly like success. |
63.11. Verifying the token in your backend
The token is a compact ES256 JWT with typ of cn1-attest+jwt, signed by a key published at /.well-known/cn1-attest-jwks.json and named by the header’s kid. Verification is ordinary JWT verification against a JWKS URL — NimbusJwtDecoder.withJwkSetUri in Spring, jose in Node, PyJWT[crypto] in Python — and the console renders a copy-paste quickstart for each, including a Cloudflare Worker for the zero-code-change case.
Beyond the standard iss, aud, sub, iat, exp and jti, the claims your middleware acts on are:
pkgandplat— the package name and platform the token was minted for. Check them against the app you expect.vrd— the verdict:attested,monitoredorunverified.dec— the decision under the current policy:allow, orwould_denywhile the app is still in monitor mode.sig— the signals the device reported.pol— the policy version the decision was made under.ph— the payload binding, when the request asked for one.
Roll it out in two stages, and keep the two sides independent. While the service is in monitor mode it mints a token for everyone and marks the ones it would have refused, so you can watch the would-deny rate against real traffic before anything breaks. Your middleware has its own switch: log and pass through, or reject. Move one at a time.
Reject with an opaque 403, not a 401. A 401 invites the client to retry with fresh credentials, which is exactly the loop you don’t want, and a detailed reason is an oracle for whoever is probing you. |
63.12. iOS App Attest specifics
Apple’s model is one attestation, then many assertions: the first token carries a hardware-backed public key and its attestation, and every later token is a small assertion naming the key. The framework manages the key, the state and the retry policy in the keychain, including recovery when iOS invalidates the key — a restore to a new device, or a reinstall — and Apple’s rate limits, which are strict enough that attesting per request gets an app throttled.
The one thing your code has to do is close the loop when the backend has stored the key, because a registration call that was lost leaves the device asserting against a key the server has never seen:
// iOS App Attest is attest-once, assert-many: the FIRST token carries the public
// key, every later one is an assertion naming it. Call this once your backend
// has stored that key, or a device whose registration call was lost keeps
// sending assertions for a key the server never saw.
DeviceIntegrity.confirmAttestation(keyId);DeviceIntegrity.resetAttestation() throws the key away and starts again, which is the recovery path for a backend that no longer knows the key.
| App Attest doesn’t work in Apple’s iOS simulator — it needs the Secure Enclave. Test the iOS path on a real device, and use the simulator menu below for everything else. |
63.13. Testing it in the simulator
None of this is testable against a real service on a developer’s desktop, so the simulator ships a simulation engine behind Simulate > App Shield. Switching on any item installs it; leaving the menu alone leaves the shield inert.
| Menu item | What it makes reachable |
|---|---|
Attestation Supported | Unchecking it simulates a platform with no attestation at all. |
Attestation Result |
|
Device signal toggles | Rooted / jailbroken, hooking framework, emulator, debugger, repackaged, untrusted accessibility service — each raising the signal your code reacts to. |
Screen Overlay (Tapjacking) | Fakes another app drawing over yours. It drives the real reporting path rather than setting a flag, so your tapjacking listener fires and the |
Serve Expired Token | The refresh path, without waiting out a real token’s lifetime. |
Force Pin Mismatch On Next Request | The most valuable item here: a fail-closed pinning branch is otherwise only reachable by mis-pinning a live host on purpose. It’s a one-shot that disarms itself once spent. |
Fail Pin Fetch | Confirms that a failed pin refresh doesn’t fail requests. |
Show Shield Status… | What the simulation is currently set to, and whether the simulated engine is registered. |
The simulated token is stamped so it can’t be mistaken for a real one, and the simulator’s engine never contacts the service. A backend that accepts a simulated token is a backend that isn’t verifying signatures.
63.14. When there is no engine
Every method in this chapter is safe to call in a build without the engine — an open-source build, an unentitled account, the simulator with the menu untouched. The degradation contract is explicit, and it’s the reason you don’t need to guard your call sites:
init()succeeds and logs one line.isProtected()returnsfalse.fetchToken()always completes, withUNPROTECTED, and never hangs.attach()does nothing. No header, no exception.No request is ever blocked, including one to a host registered as
ENFORCED. Fail-closed enforcement requires an engine to fail; with no engine there is nothing to enforce and the app must keep working.getSignals()still returns realDeviceIntegritydata, so the free-tier detections described in the security chapter keep working.
64. App Hardening
Every Codename One app is already obfuscated by default. On Android the release build runs through R8, which renames the Java names. On iOS and the other native ports your code is compiled to native machine code through ParparVM, which is hard to reverse engineer on its own — but the class names, method names and string literals still travel into the binary as readable text, so a reader who can’t follow the machine code can still read the labels and the constants.
App Hardening is the Enterprise layer that closes that remaining gap across all the ports from one place. It renames classes, methods and fields; encrypts string constants so they’re not present as plaintext in the binary; and obfuscates control flow — and it does this to the merged application before each platform build, so Android, iOS, JavaScript and the native desktop targets are all covered by one transform and one mapping.
This is a tool for apps that face serious security scrutiny — banking, payments, government and other high-risk targets. It raises the cost of static analysis and tampering; it’s one layer, so pair it with Chapter 63, App Shield so the statement your backend trusts is made by hardware the attacker doesn’t control.
App Hardening is an Enterprise feature. A build that asks for it without an Enterprise subscription fails with an explanation rather than producing an unhardened binary that would look protected without being so.
64.1. What it changes, per port
The transform runs on the merged application jar, at the bytecode level, before any platform-specific build step. That’s why one implementation reaches every port: iOS/ParparVM translates the already-hardened bytecode to C (so the C constant pool never sees the plaintext), R8 consumes already-hardened classes on Android, and the JavaScript backend minifies already-hardened classes.
| Transform | Ports | Notes |
|---|---|---|
Class / method / field renaming | iOS, JavaScript, Windows, Linux, desktop | Android keeps R8 as its sole renamer — renaming twice would only force a pointless mapping composition. The renamer uses a distinctive name dictionary on purpose: short names such as |
String constant encryption | iOS, Android, Windows, Linux, desktop | Both channels are handled: the One caveat: an encrypted app literal is a different object from an equal un-encrypted literal elsewhere — for example a literal of the same value returned by the framework, which isn’t hardened. Reference ( One exclusion: a string used as an annotation value (or an annotation-method default) is stored by javac in the annotation metadata, not as an Another exclusion: string concatenation such as |
Control-flow obfuscation | Android, desktop | An opaque predicate guarded by a value the decompiler can’t fold. Left off the ParparVM native ports, where it fights the translator’s optimizer and the arithmetic reducer, and off JavaScript, where it inflates the bundle. Never applied to constructors. |
64.2. Turning it on
Add the level to your codenameone_settings.properties:
codename1.arg.harden.level=standard| Build hint | Default | Description |
|---|---|---|
|
| Master switch: |
| (level) | Override renaming on/off independently of the level. |
| (level) |
|
| (level) | Override control-flow obfuscation on/off. |
| (none) | Keep rules in ProGuard syntax, one rule per line, for classes resolved by name at runtime that the automatic analysis can’t see. Same syntax as |
|
| Per-port opt-out ( |
|
| Fail the build if the symbol/mapping upload fails. Losing a hardened build’s mapping makes its crash reports permanently unreadable, so this defaults to strict. |
|
| Escape hatch: allow a local or source-project target to build unhardened instead of failing the pre-flight. |
| (build id) | Fixes the renaming seed for a reproducible mapping across rebuilds; leave unset for a fresh mapping per build. |
64.3. Levels
The level is the one decision most projects need to make. The individual switches are overrides on top of it.
off | standard | aggressive | paranoid | |
|---|---|---|---|---|
Class/method/field renaming | — | yes | yes | yes |
String encryption | — | constants | all | all |
Control-flow obfuscation | — | — | yes | yes + opaque predicates |
Local-variable debug stripping | — | yes | yes | yes |
Symbol/mapping upload | — | required | required | required |
On a renamed build the source file name (SourceFile) is stripped, matching DexGuard: the engine-renamed ports drop it, and on a minified Android release R8 drops it too. LineNumberTable is kept so a hardened crash still retraces to a line number against the mapping; the retrace reconstructs the file name from the (retraced) class name. Renaming also removes the local-variable and parameter names.
An explicitly unminified Android build (android.enableProguard=false, which android.onDeviceDebug also forces) doesn’t rename at all — only string encryption and control-flow obfuscation apply — so its class names, and SourceFile along with them, remain. That’s a debug configuration, not the release artifact hardening targets.
64.4. Keeping what must not be renamed
Renaming is safe for code the compiler and runtime resolve by symbol. Codename One has no runtime reflection — Class.forName never resolved an obfuscated application class — so there is no reflective seam to protect, and there is no serialization to keep members for. What must survive is the small set the build resolves by name: the main class and its generated stub, the generated router and annotation bootstraps, and each native interface with its generated Impl/Stub peer. The engine finds the native interfaces in the input and keeps exactly those peers, and keeps the rest of that set automatically.
PropertyBusinessObject properties are safe without any special handling: a property’s JSON key and database column come from the string passed to its Property, not from the field name, so renaming the field doesn’t change the on-disk schema or the wire format. String encryption decodes those strings back to the same value at runtime.
If you have a class the build resolves by a name the automatic analysis can’t see, add a harden.keep rule for it.
Package names are obfuscated along with class names. Codename One’s own resource loading uses absolute paths (Display.getResourceAsStream("/name"), the theme .res), which are unaffected. The one thing renaming can break is a package-relative resource lookup — getClass().getResourceAsStream("config.properties"), without a leading slash — because the runtime resolves it under the class’s now-obfuscated package while the resource stays at its original path. This is uncommon in application code, but a bundled third-party dependency might do it; if one loads a resource relative to its own package, add a harden.keep rule for that class (or its package) so its package path stays put.
64.5. Crash reports from a hardened build
Hardening and Crash Protection are designed together. The build server retains the obfuscation mapping and symbolicates incoming reports against it, so a crash from a hardened build still lands as a readable, correctly lined GitHub issue — see Chapter 55, Crash Protection. Two consequences follow: a report whose mapping has aged out of retention can no longer be retraced, and a locally hardened build (whose mapping never reached the server) can’t be symbolicated at all, which is why the pre-flight refuses to harden a local target by default.
64.6. Local and source builds aren’t hardened
Hardening runs on the Codename One build server, and only there. The engine itself is open source — it lives in this repository and ships inside the Maven plugin — so its protection isn’t the secrecy of the algorithm. What the server boundary provides is enforcement and custody: the Enterprise entitlement is checked where the account lives (a client can’t grant itself the feature), the renaming dictionary and decoder keys are seeded per build so the exact obfuscation differs each time and can’t be predicted without the build key, and the obfuscation mapping is retained server-side for symbolication rather than handed to the client.
A local or source-project target (-source, local-) never reaches the server, so its output isn’t hardened; the build fails the pre-flight rather than mislead you, unless you set harden.allowUnhardenedLocalBuild=true. The simulator is never obfuscated either — it runs your target/classes directly. App code can read com.codename1.security.hardening.Hardening.isHardened() to tell a hardened build apart from one of these.
64.7. Hardening and App Shield
These are two different Enterprise features and you can use either or both. App Hardening protects the binary — it raises the cost of reading and modifying the app on the device. App Shield protects the app-to-server relationship — it gives your backend a cryptographically verifiable statement that a request came from a genuine, unmodified app on an uncompromised device. Hardening makes an attacker work harder to patch out App Shield’s checks; App Shield makes patching them out insufficient, because the statement your backend trusts is made by a party the attacker doesn’t control.
64.8. What this doesn’t protect against
Hardening raises the cost of static analysis and casual tampering. It doesn’t stop a determined attacker with time, it doesn’t protect a secret you embed in the client (put it on your server — see the security chapter), and it’s not a substitute for server-side authorization. Treat it as one layer of defense in depth, not a guarantee.
65. Biometric Authentication
Codename One ships first-class biometric authentication (Touch ID, Face ID, Android BiometricPrompt) under the com.codename1.security package. A single entry point exposes the platform prompt, a typed enum reports the modalities currently enrolled, and a typed error enum lets callers react to failures without string matching.
A sibling SecureStorage API stores secret strings (auth tokens, refresh tokens, encryption keys) behind biometric authentication using the iOS keychain or the Android Keystore.
65.1. Quick start: Authenticate
Biometrics b = Biometrics.getInstance();
if (!b.canAuthenticate()) {
// Fall back to password
return;
}
b.authenticate("Unlock your account").onResult((success, err) -> {
if (err != null) {
BiometricError code = ((BiometricException) err).getError();
switch (code) {
case USER_CANCELED: /* user dismissed the prompt */ break;
case LOCKED_OUT: /* too many bad attempts */ break;
case NOT_ENROLLED: /* prompt the user to enrol in Settings */ break;
default: /* generic failure */ break;
}
} else {
// Authenticated. Continue with the gated action.
}
});Always gate the call on canAuthenticate() and never on isSupported() alone. isSupported() only checks for hardware, while canAuthenticate() also requires at least one enrolled credential and that the device isn’t in a locked-out state.
65.2. Quick start: Secure storage
Entries are bound to the current set of enrolled biometrics. If the user enrols a new fingerprint or face after writing, the next get fails with BiometricError.KEY_REVOKED and the application must re-prompt for the original value and write it again.
65.3. Platform behaviour
| Platform | Implementation | Notes |
|---|---|---|
iOS |
| Add the |
Android API 29+ |
| Face / iris / fingerprint per |
Android API 23-28 |
| Fingerprint only. |
JavaSE simulator |
| Toggle hardware availability, per-modality enrolment, and the next-call outcome. |
All other ports | Non-supporting fallback |
|
Application code never needs a platform if. The API itself returns the right thing on each port. On platforms without biometric hardware, the fallback reports NOT_AVAILABLE immediately.
65.4. Build hints
The Codename One Maven plugin and the build daemon both automatically inject the platform configuration when the app’s bytecode references com.codename1.security:
iOS:
LocalAuthentication.frameworkis linked into the generated Xcode project.Android:
<uses-permission android:name="android.permission.USE_BIOMETRIC" />(andUSE_FINGERPRINTwithmaxSdkVersion=28for the legacy path) is injected intoAndroidManifest.xml.
Apps that never touch the API pay nothing: no extra framework, no extra permission.
One thing the plugin won’t inject: the iOS Face ID usage description. Apple rejects placeholder text, so you must supply the build hint yourself:
ios.NSFaceIDUsageDescription=Authenticate to securely access your accountThe JavaSE simulator automatically sets this hint to a default the first time biometrics is invoked, so projects developed in the simulator have a working default; you should overwrite the text before shipping.
To share keychain entries with iOS App Extensions, set both the build hint and the runtime access group:
ios.keychainAccessGroup=TEAMID123.group.com.example.appSecureStorage.getInstance().setKeychainAccessGroup("TEAMID123.group.com.example.app");The Team ID prefix is required; omitting it produces errSecMissingEntitlement.
65.5. Configuring the prompt
Use AuthenticationOptions to control prompt copy and security policy:
Biometrics.getInstance().authenticate(new AuthenticationOptions()
.setReason("Authorize transfer") // iOS localizedReason; Android title fallback
.setTitle("Confirm payment") // Android only
.setSubtitle("Stripe charge $25.00") // Android only
.setNegativeButtonText("Cancel") // Android only
.setBiometricOnly(true) // reject PIN / passcode fallback
.setSensitiveTransaction(true) // request class-3 ("strong") biometric (Android 30+)
);Unrecognised options are ignored, so callers can set the union without platform-checking.
65.6. Typed error handling
BiometricException.getError() returns a BiometricError:
| Code | Meaning |
|---|---|
| No biometric hardware or the platform doesn’t support it |
| Hardware present but the user hasn’t enrolled |
| Too many failed attempts; temporary |
| User must unlock with passcode before biometrics can be used again |
| Device has no PIN / pattern configured (can’t use biometrics) |
| User dismissed the prompt |
| OS dismissed the prompt (app backgrounded, system pre-empted) |
| Prompt completed but the user wasn’t recognised |
|
|
| Anything not covered above |
65.7. Cancelling an in-flight prompt
Call Biometrics.getInstance().stopAuthentication() to dismiss an active prompt; the pending AsyncResource then completes with BiometricError.USER_CANCELED. The method returns true if a prompt was cancelled, false if nothing was pending.
65.8. Listing enrolled biometrics
getAvailableBiometrics() returns a List<BiometricType> to drive UI affordances (icon, prompt copy):
FINGERPRINT: iOS Touch ID; Android fingerprint sensor.FACE: iOS Face ID; Android face recognition (API 29+).IRIS: a handful of Samsung devices; never on iOS.STRONG: Android class-3 authenticator tier (false-acceptance < 1/100,000); only Android API 30+.WEAK: Android class-2 authenticator tier; only Android API 30+. Can’t unlock Keystore-bound keys, so weak-only devices can’t useSecureStorage.
Never use this list to decide whether to call authenticate(); always use canAuthenticate() for that decision.
65.9. Simulator workflow
The JavaSE simulator’s Simulate → Biometric Simulation submenu lets you exercise every code path without a device:
Hardware Available: toggles
isSupported()andcanAuthenticate().Face ID Enrolled / Touch ID Enrolled / Iris Enrolled: populate
getAvailableBiometrics().Next authenticate() Outcome: radio button that picks the outcome of the next prompt:
SUCCEED,FAIL,CANCEL,LOCKED_OUT,PERMANENTLY_LOCKED_OUT,NOT_ENROLLED,PASSCODE_NOT_SET. The selection is sticky; change it any time.
When authenticate() is invoked, a small modal Swing dialog mirrors the platform prompt so the developer can see the trigger fire and click through. State persists across simulator restarts via java.util.prefs.
SecureStorage round-trips against java.util.prefs in the simulator, so you can test the full set → get → KEY_REVOKED flow end-to-end.
65.10. Security notes
The Android backing for authenticate() doesn’t simply forward the OS success callback; it binds the prompt to a single-use AES probe cipher in the Android Keystore (with setUserAuthenticationRequired(true) and, on API 24+, setInvalidatedByBiometricEnrollment(true)). On success the cipher performs a real doFinal operation. A hooked or spoofed success callback fails because the Keystore refuses the operation. This guards against the bypass class documented by CodeQL’s java/android/insecure-local-authentication rule.
66. Authentication and Identity
This chapter covers Codename One’s modern sign-in stack: OpenID Connect, Sign in with Apple, Google, Facebook, Microsoft Entra ID, Auth0 and Firebase Authentication.
The stack is rebuilt around two new primitives:
com.codename1.io.oidc.OidcClient— a full OpenID Connect / OAuth 2.0 client with PKCE, discovery, refresh and token persistence.com.codename1.io.oidc.SystemBrowser— routes the sign-in step through the platform’s hardened sign-in surface (ASWebAuthenticationSessionon iOS, Android Custom Tabs, the user’s default browser on JavaSE / Web).
Every provider-specific class is a thin layer on top of these primitives, so once you learn the underlying client you understand the whole stack.
The legacy com.codename1.io.Oauth2 class is deprecated. It opens an in-app WebBrowser, which modern identity providers (Google, Apple, Microsoft, Facebook) now refuse to render — they detect the embedded view and block the page. The new OidcClient works the same on every supported platform without that limitation. See Section 66.10, “Migrating from Oauth2” for a migration recipe. |
66.1. Why the change
Identity providers tightened their rules in 2023 and 2024:
Google — the legacy
GoogleSignInSDK has been replaced by Google Identity Services (GIS). GIS expects PKCE and discourages embedded WebViews.Apple — Sign in with Apple, mandatory for App Store apps that offer any other social login, requires a native ASAuthorizationAppleIDProvider call on iOS 13+ or a web flow with
form_postresponse_mode.Microsoft — Entra ID (formerly Azure AD) requires PKCE for public clients and forwards all browser flows through Microsoft Authenticator when installed.
Facebook — Facebook Login still supports OAuth 2.0 but its embedded-WebView detection now blocks unknown user agents.
The old Oauth2 class drove the entire flow through com.codename1.components.WebBrowser, which is an embedded view. That model no longer works on a Codename One device build for these providers.
66.2. Quick start — any OpenID Connect provider
If your identity provider publishes a standard .well-known/openid-configuration document (Google, Microsoft, Apple, Auth0, Okta, Keycloak, AWS Cognito, Authentik, and most others do) you can sign users in with about ten lines of code.
OidcClient.discover("https://accounts.google.com").ready(new SuccessCallback<OidcClient>() {
public void onSucess(OidcClient client) {
client.setClientId("YOUR_CLIENT_ID")
.setRedirectUri("com.example.app:/oauth2redirect")
.setScopes("openid", "email", "profile");
client.authorize().ready(new SuccessCallback<OidcTokens>() {
public void onSucess(OidcTokens tokens) {
// tokens.getAccessToken() -- bearer for API calls
// tokens.getIdToken() -- JWT with user identity claims
// tokens.getEmail() -- convenience accessor
}
}).except(new SuccessCallback<Throwable>() {
public void onSucess(Throwable err) {
System.out.println("Sign-in failed: " + err.getMessage());
}
});
}
});That call:
Fetches
accounts.google.com/.well-known/openid-configuration.Generates a PKCE pair (S256), a
state, and anonce.Opens the OS system-browser sheet at the discovered authorization endpoint.
Exchanges the code for tokens on the discovered token endpoint.
Verifies
stateandnonce, decodes the ID token, and persists the tokens via the defaultTokenStore.
66.2.1. Picking a redirect URI
For mobile apps, use a custom scheme unique to your app, for example com.example.app:/oauth2redirect. Register the scheme with the OS via the build hints below so the system browser can hand the redirect back to your app.
For web / simulator runs, use a normal HTTPS URL pointing at a page you control. The Codename One fallback BrowserWindow closes as soon as the URL matches.
iOS
Add the URL scheme to your Info.plist via the standard build hint:
ios.urlScheme=<key>CFBundleURLTypes</key>\n<array>\n <dict>\n <key>CFBundleURLSchemes</key>\n <array>\n <string>com.example.app</string>\n </array>\n </dict>\n</array>
AuthenticationServices.framework is added to the linker automatically whenever your app references anything in com.codename1.io.oidc or com.codename1.social.AppleSignIn — you don’t need to add ios.add_libs=AuthenticationServices.framework manually.
Android
Add an intent filter for the redirect scheme to the application manifest via the android.xintent_filter build hint:
android.xintent_filter=<intent-filter>\n <action android:name="android.intent.action.VIEW"/>\n <category android:name="android.intent.category.DEFAULT"/>\n <category android:name="android.intent.category.BROWSABLE"/>\n <data android:scheme="com.example.app"/>\n</intent-filter>
The androidx.browser:browser:1.8.0 Gradle dependency (for Custom Tabs) is added to your app’s Gradle build automatically whenever it references anything in com.codename1.io.oidc. Override the version with build hint android.customTabsVersion=1.x.y if needed.
66.2.2. Saving and restoring tokens
OidcClient saves the response under a per-issuer + per-client-ID key using com.codename1.io.oidc.TokenStore.DefaultStorageTokenStore (which serializes to com.codename1.io.Storage). To restore on next launch:
If the saved access token is within 60 seconds of expiring and a refresh token is available, refreshIfExpired performs a refresh-token grant in the background and persists the new tokens.
66.2.3. Encrypting tokens at rest
The default token store uses com.codename1.io.Storage, which is sandboxed but not encrypted. For biometric-gated storage, implement TokenStore over com.codename1.security.SecureStorage (see the source of DefaultStorageTokenStore for the pattern — swap the Storage.writeObject / readObject calls for SecureStorage.set / get).
66.3. Sign in with Apple
com.codename1.social.AppleSignIn consolidates the previous cn1-applesignin cn1lib into core. On iOS 13+ it uses native ASAuthorizationAppleIDProvider; on Android, JavaSE and the Web port it uses the public Apple OIDC issuer through OidcClient.
66.3.1. iOS
The iOS port implements the com.codename1.social.AppleSignInNative interface. No build hints are required beyond enabling the Sign in with Apple capability:
ios.signinwithapple=true
AppleSignIn.getInstance().signIn("name email", new AppleSignInCallback() {
public void onSuccess(AppleSignInResult result) {
// result.getIdentityToken() -- JWT to verify on your server
// result.getUserId() -- stable opaque user id, use as PK
// result.getEmail() -- may be a real or relay address
}
public void onError(String err) { }
public void onCancel() { }
});Apple only returns the user’s name and email on the first authorization. AppleSignIn persists those values in Preferences so the result is consistent on subsequent sign-ins. |
66.3.2. Android, JavaSE, Web
Apple requires a separate Services ID (a "web client") for non-iOS environments and a client_secret JWT generated by your server. The recipe lives at Section 66.3.3, “One-time Apple setup”.
66.3.3. One-time Apple setup
In the Apple Developer portal, create a Services ID alongside your App ID. Enable "Sign in with Apple" for both.
Configure the Services ID’s Web Authentication Configuration with the primary App ID and your redirect URI.
Generate an AuthKey private key in the Apple developer portal (
.p8file). Apple doesn’t allow public mobile clients to mint theclient_secretJWT themselves; your backend must do it. See Apple’s docs for the JWT recipe.
66.4. Google Sign-In
com.codename1.social.GoogleConnect now offers a modern signIn(…) method that runs entirely through OidcClient:
signIn works on iOS, Android, JavaSE and Web with the same code, against the Web Application OAuth 2.0 client ID from Google Cloud Console. The redirect URI you supply must match one of the Authorized redirect URIs configured for that client.
The legacy doLogin() / setClientSecret(…) path is still available for source compatibility but is no longer recommended.
66.4.1. Migrating from the legacy Google integration
If you currently rely on GoogleConnect.doLogin() with the Google Sign-In SDK on Android or GIDSignIn on iOS, you can switch to the modern flow without touching your build:
On Android, the legacy code uses
com.google.android.gms.auth.api.Auth.GoogleSignInApi— this is the part Google deprecated. New code viasignIn(…)doesn’t require the native SDK at all.On iOS, the legacy code uses
GIDSignIn(Google Sign-In SDK). The new code usesASWebAuthenticationSessionviaSystemBrowser, which is what Google now recommends for non-broker apps.
66.5. Facebook Login
com.codename1.social.FacebookConnect exposes both the old SDK-based doLogin() and a new SDK-free signIn(…) that uses the system browser via OidcClient. Use the new method for the simulator, the web port, and for apps that don’t want to bundle the Facebook SDK at all:
Facebook doesn’t issue OpenID-Connect ID tokens for classic OAuth flows, so getIdToken() returns null. Read user profile fields via the Graph API.
66.6. Microsoft / Entra ID
com.codename1.social.MicrosoftConnect wraps the same OIDC client against https://login.microsoftonline.com/{tenant}/v2.0. The default tenant common accepts personal and work / school accounts; pass a tenant GUID, organizations, or consumers to restrict.
Apps that need broker (Microsoft Authenticator) support for Conditional Access can bundle the MSAL SDK manually and bypass MicrosoftConnect. For the vast majority of apps the system-browser flow is sufficient and lets the simulator and web port share the same code path. |
66.7. Auth0
Auth0Connect is the simplest of the providers because Auth0 is a clean OIDC provider; everything beyond withDomain is optional.
66.8. Firebase Authentication
Firebase Auth isn’t an OIDC provider — it issues Google-Identity-Toolkit-style tokens via REST endpoints. com.codename1.social.FirebaseAuth wraps those endpoints:
For federated sign-in (Google / Apple / Microsoft as Firebase providers), first obtain an ID token via the matching *Connect class, then swap it for a Firebase session:
Refresh the Firebase session at app launch:
66.9. Passkeys / WebAuthn
Codename One ships a portable WebAuthn client at com.codename1.io.webauthn.WebAuthnClient. It wraps the OS public-key credential APIs (ASAuthorizationPlatformPublicKeyCredentialProvider on iOS 16+, androidx.credentials.CredentialManager on Android API 28+) behind a JSON-friendly Java surface so you can talk to any relying-party server with the same code on every supported platform.
66.9.1. When you actually need this class
If you sign users in via OidcClient against Google, Apple, Microsoft Entra ID, Auth0 or Firebase, the identity provider already supports passkeys. The user’s web browser at the IdP shows the passkey sheet, and OIDC just hands you the resulting ID / access tokens. You don’t have to call WebAuthnClient at all — everything in the rest of this chapter that signs users in via OidcClient already gets passkey-backed sign-in transparently, with no additional code on your side.
Reach for WebAuthnClient when:
Your app talks to your own relying-party server and you want passwordless sign-in / step-up auth backed by a passkey.
You wire up a direct Auth0 or Firebase passkey ceremony (see Section 66.9.5, “Auth0 passkeys” and Section 66.9.6, “Firebase passkeys”).
You drive a third-party SDK that emits a WebAuthn challenge.
66.9.2. Quick start — own backend
Pseudo-code (the actual HTTP calls depend on your server library):
PublicKeyCredential#toJson() is in the W3C RegistrationResponseJSON / AuthenticationResponseJSON format, which every WebAuthn server library accepts as-is. On the server, verify the response with one of:
Java — webauthn4j
Node — @simplewebauthn/server
Rust — webauthn-rs
Python — py_webauthn
Do not try to verify the attestation or assertion on the device. The relying-party server holds the credential record and the signature counter; only it can detect cloned authenticators.
66.9.3. Platform requirements
| Platform | Notes |
|---|---|
iOS | iOS 16+. The |
Android | API 28+ via |
JavaSE / desktop, Web port |
|
66.9.4. Build hints
iOS:
ios.entitlements.com.apple.developer.associated-domains=<array>\n <string>webcredentials:example.com</string>\n</array>
Android: nothing beyond the dependency that gets injected automatically. The asset-links file lives on your server; the build doesn’t touch it.
66.9.5. Auth0 passkeys
Auth0Connect exposes two passkey helpers driven by Auth0’s WebAuthn grant (urn:okta:params:oauth:grant-type:webauthn). They drive WebAuthnClient under the hood, so the same iOS / Android platform requirements apply.
Enable Passkeys in the Auth0 dashboard (Authentication → Database → your connection → Authentication Methods → Passkey), and add WebAuthn to the application’s Grant Types.
66.9.6. Firebase passkeys
FirebaseAuth exposes registerPasskey (enroll a passkey for the signed-in user) and signInWithPasskey (sign in with an existing passkey). Both use Firebase Identity Platform’s v2 passkey REST endpoints (accounts/passkeyEnrollment:start|finalize, accounts/passkeySignIn:start|finalize).
Passkey support requires the Identity Platform tier of Firebase Auth (the upgraded plan). The free Firebase Auth tier doesn’t expose the passkey endpoints; the calls will fail with an HTTP 403. Check your project plan in the Firebase console under Build → Authentication → Settings → User account linking.
66.9.7. Mapping WebAuthn errors
WebAuthnException.getError() returns one of the W3C-defined error names:
| Code | Meaning |
|---|---|
| User dismissed the OS sheet, no matching credential, or the authenticator denied the request. |
| The credential being created already exists on the authenticator. |
| Platform doesn’t support the requested algorithm / transport combo. |
| Origin / RP-ID validation failed. Most often an Associated Domain (iOS) or asset-links (Android) misconfiguration. |
| Caller cancelled the ceremony. |
| A constraint (resident key, user verification) couldn’t be satisfied. |
| The platform has no native WebAuthn implementation at all. Caller should fall back to password sign-in. |
| Network failure while POSTing to your relying-party server. |
| The options JSON received from the relying party couldn’t be parsed. |
| The response returned by the authenticator couldn’t be parsed. |
66.10. Migrating from Oauth2
A typical legacy snippet:
Oauth2 oauth = new Oauth2(
"https://provider.example.com/oauth2/authorize",
"CLIENT_ID",
"https://example.com/callback",
"openid email",
"https://provider.example.com/oauth2/token",
"CLIENT_SECRET");
oauth.showAuthentication(new ActionListener() {
public void actionPerformed(ActionEvent e) {
if (e.getSource() instanceof AccessToken) {
AccessToken t = (AccessToken) e.getSource();
// null
}
}
});becomes:
Or, if the provider exposes a discovery document:
OidcTokens#toAccessToken() returns a com.codename1.io.AccessToken, so callers that already deal in AccessToken (most subclasses of com.codename1.social.Login) can adopt OidcClient without changing their token type.
66.11. A universal sign-in demo
A complete sample is included under samples/UniversalSignInDemo in the repository. It renders one button per provider (Apple, Google, Microsoft, Facebook, Auth0, Firebase, generic OIDC) and dumps the resulting tokens to a TextArea so you can inspect them. See its README.md for the credentials wiring.
67. Deep-Link Routing
Codename One can dispatch a deep link — an iOS Universal Link, an Android
App Link, a custom-scheme URL, a push-notification payload, or anything
else the platform delivers as a URL — to a specific Form by class or by
static factory method. The same route table powers in-app navigation
through Navigation.navigate("/path"), so the application chooses
declarative or imperative per call site without maintaining two parallel
maps.
The application surface is two annotations plus a tiny Navigation
class — five static methods and one value type.
67.1. Declare a route
Annotate the target Form class:
@Route("/users/:id")
public class ProfileForm extends Form {
public ProfileForm(@RouteParam("id") String id) {
setTitle("Profile " + id);
// null
}
}Or annotate a static factory method:
Both forms are supported and a project can mix them. Path variables in
the pattern (:id, , *) are matched by name against parameters
annotated with @RouteParam. Missing @RouteParam on a path-variable
parameter fails the build.
67.2. Path syntax
| Pattern | Matches | Bound |
|---|---|---|
|
| — |
|
|
|
|
|
|
|
|
|
Query string parameters are bound the same way as path variables. The build prefers a path-variable match for a given name and falls back to the query string when the pattern doesn’t include that name.
67.3. Navigate from app code
The Navigation class is the imperative counterpart to @Route.
Calling Navigation.navigate("/users/42") from anywhere in the app
resolves the URL through the same generated route table that handles
incoming deep links, builds the matching Form, pushes it onto the
navigation stack, and shows it.
The five-method surface (navigate, back, getCurrent, getStack,
popTo) is everything the application sees — the rest of the URL-to-
form machinery is generated. Applications that prefer raw
new MyForm().show() keep working unchanged; only URL-driven calls
update the Navigation stack.
67.4. How it works
Codename One scans the project’s compiled bytecode at build time and
generates an internal dispatcher class from every @Route declaration.
The dispatcher is bound into the per-platform application stub before
Display.init(…), so deep links delivered during launch see the route
table immediately. The validation gate catches every problem in a single
build run:
@Routedeclared on a class that doesn’t extendFormPattern with no leading
/or empty valuePath variable with no matching
@RouteParamon the constructor / factoryDuplicate pattern declared on two different targets
@Routeon an abstract class or non-public staticmethod
67.5. iOS Universal Links
Host an apple-app-site-association JSON file at
https://your.domain/.well-known/apple-app-site-association over HTTPS
without redirects. The plugin’s AasaBuilder produces the payload:
Tell iOS which domains your app claims by setting the
ios.associatedDomains build hint — a comma-separated list of
applinks: entries. The iOS builder writes the Associated Domains
entitlement so the resulting .ipa is signed for those domains
automatically.
codename1.arg.ios.associatedDomains=applinks:example.com,applinks:www.example.com67.6. Android App Links
Host an assetlinks.json file at
https://your.domain/.well-known/assetlinks.json. The plugin’s
AssetLinksBuilder produces the payload:
Tell Android which URLs to intercept by setting the
android.xintent_filter build hint with a verified intent filter for
your domain. The Android builder injects the filter into the manifest.
The SHA-256 fingerprint comes from keytool -list -v -keystore …, or
from the Play Console under Setup > App integrity when using Play
App Signing.
67.7. Testing
67.7.1. iOS Simulator
xcrun simctl openurl booted "https://example.com/users/42"67.7.2. Android Emulator
adb shell am start -a android.intent.action.VIEW \
-d "https://example.com/users/42" com.example.app67.7.3. Desktop Simulator
Pass --cn1-arg=https://example.com/users/42 on the run command, or use
the simulator’s URL-injection helper.
67.8. Back-press guard
Independent of deep linking, individual forms can intercept back / pop attempts so they can confirm before discarding unsaved work:
The guard fires for the toolbar back button, the Android hardware back
key, the iOS edge-swipe gesture, and any programmatic back navigation.
PopReason distinguishes the trigger so a guard can be selective.
68. JSON / XML Object Mapping
Codename One includes a build-time POJO mapping framework that turns a
plain Java class — or a PropertyBusinessObject — into JSON or XML
without any runtime reflection. The Maven plugin scans the project’s
compiled bytecode at build time, generates a typed Mapper next to each
@Mapped class, and ships it alongside the source. The runtime entry
point is two methods on com.codename1.mapping.Mappers.
The framework sits next to the existing JSONParser, XMLParser and
PropertyIndex.toJSON / fromJSON helpers — it doesn’t replace them.
Use the imperative APIs when you want to read a foreign JSON shape
without modelling it; use the annotation framework when you have a model
class and want a one-liner round-trip.
68.1. Annotate the model
Apply @Mapped to the class. The processor accepts POJOs with public
fields, PropertyBusinessObject-style classes with Property fields,
or any mix:
@Mapped
@XmlRoot("user")
public class User {
@JsonProperty("first_name")
@XmlElement("first")
public String firstName;
public int age;
// Renders as <user role="admin"/> in XML; omitted from JSON.
@XmlAttribute
@JsonIgnore
public String role;
public User() { } (1)
}| 1 | Every @Mapped class must declare a public no-arg constructor — the generated mapper calls it from fromJson / fromXml. |
For PropertyBusinessObject-style classes the same annotations work on
Property<T> fields. The processor reads through Property#get /
Property#set so subscribers (addChangeListener) still see the
mutation:
68.1.1. Field-level annotations
| Annotation | Purpose |
|---|---|
| Rename the JSON key. Default: the field name. |
| Omit the field from JSON. |
| Rename the XML element. Default: the field name. |
| Lift the field into an XML attribute rather
than a nested child element. Only valid for
scalar or |
| Omit the field from XML. |
68.1.2. Supported field types
| Kind | Detail |
|---|---|
Scalars |
|
|
|
| Same rules as |
| Read from the field’s generic signature. |
Nested | Recursive serialization through the registered nested mapper. |
68.2. Round-trip
Mappers.fromJson and Mappers.fromXml both accept either a String
or a java.io.Reader, so streamed responses (network, file, resource)
don’t need to be fully buffered first.
68.3. How the plumbing works
At build time:
cn1:process-annotations(PROCESS_CLASSES phase) scanstarget/classesfor every class carrying@Mapped.The processor validates each one (concrete, public no-arg constructor, supported field types) and fails the build on the first offender — every offending class shows up in the same error report.
A
<SimpleName>Cn1Mapperclass is generated for every@Mappedtype in the same package as the source class (e.g.com.example.UserCn1Mappernext tocom.example.User). Each generated mapper exposes a publicstatic register()hook.A single
cn1app.MapperBootstrapis generated whose constructor callsUserCn1Mapper.register(),ItemCn1Mapper.register(), … for every accepted@Mappedclass.
At app start:
On iOS / Android, the build server probes the project zip for
cn1app/MapperBootstrap.class. When found it splicesnew cn1app.MapperBootstrap();into the per-build application stub right beforeDisplay.init. ParparVM rename and R8 obfuscation rewrite the call site and the generated class together, so the direct symbol reference stays valid after the pass.On the JavaSE simulator and desktop run,
JavaSEPort#postInitloads the bootstrap viaClass.forName("cn1app.MapperBootstrap"). The classloader is the legitimate path here — JavaSE runs unobfuscated and the sameClass.forNamepattern is used by the @Route dispatcher.
Projects that ship no @Mapped classes produce no bootstrap, the build
server probe falls through, and JavaSEPort catches the
ClassNotFoundException — the registry stays empty and Mappers.toJson
throws a clear "no mapper registered" error.
The runtime registry is keyed on Class#getName(). The map keys survive
obfuscation because both the registration site and the lookup site see
the same renamed name within a single execution — the keys are never
persisted across builds.
68.4. Custom mappers
Sometimes a class lives in a third-party JAR the build can’t annotate.
Hand-write a Mapper<T> and register it at startup:
Hand-written mappers take precedence over generated ones for the same class.
69. Component Binding
The component binding framework wires a model field to the matching
component in a Form or Container by name. The Maven plugin generates
a <SimpleName>Cn1Binder per @Bindable class at build time, so the
wiring happens through direct symbol references — no reflection, no
listener bookkeeping in application code.
It’s a thin alternative to the imperative UiBinding API
(com.codename1.properties.UiBinding). Both can be used together.
69.1. Annotate the model
@Bindable
public class LoginModel {
@Bind(name = "userField", attr = BindAttr.TEXT)
private String user;
public String getUser() { return user; }
public void setUser(String u) { this.user = u; } (1)
@Bind(name = "rememberMe", attr = BindAttr.SELECTED)
public boolean remember; (2)
@Bind(name = "banner", attr = BindAttr.UIID, twoWay = false)
public String bannerStyle;
@Bind(name = "fullName",
attr = BindAttr.TEXT,
getter = "computeFullName",
setter = "applyFullName") (3)
private String fullName;
public String computeFullName() { return fullName.toUpperCase(); }
public void applyFullName(String f){ this.fullName = f.trim(); }
}| 1 | JavaBeans getUser / setUser are detected automatically when the
field is private. The processor instruments setUser to fire a
change notification for two-way bindings. |
| 2 | Public field still works — direct field access falls back when no accessor matches the JavaBeans convention. |
| 3 | Explicit getter / setter override the JavaBeans search. Use
when the convention doesn’t apply (renamed accessors, transforms,
fluent setters). |
Every @Bind(name=…) is looked up against Component#getName(),
walking the container’s children recursively until a match is found.
The default lookup matches GUI-builder names exactly.
69.1.1. Attribute kinds
BindAttr | Mirrors |
|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
| Calls |
|
|
69.2. Bind at runtime
Binding is the handle the binder returns:
| Method | Purpose |
|---|---|
| Push the current model values into every bound
component. Use after mutating the model outside the
form, or to re-sync after |
| Pull current component values back into the model. Useful before validating / submitting when none of the bindings is two-way. |
| Remove every listener the binder installed and unregister the binding from the change-notification fan-out. |
69.3. Two-way bindings and the change-notification contract
A binding declared twoWay = true flows in both directions:
Component → model. The generated binder installs a listener on the editable component (
TextField,CheckBox, etc.). When the user mutates the component, the binder calls the model’s setter (or assigns the public field). The setter’s instrumented exit callsBinders.notifyChanged(this).Model → component. Application code that mutates the model through a setter causes
Binders.notifyChanged(this)to fire, which walks every live binding for that model and pushes the new value into the matching component.
The two paths together would loop forever if left alone — the model
setter fires a change event, which refreshes the component, which
fires its own change event, which calls the model setter again, …
To break the loop, every framework-initiated mutation runs inside an
update region guarded by a thread-local depth counter. While the
counter is positive, notifyChanged is a no-op and component
listeners short-circuit.
Concretely:
Binders.bind(model, container)enters an update region for the initial model → component push.Binding#refresh()enters an update region for every subsequent model → component push.Binding#commit()enters an update region for the component → model pull.The generated component listener enters an update region before calling the setter.
69.3.1. Setter instrumentation
For every two-way @Bind field whose write accessor is a method
(whether you wrote @Bind(setter="setName") or the processor detected
setName(String) via the JavaBeans convention), the
cn1:process-annotations Mojo reads the original .class file with
ASM and inserts the equivalent of:
The injection lands before every return point of the setter. The
instrumented setter is written back to target/classes, replacing the
original. Application code that calls model.setName(…) — from any
thread, any code path — now triggers the binding fan-out
automatically.
69.3.2. Limitation — cross-field setter chains
When a setter synchronously mutates a second bound field
(setFirstName also calls setFullName, for example), the second
field’s notifyChanged lands inside the same update region as the
first and is suppressed. The bound component for fullName won’t
catch up until something exits the region and a separate event drives
the refresh. If you need the cross-field update to propagate, call
binding.refresh() explicitly after the setter chain completes, or
restructure the model so the cross-field mutation happens outside the
setter’s call frame — for example via a Display.callSerially.
69.4. POJOs versus Property objects
A String, int, or boolean field is read and written through the
resolved accessors. A Property<T, ?> field is read through get()
and written through set() — so existing PropertyChangeListener
subscribers fire as expected. Both styles can sit on the same class.
69.5. Validation annotations
The same @Bind field can carry validation annotations that are wired
into a com.codename1.ui.validation.Validator. The validator is built
by the generated binder at the moment you call Binders.bind(…) and
is reachable via Binding#getValidator() — so the same generated
plumbing that pushes model values into components also installs the
constraints that gate them.
| Annotation | Maps to | Notes |
|---|---|---|
|
| "Field must be non-empty." |
|
| Minimum string length. |
|
| Same dialect as |
|
| The standard email regex (also accepts empty — stack with |
|
|
|
|
| Bounds are inclusive; default range is unbounded. |
|
| Whitelist of allowed string values. |
|
| Escape hatch — the class must have a public no-arg constructor and implement |
Multiple annotations on the same field are combined into a
GroupConstraint (first failure wins), matching the behaviour of
Validator.addConstraint(Component, Constraint…).
After binding, drive validation through the returned handle:
Binding#getValidator() never returns null — when the model has no
validation annotations the validator is empty and isValid() returns
true. The validator owns the listener and emblem plumbing on the
matching components; calling addSubmitButtons after bind is the
typical pattern.
69.6. Build-time validation
In addition to the runtime constraints above, the annotation processor itself fails the build when:
@Bindis applied to a field with no accessible read path — the field must be public, declare a JavaBeansgetX/isXgetter, or the annotation must name an explicitgetter.A two-way
@Bindfield on aTEXTorSELECTEDattr has no writable accessor. SettwoWay=falseto keep the binding one-way, or add a setter / explicitsetter=.@Bind(name=…)is empty.The field’s static type isn’t supported (raw collections, opaque references that aren’t
@Bindablethemselves, …).@Regexis missing a pattern, or@ExistInis missing values.
Errors are accumulated so a single build run reports every offending field at once.
69.7. How the plumbing works
cn1:process-annotations writes one
<SimpleName>Cn1Binder per @Bindable class in the source class’s
package, plus a single cn1app.BinderBootstrap whose constructor calls
UserCn1Binder.register(), LoginModelCn1Binder.register(), … for
every accepted @Bindable class. At app start:
On iOS / Android the build server probes the project zip for
cn1app/BinderBootstrap.classand splicesnew cn1app.BinderBootstrap();into the per-build application stub beforeDisplay.init. ParparVM rename and R8 obfuscation rewrite the direct symbol reference together with the generated class so the binding still resolves after the pass.On JavaSE
JavaSEPort#postInitloads the bootstrap viaClass.forName("cn1app.BinderBootstrap")— the unobfuscated classloader path.
Projects with no @Bindable classes produce no bootstrap; the build
server probe falls through and the registry stays empty.
The runtime registry is keyed on Class#getName(); obfuscation renames
the call sites and the registered keys together within a single
execution.
70. SQLite ORM
The SQLite ORM framework turns a plain Java class into a typed data
access object at build time. The Maven plugin reads @Entity /
@Id / @Column annotations from the project’s compiled bytecode,
generates one <SimpleName>Cn1Dao per entity in the source class’s
package, and hands the dao to com.codename1.orm.EntityManager for
typed retrieval. The dao issues prepared statements through
com.codename1.db.Database, the same surface every cn1 SQLite port
exposes.
The framework is a JPA-inspired, simplified alternative to the existing
imperative SQLMap. It doesn’t replace SQLMap; both can be used side
by side.
70.1. Annotate the entity
@Entity(table = "users")
public class User {
@Id(autoIncrement = true)
public long id;
@Column(name = "full_name", nullable = false)
public String name;
public int age;
public java.util.Date createdAt;
@DbTransient
public String cacheKey; (1)
public User() { }
}| 1 | Excluded from the generated table. |
Property fields work the same way; the dao calls Property#get and
Property#set for read and write.
70.1.1. Field-level annotations
| Annotation | Purpose |
|---|---|
| Marks the primary-key field. Exactly one per entity.
|
| Rename the column. Default: the field name. |
| Override the SQL type. Default: inferred from the
Java type ( |
| Adds |
| Excludes the field from the table. |
70.2. Use the dao
EntityManager is a thin façade over Database. The underlying
connection is reachable through em.database() for raw SQL when the
dao surface isn’t enough. Transactions:
70.3. Relationships
Relationship annotations (@OneToMany, @ManyToOne, …) aren’t yet
supported. An entity field that references another entity or a
java.util.List<X> of entities fails the build with a clear error — mark such fields @DbTransient and persist the foreign key (id) as a
separate scalar column for now.
70.4. Validation
The annotation processor fails the build when:
@Entitylands on an abstract class or interface.The class has no public no-arg constructor.
No field carries
@Id, or more than one does.A field’s static type isn’t supported (relationships, unsupported reference types).
Errors are accumulated so the first build run reports every offending entity at once.
70.5. How the plumbing works
cn1:process-annotations writes one
<SimpleName>Cn1Dao per @Entity in the source class’s package
(com.example.UserCn1Dao next to com.example.User), plus a single
cn1app.DaoBootstrap whose constructor calls
UserCn1Dao.register(), OrderCn1Dao.register(), … for every
accepted @Entity class. At app start:
On iOS / Android the build server probes the project zip for
cn1app/DaoBootstrap.classand splicesnew cn1app.DaoBootstrap();into the per-build application stub beforeDisplay.init. ParparVM rename and R8 obfuscation rewrite the call site and the generated dao together, so the direct symbol reference stays valid after the pass.On the JavaSE simulator and desktop run
JavaSEPort#postInitloads the bootstrap viaClass.forName("cn1app.DaoBootstrap"). Class-loading is the legitimate path here — JavaSE runs unobfuscated.
Projects with no @Entity classes produce no bootstrap; the build
server probe falls through and the registry stays empty.
The runtime registry is keyed on Class#getName(); obfuscation renames
the call sites and the registered keys together within a single
execution. The keys are never persisted across builds, so the renaming
has no observable effect on behavior.
71. AI, Chat UI, and Speech
Codename One ships a portable LLM client, a streaming chat component, speech-to-text and text-to-speech APIs, built-in vision and language services, and a portable LiteRT inference API. The builders add native frameworks and dependencies when application bytecode references the corresponding entry point.
This chapter introduces every piece in turn:
com.codename1.ai— provider-agnostic chat, embeddings, tool calls, and image generation.com.codename1.components.ChatView— a theme-aware chat surface that streams tokens in place.com.codename1.media.SpeechRecognizerandcom.codename1.media.TextToSpeech— on-device speech-to-text and speech synthesis.com.codename1.security.SecureStoragenon-prompting overloads — silent reads for secrets the network layer needs on every call, such as LLM API keys.com.codename1.ai.vision— OCR, barcode, face, labeling, pose, segmentation, document correction, and camera-frame pipelines.com.codename1.ai.inference— reusable LiteRT sessions for.tflitemodels.com.codename1.ai.language— language identification, translation, and smart reply.
Each async call in this chapter returns an
com.codename1.util.AsyncResource. Use .ready(…) for the success
path, .except(…) for errors, and .cancel() to abort an in-flight
request. The streaming chat call also dispatches deltas through a
StreamingListener; both listener callbacks and ready callbacks fire
on the EDT. |
71.1. The com.codename1.ai package
The LlmClient class is the single entry point. Static factories return
a configured client for each supported provider. Every client speaks the
same ChatRequest and ChatResponse value types, so the call site does
not change when you swap providers:
// OpenAI (also drives Ollama, vLLM, llama.cpp, and other
// OpenAI-compatible endpoints).
LlmClient openai = LlmClient.openai(apiKey);
// Local Ollama on the default port (http://localhost:11434).
LlmClient ollama = LlmClient.ollama("llama3.2");
// Any OpenAI-compatible endpoint (Together, Groq, Fireworks, vLLM, null).
LlmClient together = LlmClient.localOpenAiCompatible(
"https://api.together.xyz/v1",
apiKey,
"meta-llama/Llama-3.3-70B-Instruct-Turbo");
// Anthropic and Google Gemini, both via their OpenAI-compatible
// endpoints. The wire format is identical; only the base URL,
// default model, and auth differ.
LlmClient anthropic = LlmClient.anthropic(apiKey);
LlmClient gemini = LlmClient.gemini(apiKey);All five factories return the same LlmClient API. OpenAI, Ollama,
vLLM, and llama.cpp share the canonical wire format. Anthropic’s
https://api.anthropic.com/v1/chat/completions and Google’s
https://generativelanguage.googleapis.com/v1beta/openai/chat/completions
implement the same shape, so the framework speaks to all three through
one network layer. Default models pick a sensible production-grade
target per provider (gpt-4o-mini, claude-sonnet-4-5,
gemini-2.0-flash, llama3.2); override per request with
ChatRequest.builder().model(…).
71.1.1. A first chat
ChatRequest is a builder. The bare minimum is a model identifier and
one user message:
ChatResponse.getText() concatenates every text part of the assistant
message. getFinishReason() returns one of "stop", "length",
"tool_calls", "content_filter", or "error". getUsage() returns
prompt, completion, and total token counts when the provider reports
them; the fields return -1 when the provider omits them.
71.1.2. Streaming tokens
chatStream(…) opens an SSE connection and dispatches deltas through
a StreamingListener on the EDT. The returned AsyncResource resolves
to the final aggregated ChatResponse when the stream completes;
calling cancel() on the resource closes the underlying socket:
The decoder reassembles fragmented SSE deltas before invoking the
listener, so onContentDelta always receives a complete token chunk.
Tool-call fragments are reassembled the same way and surfaced through
onToolCallDelta(index, id, name, argumentsFragment); name is non-null
on the first fragment and id is present on the first call.
71.1.3. Tool calling
Tool describes a callable function with a JSON schema. Pass a
ToolHandler to make it executable; the model can then call the tool
and the handler returns the JSON result that gets fed back into the
conversation:
ToolChoice covers the four standard modes:
ToolChoice.AUTO— the model picks at will (default).ToolChoice.NONE— the model must not call any tool.ToolChoice.REQUIRED— the model must call exactly one tool.ToolChoice.named("get_weather")— force a specific tool.
71.1.4. Structured output
Constrain a response to JSON with ResponseFormat.JSON_OBJECT. The
client adds the provider-specific flag, and ChatResponse.getText()
returns a string the runtime can hand to JSONParser:
71.1.5. Multi-modal messages
Attach an image to a user message by adding an ImagePart. The part
accepts either inline bytes plus a MIME type or a remote HTTPS URL:
71.1.6. Embeddings
embed(EmbeddingRequest) returns one Embedding vector per input. Use
the vectors for semantic search, deduplication, or downstream
clustering:
71.1.7. Image generation
ImageGenerator mirrors the LLM client shape. The OpenAI factory drives
DALL-E 3 today; the on-device factory routes through the optional
cn1-ai-stablediffusion cn1lib (when present in the consumer project):
DALL-E 3 supports count = 1 only. Larger batches require a different
underlying model; pass it via setModel(…).
71.1.8. Conversation persistence
ConversationStore wraps Storage to serialize a list of
ChatMessage values to JSON under a named key:
Tokenizer.estimateMessages(history) returns a rough token count so you
can trim the oldest turns before the conversation outgrows the model’s
context window.
71.1.9. Prompt templates
PromptTemplate does simple {placeholder} substitution. Unknown
placeholders pass through unchanged so partially-filled templates are
safe to log:
71.1.10. Retry policy
RetryPolicy.exponentialBackoff() returns a sensible default (four
attempts, 500ms initial delay, 30s cap, jitter). Wrap any chat call in a
retry loop yourself, or attach the policy to a higher-level wrapper.
LlmException.getRetryAfterSeconds() returns the provider’s
Retry-After header value when present, or -1, so the policy can honor
rate-limit hints.
71.1.11. Simulator redirect for offline development
The JavaSE simulator pings localhost:11434 at startup. When Ollama is
running, the simulator exports the flag cn1.ai.ollamaDetected=true. A
second system property, cn1.ai.simulatorRedirect, controls whether the
simulator transparently routes LlmClient.openai(…) calls to the
local Ollama endpoint instead:
| Value | Behavior |
|---|---|
| The default on a device. Calls go to the configured provider, even in the simulator. |
| The default in the simulator. If Ollama is reachable, route
OpenAI calls through it. Otherwise behave like |
| Force redirect to Ollama. Use this in offline-only development environments. |
The redirect target is also configurable: cn1.ai.ollamaUrl defaults to
http://localhost:11434/v1, and cn1.ai.ollamaModel defaults to
llama3.2. Unchanged production code therefore runs offline against a
local model without any conditional wiring at the call site.
71.1.12. Storing the API key
Never hard-code a provider API key in source, ship it in a
bundled resource, or commit it to git. Mobile binaries are trivially
reverse-engineered; any key embedded in the app is a key your users
can extract. Fetch the key from a server endpoint that the user
authenticates against, then cache it locally with the non-prompting
SecureStorage overloads: |
71.2. The ChatView component
ChatView is a scrollable, theme-aware chat surface that handles the
list of bubbles, the streaming append, the typing indicator, and the
input strip in one component. Drop it into a Form with a single
BorderLayout.CENTER:

ChatView rendered in the JavaSE simulator under the iOS Modern themeThe component exposes thread-safe addMessage, appendToLastMessage,
and setTypingIndicatorVisible methods, so background callbacks from
chatStream(…) can mutate the view directly:
ChatBubble and ChatInput are public, so subclass them for custom
rendering. Override ChatView.createBubble(message) to swap in a
custom subclass when the view builds the message list.
71.2.1. Theming
ChatView exposes the following UIIDs out of the box:
| UIID | Applies to |
|---|---|
| The outer container. |
| The scrollable message column. |
| The container for a user message. |
| The container for an assistant message. |
| The container for a system message. |
| The inner |
| The animated typing dots. |
| The input strip. |
| The text field inside the strip. |
| The send button. |
| The attach button. |
| The voice button. |
Style them from theme.css to align with the rest of the app. Hide the
voice or attach button by leaving its listener unset; the corresponding
Button instance is hidden when no ActionListener is registered.
71.2.2. One-call binding to an LLM
LlmChatBinding.bind(view, client, baseRequest) wires the input bar
directly to chatStream(…). Every send replays the conversation
history, dispatches the response into the view, and updates the typing
indicator. Use it for prototypes, or as a reference implementation when
you need a custom send pipeline:
71.3. Speech recognition and TextToSpeech
The new media APIs route through Display and into the implementation
hooks on CodenameOneImplementation, so the call surface is identical
on every platform. The default implementation returns false from
isSupported() and is a no-op for recognize/speak.
71.3.1. SpeechRecognizer
iOS uses SFSpeechRecognizer, Android uses android.speech.SpeechRecognizer,
and the JavaSE simulator stays unsupported unless the optional
cn1-ai-whisper cn1lib is on the classpath. Call stop() to end an
active session early; partial results stop firing immediately.
71.3.2. TextToSpeech
if (TextToSpeech.isSupported()) {
TtsOptions opts = new TtsOptions()
.setLanguageTag("fr-FR")
.setRate(1.0f);
TextToSpeech.speak("Bonjour", opts);
}iOS uses AVSpeechSynthesizer, Android uses
android.speech.tts.TextToSpeech, and the JavaSE simulator falls back
to say on macOS, espeak on Linux, and the platform SAPI bridge on
Windows.
getAvailableVoices() returns the platform-specific voice identifiers
when the OS exposes them; setVoiceId(…) accepts any of those
strings, or null to use the default voice for the configured
language.
71.4. On-device vision
The vision API accepts JPEG, PNG, NV21, or RGBA8888 data through
VisionImage. VisionImage.fromCameraFrame(frame) is normally the
best way to connect a camera because it copies the frame’s
callback-owned buffers and preserves the frame rotation before analysis
becomes asynchronous. For an encoded gallery or file image whose pixels
need an EXIF display rotation, use
VisionImage.encoded(bytes, rotationDegrees); the one-argument overload
assumes the stored pixels are already upright and doesn’t inspect EXIF
metadata. Each analyzer returns stable Codename One result types. Bounds
and points use normalized coordinates in the range 0 through 1.
VisionOptions.minimumConfidence(…) clamps finite and infinite values to
that range and rejects NaN.
Android uses ML Kit. iOS and Mac native builds default to Apple Vision and Core Image. iOS can select ML Kit explicitly:
VisionOptions options = new VisionOptions()
.backend(VisionBackends.mlKitTextRecognition())
.minimumConfidence(0.5f);
new TextRecognizer(options)
.process(VisionImage.encoded(jpegBytes))
.ready(result -> Log.p(result.getText()))
.except(error -> Log.e(error));71.4.1. Reading non-Latin text
TextRecognizer reads the Latin script by default. Select a writing
system with VisionOptions.textScript(…) to read Chinese, Devanagari,
Japanese, or Korean:
TextRecognizer recognizer = new TextRecognizer(new VisionOptions()
.textScript(TextScript.japanese()));
recognizer.process(VisionImage.encoded(jpegBytes))
.ready(result -> Log.p(result.getText()))
.except(error -> Log.e(error));The selector names a script rather than a language, because that’s what the underlying recognizers are organized by. One script covers every language written in it, and each script model also reads the Latin characters mixed into the same page. Recognize one script per analyzer; create a second analyzer when a screen needs both.
Android maps each script to the matching ML Kit recognizer. Apple
platforms map it to the Vision recognition languages for that script,
asking the OS which languages it supports rather than assuming a list.
When the OS recognizes none of them, the analysis fails with
VisionException.UNSUPPORTED rather than returning Latin OCR of the
page. Select VisionBackends.mlKitTextRecognition() to use ML Kit’s
model for that script on iOS instead.
Each script is a separate model, and referencing TextScript.japanese()
is what adds it: the ML Kit script bundle on Android, and on iOS the
matching pod when the ML Kit backend was also selected. An application
that never names a script carries only the Latin model, and one that
names Japanese doesn’t carry the Korean or Devanagari models.
On an iOS simulator, the Apple barcode backend uses Vision barcode request revision 1. Newer simulator runtimes can otherwise complete a barcode request without reporting valid QR codes. Physical devices use the latest revision supplied by the OS. Test newer symbologies such as Micro QR on a device, or select the matching ML Kit backend.
Create and reuse an analyzer when processing a sequence. Call close()
when the analyzer is no longer needed. Before showing a feature, call
its isSupported() method: availability can depend on the target,
linked backend, and OS version.
VisionPipeline attaches an analyzer to a CameraSession frame stream
and keeps only the newest pending frame. Live OCR and pose detection
therefore can’t build an unbounded queue when inference is slower than
the camera. While an analysis is busy, the pipeline reuses the pending
buffer when newer same-sized frames replace it. Results and errors are
delivered on the Codename One EDT.
CameraFrame.getRawBytes() can be null even after requesting NV21 or
RGBA8888 when a port can’t expose that format. JPEG bytes remain available;
VisionImage.fromCameraFrame(…) automatically selects that fallback.
DocumentScanner currently performs still-image rectangle correction on
Apple platforms. Google’s Android document scanner is an interactive
camera flow rather than an analyzer for an existing VisionImage, so the
Android backend reports it as unsupported rather than launching a UI flow.
71.4.2. Vision feature and dependency selection
The Java package is always part of core. The builders scan the concrete analyzer classes and retain only the native adapter and dependency for each class the application actually uses:
| API | Android | Apple default / optional backend |
|---|---|---|
| ML Kit text recognition | Vision / |
| ML Kit bundle for that script | Vision recognition languages / |
| ML Kit barcode scanning | Vision / |
| ML Kit face detection | Vision / |
| ML Kit image labeling | Vision / |
| ML Kit pose detection | Vision / |
| ML Kit selfie segmentation | Vision / |
| Unsupported for still images | Core Image perspective correction |
The optional iOS ML Kit pod is added only when both the analyzer and its
feature-specific selector are referenced. For example,
VisionBackends.mlKitBarcodeScanning() adds only the barcode pod.
Current Google ML Kit iOS pods require iOS 15.5. Selecting one of these
optional backends automatically raises the effective application and
CocoaPods deployment target to 15.5 when the configured target is lower.
Referencing one Android analyzer doesn’t compile or package the other
five adapters.
71.5. Portable LiteRT inference
InferenceSession loads .tflite data from bytes, a bundled resource,
or a private file. Android uses LiteRT and can request NNAPI. iOS uses
TensorFlow Lite Objective-C and may request the Core ML delegate. Both
mobile implementations fall back to CPU unless
allowFallback(false) is set. Android and iOS reject strict
Accelerator.NPU sessions: NNAPI can mix delegated and CPU operations,
and the Core ML delegate can schedule work across the Neural Engine, GPU,
and CPU. Neither reports that the entire graph ran on the requested NPU.
With fallback enabled, NPU selection is a best-effort accelerator
preference.
On iOS, strict Accelerator.CORE_ML sessions are also rejected because
the delegate doesn’t report whether unsupported model operations remained
on LiteRT’s CPU path.
The JavaSE simulator and targets without
a native LiteRT runtime, including Mac native, return false from
InferenceSession.isSupported().
InferenceSession.open(
ModelSource.resource("/models/classifier.tflite"),
new InferenceOptions().accelerator(
InferenceOptions.Accelerator.AUTO))
.ready(session -> {
Tensor input = Tensor.floats("serving_default_input",
new int[] {1, 224, 224, 3}, pixels);
session.run(new Tensor[] {input})
.ready(outputs -> {
try {
consume(outputs[0]);
} finally {
session.close();
}
})
.except(error -> {
try {
Log.e(error);
} finally {
session.close();
}
});
})
.except(error -> Log.e(error));Open is asynchronous because model initialization can allocate native
resources. A session is reusable and supports multiple named inputs,
multiple outputs, and resizeInput(…). A session serializes its mutable
native interpreter: while run(…) is pending, another run, input resize,
or input/output metadata query throws IllegalStateException. Tensor data is
copied across the port boundary. Always close the session.
Bundle small models as resources. For larger models use
ModelCache.fetch(url, cacheKey, sha256), which downloads over HTTPS,
verifies the supplied SHA-256 digest, and reuses the app-private cached
file. The initial URL must use HTTPS. Ports that expose redirect responses
reject a redirect to HTTP and discard the temporary download. iOS follows
redirects below the portable network layer, so iOS requires the SHA-256
argument and rejects the unpinned two-argument overload. Supply the digest
on every platform for every third-party or remotely mutable model.
Interrupted downloads restart through a temporary .download file and are
never promoted to the cache until verification succeeds. Concurrent calls for
the same cache key and content identity share one download but receive
independent asynchronous resources. Canceling one caller suppresses only that
caller’s notification; it doesn’t cancel the shared download or the other
callers. When a cache key already has an active download, a request with a
conflicting URL or digest fails instead of sharing the temporary file.
71.6. On-device language services
LanguageIdentifier, Translator, and SmartReply share
LanguageOptions. Its minimum-confidence threshold clamps to 0 through 1 and
rejects NaN. Translation models are downloaded and cached by ML Kit when a
language pair is first used. Android and iOS builders
select language-id, translate, and smart-reply independently, so
using language identification alone doesn’t package the other two
SDKs.
LanguageOptions options = new LanguageOptions()
.backend(LanguageBackends.mlKitTranslation());
if (Translator.isSupported(options)) {
Translator.translate("Where is the station?", "en", "fr",
options)
.ready(value -> Log.p(value))
.except(error -> Log.e(error));
}LanguageBackends.auto() selects ML Kit on Android and Apple’s Natural
Language framework for language identification on iOS. The Apple default
keeps arm64 simulator builds native and adds no third-party dependency.
LanguageBackends.mlKitLanguageIdentification() opts identification into
the ML Kit iOS pod. iOS translation and Smart Reply are explicit opt-ins:
use LanguageBackends.mlKitTranslation() or
LanguageBackends.mlKitSmartReply() respectively. Merely referencing
Translator or SmartReply doesn’t add a pod or exclude the arm64
simulator. Selecting one of those ML Kit backends requires the x86_64
simulator slice and raises an iOS deployment target below 15.5.
The static language methods are convenient for one operation and close their
temporary backend after either success or failure. For repeated work, call
LanguageIdentifier.open(…), Translator.open(…), or
SmartReply.open(…), reuse the returned feature session, and close it when
the last pending operation completes. Reusable sessions retain backend state
and, on Android, cache ML Kit clients and translation clients per language
pair.
Mac native and the other unsupported targets return false from the
language service isSupported() checks. Completion and failure callbacks
arrive on the EDT.
71.7. Platform availability
The public API and the unsupported fallback are present on every Codename One target. Vision has native implementations on Android, iOS, and Mac native (Mac Catalyst); Apple Vision is the default on Apple targets and Android uses ML Kit. Language services and LiteRT inference have native implementations on Android and iOS. JavaSE, JavaScript, native Windows, native Linux, watchOS, and tvOS report unsupported for these new APIs; Mac native reports unsupported for language and LiteRT. No target sends data to a cloud inference service. Large portable runtimes or model payloads for the remaining targets remain appropriate opt-in libraries.
No build hints or cn1lib coordinates are required for the built-in
mobile implementations. The local Maven plugin and BuildDaemon use the
same PlatformFeatureCatalog, so local and cloud builds make the same
dependency decisions.
71.8. Migrating from the AI cn1libs
The old com.codename1.ai.mlkit.* and com.codename1.ai.tflite
packages aren’t compatibility aliases. Remove those dependencies and
move directly to com.codename1.ai.vision,
com.codename1.ai.language, or com.codename1.ai.inference. Result
coordinates are normalized floats rather than packed
platform-specific integer arrays. cn1-ai-whisper and
cn1-ai-stablediffusion remain cn1libs because their native payloads
and models are intentionally large.
Remove the retired cn1lib dependency before adding the built-in class. During migration, the builders deduplicate identical CocoaPods names and preserve an explicitly declared user version constraint. Removing the old library is still required because compatibility aliases would keep its old native-interface and packaging contracts alive.
71.8.1. Putting it all together
The pieces compose well. The following loop captures a photo,
extracts text with the multi-modal gpt-4o model, speaks the result,
and streams the same text into a ChatView:
The same code runs unchanged in the simulator when Ollama is detected, on Android with the multi-modal native client, and on iOS through the cloud build pipeline.
72. Near-Field Communication (NFC)
Codename One ships an NFC API under com.codename1.nfc that covers the three things most apps need: read and write NDEF tags, exchange APDUs with ISO 7816 / MIFARE / FeliCa smart cards, and act as a host-emulated card for a nearby reader/terminal.
A single entry point exposes the platform NFC controller, a typed enum reports the technologies the discovered tag supports, and a typed error enum lets callers react to failures without string matching.
72.1. Quick start: Read an NDEF URI
Nfc nfc = Nfc.getInstance();
if (!nfc.canRead()) {
// no NFC hardware, or it is disabled in system settings
return;
}
nfc.readNdef(new NfcReadOptions()
.setNdefOnly(true)
.setAlertMessage("Hold near the poster"))
.onResult((NdefMessage msg, Throwable err) -> {
if (err != null) {
return;
}
String url = msg.getFirstRecord().getUriPayload();
Display.getInstance().execute(url);
});setNdefOnly(true) picks the fastest iOS Core NFC session (NFCNDEFReaderSession) and matches the most common tag layout. For mixed payloads use readTag(…) and inspect tag.getTypes().
72.2. Quick start: Write an NDEF URI
NDEF records carry one of the well-known types (T, U, Sp), a MIME media type, an absolute URI, or an external domain:type. Use the factory methods on NdefRecord rather than constructing raw byte arrays:
| Factory | Use for |
|---|---|
| URI records — launches the associated app on tap |
| Human-readable text |
| Binary payloads (vCard, JSON, …) |
| Custom vendor types |
| Android Application Record (AAR) |
72.3. Tag-technology APIs
Beyond NDEF, the discovered Tag exposes accessors for the underlying technologies:
Each accessor returns null when the tag doesn’t advertise the corresponding technology, so always null-check before calling.
| Accessor | Android | iOS | Notes |
|---|---|---|---|
| yes | yes | ISO 7816 — EMV, ePassport, smart cards |
| yes | — | Apple doesn’t expose MIFARE Classic on iOS |
| yes | yes | NTAG21x, Ultralight C |
| yes | yes (limited) | Raw ISO 14443-3A |
| yes | — | Raw ISO 14443-3B (Android-only) |
| yes | yes | FeliCa (Suica / PASMO / ICOCA) |
| yes | — | ISO 15693 (Android-only) |
For FeliCa on iOS, set the system codes in NfcReadOptions:
The Codename One Maven plugin and build daemon automatically register com.apple.developer.nfc.readersession.felica.systemcodes from these values.
72.4. Quick start: Host card emulation
Host Card Emulation (HCE) lets the device pretend to be a contactless smart card. A nearby reader (Android phone, payment terminal, access control gate) sends ISO 7816 APDUs and your app responds. Subclass HostCardEmulationService and register the instance:
Set the AIDs as a build hint so they appear in the platform routing tables:
android.hceAids=F0010203040506
android.hceCategory=otherThe Maven plugin and BuildDaemon generate apduservice.xml on Android, register the CodenameOneHostApduService in the manifest, and inject the iOS HCE entitlement so the same code path works on both platforms.
iOS HCE (CardSession) requires iOS 17.4+ and, as of 2026, is EU-only. The Codename One plugin still injects the entitlement when you reference the class, but canHostEmulate() will report false on non-EU devices.
72.5. Permissions and build hints
The Codename One build pipeline automatically detects NFC usage. Apps that never touch com.codename1.nfc see no manifest / plist change.
| Reference | Android injected | iOS injected |
|---|---|---|
|
|
|
|
|
|
Override any of the defaults with the matching build hint:
| Build hint | Default | Notes |
|---|---|---|
| "Hold near an NFC tag to continue" | Localise this — Apple rejects builds that ship the default copy |
|
| Multi-line entitlement value |
| (none) | Comma-separated; required for HCE on Android |
|
|
|
|
| Force lock screen unlock before APDU routing |
| falls back to | iOS HCE AID list |
72.6. Simulator support
The JavaSE simulator implements Nfc via a virtual tag you can edit and tap from the Simulate → NFC submenu:
| Menu item | Effect |
|---|---|
Hardware Available / NFC Enabled / HCE Available | Toggle what |
Next read outcome | Pick |
Tap virtual tag | Fire the configured outcome on any pending read or registered listener |
Set virtual tag URI… | Replace the virtual tag’s NDEF payload with a URI record |
Set virtual tag text… | Replace the virtual tag’s NDEF payload with a text record |
Tag is read-only | Lock the virtual tag so the next write fails with |
Send APDU to HCE service… | Hex-entry dialog that dispatches the bytes to your registered |
Deactivate HCE field | Fires |
All toggles persist between simulator runs (under NfcSim.* user preferences) so you can drive tests deterministically.
72.7. Platform behaviour
| Platform | NDEF read | NDEF write | Tag tech | HCE | Notes |
|---|---|---|---|---|---|
Android | yes | yes | full set | yes |
|
iOS | yes (iOS 11+) | yes (iOS 13+) | ISO 7816, FeliCa, MIFARE Ultralight | iOS 17.4+ EU-only | MIFARE Classic and NFC-B/V not exposed by Apple |
JavaSE simulator | yes (virtual tag) | yes (virtual tag) | configurable | yes (synthetic APDUs) | Drive everything from the Simulate → NFC menu |
Desktop deploy / JavaScript | no | no | no | no | Fallback base class — every method completes with |
Always gate user-facing affordances on canRead() (for tag operations) or canHostEmulate() (for HCE). isSupported() only reports whether the hardware is present.
73. Bluetooth
Codename One ships a first-class Bluetooth API under com.codename1.bluetooth that covers both Bluetooth Low Energy roles and classic Bluetooth: scan for and connect to BLE peripherals (the GATT client), act as a BLE peripheral (a local GATT server plus advertising), stream bytes over L2CAP connection-oriented channels, and exchange RFCOMM streams with classic serial devices.
Bluetooth.getInstance() is the single entry point and never returns null — ports without Bluetooth return a fallback whose operations fail fast with BluetoothError.NOT_SUPPORTED, so calling code needs no platform-specific if. Every callback of the API — AsyncResource results, scan sightings, connection events, notifications, adapter state changes — is delivered on the EDT; the only exceptions are the blocking RFCOMM/L2CAP streams, which must be consumed off the EDT.
| Capability | Android | iOS / Mac Catalyst | Simulator (mock) | Simulator (native backend) | JavaScript |
|---|---|---|---|---|---|
BLE central (scan, GATT client) | yes | yes | yes | yes | browser chooser only |
BLE peripheral (GATT server + advertising) | yes | yes (not tvOS/watchOS) | yes | — | — |
L2CAP channels | yes (Android 10+) | yes (iOS 11+) | yes | — | — |
Classic RFCOMM | yes | — | yes | — | — |
Bonding | yes | OS-managed | yes | — | — |
On the JavaScript port, Web Bluetooth limits the central role to the browser’s device chooser (Chrome-family browsers over HTTPS): startScan(…) surfaces the chooser built from the scan filters and delivers the single user-picked device as one ScanResult. No further sightings ever arrive, the RSSI is unknown, the MTU is fixed at 512 and peripheral mode, classic Bluetooth and L2CAP are unavailable.
Always branch through the capability queries — isLeSupported(), isPeripheralModeSupported(), isL2capSupported(), isClassicSupported() — rather than through platform detection.
73.1. Quick start: Scan and connect
Bluetooth bt = Bluetooth.getInstance();
if (!bt.isLeSupported()) {
// hide the feature on ports without BLE
return;
}
bt.requestPermissions(BluetoothPermission.SCAN, BluetoothPermission.CONNECT)
.onResult((granted, permissionErr) -> {
if (permissionErr != null || !granted) {
return;
}
ScanSettings settings = new ScanSettings()
.addFilter(new ScanFilter()
.setServiceUuid(BluetoothUuid.fromShort(0x180D))
.setNamePrefix("Polar"));
BleScan[] scan = new BleScan[1];
scan[0] = bt.getLE().startScan(settings, sighting -> {
scan[0].stop();
sighting.getPeripheral().connect()
.onResult((peripheral, connectErr) -> {
if (connectErr != null) {
return;
}
peripheral.discoverServices()
.onResult((services, discoverErr) -> {
// the GATT database is ready -- see the
// following sections
});
});
});
});ScanFilter criteria on one filter are AND-combined; multiple filters added to the same ScanSettings are OR-combined, and a scan without filters reports every advertising device. Any number of scans may run concurrently — each BleScan handle only sees advertisements matching its own filters, and the platform scan stops when the last handle stops. On iOS a service-UUID filter is also what keeps scans alive in the background, so prefer filtered scans.
Peripheral addresses returned by BluetoothDevice.getAddress() are stable per app install — the MAC address on Android and desktop, the per-app CoreBluetooth identifier on iOS — and safe to persist for later reconnection through BluetoothLE.getPeripheral(String). They’re not portable across devices or platforms, so never treat them as the peripheral’s real hardware address.
getAdapterState() reports where the local radio stands (POWERED_ON, POWERED_OFF, UNAUTHORIZED, …) and addAdapterStateListener(…) fires on the EDT whenever it changes — the natural place to pause scans and gray out UI. requestEnable() shows the Android system dialog asking the user to turn the adapter on; on iOS there is no programmatic enable flow, so it resolves false and the app should direct the user to the Settings app instead.
Connection lifecycle is equally explicit. connect(ConnectionOptions) accepts a timeout (iOS connect requests never time out on their own, so set one) and an autoConnect flag that asks the platform to re-establish the link whenever the peripheral comes back into range. addConnectionListener(…) reports every transition including link loss, and every failure across the API surfaces as a BluetoothException whose getError() returns a typed BluetoothError constant — no string matching required.
73.2. Reading and writing characteristics
discoverServices() caches the peripheral’s GATT database; from there getService(…), getCharacteristic(…) and the convenience accessors on GattCharacteristic cover the day-to-day operations:
GattCharacteristic measurement = peripheral.getCharacteristic(
BluetoothUuid.fromShort(0x180D),
BluetoothUuid.fromShort(0x2A37));
if (measurement != null && measurement.canRead()) {
measurement.read().onResult((data, err) -> {
if (err == null) {
// raw bytes, delivered on the EDT
updateHeartRateLabel(data[1] & 0xFF);
}
});
}
GattCharacteristic controlPoint = peripheral.getCharacteristic(
BluetoothUuid.fromShort(0x180D),
BluetoothUuid.fromShort(0x2A39));
if (controlPoint != null && controlPoint.canWrite()) {
controlPoint.write(new byte[] {1})
.onResult((acknowledged, err) -> {
// resolves once the peripheral acknowledged the write
});
}All GATT operations return independent AsyncResource handles and may be issued concurrently: an internal per-peripheral queue serializes them toward the platform stack (which allows only one in-flight request per connection) and applies a safety timeout, so a lost platform callback can never wedge the queue. Operations on different peripherals run fully concurrently. writeWithoutResponse(…) resolves once the value is queued to the controller — there is no remote acknowledgement.
A default BLE connection carries 23 bytes per attribute operation; requestMtu(…) negotiates a larger value and resolves with what was granted (on iOS the OS negotiates by itself, so the request resolves immediately with the current value — check getMtu() before chunking data). requestConnectionPriority(…) trades latency against battery on Android and is a successful no-op on iOS. createBond() initiates pairing where the peripheral requires an encrypted link; on iOS bonding is OS-managed and triggered automatically by encrypted characteristics, so the call resolves true without user interaction.
73.3. Notifications
GattCharacteristic measurement = peripheral.getCharacteristic(
BluetoothUuid.fromShort(0x180D),
BluetoothUuid.fromShort(0x2A37));
GattNotificationListener listener = (characteristic, data) -> {
// fires on the EDT for every notification while subscribed
updateHeartRateLabel(data[1] & 0xFF);
};
measurement.subscribe(listener).onResult((armed, err) -> {
if (err != null) {
// the CCCD write was rejected or the link dropped
}
});
// later, e.g. when leaving the form:
measurement.unsubscribe(listener);The Client Characteristic Configuration descriptor (CCCD) is handled automatically: the first listener triggers the descriptor write that arms notifications (indications are used when the characteristic only supports those) and removing the last listener disarms it again. Values stream to the listeners on the EDT until unsubscribed or disconnected.
73.4. Peripheral mode
When isPeripheralModeSupported() returns true the device can serve data itself — open a local GATT server, add service definitions and advertise them:
Bluetooth bt = Bluetooth.getInstance();
if (!bt.isPeripheralModeSupported()) {
return;
}
GattLocalCharacteristic status = new GattLocalCharacteristic(
BluetoothUuid.fromShort(0x2A37),
GattCharacteristic.PROPERTY_READ
| GattCharacteristic.PROPERTY_NOTIFY,
GattLocalCharacteristic.PERMISSION_READ)
.setValue(new byte[] {0, 72});
GattLocalService service = new GattLocalService(
BluetoothUuid.fromShort(0x180D))
.addCharacteristic(status);
bt.getLE().openGattServer(new GattServerAdapter() {
@Override
public void centralConnected(BleCentral central) {
// a central connected to this device
}
@Override
public void characteristicWriteRequest(GattWriteRequest request) {
// handle the written bytes, then acknowledge
if (request.isResponseRequired()) {
request.respond();
}
}
}).onResult((server, err) -> {
if (err != null) {
return;
}
server.addService(service).onResult((added, addErr) -> {
if (addErr != null) {
return;
}
bt.getLE().startAdvertising(
new AdvertiseSettings(),
new AdvertiseData()
.addServiceUuid(BluetoothUuid.fromShort(0x180D))
.setIncludeDeviceName(true),
null).onResult((advertisement, advErr) -> {
// broadcasting; keep the handle and stop() it when done
});
// push a new value to every subscribed central
server.notifyValue(status, new byte[] {0, 80});
});
});Characteristics with a static value (setValue(…)) are served without involving the listener; characteristics without one route every read to characteristicReadRequest(…), which must answer via respond(…) or reject(…) — centrals time out unanswered requests.
Two iOS platform notes: CoreBluetooth only broadcasts the local name and service UUIDs, dropping manufacturer data, service data and TX power from advertisements (Android broadcasts everything). And iOS serves descriptors from their static values only — descriptor read/write requests never reach the listener there, so always give local descriptors a static value for cross-platform behavior.
73.5. L2CAP channels
L2CAP connection-oriented channels provide a raw bidirectional byte stream — much higher throughput than chunking data through GATT characteristics. The peripheral side opens a listener and publishes its Protocol/Service Multiplexer (PSM), typically through a GATT characteristic; the central side connects to that PSM:
if (!Bluetooth.getInstance().isL2capSupported()) {
return;
}
peripheral.openL2capChannel(psm, true).onResult((channel, err) -> {
if (err != null) {
return;
}
// the streams block -- always consume them off the EDT
CN.startThread(() -> {
try {
OutputStream out = channel.getOutputStream();
out.write(new byte[] {1, 2, 3});
out.flush();
InputStream in = channel.getInputStream();
byte[] buffer = new byte[4096];
int size = in.read(buffer);
// process the response...
} catch (IOException ioErr) {
// transport failure
} finally {
try {
channel.close();
} catch (IOException ignored) {
}
}
}, "L2CAP IO").start();
});
// the peripheral side listens and publishes its PSM to centrals
Bluetooth.getInstance().getLE().openL2capServer(true)
.onResult((server, serverErr) -> {
if (serverErr == null) {
int assignedPsm = server.getPsm();
// advertise assignedPsm through a GATT characteristic,
// then server.accept() incoming channels
}
});On Android an L2CAP channel establishes its own link and doesn’t require connect() first; on iOS the peripheral must be connected. The streams throw plain java.io.IOException on transport failure and, like all Bluetooth streams, block — never touch them on the EDT.
73.6. Classic Bluetooth
Classic (BR/EDR) Bluetooth covers inquiry discovery, bonding and RFCOMM stream connections — the Serial Port Profile (SPP) world of printers, scanners and industrial equipment. iOS doesn’t expose classic Bluetooth to applications, so this role is Android, desktop and simulator only; isClassicSupported() is the gate:
Bluetooth bt = Bluetooth.getInstance();
if (!bt.isClassicSupported()) {
// classic Bluetooth is unavailable -- iOS among others
return;
}
BluetoothClassic classic = bt.getClassic();
classic.startDiscovery(sighting -> {
if ("SerialPrinter".equals(sighting.getDevice().getName())) {
classic.connect(sighting.getDevice(), BluetoothUuid.SPP, true)
.onResult((connection, err) -> {
if (err != null) {
return;
}
// consume the blocking streams off the EDT, exactly
// like the L2CAP example
});
}
});
// accepting incoming SPP clients
classic.listen("Codename One SPP", BluetoothUuid.SPP, true)
.onResult((server, err) -> {
if (err == null) {
server.accept().onResult((connection, acceptErr) -> {
// one client accepted; call accept() again for the next
});
}
});startDiscovery(…) runs an inquiry scan (about 12 seconds) and returns a live ClassicDiscovery handle that resolves when the inquiry ends. getBondedDevices() lists already-paired devices without a discovery, and connect(String, BluetoothUuid, boolean) reconnects to a persisted address directly.
73.7. Permissions and build hints
The build pipeline scans the application’s bytecode and injects only what the referenced packages need — apps that never touch com.codename1.bluetooth see no manifest or plist change, and a central-only app never carries advertise permissions.
| Detected usage | Android injected (target SDK 31+) | iOS injected |
|---|---|---|
Any |
|
|
Scanning ( |
| — |
Connections (GATT, |
| — |
Peripheral mode ( |
| — |
Classic ( |
| not supported |
Builds targeting an SDK below 31 receive the legacy permissions uncapped and none of the Android 12 ones. Permissions you declare yourself (via android.xpermissions) are never duplicated.
Override the defaults with the matching build hints:
| Build hint | Default | Notes |
|---|---|---|
|
| Declares that scan results never derive the user’s location, which caps |
|
| Marks the BLE hardware feature required so stores hide the app on devices without it |
| (none) |
|
| "Communicates with nearby Bluetooth accessories." | Localise this — Apple rejects builds that ship generic privacy copy |
Beacon and indoor-positioning apps are the one case where the neverForLocation default is wrong: an app that derives location from BLE sightings must set android.bluetooth.neverForLocation=false, otherwise Android 12+ filters beacon advertisements out of its scan results. With the hint set to false the location permission stays uncapped and the app keeps prompting for it on Android 12+.
73.8. Simulator support
The JavaSE simulator implements the whole API against a scriptable virtual Bluetooth stack. Simulate → Bluetooth Simulation opens a window with a tree of the simulated adapter, the virtual peripherals and the app’s own peripheral role; selecting a node opens its detail editor (hex value editors on characteristics), a toolbar stages demo devices, failure injection arms the next operation of a chosen kind (connect, read, write, discover, subscribe, scan and the rest) to fail with a chosen BluetoothError, a latency spinner delays every asynchronous completion and a live event log shows what the stack does. All settings persist between simulator runs.

The window’s backend selector switches the simulator between the virtual stack and a native backend that drives the host machine’s real Bluetooth radio through a bundled btleplug library (libcn1ble) loaded in-process (CoreBluetooth on macOS, BlueZ on Linux, WinRT on Windows). The native backend is central-only — real scanning, connections and GATT operations against physical devices, without leaving the simulator. The initial backend comes from the cn1.bluetooth.backend system property (default simulator); point cn1.bluetooth.libraryPath at a locally built libcn1ble to override the bundled one.

The Simulate → Bluetooth menu exposes the same operations as one-click hooks; every item is also callable from cross-platform code via CN.execute("bluetooth:itemN"):
| Hook | Menu label | Effect |
|---|---|---|
| Toggle Adapter | Flips the simulated adapter between |
| Add Demo Peripheral | Registers the canonical demo device: |
| Push Demo Notification | Pushes a rolling one-byte notification from the demo peripheral’s |
| Disconnect All | Drops every live connection from the remote side |
| Clear Peripherals | Removes every registered virtual peripheral |
| Use Simulator Backend | Switches back to the virtual stack |
| Use Native Backend | Switches to the host machine’s real radio |
| (API only) | Arms the next GATT read to fail with |
Everything the window does goes through the scriptable BluetoothSimulator API in com.codename1.impl.javase.bluetooth, so tests and sample apps can stage the same devices programmatically. This code runs against the JavaSE port only — it isn’t part of the cross-platform API and won’t compile in a portable code base, so keep it in your test or debug scaffolding:
BluetoothSimulator.addPeripheral(
new VirtualPeripheral("AA:BB:CC:DD:EE:10")
.setName("Thermometer")
.addAdvertisedServiceUuid(BluetoothUuid.fromShort(0x1809))
.withService(new VirtualService(BluetoothUuid.fromShort(0x1809))
.withCharacteristic(new VirtualCharacteristic(
BluetoothUuid.fromShort(0x2A1C),
GattCharacteristic.PROPERTY_READ
| GattCharacteristic.PROPERTY_INDICATE,
new byte[] {0, 0, 0, 98})
.withDescriptor(new VirtualDescriptor(
BluetoothUuid.CCCD, new byte[] {0, 0})))));
BluetoothSimulator.setLatencyMillis(50);
BluetoothSimulator.failNext("connect",
BluetoothError.CONNECTION_FAILED, "Injected for testing");73.8.1. Record and replay
Fixtures bridge the two backends: the window’s "Record from real hardware" button (or scripts/bluetooth/capture-fixture.sh) scans the host machine’s real radio through the native backend for a chosen duration, captures device identities, RSSI timelines, advertisement payloads and GATT databases, scrambles the trace deterministically so committed fixtures never carry real device identities, and writes it as JSON. BluetoothSimulator.loadFixture(InputStream) replays the trace into the virtual stack — devices appear at their recorded first-sighting times and their RSSI timelines replay on the stack’s scheduler, so a scan against messy real-world radio traffic becomes a reproducible test input.
73.9. Testing
Cross-platform test code drives the simulation through the hooks: CN.execute("bluetooth:item2") stages the demo peripheral, the test scans for SimulatedSensor, connects and subscribes to 0x2A37, and CN.execute("bluetooth:item3") pushes a notification to assert on — no simulator-only imports needed, so the same test class compiles for device targets and runs unchanged in the simulator’s test runner. Failure paths test the same way: CN.execute("bluetooth:item8") arms the next GATT read to fail with GATT_ERROR, letting a portable test verify the app’s error handling.
For fully deterministic unit tests the JavaSE port also allows constructing a private SimulatedBluetoothStack on a ManualScheduler, where time only advances when the test pumps it — no sleeps, no flakiness from real timers; see the Bluetooth tests under the javase Maven module for the pattern.
73.10. Platform behaviour
| Platform | Address semantics | MTU | Bonding | Notes |
|---|---|---|---|---|
Android | Real MAC address |
|
| Background scanning is throttled by the OS; use filtered scans and expect slower sightings |
iOS / Mac Catalyst | Per-app CoreBluetooth identifier UUID | Negotiated by the OS; | OS-managed, triggered by encrypted characteristics; | Background operation needs |
Simulator (mock) | Synthetic ( | Simulated negotiation | Simulated | Timestamps come from a monotonic counter — treat them as ordered, not as wall-clock times |
Simulator (native backend) | Host-OS device identifier | Real negotiation | Not supported | Central role only; requires the bundled |
JavaScript | Per-origin Web Bluetooth identifier | Fixed at 512 | Browser-managed | One user-picked device per chooser; |
Persist addresses only for same-install reconnection, branch on the capability queries rather than on Display.getPlatformName(), and keep every byte-stream consumer off the EDT — those three rules keep one code base working across every column of the capability matrix.
74. Health
Codename One ships a cross-platform health API under com.codename1.health that reads and writes the platform health store — HealthKit on iOS and watchOS, Health Connect on Android — summarizes data over time, watches it for changes, records workouts, and streams live measurements from standard Bluetooth health sensors.
Health.getInstance() is the single entry point and never returns null: ports without health support return a fallback whose operations fail fast with HealthError.NOT_SUPPORTED, so calling code needs no platform-specific if.
Every callback — AsyncResource results, sensor samples, workout events, change batches — is delivered on the EDT, on every platform. That includes the local-backed ports: the simulator, desktop and JavaScript stores hand results back on the EDT rather than on whichever thread called, so a read started from a worker thread can update the UI from its callback directly, with no callSerially of your own. A background change delivery may arrive with no visible UI, after the OS relaunched your app, but it’s still on the EDT.
| Capability | iOS 26+ | iOS < 26 | watchOS | Android | Simulator | Desktop / JavaScript |
|---|---|---|---|---|---|---|
Read samples and aggregates | yes | yes | yes | yes | yes (scripted) | local only |
Write samples | yes | yes | yes | yes | yes | local only |
Read-authorization introspection | no | no | no | yes | yes | n/a |
Background push delivery | no | no | no | no | no | no |
Change delivery while running | yes | yes | yes | yes | no | no |
Live workout session | recorded | recorded | recorded | recorded | recorded | recorded |
Automatic sensor collection in a workout | no | no | no | no | no | no |
Bluetooth health sensors | yes | yes | limited | yes | yes | yes |
Subscriptions are the one place the local-backed ports aren’t a
substitute for a device. subscribe() registers, persists its cursor and
restores across launches everywhere, but nothing on the local store records
a mutation as a change, so drainChanges() there resolves with zero and no
listener ever fires. Subscription code can be written and its registration
exercised on the desktop; whether it actually delivers has to be tested on
a phone.
Branch through the capability queries — Health.getAvailability(), HealthStore.isTypeSupported(…), WorkoutManager.isLiveSessionSupported(), HealthSubscription.isPushDelivery() — rather than through platform detection.
74.1. Quick start
Health health = Health.getInstance();
HealthAvailability availability = health.getAvailability();
if (availability == HealthAvailability.PROVIDER_NOT_INSTALLED
|| availability == HealthAvailability.PROVIDER_UPDATE_REQUIRED) {
health.openProviderSetup();
return;
}
if (availability == HealthAvailability.NOT_SUPPORTED) {
return;
}
HealthStore store = health.getStore();
store.requestAuthorization(
HealthAccess.read(HealthDataType.STEPS),
HealthAccess.read(HealthDataType.HEART_RATE))
.onResult((asked, err) -> {
if (err != null) {
Log.e(err);
return;
}
// asked == true means the user has now been ASKED, not that
// anything was granted. On iOS the sheet completes identically
// whether they enabled every switch or none.
});Check getAvailability() before anything else. On Android it distinguishes a working provider from one that’s missing or out of date, and both of those are recoverable by the user through openProviderSetup(). On the desktop and JavaScript ports it returns LOCAL_ONLY, meaning reads and writes work and are durable but the data is only ever your own app’s.
74.2. Permissions, and the one thing that will surprise you
You can’t ask whether you are allowed to read.
HealthKit doesn’t disclose read authorization. A read the user denied returns an empty result, indistinguishable from having no data at all, because an app that could tell the two apart could infer that a user is hiding a pregnancy or a prescription. That’s a privacy guarantee, not a gap in this API.
Three consequences follow, and all three are load-bearing:
requestAuthorization(…)resolvingtruemeans the user has been asked, not that anything was granted. On iOS the sheet completes identically whether they enabled every switch or none of them.getReadAuthorizationStatus(…)returnsUNKNOWNon iOS in every case. Android answers, because its read permissions are ordinary runtime grants; the Android port doesn’t pretend otherwise, and neither should your UI.There is no
hasReadPermission()anywhere in this API, because on iOS it would be a lie.
HealthStore store = Health.getInstance().getStore();
// Write authorization is answerable on both platforms.
HealthAuthorizationStatus write =
store.getWriteAuthorizationStatus(HealthDataType.BODY_MASS);
// Read authorization is NOT. On iOS this is always UNKNOWN, by design.
HealthAuthorizationStatus read =
store.getReadAuthorizationStatus(HealthDataType.STEPS);
if (read == HealthAuthorizationStatus.UNKNOWN) {
// The only honest probe: ask whether any data actually came back.
store.hasAnyData(HealthDataType.STEPS, HealthTimeRange.lastDays(7))
.onResult((hasData, err) -> {
if (err == null && !hasData.booleanValue()) {
// Denied OR genuinely empty -- indistinguishable.
// Say "no data available", never "you denied access".
Health.getInstance().openHealthSettings();
}
});
}hasAnyData(…) is the only honest probe, and its name says exactly what it measures. Note also that on iOS your own writes stay readable to you even when read access was denied, so a true here doesn’t prove you can see other apps' data.
Never tell a user "you denied access" on the strength of an empty result. Say "no data available," and offer openHealthSettings(). Getting this wrong produces an app that accuses users of something they didn’t do.
Request the narrowest set of types you actually need, at the moment you need them. Both stores present every requested type on one sheet, and a long list at first launch is the most common reason people decline.
74.3. Reading samples
SampleQuery query = new SampleQuery()
.addType(HealthDataType.HEART_RATE)
.setTimeRange(HealthTimeRange.lastHours(24))
.setSortDescending(true)
.setLimit(500);
Health.getInstance().getStore().readSamples(query)
.onResult((samples, err) -> {
if (err != null) {
Log.e(err);
return;
}
for (HealthSample s : samples) {
QuantitySample hr = (QuantitySample) s;
// Reading a value forces you to name the unit, which is
// what removes the whole wrong-unit class of bug.
double bpm = hr.getValue(HealthUnit.COUNT_PER_MINUTE);
Log.p(hr.getStartMillis() + ": " + bpm + " bpm");
}
});Values always come back in the type’s canonical unit unless the query asks for another, so the two ports return identical objects. Reading a number out of a HealthQuantity requires naming the unit at the call site — there is no zero-argument getValue() — which removes the entire class of bug where pounds are read as kilograms and every downstream chart is wrong by a factor of 2.2.
On Android a limit applies per data type when a query names several: Health Connect pages per record type, so a limit of ten over two types can return twenty. Query one type per call when the cap has to be exact, which is what iOS does anyway — HKSampleQuery reads one type per query.
Always set a limit for high-frequency types. A year of continuous heart rate is on the order of half a million samples; the default cap of 10,000 exists so a naive query can’t exhaust the heap, and readSamplePage(…) is there for walking more than that.
Health Connect stores a heart-rate series as one record containing many samples, while HealthKit returns many independent samples. SampleQuery.setFlattenSeries(boolean) defaults to true so both platforms hand back plain QuantitySample objects. Turn it off to keep a Health Connect record whole, which is what you want when you intend to delete it: you get one SeriesSample carrying the record identifier and every measurement in it. HealthKit has no series records at all, so iOS answers with plain samples whichever way the flag is set. Every flattened measurement still carries its record identifier, so record-level deletion works either way — and isDeletable(…) is a separate question from isWritable(…), so the series-shaped types Health Connect won’t let you write can still be deleted.
Writing a SeriesSample to a phone stores its measurements individually — neither platform accepts a series through this API — so the write result carries one identifier per measurement rather than one for the record. A series is unit-checked and converted exactly like a scalar write, and one longer than the platform’s batch limit is split across several calls. Sleep and workout samples can’t be written to HealthKit or Health Connect at all; writing one is refused with TYPE_NOT_SUPPORTED rather than reported as a success that stored nothing.
Sleep isn’t readable on either phone in this release. The iOS type map carries quantity types only, so HealthDataType.SLEEP is refused before a query runs, and SampleQuery.setSleepSessionGapMillis(long) — which configures the session reassembly that port will eventually need — changes nothing today. Android refuses it too: sleep is absent from the readable type set and the bridge has no record class for it, so a query fails with TYPE_NOT_SUPPORTED rather than returning nothing. Sleep works fully against the local and simulator stores, which is where to develop against it for now.
74.4. Aggregates and time buckets
AggregateQuery query = new AggregateQuery()
.addType(HealthDataType.STEPS)
.addMetric(AggregateMetric.TOTAL)
.setTimeRange(HealthTimeRange.calendarDays(7, ZoneId.systemDefault()))
// Calendar days, not a fixed 24 hours: a day is 23 or 25 hours
// across a daylight-saving transition.
.setBucket(HealthInterval.calendarDays(1, ZoneId.systemDefault()));
Health.getInstance().getStore().aggregate(query)
.onResult((buckets, err) -> {
if (err != null) {
Log.e(err);
return;
}
for (AggregateResult bucket : buckets) {
HealthQuantity total = bucket.get(HealthDataType.STEPS,
AggregateMetric.TOTAL);
if (total == null) {
// No data for that day. NOT the same as zero steps --
// render a gap rather than a bar at zero.
continue;
}
Log.p(bucket.getBucketStartMillis() + ": "
+ (long) total.getValue(HealthUnit.COUNT));
}
});Two rules here are easy to get wrong and hard to notice.
A bucket with no data returns null, never zero. A day on which no data was recorded and a day on which the user genuinely took no steps are different facts. Substituting zero turns an absence of data into a claim that nothing happened and draws a flat line through every day the phone stayed in a drawer.
Use calendar buckets when your UI labels them with dates. HealthInterval.calendarDays(1, tz) follows the calendar; a fixed 86_400_000 doesn’t, and drifts against the dates the user sees twice a year at each daylight-saving transition. Calendar intervals require an explicit TimeZone — nothing in this API reads the JVM default, because a server-side default of UTC would file a user’s evening walk under the wrong day.
Overlapping sources are counted twice, on every platform including iOS. When a phone and a watch both record steps for one walk, a total over them counts the walk twice. HealthKit’s statistics engine does de-duplicate overlapping sources, but no port uses it in this release — every metric is computed by shared code from raw samples, so the bucket arithmetic has one implementation rather than one per platform that can drift, and iOS double-counts exactly as Android does. This API leaves that visible rather than papering over it with a heuristic, because guessing which of two overlapping sources is authoritative is exactly the kind of quiet wrongness health data can’t afford. Use addSource(…) to pin a query to the source you trust, and tell the user which device a figure came from. |
74.5. Writing samples
QuantitySample weight = QuantitySample.create(
HealthDataType.BODY_MASS,
new HealthQuantity(178.4, HealthUnit.POUND),
System.currentTimeMillis());
weight.setRecordingMethod(RecordingMethod.MANUAL_ENTRY);
Health.getInstance().getStore().write(weight)
.onResult((result, err) -> {
if (err instanceof HealthException
&& ((HealthException) err).getError()
== HealthError.UNAUTHORIZED) {
Health.getInstance().openHealthSettings();
return;
}
if (result != null && result.hasRejections()) {
// A batch can partially succeed; surface what was dropped
// rather than discarding it silently.
for (String reason : result.getRejections()) {
Log.p("rejected: " + reason);
}
}
});Writes are validated before the platform is touched: a type this app can’t write, an instantaneous sample of a cumulative type such as STEPS, or a quantity whose unit measures the wrong dimension all fail immediately with a message naming the offending sample, rather than as an opaque platform error later. Large batches are chunked automatically to the platform’s limit.
Set RecordingMethod on what you write. Other apps use it to decide how much to trust a value, and a manually typed weight is a different kind of evidence from one a scale reported.
HealthSample.getId() is assigned by the platform, is scoped to this install, and won’t survive a reinstall, so don’t use it as a primary key on your server. Keep your own identifier in your own storage and correlate on that. getMetadata() looks like the natural home for it and isn’t: metadata round-trips through the local and simulator stores but isn’t written to HealthKit or Health Connect in this release, so on a phone the identifier is gone the moment you read the sample back.
74.6. Background delivery
SubscriptionRequest request = new SubscriptionRequest("steps-v1")
.addType(HealthDataType.STEPS)
.setIncludeDeletions(true);
HealthSubscription sub = Health.getInstance().getStore()
.subscribe(request, StepWatcher.class);
if (!sub.isPushDelivery()) {
// Android: Health Connect never wakes the app. Drain from your
// background-fetch handler instead of assuming push.
Display.getInstance().setPreferredBackgroundFetchInterval(900);
}The subscription id keys the persisted cursor that records how far you have read. Reuse it across launches and app updates and you resume exactly where you left off; change it and the framework treats it as new and resynchronizes from scratch. Hard-code it, and version it explicitly ("steps-v1") if you ever want a clean start.
No platform wakes your app for health data today. isPushDelivery() answers false everywhere, and that’s the honest answer rather than a placeholder: nothing arrives while your app is closed, so your app has to ask.
On Android this is permanent. Health Connect has no push mechanism at all and Google’s own guidance is to poll. On iOS, HealthKit does offer HKObserverQuery with background relaunch, but this release doesn’t register one, so iOS behaves the same way as Android for now. isPushDelivery() is the query to branch on; it will start answering true on iOS when observers land, and code that already polls will simply poll less often.
Draining is what delivers changes, and your app has to ask for it. Nothing here hooks the application lifecycle: call drainChanges() when you come to the foreground, and from your background-fetch handler. Omit it and a subscription delivers nothing at all, however much data arrives. This is the one place where forgetting a call looks exactly like having no new data.
The two backends drain differently, and the difference is visible to you. Android uses Health Connect change tokens, so a drain reports deletions as well as additions and never re-reports a sample you have already seen. iOS re-reads each subscribed type over the window since the last drain: additions arrive, deletions don’t, and a sample edited in place looks like a new one. Both advance their cursor only after your listener returns, so a crash re-reads rather than skips.
On iOS a subscription can miss backdated data, and there is no way around it in this release. The cursor is a timestamp, so it finds samples by when they were measured, not by when they arrived in the store. A watch that syncs an hour late, or a reading the user types in for yesterday, lands entirely behind the cursor and no later drain will ever see it. HealthKit’s own HKAnchoredObjectQuery is what solves this — it’s ordered by insertion and would fix deletions and edit-detection at the same time — and this release doesn’t use it. If your app has to be complete rather than merely current on iOS, do a full readSamples over the range you care about on a schedule of your own, and treat the subscription as a prompt to refresh rather than as the source of truth. Android is unaffected: change tokens are insertion-ordered already.
A busy window on iOS can hold more samples than one HealthKit query returns, and HealthKit offers no continuation token. When that happens the cursor advances only as far as the samples actually delivered and the batch reports hasMore(), so the next drain picks up the remainder rather than skipping it. Draining more often keeps each window small; a subscription left undrained for weeks will take several drains to catch up.
Handle isResyncRequired(). A Health Connect change token expires after 30 days and an iOS anchor can be rejected after a restore from backup; when that happens the batch carries no data and you must do a full time-range read to catch up.
A HealthBackgroundListener must be a public top-level class with a public no-argument constructor. Unlike some older callback APIs in this framework there is no need to do anything to keep it from being stripped: the build server scans for implementations and generates a factory that constructs each one with a direct new, so shrinking and obfuscation both follow the reference correctly.
74.7. Workouts
WorkoutManager workouts = Health.getInstance().getWorkouts();
workouts.startSession(new WorkoutConfiguration()
.setActivityType(WorkoutActivityType.RUNNING)
.setLocationType(WorkoutLocationType.OUTDOOR))
.onResult((session, err) -> {
if (err != null) {
Log.e(err);
return;
}
if (!session.isLive()) {
// Android phones and iOS before 26: the clock and the saved
// record are real, but nothing is collected unless you feed
// it -- from a sensor, from location, or by hand.
Log.p("Recording; connect a strap for heart rate");
}
session.start();
});Two capabilities that are easy to conflate and that this API keeps separate:
isLiveSessionSupported()— the OS runs a real session and keeps the app alive. False everywhere in this release.HKWorkoutSessionexists on watchOS and on iOS 26 and later, andandroidx.health.servicesexists on Wear OS, but neither is wired up yet, so every platform currently uses the recorded session described below. Branch on this query rather than on the OS version and your code will pick up native sessions when they land.isSensorCollectionSupported()— the OS also gathers heart rate and energy into that session by itself. False everywhere in this release, for the same reason: the live session is what collects, and there isn’t one yet.
The second being false everywhere today, a workout records only what you feed it. On an Android phone that isn’t a degraded fallback: Health Connect has no live-session concept, and inserting a session, batching your own data and updating it at the end is precisely the flow Google documents. Feed it with addSamples(…), or by attaching a Bluetooth sensor.
getStatistic(…) returns null rather than a fabricated zero when nothing has been collected. Sessions aren’t restored after the process dies — a killed workout is over, end() was never called, and nothing is written.
Ending a workout tells you what the platform would not keep. WorkoutSample.WORKOUT_NOT_PERSISTED is set when the session record itself has no write form — neither mobile platform accepts one through this API — and WorkoutSample.SAMPLES_NOT_PERSISTED names the data types whose samples were refused, comma separated. Power, speed and both cadences are the ones that bite: they’re exactly what a bike or foot pod feeds in, and Health Connect has no single-value write form for any of them. Check both and upload what matters to you; the workout object itself is complete either way.
74.8. Bluetooth health sensors
HealthSensors sensors = Health.getInstance().getSensors();
if (!sensors.isSupported()) {
return;
}
SensorScanSettings settings = new SensorScanSettings()
.addProfile(HealthSensorProfile.HEART_RATE)
.setTimeoutMillis(15000);
sensors.startScan(settings, new SensorDiscoveryListener() {
public void sensorDiscovered(HealthSensor sensor) {
sensors.connect(sensor, HealthSensorProfile.HEART_RATE,
new SensorSessionOptions().setAutoReconnect(true))
.onResult((session, err) -> {
if (err != null) {
return;
}
session.addListener(new SensorSampleListener() {
public void sensorSample(SensorSession s,
HealthSample sample) {
Log.p("bpm: " + ((QuantitySample) sample)
.getValue(HealthUnit.COUNT_PER_MINUTE));
}
public void sensorStateChanged(SensorSession s,
SensorSessionState state) { }
public void sensorError(SensorSession s,
HealthException e) { }
});
});
}
public void scanFailed(HealthException e) {
Log.e(e);
}
});com.codename1.health.sensors covers the adopted Bluetooth SIG profiles — Heart Rate, Cycling Power, Cycling and Running Speed & Cadence, Health Thermometer, Weight Scale, Blood Pressure and Glucose — so any conforming device works without per-vendor code.
This layer is built entirely on com.codename1.bluetooth.le and needs no platform health store, so it works identically everywhere Bluetooth LE does, including the desktop and JavaScript ports where no health store exists at all. It needs Bluetooth permissions, not health ones, and the build server makes the same distinction: an app that uses only this package isn’t treated as a health-data app and gets neither a HealthKit entitlement nor a Google Play health-permissions review.
Speed and cadence sensors transmit cumulative counters rather than rates, with counters and event timers that wrap every 32 or 64 seconds. The framework differences them for you; hand-rolling that arithmetic is the most commonly botched part of these profiles.
SensorSessionOptions.setWriteToStore(…) defaults to false on purpose. When the OS is recording heart rate into HealthKit during a workout, a strap that also writes its own samples double-counts in every downstream average. Attach the session to the workout with setWorkoutSession(…) instead; turn write-through on for standalone measurements the OS knows nothing about, such as a weight from a scale.
A heart-rate session reports the rate. RR intervals are decoded by HeartRateMeasurement but aren’t delivered as samples — they’re the input to an HRV calculation, not a measurement of it, and no platform has a data type that would store them. If you need HRV, subscribe to characteristic 0x2A37 through com.codename1.bluetooth.le and call HeartRateMeasurement.parse(…) on the raw value yourself; both are public API.
Blood pressure is the exception: it’s two values in one reading, which HealthKit models as a correlation and Health Connect as its own record type, and neither is implemented in this release. A cuff reading routed to the store fails with TYPE_NOT_SUPPORTED on both phones rather than being dropped without a word; the local and simulator stores keep it fine. Read it off the session and persist it yourself for now.
74.9. Nutrition
com.codename1.health.nutrition logs food and drink as a sparse set of nutrient amounts. A logged apple sets four fields and a scanned packaged food might set thirty; both platforms model this as a record with several dozen optional fields, and NutritionSample keeps that sparseness explicit rather than exposing forty nullable getters. A nutrient that was never measured reads back as null, not zero — the same distinction aggregate buckets make, and one that matters to someone managing their sodium.
HealthDataType.NUTRITION is local and simulator only in this release. Neither the wire format nor either port’s type map knows the multi-nutrient record shape, so a read or write of it on a phone is refused with TYPE_NOT_SUPPORTED before it reaches the platform rather than being dropped without a word. Individual dietary quantities do reach the phones as ordinary quantity samples — HYDRATION on both, DIETARY_ENERGY on iOS — so use those when the number has to land in the user’s real health store.
74.10. Build configuration
Health data is the most regulated data these APIs touch, and the build is strict about it.
| Hint | Effect |
|---|---|
| Why your app reads health data. Required if you touch the store; the build fails without it. |
| Why your app writes health data. Required if you write. |
| Adds the background-delivery entitlement. Inferred from observer usage. |
| Adds the estimate-recalibration entitlement. |
| Adds |
| Hint | Effect |
|---|---|
| Comma-separated data types to read. Required. |
| Comma-separated data types to write. |
| Adds |
| Adds |
| Your privacy policy. Required. |
| Overrides the Health Connect client version. |
Codename One doesn’t inject a placeholder privacy string for health, unlike camera or Bluetooth. Apple reviews health purpose strings against what the app actually does, so a generic placeholder is precisely what gets an app rejected — it would not even achieve the "keeps the build working" goal. The build fails with a message naming the hint instead.
The Android data types can’t be inferred. A data type is referenced as a constant, which compiles to a field read, and the build server’s class scanner records only type and method references — so the permission set genuinely can’t be derived from your bytecode. Declaring it explicitly also matches Google Play policy, which requires you to request exactly what you use. Health Connect additionally raises minSdkVersion to 26 and requires targetSdkVersion 30 or higher.
HealthKit is entitlement-gated, unlike CoreBluetooth. The com.apple.developer.healthkit capability must be enabled for your App ID and present in the provisioning profile you build with, or the build fails at code-signing. |
An app that only uses Health.getSensors() needs none of this. The sensor
layer is built on com.codename1.bluetooth.le and touches no HealthKit, so
the build injects neither the framework nor the entitlement nor the usage
strings, and none of the hints above apply — it needs
ios.NSBluetoothAlwaysUsageDescription instead. Reaching for the store is
what pulls HealthKit in, and it’s getStore() rather than
Health.getInstance() that reports a missing usage string, so the
sensor-only path stays clear of the whole apparatus.
74.11. Privacy and store policy
Read this section before shipping. Both stores enforce policies that go well beyond the technical permissions.
Apple. HealthKit data may not be used for advertising or use-based data mining beyond health, fitness and medical research, and may not be shared with third parties without explicit consent for that specific sharing. A privacy policy URL in App Store Connect is mandatory — HealthKit apps are rejected without one. HealthKit data may not be stored in iCloud. Purpose strings must be specific: "Reads your step count to show weekly activity trends," not "Needs health access."
Google. Health Connect access is gated by the Play Console health apps declaration form, and each permission is approved individually. Your app must implement a privacy-policy activity that’s shown before the permission dialog — Codename One declares it for you, and this isn’t optional: Health Connect declines to show its consent dialog to an app that lacks one. Play’s Health Apps policy prohibits using the data for ads, for credit, insurance or employment decisions, or transferring it to a data broker.
What Codename One itself does. The framework never uploads health data anywhere. The simulator’s event log records data types and counts but never sample values. And the build fails rather than inventing a purpose string on your behalf.
Practical rules. Request the narrowest type set, at the moment of use rather than at launch. Never persist samples to unencrypted Storage. Treat the on-device store as the source of truth and avoid server round-trips. Delete health data on account deletion.
Finally, the read-authorization asymmetry is a privacy feature, not an obstacle. iOS hides read denial so that an app can’t infer what a user is concealing. Design your UI to respect that.
74.12. Simulating health
The simulator ships a scriptable health store under Simulate → Health, and every action is also callable from a test with CN.execute("health:itemN").
| Action | Effect |
|---|---|
Grant / Deny All Permissions | The permissive and fully denied cases |
Grant Write, Deny Read Without Error | Reproduces the iOS trap exactly |
Load Demo Dataset (7 days) | Synthetic steps, heart rate, sleep and weight |
Emulate HealthKit / Health Connect Permissions | Switches read-denial behaviour |
Make Health Unavailable | Emulates a missing provider |
| Arm a one-shot query or save failure |
Click "Grant Write, Deny Read Without Error" before you ship. It’s the default-adjacent case real users will produce and the one a permissive store never shows you: authorization appears to succeed, the status reads UNKNOWN, and every query comes back empty with no error. If your UI shows an error or accuses the user of denying access, it’s wrong.
The simulator’s data is synthetic and seeded, not recorded from anyone. That’s intentional: unlike Bluetooth traces, where the sensitive parts are identifiers that can be scrubbed, the sensitive part of a health sample is the value being asserted on, and a resting heart rate together with sleep timing and step cadence is quasi-identifying.
74.13. Troubleshooting
A query returns empty even though permission was granted. On iOS you can’t distinguish a denied read from an empty store — this is by design. Use hasAnyData(…), show "no data available," rather than an error, and offer openHealthSettings(). Reproduce it in the simulator with "Grant Write, Deny Read Without Error."
The chart shows zero for days the user was active. You are substituting zero for a null aggregate. An empty bucket means no data, not no steps.
Totals are double. A phone and a watch are both writing the same type, on iOS as much as on Android — aggregation runs on raw samples in shared code, so HealthKit’s de-duplicating statistics engine never sees the query. Pin it with addSource(…).
Background delivery never fires. No platform pushes health data to a closed app in this release — see the subscriptions section. Call drainChanges() from your background-fetch handler and branch on isPushDelivery() rather than assuming.
Replaying stored glucose records isn’t implemented. SensorSession.requestStoredRecords(…) always fails with NOT_SUPPORTED in this release. Replay runs over the Record Access Control Point — a stateful protocol on a second characteristic — and shipping it untested against real meters would be worse than saying so. Live glucose notifications work normally.
Sample metadata doesn’t reach the phone’s health store. HealthSample.getMetadata() round-trips locally — the simulator, desktop and JavaScript store — but isn’t persisted to HealthKit or Health Connect in this release, so a sample written and read back on a device returns without it. Health Connect has no arbitrary metadata at all, only a single client record id. Keep your correlation identifier in your own storage.
Recorded workouts aren’t kept alive on Android. The manifest declares no foreground service, so a recorded workout lives exactly as long as your process does. If you need one to survive backgrounding, keep the app alive yourself.
BODY_MASS_INDEX is rejected on Android. Health Connect has no BMI permission or record — BMI is derived, not stored — so the build fails rather than requesting an unrelated body-composition permission on your behalf. Read BODY_MASS and HEIGHT and compute it. HealthKit does store BMI, so iOS is unaffected.
Deleting a sample by id does nothing. Health Connect deletes by record class plus id, so HealthDeleteRequest.byId(…) takes the data type alongside the identifier. Naming the wrong type deletes nothing and still reports success.
The weekly chart is off by a day twice a year. You are bucketing by a fixed 24 hours across a daylight-saving transition. Use HealthInterval.calendarDays(1, tz).
The iOS build fails complaining about a usage description. That’s intentional — add ios.NSHealthShareUsageDescription with text describing what your app actually does with the data.
The Health Connect permission dialog never appears. Health Connect requires the permissions-rationale activity, which Codename One declares only when it detects health usage. Check that the build log mentions the health manifest fragments.
75. Smart Home
Codename One ships a cross-platform smart-home API under com.codename1.home that reads the accessories in a user’s home, reads and writes what they can do, watches them for change, runs scenes, and adds new Matter accessories.
SmartHome.getInstance() is the single entry point and never returns null: ports without smart-home support return a fallback whose operations fail fast with HomeError.NOT_SUPPORTED and whose graph accessors return empty lists, so calling code needs no platform-specific if.
Every callback — AsyncResource results, change batches, structure events — is delivered on the EDT, on every platform. That includes the desktop, the simulator and the JavaScript port, which marshal rather than answering on whichever thread called, so a read started from a worker thread can update the UI from its callback directly.
75.1. The model
A HomeStructure holds rooms (HomeRoom) and accessories (Accessory). An accessory has one or more services (AccessoryService) — a two-gang wall switch is one accessory with two services — and a service exposes traits (Trait).
A trait is a canonical capability, not a platform identifier. Trait.BRIGHTNESS is the same constant whether the accessory is behind HomeKit or Matter, and the port maps it to HMCharacteristicTypeBrightness or to Level Control’s CurrentLevel for you. No HomeKit characteristic string and no Matter cluster id ever reaches your code.
Graph objects are immutable snapshots. Nothing on an Accessory calls into the platform when you read a getter; when the topology moves, a HomeStructureListener tells you to call refresh() and read the graph again once it completes.
| Capability | iOS / iPadOS | watchOS / tvOS | Android (default) | Android (Home APIs) | Simulator / desktop |
|---|---|---|---|---|---|
Read the accessory graph | yes | yes | no | yes | yes (synthetic) |
Read and write traits | yes | yes | no | yes | yes |
Run scenes | yes | yes | no | yes | yes |
Create scenes | yes | yes | no | varies | yes |
Live change delivery | yes (foreground) | yes (foreground) | no | no | no |
Add a Matter accessory | yes | no | yes | yes | yes (synthetic) |
Zones | yes | yes | no | no | no |
Automations and triggers | no | no | no | no | no |
Branch through the capability queries — SmartHome.getAvailability(), AccessoryService.supports(…), TraitSubscription.isPushDelivery(), Commissioner.isSupported() — rather than through platform detection.
75.2. Quick start
SmartHome home = SmartHome.getInstance();
HomeAvailability availability = home.getAvailability();
if (availability == HomeAvailability.PROVIDER_NOT_INSTALLED
|| availability == HomeAvailability.PROVIDER_UPDATE_REQUIRED) {
home.openProviderSetup();
return;
}
if (availability == HomeAvailability.NOT_CONFIGURED) {
// Authorized, and the user has never set up a home. Sending them
// to the ecosystem app is the only way forward.
home.openEcosystemApp();
return;
}
if (availability == HomeAvailability.COMMISSIONING_ONLY) {
// The ordinary Android answer: accessories can be ADDED and not
// read. Say so rather than rendering an empty house.
Log.p("smart home is add-only on this build");
}
home.refresh().onResult((structures, err) -> {
if (err != null) {
Log.e(err);
return;
}
HomeStructure h = home.getPrimaryStructure();
if (h == null) {
return;
}
for (Accessory a : h.getAccessoriesSupporting(Trait.ON_OFF)) {
cnt.add(new Label(a.getName()));
}
});Check getAvailability() before anything else. Several of its states are recoverable by the user, and the recovery differs: sending someone to Google Play for a provider update when what they need is to open the Home app helps nobody.
75.3. Android’s default answer isn’t "available"
This is the one thing worth understanding before you design a screen.
With no extra setup, an Android app can commission a Matter accessory into the user’s Google Home and can do nothing else. The graph is empty and no trait can be read or written. getAvailability() reports COMMISSIONING_ONLY, and that state exists so the word AVAILABLE doesn’t mean something different on Android than it does on iOS.
Reading and controlling accessories on Android needs the Google Home APIs, which need a Google Cloud project and a Google Home Developer Console registration carrying the SHA-1 of your own signing key. Codename One can’t create those on your behalf. That integration isn’t in this release; commissioning is.
SmartHome.getConfigurationProblems() explains the gap in text aimed at you rather than at your user — log it or show it in a debug screen, and don’t put it in front of somebody holding a phone.
75.4. Reading and writing
A read returns one TraitReading per requested trait, and a partial success is the normal case: three values and one unreachable accessory is a successful read with one failed row, not a failed operation.
TraitReadRequest request = new TraitReadRequest()
.add(thermostat, thermostatService, Trait.CURRENT_TEMPERATURE)
.add(thermostat, thermostatService, Trait.CURRENT_HUMIDITY);
SmartHome.getInstance().read(request).onResult((readings, err) -> {
if (err != null) {
Log.e(err);
return;
}
for (TraitReading reading : readings) {
if (reading.isFailed()) {
label.setText("unavailable");
} else if (!reading.hasValue()) {
// Not an error, and not zero: the accessory has nothing to
// report yet. Rendering this as 0 degrees is the bug this
// check exists to prevent.
label.setText("no reading yet");
} else if (reading.getTrait() == Trait.CURRENT_TEMPERATURE) {
label.setText(reading.getValue()
.getDouble(TraitUnit.CELSIUS) + " C");
}
}
});Note the three-way branch. A reading can carry a value, carry an error, or carry neither — and the third is the one that catches people. An accessory can legitimately have nothing to report: a sensor that hasn’t measured yet, a light in white mode that has no meaningful hue. Nothing in this API substitutes a zero for a measurement that was never taken, so hasValue() has to be asked.
Writing is the mirror image, and a batch write partly succeeding is equally normal — "turn off every light" against a home with one dead bulb mostly worked.
AccessoryService svc = lamp.getPrimaryService();
TraitConstraint dimming = svc.getConstraint(Trait.BRIGHTNESS);
// The accessory's own range, not the trait's nominal 0..100. A slider
// built from the wrong one offers values the lamp refuses -- and a
// refused write is an error rather than a silent clamp.
Slider slider = new Slider();
slider.setMinValue((int) dimming.getMinimum());
slider.setMaxValue((int) dimming.getMaximum());
SmartHome.getInstance()
.write(new TraitWrite(lamp, svc, Trait.BRIGHTNESS,
TraitValue.of(slider.getProgress(), TraitUnit.PERCENT)))
.onResult((result, err) -> {
if (err != null) {
Log.e(err);
} else if (!result.isApplied()) {
Log.p("the lamp refused: " + result.getError());
}
});Build controls from the accessory’s own TraitConstraint rather than from the trait’s nominal range. A dimmer whose floor is 10 percent says so there, and writing below the floor is refused rather than clamped: an app that asked for 5 percent and got 10 percent without being told never learns it was wrong.
75.5. Values and units
TraitValue is one type with kind-checked getters rather than a class per trait. There’s no zero-argument getDouble() on purpose: getDouble(TraitUnit) makes you name the unit you expect and refuses a cross-dimension request, which is what stops a Celsius setpoint being rendered as Fahrenheit.
Everything proportional is normalized to a percentage, so Matter’s 0-254 level control and 0-10000 covering position never reach your code. Color temperature is in mireds, because that’s what both platforms use natively — and remember that a higher mired value is a warmer light. TraitValue.getColorTemperatureKelvin() converts if you would rather think in Kelvin.
Where a mapping is lossy, TraitValue.getRawPlatformValue() carries the platform’s own ordinal alongside the canonical one. Air quality has six levels on HomeKit and seven on Matter; the canonical enum follows Matter and the raw value is there for an app that needs to be exact.
75.6. Watching for change
Nothing wakes your app for an accessory change. HomeKit delivers changes only while your app is running in the foreground, and the Google Home APIs need a live signed-in client — the home hub, not your app, is what reacts to a sensor while the phone is asleep.
TraitReadRequest resync = new TraitReadRequest()
.add(lamp, lamp.getPrimaryService(), Trait.ON_OFF)
.add(lamp, lamp.getPrimaryService(), Trait.BRIGHTNESS);
SubscriptionRequest request = new SubscriptionRequest()
.add(lamp, lamp.getPrimaryService(), Trait.ON_OFF)
.add(lamp, lamp.getPrimaryService(), Trait.BRIGHTNESS)
.setDeliverInitialValues(true);
TraitSubscription subscription = SmartHome.getInstance()
.subscribe(request, batch -> {
if (batch.isResyncRequired()) {
// Changes were missed, so everything not in this batch
// is stale. Ignoring this leaves a screen showing
// values from before the gap, indefinitely.
SmartHome.getInstance().read(resync);
}
for (TraitReading reading : batch.getReadings()) {
label.setText(String.valueOf(reading.getValue()));
}
});
if (!subscription.isPushDelivery()) {
// Everywhere except HomeKit in the foreground. Without a drain the
// listener never fires, which looks exactly like a sensor that
// never triggers.
SmartHome.getInstance().drainChanges();
}Ask isPushDelivery() rather than assuming. Where it answers false, which is everywhere except HomeKit in the foreground, the listener fires only when you call drainChanges(). Wire that into the point where your app comes to the foreground.
Within a subscription’s window, changes are coalesced per accessory, service and trait, keeping only the newest value — so dragging a dimmer produces one reading showing where it ended up rather than forty showing the journey. A batch is a state update, not an event log.
Hold on to the TraitSubscription and stop it. A dropped one keeps its listener reachable and keeps the platform delivering.
75.7. Scenes
A scene is a named set of accessory states that can be applied in one go: HomeKit’s action set, a Google Home scene. TraitWrite.toSceneAction() turns the changes a user just made into one.
Automations — a scene plus a trigger — aren’t supported. HomeKit, Google Home and Matter model triggers in three incompatible ways and Matter has none, so there’s no honest common shape. SmartHome.isAutomationSupported() answers false everywhere, so an app can say why the feature it wanted isn’t offered.
75.8. Adding an accessory
Commissioner commissioner = SmartHome.getInstance().getCommissioner();
if (!commissioner.isSupported()) {
commissioner.openEcosystemApp();
return;
}
// Validated here, in your own words, rather than failing inside the
// operating system's sheet with wording about the app.
SetupPayload payload;
try {
payload = SetupPayload.parse(scannedCode);
} catch (IllegalArgumentException badCode) {
label.setText(badCode.getMessage());
return;
}
commissioner.commission(new CommissioningRequest()
.setSetupPayload(payload)
.setSuggestedName("Kettle"))
.onResult((result, err) -> {
if (err != null) {
Log.e(err);
return;
}
if (result.wasCommissionedToThisApp()) {
SmartHome.getInstance().refresh();
} else {
// Added to the user's home, and this app cannot
// address it. Say that, rather than showing an empty
// device screen.
label.setText("Added " + result.getAccessoryName()
+ " to your home");
}
});Two things about this flow.
The interaction isn’t yours. Both mobile backends hand it to an operating-system sheet, and the user may be several minutes — they have to power the accessory on, hold a button, sometimes join it to Wi-Fi. There’s no progress reporting. Don’t put a short timeout or a determinate progress bar behind it.
Success doesn’t always mean you got a device. wasCommissionedToThisApp() is the difference between "the accessory was added to the user’s home" and "your app can address it." On Android with Play services alone the answer is the former: you’re told the name and nothing more. On iOS it’s the former too — Apple’s sheet reports that the flow finished without saying what was added or which home it went to — so refresh the graph and look at what’s new. An app that assumes otherwise shows a "your new device" screen with nothing on it.
SetupPayload.parse() validates a scanned QR or typed manual code in pure Java before any of that starts, so a mis-scanned sticker gets a message in your wording rather than an opaque failure inside the OS sheet.
75.9. Build hints
# iOS: required as soon as your app touches accessories. The build FAILS
# without it, deliberately -- iOS terminates an app that reaches HomeKit with
# no usage description, and Codename One will not invent privacy copy in your
# name.
codename1.arg.ios.NSHomeKitUsageDescription=Controls the lights and locks in your home
# Optional. Opt out of the generated Matter add-device extension target.
codename1.arg.ios.home.commissioning=false
# Optional. The app group the extension and the app share; defaults to
# group.<your.package.name>.
codename1.arg.ios.home.appGroup=group.com.example.myapp
# Optional. Refuse to install on a device without HomeKit.
codename1.arg.ios.home.required=trueEverything else is automatic, and automatic in both directions: an app that never references com.codename1.home gets no HomeKit framework, no entitlement, no Play services dependency and no extra Xcode target. The build server decides by scanning your bytecode.
Two consequences worth knowing:
The
com.apple.developer.homekitentitlement is added only when your app actually touches accessories. An app that only callsgetAvailability()links HomeKit and gets no entitlement — which matters, because that entitlement has to be enabled on your App ID and signing without it fails. If your app does touch accessories, enable HomeKit for your App ID in the Apple developer console and regenerate your provisioning profile; the build checks and tells you if you haven’t.Commissioning is separated because on iOS it costs an entire generated app-extension target. That’s why
com.codename1.home.commissioningis its own package: referencing the package is what asks for the extension.
75.10. Previewing in the simulator
The simulator, the desktop ports and the JavaScript port run a local simulated house rather than reporting themselves unsupported. It’s awkward rather than tidy on purpose — a two-gang switch, a bridged pair of lights behind a hub, an unreachable socket, a thermostat in auto mode where TARGET_TEMPERATURE genuinely has no value, and a dimmer with a real floor — because those are the shapes that break naive code.
It also doesn’t push changes and never completes an operation inline, matching what a real backend does. Code written against a store that answers instantly races the moment it meets one that doesn’t.
75.11. Not claimed in this release
Stated plainly, because each of these has a query that answers rather than a silence:
Automations, triggers and conditions. Scenes only.
Background accessory events. Nothing wakes your app; see
isPushDelivery().Topology writes. Creating homes, renaming rooms, moving accessories between rooms, inviting users. The graph is read-only.
Cameras and video. A camera is visible in the graph and there’s no stream, snapshot or recording API.
Security systems and alarm panels. Matter has none in shipping releases, and a half-working alarm API is a safety problem rather than a feature gap.
Matter events. Only attributes, which is why
LockState.JAMMEDis unreachable outside HomeKit — a jam is an event on Matter and an attribute on HomeKit.Energy, appliance and diagnostic clusters.
The Google Home APIs accessory graph on Android. See above.
And one structural point: by default Codename One isn’t a Matter controller. There’s no fabric of its own, no direct on-network commissioning and no Thread border-router interaction. Everything Matter goes through the operating system’s ecosystem, so the Apple Home or Google Home app has to be installed and set up.
75.12. Commissioning onto your own fabric
CommissioningRequest.setCommissionToThisApp(true) asks for one thing more: that the accessory also join a Matter fabric your app owns, as a second administrator beside the user’s home. On iOS the generated commissioning extension then carries Apple’s own Matter stack, a fabric key it keeps in the keychain and the controller storage that fabric persists through — so the build sees the call and switches that machinery on. Set codename1.arg.ios.home.commissioning.fabric=true if your call is somewhere the class scanner can’t see, such as behind reflection, and codename1.arg.ios.home.commissioning.vendorId to your own Matter vendor id — the default is the test vendor 0xFFF1, which some accessories refuse.
Apple’s Matter framework starts at iOS 16.4, so an own-fabric extension is built for 16.4 while your app keeps the 16.1 floor MatterSupport asks for. On 16.1 through 16.3 the extension can’t load, and Commissioner.getStyle() answers ECOSYSTEM_APP_HANDOFF there rather than OS_OWNED_UI — the accessory is added in the Home app, exactly as in a build with no extension. Ask for the style before you offer the button and that difference is invisible to your user.
Read the generated CN1MatterSetup/RequestHandler.swift before you turn it on. The implementation ships in every commissioning build, commented out, precisely so that what you enable is code you have read.
What it doesn’t buy you is a way to talk to the accessory over that fabric: Codename One has no API for that yet, and reads and writes still go through the ecosystem. What it buys is that the accessory is already commissioned when such an API arrives, and that CommissioningResult.wasCommissionedToThisApp() can be true. Android’s Play Services commissioning can’t do it at all, and ignores the request.
76. Printing
Codename One can hand a document to the platform printing system through the com.codename1.printing package. The API shows the native print dialog where the user picks a printer, adjusts options and confirms the job. It works on iOS (AirPrint), Android, desktop builds, the simulator, Windows and the JavaScript port.
The document is a file in FileSystemStorage identified by its path and mime type. Every printing platform accepts PDF (application/pdf) and common image types (image/png, image/jpeg).
76.1. Quick start: Print a PDF
Printer.printPDF(path, listener) is shorthand for Printer.print(path, "application/pdf", listener). Use the general print variant for other document types, for example Printer.print(photoPath, "image/jpeg", listener).
Gate the call on isPrintingSupported(). When it returns false the listener receives a FAILED result without any UI appearing, so an unguarded call does no harm, but a well-behaved app hides or disables its print button instead.
76.2. Printing images
Printer.printImage(image, listener) prints a com.codename1.ui.Image directly. The image is encoded to a temporary PNG file behind the scenes and the file is deleted once the print flow finishes:
This pairs well with drawing on a mutable image, so you can compose a printable page (a receipt, a ticket, a chart) with the standard Graphics API and send it to paper without generating a PDF.
76.3. Handling the result
The listener receives a PrintResult on the EDT, exactly once per request. The listener may be null for fire-and-forget printing. There are three statuses:
COMPLETED– the job was handed to the platform printing system. Most platforms can’t observe the physical printer, so this means "queued/sent," not "paper came out."CANCELLED– the user dismissed the print dialog without printing, on platforms that can observe the dialog outcome.FAILED– the job couldn’t start or the printing system reported an error.getError()may carry a short platform message.
Cancel detection is best-effort. iOS, Windows, PDF printing on Android and image printing in the simulator report CANCELLED reliably. Image printing on Android, PDF hand-off on the desktop and the browsers report COMPLETED once the job is posed, since their printing pipelines don’t expose the user’s choice.
76.4. Permissions and the user gate
Printing requires no permission, entitlement, manifest entry or build hint on any platform. This is safe because printing is always user-confirmed: the API can only pose the native print dialog, and nothing reaches a printer until the user approves the job there. In that sense it follows the same trust model as the share API.
Silent printing - sending a job to a preselected printer without showing a dialog - isn’t supported by design.
Device policy can disable printing entirely, for example a managed Android work profile with the printing restriction or an iOS MDM profile that blocks AirPrint. Those cases surface as isPrintingSupported() returning false or as a FAILED result, so the result-handling code above covers them.
76.5. Platform notes
iOS –
UIPrintInteractionControllerpresents the AirPrint sheet; on the iPad it appears as a popover. The completion handler reports completed, cancelled or failed.Android – the
android.printframework. PDFs stream through aPrintDocumentAdapter; images go through the support libraryPrintHelper, which reports completion but can’t observe cancellation. Printing requires a foreground activity, so calls from background mode fail.Desktop / simulator – images print through
java.awt.print.PrinterJobwith the native dialog; PDFs are handed to the operating system’s default PDF print flow.Windows (native port) – the Win32 print dialog with GDI rendering; PDF pages render through the
Windows.Data.PdfAPI at the printer’s resolution.JavaScript – the document loads into a hidden frame and prints through the browser’s print dialog. Browsers don’t report whether the user printed or cancelled, and PDF behavior varies with the browser’s built-in viewer.
76.6. Trying it in the simulator
The PrinterSample in the samples project demonstrates both flows: it prints a generated image and downloads a small PDF to print. On the desktop the native print dialog of your operating system appears, which makes it a convenient way to test result handling - print to a file or preview instead of paper.
77. Deeper Network Connectivity
Codename One ships a set of APIs under com.codename1.io.wifi, com.codename1.io.bonjour, com.codename1.io.usb and an extension of com.codename1.io.NetworkManager that lets apps inspect and manage the device’s local network beyond plain HTTP.
A quick connectivity check is NetworkManager.getInstance().isConnected() — it reads the cached platform network state and returns immediately without an HTTP probe, so it’s safe to call from the EDT before deciding whether to fire a ConnectionRequest.
These APIs share three guarantees:
Every callback runs on the EDT so you can update UI directly from the result.
The build pipeline injects the matching Android permissions, iOS entitlements, and
NSXxxUsageDescription/NSBonjourServicesInfo.plist entries automatically by scanning the classpath. Apps that never reference these classes see no manifest or entitlement changes.The simulator implements best-effort versions of each API so you can wire and test your UI without a device. The simulator also prints the list of permissions/entitlements each API will need in a real build the first time you call it.
The simulator’s "API usage report" prints to stdout on JVM shutdown so you can spot anything you pulled in via a transitive cn1lib.
77.1. WiFi information
The fastest way to know whether the user is on WiFi, what SSID they joined, and what their local IP is:
if (WiFi.isInfoSupported()) {
String ssid = WiFi.getCurrentSSID(); // e.g. "Codename One"
String bssid = WiFi.getBSSID(); // "aa:bb:cc:11:22:33"
String gw = WiFi.getGateway(); // "192.168.1.1"
String ip = WiFi.getIp(); // "192.168.1.42"
}Any of these calls may return null if the device isn’t on WiFi, if the user denied a runtime permission, or if the platform never exposed the value to apps. The framework normalizes the wrapping that Android adds to the SSID and treats <unknown ssid> and the obfuscated BSSID 02:00:00:00:00:00 as null.
77.1.1. Required permissions and entitlements
The build pipeline injects the following automatically the first time it sees com.codename1.io.wifi.WiFi on the classpath:
| Platform | Injected | Notes |
|---|---|---|
Android |
| "normal" permissions; no runtime prompt |
Android API 26+ |
| Required by the OS to return a real SSID |
Android API 33+ |
| Replaces fine-location for scan flows |
iOS |
| Required since iOS 13 |
iOS |
| iOS still checks CoreLocation behind the scenes |
You can override any injected automatically value via the standard build hints:
ios.locationUsageDescription=Allow access to read your Wi-Fi network name to discover printers on your network.
android.xpermissions=<uses-permission android:name="android.permission.ACCESS_FINE_LOCATION" />77.2. WiFi scan
Scanning returns an array of `WiFiNetwork`s sorted by signal strength. The callback fires once.
iOS doesn’t expose a public WiFi scan API. On iOS |
Android throttles scans to 4 per 2 minutes per foreground app on API 28+; throttled scans return cached results, not an error.
77.3. WiFi connect
To associate the device with a specific SSID:
On Android 10+ the OS shows a system confirmation dialog with the SSID before joining; this dialog can’t be bypassed.
On Android 9 and below the framework falls back to the legacy
WifiConfigurationAPI and joins without an in-app prompt.On iOS 11+ this uses
NEHotspotConfiguration. The user is shown a system prompt the first time the app tries to join the SSID; subsequent attempts reuse the cached configuration.WiFiSecuritymust match the AP’s actual security mode (OPEN,WEP,WPA_PSK,WPA3_SAE). Passing the wrong mode causes the join to fail.
WiFi.disconnect(ssid) releases the request on Android 10+ and removes the hotspot configuration on iOS.
On iOS the build pipeline also enables the |
77.4. Bonjour / mDNS discovery
BonjourBrowser watches the local network for services of a given mDNS type. BonjourPublisher advertises a service.
BonjourBrowser browser = BonjourBrowser.browse("_http._tcp.",
new BonjourServiceListener() {
@Override
public void onServiceResolved(BonjourService s) {
Log.p("Found " + s.getName() + " at " + s.getHost() + ":" + s.getPort());
}
@Override
public void onServiceLost(BonjourService s) { /* null */ }
@Override
public void onBrowseError(Throwable t) { Log.e(t); }
});
// when done:
browser.stop();To advertise an HTTP server you wrote on port 8080:
77.4.1. iOS requirements
Bonjour on iOS 14+ returns no results unless:
The Info.plist
NSLocalNetworkUsageDescriptionkey explains why the app needs local-network access.The Info.plist
NSBonjourServicesarray lists each service type the app expects to find.
The build pipeline injects both keys automatically when com.codename1.io.bonjour is on the classpath, with _http._tcp. as the seed type. To publish or browse a custom type, set the build hint:
ios.NSBonjourServices=_myapp._tcp.,_http._tcp.
ios.NSLocalNetworkUsageDescription=Discover other instances of MyApp on this Wi-Fi network.The comma-separated values are expanded into the Info.plist array at build time.
77.4.2. Android requirements
The pipeline adds CHANGE_WIFI_MULTICAST_STATE automatically. NsdManager does the rest; there is no runtime permission prompt.
77.4.3. Simulator behaviour
If javax.jmdns.JmDNS is on the simulator classpath, browse calls dispatch through it. Otherwise the listener receives a single UnsupportedOperationException and the simulator prints a hint. Add JmDNS to your application’s executable-jar / simulator profile (typically the <profile id="executable-jar"> block in your cn1app’s common/pom.xml or your javase/pom.xml) to exercise real discovery in the simulator:
<!-- in YOUR app's pom, NOT in the framework / common pom that gets shipped
to the device. The cn1app archetype's executable-jar profile is the
right place because it only applies when launching the simulator. -->
<dependency>
<groupId>org.jmdns</groupId>
<artifactId>jmdns</artifactId>
<version>3.5.9</version>
<scope>runtime</scope>
</dependency>Don’t add JmDNS to the cn1app |
77.5. Network type change events
Subscribe to network type transitions (WiFi <→ Cellular <→ Ethernet <→ None):
NetworkManager.getInstance().addNetworkTypeListener(new NetworkTypeListener() {
@Override
public void onNetworkTypeChanged(int oldType, int newType, boolean vpnActive) {
if (newType == NetworkManager.NETWORK_TYPE_NONE) {
// offline -- queue uploads for later
}
if (vpnActive) {
// refuse to roam to corporate-only resources
}
}
});The current snapshot is available without subscribing:
int type = NetworkManager.getInstance().getCurrentNetworkType();
boolean vpn = NetworkManager.getInstance().isVPNActive();The platform implementations are:
Android:
ConnectivityManager.registerNetworkCallbackon API 21+, falling back to the legacyCONNECTIVITY_ACTIONbroadcast on older devices.iOS:
SCNetworkReachabilitywith a kernel callback scheduled on the main run loop.Simulator: derives the type from
NetworkInterface.getDisplayName; transitions aren’t synthesized.
VPN detection is best-effort and intentionally heuristic. On Android it uses NetworkCapabilities.TRANSPORT_VPN plus an interface-name probe; on iOS it inspects utun*, tun*, ppp* and ipsec* interfaces. Use it as a hint, not as a security boundary.
77.6. WiFi Direct (Wi-Fi P2P)
WiFi Direct lets two devices form a peer-to-peer link without an access point. The API is Android-only — iOS uses MultipeerConnectivity for similar scenarios and is intentionally out of scope.
The build pipeline injects CHANGE_WIFI_STATE, ACCESS_WIFI_STATE, ACCESS_NETWORK_STATE, ACCESS_FINE_LOCATION and NEARBY_WIFI_DEVICES automatically when WiFiDirect is on the classpath, plus a <uses-feature android:name="android.hardware.wifi.direct"/> declaration so devices without the radio can still install the app via Play Store filtering.
77.7. USB host
The USB API in com.codename1.io.usb lets the device act as a USB host and talk to attached peripherals — a barcode scanner, a serial converter, a microcontroller. It’s Android-only; iOS has no third-party USB host access and the simulator stubs everything out.
if (!Usb.isSupported()) { return; }
Usb.addDeviceListener(new UsbDeviceListener() {
@Override
public void onDeviceAttached(UsbDevice d) {
if (d.getVendorId() == 0x0403 && d.getProductId() == 0x6001) {
Usb.requestPermission(d);
}
}
@Override
public void onDeviceDetached(UsbDevice d) { }
@Override
public void onPermissionResult(UsbDevice d, boolean granted) {
if (granted) {
try (InputStream in = Usb.openInputStream(d, 0x81);
OutputStream out = Usb.openOutputStream(d, 0x02)) {
out.write("AT\r\n".getBytes());
byte[] buf = new byte[64];
int n = in.read(buf);
// null
} catch (IOException e) { Log.e(e); }
}
}
});The build pipeline injects:
<uses-feature android:name="android.hardware.usb.host" android:required="false"/>.
If you want the OS to launch your app when a matching device is plugged in, ship a device_filter.xml resource and declare an <intent-filter> via the android.xintent_filter build hint:
<!-- native/android/res/xml/device_filter.xml -->
<resources>
<usb-device vendor-id="1027" product-id="24577" />
</resources>android.xintent_filter=<intent-filter><action android:name="android.hardware.usb.action.USB_DEVICE_ATTACHED" /></intent-filter><meta-data android:name="android.hardware.usb.action.USB_DEVICE_ATTACHED" android:resource="@xml/device_filter" />77.8. Releasing platform resources
Most of these APIs hold background resources (broadcast receivers, network callbacks, NSNetService delegates) that you must release explicitly:
BonjourBrowser— call.stop().BonjourPublisher— call.unpublish().WiFiDirect— call.stopDiscovery()and.disconnect().WiFi.connect(…)— callWiFi.disconnect(ssid)when the user navigates away.Usb.addDeviceListener(…)— callremoveDeviceListener(…).NetworkManager.addNetworkTypeListener(…)— callremoveNetworkTypeListener(…).
Each of these keeps a radio or system service awake. Bonjour browsers and WiFi scans in particular drain battery noticeably — they’re fine during a few user-facing screens but shouldn’t stay armed for the lifetime of the app. Release them as soon as the screen that needs them is no longer visible.
78. Signing, certificates & provisioning
In this section you try to explain how to acquire certificates for the various platforms and how to set them up.
The good news is that this is a "one time issue" and once it’s done the work becomes easier (except for the case of iOS where a provisioning profile should be maintained).
78.1. Common terms in signing & distribution
This section uses some terms that you might not be familiar with if you haven’t used cryptography or built mobile apps before. Here is a quick "FAQ" covering some common terms/concepts in this section.
78.1.1. What’s a certificate
Certificates use cryptographic principals to "sign" data (for example, an application). Think of them as you would think of a company stamp, you use them to sign an app so users know who it’s from.
78.1.2. What’s provisioning
Provisioning provides the hints/guidelines for the application install. For example, if an application needs some service from the OS such as push it can request that with provisioning.
In iOS provisioning is separate from the app and you need to also define the devices supported by the app during development.
78.1.3. What’s a signing authority
Certificates are issued by a signing authority which is a body that certifies that you’re who you say you are. Apple issues certificates for iOS and is in effect a signing authority.
Android uses self-signed certificates which don’t use a signing authority so anyone can ship an Android app.
The logic with the Android approach is that a signature indicates that you’re the same person who earlier shipped the app. Hence an app will be updated with the exact same certificate.
78.1.4. What’s UDID
The UDID is the Universal Device Identifier. It identifies mobile devices uniquely, notice that some operating systems for example, iOS block access to this value due to privacy concerns.
You need the iOS device UDID value during development to add the device into the list of allowed devices.
| Don’t use an app to get the UDID! Most return the wrong value. Use the Finder device summary (macOS), Apple Configurator, or a trusted service such as http://get.udid.io/ which seems to work rather well |
78.1.5. Should you reuse the same certificate for all apps
For iOS yes. It’s designed to work in that way.
You would recommend it for all platforms for simplicity but some developers prefer creating per-application certificates for Android. The advantage here is that you can transfer ownership of the application later on without giving away what’s effectively "your house keys."
78.2. Certificate Wizard
Codename One features a standalone Certificate Wizard to manage signing assets for Apple, Android and desktop targets. It replaces the old certificate wizard inside CodenameOneSettings and is launched as a Maven tool bound to the current project.
Run the wizard from a Codename One Maven project:
mvn cn1:certificatewizardThe Maven goal resolves the wizard artifact and its runtime dependencies from Maven, then launches it with the current project’s settings path. The wizard uses the Codename One cloud signing API for Apple assets and local keytool for Android keystores. On a first run the overview shows that the App Store Connect API key isn’t configured and links to the API key page. This is an Apple credential that allows the cloud service to create and manage certificates, bundle IDs, devices, provisioning profiles, APNs keys and Mac signing assets for your Apple Developer Program team.
78.2.1. Creating the App Store Connect API key
Open App Store Connect > Users and Access > Integrations > App Store Connect API. If this is the first time your team uses the API, App Store Connect asks you to request API access first. Click Request Access, accept the terms, and submit the request.
Once access is enabled, go to Team Keys and click Generate API Key. Give the key a recognizable name, such as Codename One Signing, and choose Admin access.
| Use Admin access for the Certificate Wizard. The wizard needs to create and list signing certificates, bundle IDs, devices, and provisioning profiles. App Manager or Developer access may not be sufficient for these operations. |
After creating the key, App Store Connect shows the Issuer ID above the table and the Key ID in the key row. Copy both values into the wizard. Download the API key file. Apple only allows the .p8 file to be downloaded once, so store a backup in a secure location.
In the Codename One Certificate Wizard, fill these fields:
Key ID: The value shown in the generated key row in App Store Connect. This isn’t your Apple ID.
Issuer ID: The UUID shown above the Team Keys table on the App Store Connect API page.
Private key .p8: Click Import .p8 file to select the downloaded file with the native file chooser, or paste the full file contents, including the
BEGIN PRIVATE KEYandEND PRIVATE KEYlines.
The .p8 private key is sent to the Codename One cloud signing service and isn’t returned by the API later. If you delete the key from App Store Connect or lose the local .p8 backup, generate and store a new API key.
When you download a generated .p12 certificate from the wizard, the P12 password field is a new password that you choose for that downloaded file. It’s not the App Store Connect Issuer ID, and it doesn’t come from Apple.
78.2.2. Recommended fast path: Auto Setup
After the API key is stored, the top toolbar shows Auto Setup next to the API key status. This is the recommended path for a normal Codename One project. It creates the common Apple signing assets for the current project and installs the downloaded files into codenameone_settings.properties.
Click Auto Setup. The wizard reads the current project’s codenameone_settings.properties, uses codename1.packageName as the bundle ID, uses codename1.displayName or codename1.mainName as the app name, enables push notifications for the bundle ID, and then creates or reuses the signing assets it needs.
The fast path creates the common Apple signing setup:
A Bundle ID for the current project, if it doesn’t already exist.
An iOS Development certificate, if no compatible active certificate exists.
An iOS Development provisioning profile, if at least one development device is registered.
An iOS Distribution certificate, if no compatible active certificate exists.
An App Store provisioning profile.
Debug signing settings for the development certificate/profile pair.
Release signing settings for the App Store certificate/profile pair.
Mac App Store or Developer ID assets when you use the Mac Signing page.
Development provisioning requires at least one registered device. If no devices are registered, the wizard defers development profile creation and continues with the App Store signing assets. Register the device in the Devices section and run Auto Setup again to fill in the debug signing settings.
The wizard writes downloaded Apple .p12, .mobileprovision and Mac .provisionprofile files into the current project signing configuration. For a development iOS profile it updates the iOS debug settings. For an App Store iOS profile it updates the iOS release settings. For Mac profiles it updates codename1.mac.certificate, codename1.mac.certificatePassword, codename1.mac.provision and the relevant macNative.* hints.
78.2.3. Mac signing and notarization
The Mac section uses the same App Store Connect API key and the unified Apple signing API. It supports Mac App Store certificates/profiles and Developer ID certificates for direct distribution. Developer ID builds can use notarization credentials derived from the stored App Store Connect key when the build server performs notarization.
Mac native signing uses the project settings documented in the Mac native chapter:
codename1.mac.certificate: The generated or imported Mac.p12.codename1.mac.certificatePassword: The password for that.p12.codename1.mac.provision: The Mac.provisionprofile.codename1.arg.macNative.enabled=true: Enables the Mac native signing path.codename1.arg.macNative.distribution=appStoreordeveloperID: Chooses the signing channel.
78.2.4. Android signing
The Android section generates a local self-signed Android keystore using the JDK keytool executable. It stores the file under androidCerts/KeyChain.ks in the project by default and writes:
codename1.android.keystorecodename1.android.keystoreAliascodename1.android.keystorePassword
| Back up the generated keystore and password. Android apps already published with one certificate can’t be updated with a different certificate. |
78.2.5. Windows signing
The Windows section doesn’t issue certificates. Windows Authenticode certificates must come from a code-signing certificate authority or a managed signing service such as Azure Trusted Signing, DigiCert KeyLocker, GlobalSign GCC, Sectigo, or another OV/EV provider. Once you have a .pfx or .p12, configure:
codename1.windows.signing.certificatecodename1.windows.signing.passwordcodename1.windows.signing.timestamp
78.2.6. Clearing cached signing data
The Clear Signing Data section is a privacy tool, not a recommended part of normal signing setup or troubleshooting. Use it only when you need to delete cached signing data owned by the current Codename One account from the cloud signing service.
It clears stored Apple API credentials, generated certificate private keys, provisioning profile metadata, APNs keys and notarization data. It doesn’t delete assets from Apple, but future cloud builds will need signing data to be regenerated or re-imported.
78.2.7. Manual asset management
Use the individual wizard sections when you need to inspect assets, register a device, sync certificates with Apple, create an ad-hoc or Mac profile, install a specific certificate/profile pair, generate an Android keystore, or delete/revoke an obsolete asset.
The asset tables are live-filterable and sortable. Click a row to show the values returned by the signing API. Existing Apple assets can’t currently be edited through this API; for changes, create a new asset or delete/revoke the old one where Apple permits it. Destructive actions such as deleting a profile, deleting an APNs key, deleting the stored API key, or revoking a certificate prompt for confirmation.
78.2.8. Selecting devices
Development and ad-hoc provisioning profiles can only include devices that are registered on your Apple Developer account. In the standalone wizard, open the Devices section to register a device by name and UDID before creating a development or ad-hoc provisioning profile.

Select the ones that you want to include in your provisioning profile and click next.
| Apple allows up to 100 devices per device type (iPhone, iPad, Apple Watch, Apple TV, and Apple Vision) for testing purposes in each membership year. Make sure every device you intend to install builds on is registered here before you generate a new provisioning profile. |

If you don’t have any devices registered yet, you can click the "Add New Device" button, which will prompt you to enter the UDID for your device.
78.2.9. Decisions & edge cases
| If you already have iOS P12 development/distribution certificates you should reuse them for all your apps from that account and you shouldn’t regenerate them |
After you click Next on the device form, the wizard checks to see if you already have a valid certificate. If your project already has a valid certificate and it matches the one that’s active in your Apple developer account, then it will use the same certificate. If the certificate doesn’t match the currently active one, or you haven’t provided a certificate, you will be prompted to overwrite the old certificate with a new one.


The same decision need to be made twice: Once for the development certificate, and once for the App Store distribution certificate.
| Each Apple Developer account can have three active iOS Development certificates and three active iOS Distribution certificates at a time. Reuse existing certificates whenever possible to avoid hitting this limit. |
| You can revoke a certificate when you have an application in the store shipping with said certificate! This won’t affect the shipping app see this. |
78.2.10. App IDs and provisioning profiles
The next form in the wizard asks for your app’s bundle ID. This should have been pre-filled, but you can change the app ID to a wildcard ID if you prefer.

78.2.11. Installing files locally
Once the wizard is finished generating your provisioning profiles, you should click Install Locally, which will
open a file dialog for you to navigate to a folder in which to store the generated files.



You can see the password for the P12 files in the codenameone_settings.properties file. You can use the values defined there when creating a new application |
78.2.12. Building your app
After selecting your local install location, and closing the wizard, you should see the fields of the "iOS Signing" properties panel filled in. You should now be able to send iOS debug or App Store builds without the usual hassles.

78.3. Advanced iOS signing
| You should use the Certificate Wizard, if you don’t have a Mac. This section is here for reference and edge cases that don’t work with the Certificate Wizard |
iOS signing has two distinct modes: App Store signing which is valid for distribution via App Store Connect (you won’t be able to run the resulting application without submitting it to Apple) and development mode signing.
You’ve two major files to keep track of:
Certificate - your signature
Provisioning Profile - details about the application and who is allowed to execute it
You need two versions of each file (4 total files) one pair is for development and the other pair is for uploading to App Store Connect.
| You need to use a Mac to create a certificate file for iOS |
The first step you need to do is signing up as a developer to Apple’s iOS development program, even for testing on a device this is required!
This step requires that you pay Apple on an annual basis.
The Apple website will guide you through the process of applying for a certificate at the end of this process you should have a distribution and development certificate pair. After that point you can log in to the iOS provisioning portal where there are plenty of videos and tutorials to guide you through the process. Within the iOS provisioning portal you need to create an application ID and register your development devices.
You can then create a provisioning profile which comes in two flavors:
Distribution - for building the release version of your application
Development - the development provisioning profile needs to contain the devices on which you want to test.
You can then configure the 4 files in the IDE and start sending builds to the Codename One cloud.
78.4. Provisioning profile & certificates visual guide
One of the hardest parts in developing for iOS is the certificate & provisioning process. In this step-by-step guide you walk over the manual certificate generation process. Notice that the UI for the Apple website changes occasionally but the basic process remains the same…
Start by logging in to the iOS-provisioning portal

In the certificates section you can download your development and distribution certificates.


In the devices section add device ids for the development devices you want to support. Notice no more than 100 devices are supported!

Create an application ID; it must match the package identifier of your application exactly!

Create a provisioning profile for development, make sure to select the right app and make sure to add the devices you want to use during debug.


Refresh the screen to see the profile you created and press the download button to download your development provisioning profile.

Create a distribution provisioning profile; it will be used when uploading to the App Store. No need to specify devices here.

Download the distribution provisioning profile.

You can now import the cer files into the Keychain tool on a Mac by double clicking the file, on Windows the process is slightly more elaborate

You can export the p12 files for the distribution and development profiles through the keychain tool

In the IDE you enter the project settings, configure your provisioning profile, the password you typed when exporting and the p12 certificates. It’s now possible to send the build to the server.

78.4.1. Configuring codenameone_settings.properties for manual signing
The Codename One build servers read signing assets from codenameone_settings.properties. When you bypass the Certificate Wizard, populate the following keys manually so the packaging process can locate your certificates, provisioning profiles, and keystores:
iOS
codename1.ios.debug.certificate/codename1.ios.debug.certificatePassword/codename1.ios.debug.provision: Development P12 and provisioning profile for device/debug builds.codename1.ios.release.certificate/codename1.ios.release.certificatePassword/codename1.ios.release.provision: Distribution P12 and provisioning profile for App Store/TestFlight builds.codename1.ios.certificate,codename1.ios.certificatePassword, andcodename1.ios.provision: Legacy/global defaults. The IDE uses these as fallbacks when the debug/release-specific properties are blank, so keep them aligned with your preferred certificates.codename1.ios.appext.<Name>.provision: Provisioning profile for an embedded app extension (for example the generatedCN1Widgetswidget extension), used for both build types. Addcodename1.ios.debug.appext.<Name>.provision/codename1.ios.release.appext.<Name>.provisionto use the development profile for device/debug builds and the distribution profile for release builds; the variant matching the build target wins and the unqualified key is the fallback.
Paths may be absolute or relative to the project directory. The passwords must match the values you used when exporting the P12 files from Keychain Access.
Android
codename1.android.keystore: Path to the Android keystore (.ksor.keystore).codename1.android.keystorePassword: Password protecting the keystore and key entry.codename1.android.keystoreAlias: Alias of the keypair used to sign the APK/AAB.
If the keystore fields are empty the Maven and Ant builders will create a default keystore, but production apps should commit the real paths and credentials so reproducible builds use your long-lived signing key.
78.4.2. iOS code signing failure checklist
Below is a list of common issues when singing and a set of suggestions for things to check. Notice that some of these signing failures will sometimes manifest themselves during build and sometimes will manifest during the installation of the application.
| Most of these issues aren’t applicable when using the wizard for example, a Mac isn’t required for the Certificate Wizard as it uses the Codename One cloud |
You must use a Mac to generate P12 certificates manually. The workaround you found is the Certificate Wizard!
Notice that this is something you need to do once a year (generate P12), you will also need a Mac to upload your final app to the store now.
When exporting the P12 certificate make sure that you selected BOTH the public and the private keys as illustrated here. If you see one entry (no private key) then you created the CSR (singing request) on a different machine than the one where you imported the resulting CER file.
Figure 359. p12 exportLaunch Codename One Settings with
mvn cn1:settingsand make sure the Package Name in Basic matches the App ID used by the provisioning profile.Make sure the App ID prefix in the provisioning profile matches the prefix assigned by Apple. The standalone Certificate Wizard handles this automatically for profiles it creates.
Make sure your provisioning profile’s app ID matches your package name or is a * provisioning profile. Both are sampled in the pictures below, notice that you would need an actual package name for push/in-app purchase support as well as for app store distribution.
Figure 360. The star (*) Provisioning Profile
Figure 361. Provisioning Profile with app IDMake sure the certificate and provisioning profile are from the same source (if you work with multiple accounts), notice that provisioning profiles and certificates expire so you will need to regenerate provisioning when your certificate expires or is revoked.
If you declare push in the provisioning profile then
ios.includePush(in the build arguments) MUST be set to true, otherwise it MUST be set to false (see pictures below). Notice that this should be configured via the UI in the iOS section. The build server automatically enables the notification entitlement when your project usesLocalNotification, even ifios.includePushis false, so don’t try to disable the entitlement manually to "fix" warning messages from App Store Connect.
Figure 362. Include push build hint
78.5. Android
Signing Android applications is trivial when compared to the pain of iOS signing.
The NetBeans and Eclipse plugins have a simple wizard to generate the certificate that you can launch by pressing this button:

Then fill out your details and password in the form:

This will seamlessly generate a certificate for your project, you can reuse it for other projects as well.
78.5.1. Generating an Android certificate manually
You need the JDK’s keytool executable (it should be under the JDK’s bin directory) and execute the following command:
keytool -genkey -keystore Keystore.ks -alias [alias_name] -keyalg RSA -keysize 2048 -validity 15000 -dname "CN=[full name], OU=[ou], O=[comp], L=[City], S=[State], C=[Country Code]" -storepass [password] -keypass [password]
The elements in the brackets should be filled up based on this:
Alias: [alias_name] (just use your name/company name without spaces) Full name: [full name] Organizational Unit: [ou] Company: [comp] City: [City] State: [State] CountryCode: [Country Code] Password: [password] (we expect both passwords to be identical)
Executing the command produces a Keystore.ks file in that directory. Keep it safe: if you lose it, you can no longer publish upgrades signed with the same identity. Enter its path, alias, and passwords in common/codenameone_settings.properties, or use the Android page in the standalone Certificate Wizard (mvn cn1:certificatewizard) to generate and install a keystore.
For more details see http://developer.android.com/guide/publishing/app-signing.html
79. Working with iOS
79.1. Troubleshooting iOS debug build installs
If you’ve access to a Mac, connect the device, open Xcode, and use the device explorer console to inspect messages that may explain what went wrong. If not, check the following:
Make sure the build is the debug version and not the App Store version. The App Store version won’t install on the device and can be distributed through Apple’s store or TestFlight.
Check that the UDID is correct. If you got the UDID from an app, it’s probably wrong because apps no longer have access to the device UDID. Get it from the iOS Settings app or iTunes.
Make sure the device isn’t locked for installing third-party apps. This can happen on devices configured with parental controls.
Check that you own the package name. For example, if you earlier installed an app with the same package name but a different certificate, a new install will fail. This is true for Android too. If you installed the kitchen sink from the store and then built your own app with the same package name, the installation will collide.
This can be a problem if you use a generic package name that someone else already claimed, so use your own domain.
Make sure the device has a recent enough version of iOS for the dependencies. As of 2024, Codename One builds target iOS 12.0 or newer by default. You can raise the need with the
ios.deployment_targetbuild hint if a library needs a newer version.Verify that you’re using Safari when installing on the device. If you used a cable, that isn’t a problem. Some developers had issues with Firefox not launching the install process.
Check that the
ios.includePushbuild hint matches your iOS provisioning. It must be false if your provisioning profile doesn’t include push.
79.2. Launch screen storyboard best practices
Launch screen storyboards are the default approach for Codename One iOS builds. Apple requires a storyboard-based launch experience for modern devices, so the legacy screenshot generator was removed in favor of a single adaptive layout. You can still opt back into the old behavior by setting the ios.generateSplashScreens=true build hint, but it’s best to use a storyboard unless your use case can’t be expressed with Auto Layout.
79.2.1. Key files
The build server provides a minimal launch storyboard automatically. Customize it by adding any of the following files under your project’s native/ios directory:
Launch.Foreground.png- Shown in the center of the screen instead of your app icon.Launch.Background.png- Drawn behind the content to provide a color or illustration.LaunchScreen.storyboard- A custom storyboard created in Xcode that replaces the default layout entirely.
Make sure to add the ios.multitasking=true build hint or your launch storyboard won’t be used. |
79.2.2. Designing a flexible Layout
Keep the launch storyboard simple and static. The layout is rendered before your app code runs, so avoid views that depend on live data or animation. Follow these guidelines when editing LaunchScreen.storyboard in Xcode:
Use Auto Layout constraints and safe-area guides so the design scales to every device, including split view on iPad.
Prefer system colors or vector/PDF assets for logos so the result stays crisp on high-density screens and supports Dark Mode.
Reserve text for short taglines or status messages that don’t need localization at launch. Dynamic localization isn’t available.
Avoid referencing application delegate outlets or custom classes. Only design-time UIKit elements are supported.
79.2.3. Asset reference
The default storyboard expects PNG assets with the following characteristics. All sizes are specified in points (pt). Supply @2x and @3x variants for Retina displays when possible.
| Asset | Purpose | Suggested 1x dimensions | Notes |
|---|---|---|---|
| Brand mark centered on screen | 152×152 | Provide optional |
| Full-screen backdrop | 1024×1024 | Supply complementary |
| Complete custom layout | N/A | Target iOS 12.0 and later, enable Auto Layout, and include constraints for every view. Avoid timers or code connections. |
79.2.4. Testing changes
| Changes to the launch screen don’t take effect until the device has been restarted. If you install your app on a device, then change the launch screen and update the app, the launch screen won’t change until the device is restarted. |
When iterating locally with a Mac, open the generated Xcode project and run it on a device or simulator to verify that the layout adapts. On Windows or Linux, submit a TestFlight or Ad-Hoc build and check on hardware before shipping.
79.3. Local notifications on iOS and Android
Local notifications are like push notifications, except that they’re initiated locally by the app, rather than remotely. They’re useful for communicating information to the user while the app is running in the background, since they manifest themselves as pop-up notifications on supported devices.
To set the notification icon on Android place a 24×24 icon named ic_stat_notify.png under the native/android folder of the app. The icon can be white with transparency areas |
79.3.1. Sending notifications
The process for sending a notification is:
Create a LocalNotification object with the information you want to send in the notification.
Pass the object to
Display.scheduleLocalNotification().
Notifications can either be set up as one-time or as repeating.
Example sending notification
On iOS, scheduling a local notification with an id that already exists now replaces the earlier scheduled notification with that same id instead of keeping duplicates. |
The resulting notification will look like

79.3.2. Receiving notifications
The API for receiving/handling local notifications is also like push. Your application’s main lifecycle class needs to implement the com.codename1.notifications.LocalNotificationCallback interface which includes a single method:
public void localNotificationReceived(String notificationId) {
}The notificationId parameter will match the id value of the notification as set using LocalNotification.setId().
Example receiving notification
localNotificationReceived() is called when the user responds to the notification by tapping on the alert. If the user doesn’t click on the notification, then this event handler will never be fired. |
79.3.3. Canceling notifications
Repeating notifications will continue until they’re canceled by the app. You can cancel a single notification by calling:
Where notificationId is the string id that was set for the notification using LocalNotification.setId().
79.4. iOS beta testing (testflight)
Apple provides the ability to distribute beta versions of your application to beta testers using testflight. This allows you to recruit up to 1000 beta testers without the typical UDID limits a typical Apple account has.
| This is supported for pro users as part of the crash protection feature. |
To take advantage of that capability use the build hint ios.testFlight=true and then submit the app to the store for
beta testing. Make sure to use a release build target.
79.5. Metal renderer
iOS builds use the Metal rendering backend by default. The Metal pipeline drives a CAMetalLayer, replacing the legacy OpenGL ES 2 path on CAEAGLLayer. OpenGL ES is deprecated on iOS and Metal is the supported graphics API going forward, so new projects pick it up automatically.
To opt out and fall back to the OpenGL ES 2 backend, set the build hint:
codename1.arg.ios.metal=falseIf you hit a rendering regression after the default flip, opting out with ios.metal=false is a safe escape hatch, but please file an issue with a reproducer so the Metal path can be fixed.
79.6. Choosing a color space for the Metal renderer
With the Metal renderer (the default), the CAMetalLayer is configured with the sRGB color space. This matches the behavior of the legacy OpenGL ES 2 backend on CAEAGLLayer: CG-rasterized images and gradients (which are tagged DeviceRGB in their CGBitmapContext) end up displayed with the same brightness on both backends.
For most apps the default is the right choice. Apps that need a different color profile — for example, wide-gamut artwork that should be displayed in Display P3, or a strictly device-RGB pipeline that matches a custom rendering toolchain — can override the choice with the ios.metal.colorSpace build hint:
| Value | Effect |
|---|---|
| Sets |
| Sets |
| Calls |
| Sets |
| Sets |
| Sets |
| Leaves |
The hint only takes effect on the Metal backend (the default). If you have opted out with ios.metal=false, the layer is CAEAGLLayer and the color space is fixed by the system. |
79.7. Accessing insecure URLs
Due to security exploits Apple blocked some access to insecure URLs which means that http code that worked before could stop working for you on iOS 9+. This is a good move, you should use https and avoid http as much as possible but that’s sometimes impractical when working with an internal or debug environment.
You can disable the strict URL checks from Apple by using the venerable ios.plistInject build hint and setting it to:
<key>NSAppTransportSecurity</key><dict><key>NSAllowsArbitraryLoads</key><true/></dict>For example, it seems that Apple will reject your app if you include that and don’t have a good reason.
79.8. Using Cocoapods
| CocoaPods remains fully supported, but it’s no longer the only supported iOS dependency path. Swift Package Manager (SPM) is also supported. The current guidance is documented in this section. |
CocoaPods is a dependency manager for Swift and Objective-C Cocoa projects. It has over eighteen thousand libraries and can help you scale your projects. Cocoapods can be used in your Codename One project to include native iOS libraries without having to go through the hassle of bundling the actual library into your project. Rather than bundling .h and .a files in your ios/native directory, you can specify which "pods" your app uses through the ios.pods build hint. (Other build hints also exist if you need more advanced features.)
Examples
Include the AFNetworking library in your app:
ios.pods=AFNetworking
Include the AFNetworking version 3.0.x library in your app:
ios.pods=AFNetworking ~> 3.0
For full versioning syntax specifying pods see the Podfile spec for the "pod" directive.
79.8.1. Including multiple pods
Multiple pods can be separated by either commas or semi-colons in the value of the ios.pods build hint. For example: To include GoogleMaps and AFNetworking, you could:
ios.pods=GoogleMaps,AFNetworking
Or specifying versions:
ios.pods=AFNetworking ~> 3.0,GoogleMaps
79.8.2. Other pod related build hints
ios.pods.platform : The least platform to target. Sometimes, Cocoapods require functionality that isn’t in older version of iOS. For example, the GoogleMaps pod requires iOS 7.0 or higher, so you would need to add the ios.pods.platform=7.0 build hint.
ios.pods.sources : Some pods require that you specify a URL of the source of the pod spec. This may be optional if the spec is hosted in the central CocoaPods source (https://github.com/CocoaPods/Specs.git).
79.8.3. Converting PodFile to build hints
Most documentation for Cocoapods "pods" provide instructions on what you need to add to your Xcode project’s PodFile. Here is an example from the GoogleMaps cocoapod to show you how a PodFile can be converted into equivalent build hints in a Codename One project.
The GoogleMaps cocoapod directs you to add the following to your PodFile:
source 'https://github.com/CocoaPods/Specs.git' platform :ios, '7.0' pod 'GoogleMaps'
This would translate to the following build hints in your Codename One project:
ios.pods.sources=https://github.com/CocoaPods/Specs.git ios.pods.platform=7.0 ios.pods=GoogleMaps
(Note that the ios.pods.sources directive is optional).
79.9. Using Swift package manager
Swift Package Manager can be used as an alternative to CocoaPods for remote Swift package dependencies on iOS. Select the dependency path with ios.dependencyManager. Supported values are auto, CocoaPods, spm, and both.
For an SPM-only configuration, declare the packages in ios.spm.packages using the format <identity>|<url>|<requirement> and then declare the products to link using ios.spm.products.<identity>.
ios.dependencyManager=spm ios.spm.packages=swift-collections|https://github.com/apple/swift-collections.git|from:1.1.0 ios.spm.products.swift-collections=Collections
Supported need formats are from:, exact:, branch:, revision:, and range:.
ios.dependencyManager=auto preserves backward compatibility. Existing projects with ios.pods continue to use CocoaPods. Projects with ios.spm.* use SPM. If both hint families are present, both are applied.
Explicit dependency-manager modes are validated rather than dropping
dependencies. ios.dependencyManager=spm fails when the project or a built-in
API requires a CocoaPod; use auto or both. Likewise,
ios.dependencyManager=none fails while pod or SPM hints are present; remove
the dependency hints only if suppression is intentional, or switch to
auto. This is a migration-visible change for older projects that used
spm or none to ignore declared native dependencies.
79.10. Including dynamic frameworks
If you need to use a dynamic framework (for example: SomeThirdPartySDK.framework), and it isn’t available through CocoaPods, then you can add it to your project by zipping up the framework and copying it to your native/ios directory.
For example: native/ios/SomeThirdPartySDK.framework.zip
No build hints necessary for this approach. The build server will automatically detect the framework and link it into your app.
80. On-Device Debugging (iOS)
The Codename One simulator runs your app on the JVM, so the IDE’s normal Java debugger works against it directly. Some bugs only appear on a real device — ParparVM’s threading model, iOS-specific native behaviour, performance characteristics on real hardware, memory pressure under iOS background limits, and timing around UIKit interactions are common examples. On-device debugging lets you keep using a standard Java debugger (IntelliJ IDEA, jdb, VS Code, anything that speaks JDWP) against the running iOS app on either the native iOS simulator or a physical device.
It works by adding a small listener thread to the ParparVM-generated iOS binary. The app dials out to a desktop proxy over Wi-Fi or loopback; the proxy speaks JDWP on the other side, so to the IDE everything looks like attaching to a normal remote JVM.
80.1. When to use it
You can reproduce a bug on a built iOS app but not in the Codename One simulator — for instance a native-call issue, a layout glitch that only shows up on iOS modern theme, or an AOT-vs.-JIT numerical discrepancy.
You want to single-step through real ParparVM-translated code and read the values its variables actually hold at runtime.
You want to inspect object state on a tethered device while reproducing a problem a customer reported, without having to add log lines and rebuild.
If your bug is reproducible in the simulator, stay in the simulator — its debugger is faster and has fewer limitations.
80.2. Quick start (IntelliJ IDEA)
Codename One projects generated from the cn1app-archetype ship with
three ready-made IntelliJ run configurations under the On-Device
Debug folder in the run-config dropdown: CN1 iOS On-Device Debug
Build, CN1 Debug Proxy and CN1 Attach iOS. The rest of this
section assumes you’re using them. Skip to
Using jdb instead if you prefer the
command-line debugger.
80.2.1. 1. Enable the build hints
In common/codenameone_settings.properties, uncomment the four lines
the archetype generated:
codename1.arg.ios.onDeviceDebug=true
codename1.arg.ios.onDeviceDebug.proxyHost=127.0.0.1
codename1.arg.ios.onDeviceDebug.proxyPort=55333
# Optional: block the app at startup until the IDE attaches.
codename1.arg.ios.onDeviceDebug.waitForAttach=trueThe build hint names start at ios.onDeviceDebug. Entries in
codenameone_settings.properties use the codename1.arg. prefix, as
shown above.
For a physical device, set proxyHost to the laptop’s LAN IP (run
ipconfig on Windows or ifconfig on macOS and Linux) instead of
127.0.0.1. The native iOS simulator can always use 127.0.0.1.
80.2.2. 2. Build the app as you normally do
Either the local Xcode path (cn1:buildIosXcodeProject) or a cloud
build (cn1:buildIosOnDeviceDebug) will produce an app instrumented
for on-device debugging once the build hints are set.
80.2.3. 3. Run the proxy from IntelliJ
Select CN1 Debug Proxy from the Run-config dropdown and click ▶ Run (the green play icon — not the bug icon; Debug on this config would attach IntelliJ’s own debugger to the proxy process, which is not what you want). The Run tool window opens and shows:
On-device-debug proxy starting: device : listening on tcp://0.0.0.0:55333 jdwp : listening on tcp://0.0.0.0:8000 symbols : streamed from the device on connect (no local file) [device] listening on port 55333 for ParparVM app to dial in [jdwp] listening on port 8000 for debugger (jdb) to attach
When both listener lines appear, the proxy is ready for the app.
80.2.4. 4. Launch the app and wait for the device handshake
Launch the iOS app in the native iOS simulator under Xcode or on a physical device. The app contains its compressed debug symbol table and streams it to the proxy when it connects. Wait for these lines before attaching the IDE:
[device] connected from ... [device] loaded symbols: ... [jdwp] device handshake ...
With waitForAttach=true, the app remains on the "Waiting for
debugger" overlay while you complete the next step.
Attaching the IDE before launching the app is also supported. The
proxy keeps the JDWP session open and waits for the device to stream
its symbols. If the device still hasn’t connected after ten seconds,
the proxy prints a checklist for the build hint, proxyHost, and the
device port. You can correct the problem and launch the app without
restarting the IDE session; rebuild and reinstall first if you change a
build hint.
80.2.5. 5. Attach the debugger from IntelliJ
Switch the Run-config dropdown to CN1 Attach iOS and click 🐞
Debug. IntelliJ connects to localhost:8000, opens a Debug tool
window, and releases the app after the debugger connection completes.
Set breakpoints, step, inspect, evaluate expressions, just like a
normal remote attach. Device output from
System.out.println / Log.p / printf / NSLog lands in the
CN1 Debug Proxy Run window prefixed with [device].
80.3. Quick start (NetBeans)
NetBeans uses the same proxy and connection order as IntelliJ. Generated projects ship two custom actions for it, on the project’s right-click menu:
Build for iOS On-Device Debug runs
cn1:buildIosOnDeviceDebug, which forcescodename1.arg.ios.onDeviceDebug=truefor that one build. You don’t need to editcommon/codenameone_settings.propertiesfirst — the goal sets the hint itself, so a release build stays a release build.Start iOS Debug Proxy runs
cn1:ios-on-device-debugging, which listens on55333for the device and8000for the IDE.
Install the app the first action produced, start the proxy with the
second, launch the app, and wait for the device handshake and
symbol-loading lines shown above. Then choose Debug > Attach
Debugger, select Java Debugger (JPDA) and the SocketAttach
connector, set the host to localhost and the port to 8000, and
attach. Keep the Codename One project open so NetBeans can resolve
your source files and breakpoints.
Don’t point NetBeans at port 55333. The iPhone uses 55333 to
reach the proxy. The IDE uses the proxy’s JDWP port, 8000.
If the actions are missing from an older project, they live in
tools/netbeans/nbactions.xml; copying that file from a freshly
generated project adds them.
80.4. Quick start (Maven from the command line)
If you don’t want to use the IntelliJ run configs, the same flow is two terminals:
# Terminal 1 — start the proxy
mvn cn1:ios-on-device-debugging
# Launch the app and wait for the proxy to report that it loaded symbols.
# Terminal 2 — attach jdb after the device handshake
jdb -attach localhost:8000For VS Code (Debugger for Java extension), add a launch
configuration of type java with "request": "attach",
"hostName": "localhost", "port": 8000.
80.4.1. Using jdb instead
jdb is a minimal Java debugger that ships with every JDK and works
fine over the same JDWP socket. Useful when you don’t have an IDE
available, or for scripted regression checks. Source path resolution
is manual:
jdb -attach localhost:8000 \
-sourcepath src/main/java:$HOME/.m2/repository/com/codenameone/codenameone-core/8.0-SNAPSHOT/codenameone-core-8.0-SNAPSHOT-sources.jarThe -sourcepath is required for list / where to render framework
source — jdb won’t unzip the -sources.jar automatically; if you
prefer plain files, extract it once and point at the directory.
80.5. What works today
Class loading: the IDE sees every class in your build.
Line breakpoints in user code and in the Codename One framework classes (
com.codename1.ui.,com.codename1.io., etc.).Step into / over / out.
Stack walking — full Java stack including the Codename One framework frames above your code.
Inspecting primitive locals (int, long, float, double, boolean, byte, char, short).
Inspecting
java.lang.Stringvalues directly.Inspecting object references — class name and identity, plus field-by-field drilldown via the IDE’s variables view. The proxy walks the ParparVM struct layout to read instance fields directly at known offsets, so
dump this/ "Variables" shows the same fields you’d see in a simulator debug session.Array inspection —
Object[],int[],byte[], etc. report their length and per-index values to the IDE so expanding e.g.ArrayList.elementDatashows the actual element references rather than an opaque reference. Primitive element types round-trip with their JVM type tag.Method invocation — the IDE’s "Evaluate Expression" /
printcommand can call instance and static methods on objects in scope. The classic chainDisplay.getInstance().getCurrent().getTitle()evaluates to the current form’s title string, somyForm.getComponentCount()and similar accessor calls work too. The call runs on the suspended Java thread inside a catch-all try block, so uncaught throws round-trip back as an exception reference rather than tearing down the debugger.Native device output —
System.out.println,Log.p, andprintf/NSLogfrom native code are surfaced in the proxy’s console (the IntelliJ CN1 Debug Proxy Run window when launched via the run config) prefixed with[device].Thread list — every live Java thread appears in the IDE’s Threads panel, whether it has stopped anywhere or not, named after the
java.lang.Threadit belongs to (EDT,main, …). Suspension is reported per thread, so with several parked at once the panel shows which is which.Scoped locals — a local is listed only on the source lines it’s actually in scope for. That matters where two variables share a JVM slot in disjoint blocks: only the one the code has reached is shown, rather than both, one of them displaying the other’s storage.
Deferred breakpoints — a breakpoint set in a class the IDE hasn’t seen yet (an anonymous listener, say) resolves via the ClassPrepare events the proxy raises for every matching class.
Pause and resume from the IDE.
Stack frames in methods carrying no line information — synthetic lambda bodies and
java.lang.Thread.runImpl, for instance — appear in the stack with their source line left blank, rather than ending the stack view at that frame.
80.6. Pointing the IDE at the Codename One sources
The proxy answers Method.LineTable and ReferenceType.SourceFile
for framework classes, but the IDE still needs to find the actual
.java files to render the source pane while stepping. Three options
in order of convenience:
Maven sources jar (recommended). The
codenameone-core-<version>-sources.jaris published alongside the regularcodenameone-coreartifact. IntelliJ resolves it automatically once you run Maven → Reimport with "Sources" enabled in the Maven settings. Other IDEs work the same way as long as their Maven integration is set to download sources.Local clone of the Codename One repository. If you’ve already checked out the CodenameOne GitHub repository (for instance to follow the contributor workflow), point the IDE at its
CodenameOne/srcdirectory. In IntelliJ: Run → Edit Configurations… → CN1 Attach iOS → Configuration → Source roots → +.jdb command line. Pass the framework source directory on the
-sourcepath, as shown in Using jdb instead.
Without a source path, breakpoints in framework classes still trigger and locals / fields still read — you’ll just see "Sources not found" in the IDE editor when stepping into framework code.
80.7. Known limitations
Method invocation is partial. The debugger can call instance and static methods on Codename One framework classes and on user code: jdb’s
print myForm.getTitle()and IntelliJ’s "Evaluate Expression" pop-up work for the chains you actually want (Display.getInstance().getCurrent().getTitle()is the canonical test). Methods onjava.io.,java.net.,java.nio., andcom.codename1.impl.are unsupported — those classes are linked against hand-written native code that has fallen out of sync with the generic invoke-thunk calling convention, so the translator skips them. The same limit applies to watch expressions.Constructor invocation isn’t supported. The debugger can call existing instance methods but not
new Foo(…).Hot-swap isn’t supported. Code changes require a rebuild and reinstall of the app.
Hot threads — if your app is doing heavy work on a non-EDT thread when a breakpoint hits, that other thread continues running. Only the thread that hit the breakpoint suspends by default. Use the IDE’s "suspend VM" if you need a fully frozen picture.
Local variable names are present only when the user’s Java sources were compiled with
-g. Codename One’s archetypes do compile with debug info by default; if a variable shows up asv1,v2, … that’s because that particular class was compiled without debug info. Such a local also has no declaring scope, so the debugger lists it for the whole method rather than only where it’s live.Static field reads are unsupported. Instance field reads are fully wired; static-field support requires an additional per-class static table that hasn’t been emitted yet.
NSLog on a real device (as opposed to the native iOS simulator) may not reach the
[device]console. NSLog on iOS routes toos_logwhich doesn’t always mirror tostderr.printf/fprintf/Log.pare unaffected and show up correctly.
80.8. Performance
The on-device-debug instrumentation is gated by a compile-time flag that’s only set in debug builds. Release builds are completely unaffected — no listener thread, no per-line callback, no extra metadata in the binary.
In debug builds, the per-line callback adds a predictable
load+branch around the macro that ParparVM already emits to
record source line numbers for stack traces. When no debugger is
attached, the runtime cost is close to zero. When a debugger
is attached, expect numerical inner loops to run on the order
of two to three times slower than a release build — this is
normal and matches the overhead of -g-style debugging on
other native VMs.
80.9. Debugging the generated Xcode project natively
The JDWP flow above keeps you at the Java level. For native-level work — stepping through Objective-C sources, debugging a native interface, chasing a crash inside the VM, or profiling with Instruments — debug the generated Xcode project directly:
Local build:
mvn cn1:buildIosXcodeProjectwrites the complete Xcode project undertarget/…-ios-source/.Cloud build: run
mvn cn1:settings, enable Include Source on the Basic page, save, then send the build and download the sources result from the build server.
Open the .xcworkspace file if one was generated, otherwise the .xcodeproj,
and run on a device or the native iOS simulator from Xcode as you would any iOS
app.
The .xcworkspace is no longer exclusive to CocoaPods-based builds.
Use it whenever it’s generated, whether the project uses CocoaPods, Swift
Package Manager, or both. |
Inside Xcode you get LLDB and Instruments against the real binary. Your Java
code appears as the C sources ParparVM generated from it — a Java method like
com.mycompany.MyClass.doStuff(int) becomes a C function named along the lines
of com_mycompany_MyClass_doStuff___int, so symbolic breakpoints on the
translated code work too. The native-IDE path and the JDWP path are
complementary: use Xcode for native frames and profiling, the JDWP proxy for
source-level Java debugging.
80.10. Troubleshooting
80.10.1. The proxy reports "device disconnected" before the breakpoint fires
The app might be crashing before it reaches user code. Run the
app from Xcode and watch the console — installSignalHandlers
will intercept native crashes and rethrow them as Java exceptions
you can see. If the connection drops mid-debug, check the proxy
log for a device-side I/O error.
80.10.2. "Connection refused" when the device tries to reach the proxy
The device’s ios.onDeviceDebug.proxyHost value is wrong, or a
firewall is blocking the port. Verify:
The native iOS simulator can always reach
127.0.0.1.A physical device needs the laptop’s LAN IP (not
localhost), and the laptop’s firewall must allow incoming connections on the configured port (default55333).macOS will prompt the first time the proxy listens — accept the Allow incoming connections dialog.
80.10.3. jdb reports "Internal exception: Unexpected JDWP Error: 100"
This means an unsupported JDWP command was invoked. The session itself survives; the most common cause is the IDE asking for something the proxy explicitly stubs (see "Known limitations" above). The debugger’s own message doesn’t say which command it asked for, so the proxy logs it instead:
[jdwp] declining unimplemented command set=2 cmd=13; the debugger
may report "Unexpected JDWP Error: 100"The line is printed once per command, in the proxy’s console. File an issue with the command set and number attached.
80.10.4. The app launches but the breakpoint never fires
Confirm the build hint actually took effect. Inspect the
generated Xcode project’s cn1_globals.h and look for #define
CN1_ON_DEVICE_DEBUG without a leading //. If the line is
still commented out, the build was a release/non-debug build, or
ios.onDeviceDebug wasn’t set as a build hint.
80.10.5. Make the app wait while the proxy and IDE attach
Set ios.onDeviceDebug.waitForAttach=true. The app will block
at startup until the proxy is connected and the IDE tells the
VM to continue.
81. On-Device Debugging (Android)
The companion to the iOS chapter, for the Android side. The motivation
is the same — bugs that only reproduce on a real device or on the
Android emulator — but the implementation is much simpler. The
Dalvik/ART runtime already exposes a JDWP socket per debuggable
process, so there is no desktop proxy and no custom protocol. The
Codename One Maven plugin just orchestrates adb: install the APK,
mark it as the debug-app, launch the activity, forward the JDWP
socket onto localhost, and tail logcat.
Everything below assumes you have the Android platform-tools on your
machine (Android Studio installs them, or
the
standalone package) and adb is reachable through ANDROID_HOME,
ANDROID_SDK_ROOT, or $PATH.
81.1. When to use it
A bug only reproduces on a physical Android device or in the Android emulator and not in the Codename One simulator.
You want to single-step through your code while it runs on the device, with full access to locals, fields, and the
Display.getInstance()…accessor chains.You want to attach without a USB cable — the wireless flow below covers both the legacy
adb tcpippath and the Android 11+adb pairpath.
If the bug reproduces in the simulator, stay in the simulator — its debugger is faster and has zero device-side moving parts.
81.2. Quick start (IntelliJ IDEA)
Projects generated from the cn1app-archetype ship with two run
configurations under the On-Device Debug folder: CN1 Android
On-Device Debug and CN1 Attach Android. The flow is:
81.2.1. 1. Enable the build hint
In common/codenameone_settings.properties, uncomment the line the
archetype generated:
codename1.arg.android.onDeviceDebug=trueThe build hint name is android.onDeviceDebug. Entries in
codenameone_settings.properties use the codename1.arg. prefix, as
shown above.
This flips the generated AndroidManifest.xml to
debuggable="true" and disables R8/proguard so symbols and locals
survive the build. Release builds (anything without this hint) are
unaffected.
81.2.2. 2. Build the APK
Either the cloud build (cn1:buildAndroidOnDeviceDebug — wraps
cn1:buildAndroid and force-sets the hint above) or your usual
cn1:buildAndroid once the hint is set. Both produce a signed,
debuggable APK in the project’s target/ directory.
For a fully local build, use cn1:buildAndroidGradleProject to
generate the Gradle project under target/…-android-source/ and
run ./gradlew assembleDebug from there; the Mojo will autodetect
the resulting APK under build/outputs/apk/.
81.2.3. 3. Connect the device
Plug a device in over USB with USB debugging enabled, or connect wirelessly (see Wireless debugging below).
81.2.4. 4. Run the debug session from IntelliJ
Select CN1 Android On-Device Debug from the Run-config dropdown and click ▶ Run (the green play icon — not the bug icon). The Run tool window prints:
Using adb: /Users/you/Library/Android/sdk/platform-tools/adb Target device: emulator-5554 Installing my-app-1.0.apk on emulator-5554 Marking com.example.myapp as the debug app (waits for debugger). Launching com.example.myapp.MyAppStub App PID on device: 12345 ================================================================== JDWP forwarded: localhost:5005 -> device pid 12345 Attach IntelliJ: Run -> 'CN1 Attach Android' (Remote JVM Debug) ==================================================================
After that banner, logcat output (filtered to the app’s PID) streams
through the Run window prefixed with [device].
81.2.5. 5. Attach the debugger
Switch the Run-config dropdown to CN1 Attach Android and click 🐞
Debug. IntelliJ connects to localhost:5005 and opens a Debug tool
window. The app is paused inside Debug.waitForDebugger() at this
point — set your breakpoints, then resume from the IDE to let it
proceed past boot.
Set breakpoints, step, inspect, evaluate expressions — all the normal remote-attach features work. Unlike the iOS path, there is no method-invocation or static-field limitation here; the JVM is the real Android runtime.
81.3. Wireless debugging
81.3.1. Android 11 and newer (recommended)
On the device: Settings → Developer options → Wireless debugging → Pair device with pairing code. Note the IP & port (for example
192.168.1.42:37051) and the six-digit pairing code.Pair from your laptop (this only has to be done once per network):
adb pair 192.168.1.42:37051 # When prompted, enter the 6-digit code shown on the device.Connect:
adb connect 192.168.1.42:5555The connect port is not the pairing port — it’s the one shown on the Wireless debugging screen above the Pair device button.
Run the debug session as normal. Pass the IP and port through the Mojo if you prefer to do the
adb connectin one step:mvn cn1:android-on-device-debugging \ -Dcn1.android.onDeviceDebug.wireless=192.168.1.42:5555
81.3.2. Android 10 and older
Plug the device in over USB.
Switch adb to TCP/IP mode and grab the device’s IP from Settings → About phone → Status:
adb tcpip 5555 adb connect 192.168.1.42:5555Unplug the cable, then run the debug session as normal.
In either flow, the JDWP forward, app launch, and logcat stream all happen over the same Wi-Fi link.
81.4. Quick start (Maven from the command line)
Without the IntelliJ run configs, the same flow is two terminals:
# Terminal 1 — build the APK once
mvn cn1:buildAndroidOnDeviceDebug
# Terminal 2 — install, launch, forward JDWP, tail logcat
mvn cn1:android-on-device-debuggingAttach jdb (or another JDWP client) to the forwarded port:
jdb -attach localhost:5005 \
-sourcepath src/main/java:$HOME/.m2/repository/com/codenameone/codenameone-core/8.0-SNAPSHOT/codenameone-core-8.0-SNAPSHOT-sources.jarFor VS Code (Debugger for Java extension), add a launch
configuration of type java with "request": "attach",
"hostName": "localhost", "port": 5005.
81.5. Useful command-line flags
The Mojo’s defaults match what the archetype’s run config does. The flags below exist for unusual setups:
| Property | Meaning |
|---|---|
| Use a specific adb executable (default: search |
| Force a target device when more than one is online
( |
| Run |
| Local TCP port for |
| Skip APK autodetection and install this APK instead. |
| Skip the install step — the app is already on the device. |
| Don’t run |
81.6. What you can step through
Everything runs in one Dalvik/ART process, so the JDWP attach sees every class loaded by the app. In practical terms:
Your common-module Java (
com.<yourcompany>.<app>., anything under the-commonmodule’ssrc/main/java). Breakpoints work out of the box — this is the module the *CN1 Attach Android run config is scoped to, so IntelliJ resolves the source pane and the variables view from your common-module classpath.Your android-module Java or Kotlin (
src/main/javaof the-androidmodule — native interface implementations, custom Activities, Android-only helpers). Open the file and set a breakpoint; the IDE’s Remote JVM Debug config doesn’t restrict which module breakpoints live in, the<module>setting only decides which module’s classpath is used to display state. If the variables view ever looks empty when you stop inside-androidcode, switch the run config’s Use classpath of module to the-androidmodule and reattach.Codename One framework code in
codenameone-coreand the Android port (com.codename1.impl.android.*such asAndroidImplementationandCodenameOneActivity). Both need source resolution — see the next section.*Native C/C via the NDK* is *not* debuggable through this path. JDWP only speaks JVM. If you've added native sources through the Android NDK, attach Android Studio's LLDB to the same process for C/C debugging — the two attaches are independent and can run side-by-side against one device.
81.7. Pointing the IDE at the Codename One sources
The Android runtime serves real .class files, so the IDE only needs
the matching .java files to render the source pane. The same two
options cover both codenameone-core and the Android port
(codenameone-android):
Maven sources jars (recommended). IntelliJ resolves
codenameone-core-<version>-sources.jarandcodenameone-android-<version>-sources.jarautomatically once you run Maven → Reimport with "Sources" enabled in the Maven settings.Local clone of the Codename One GitHub repository. In IntelliJ: Run → Edit Configurations… → CN1 Attach Android → Configuration → Source roots → +. Add two entries: the clone’s
CodenameOne/srcdirectory for the framework core, andPorts/Android/srcforAndroidImplementationand the rest of the Android port.
Without a source path, breakpoints in framework classes still trigger and locals / fields still read — you’ll just see "Sources not found" in the editor when stepping into framework code.
81.8. Debugging the generated Gradle project from Android Studio
Everything above drives a Codename One-built APK through adb. The
alternative is to open the generated Android project itself in Android
Studio and use it like any native Android app — useful when you’re
debugging native interface code, working on the Android port, or want
Android Studio’s profiler and layout inspector:
Local build:
mvn cn1:buildAndroidGradleProjectwrites a complete Gradle project undertarget/…-android-source/. Open that directory in Android Studio (current versions open it directly — no Gradle version fiddling required), connect a device, and press Debug.Cloud build: check the Include Source flag in Codename One Settings before sending the build, then download the sources result from the build server and open it the same way.
When iterating, regenerate the project rather than hand-merging files — the generated project is a build artifact, not a source of truth.
For native C/C++ added through the NDK, attach Android Studio’s LLDB to the process; as noted in Section 81.6, “What you can step through”, the LLDB and JDWP attaches are independent and can run side by side against one device.
81.9. Troubleshooting
81.9.1. "No Android device is online"
adb devices returns nothing useful. Common causes:
The device’s USB debugging toggle is off, or the per-laptop RSA fingerprint prompt is still pending on-device.
The cable is power-only (some short USB-C cables are charge-only).
For wireless: pairing expired (Android 11+) or the laptop is on a different Wi-Fi network.
81.9.2. "Multiple devices online"
Pass -Dcn1.android.onDeviceDebug.deviceSerial=<serial> (run
adb devices to see serials). The emulator’s serial looks like
emulator-5554; a USB-attached phone is its hardware ID; a wireless
device is <ip>:<port>.
81.9.3. App installs but won’t pause for the debugger
waitForAttach only takes effect when the APK is built with
android.onDeviceDebug=true (or android.xapplication_attr
containing android:debuggable="true"). Verify by running
adb shell dumpsys package <your.package> | grep flags — DEBUGGABLE
must be in the list. If it isn’t, rebuild with
mvn cn1:buildAndroidOnDeviceDebug.
81.9.4. Breakpoint never fires
Check the CN1 Attach Android run config:
Host is
localhost, Port matches thejdwpPortprinted by the debug session.The Use module classpath dropdown is the
-commonmodule, so IntelliJ can resolve your.javafiles.
If a class loaded on the device doesn’t match the class IntelliJ
thinks is current, breakpoints stop firing with no error message.
Rebuild and reinstall (cn1:buildAndroidOnDeviceDebug + re-run
CN1 Android On-Device Debug).
81.9.5. logcat shows the app exiting with Debug.waitForDebugger-like noise
The system killed the process for taking too long to attach. Set
-Dcn1.android.onDeviceDebug.waitForAttach=false and trigger the
code path you want to debug manually after attach — Android’s debug-app
wait isn’t bound to the breakpoint, only to process start.
81.9.6. Wireless connection drops mid-session
Wi-Fi connections to debug-mode devices are sensitive to power-saving.
On the device, keep the screen on (or set Settings → Developer
options → Stay awake while charging). For long sessions, plug into
USB and use adb -s <wireless-serial> to keep the wireless TCP socket
alive without depending on the radio.
82. Working with JavaScript
This section covers the Codename One JavaScript port, which allows you to compile your app as native JavaScript and run it inside a browser. This is different from the BrowserComponent and other methods of displaying HTML/JavaScript inside a Codename One app.
82.1. Choosing the JavaScript compiler
JavaScript builds use the ParparVM-based JavaScript port by default. The same builder is available to all Codename One accounts and is also used by the local local-javascript Maven target.
Cloud builds retain the original TeaVM port as a public fallback. Select the compiler with the javascript.port build hint:
| Value | Behavior |
|---|---|
| Use the current ParparVM/JavaScriptPort builder. This is the default. |
| Use the legacy TeaVM builder. |
For example, add javascript.port=teavm to codenameone_settings.properties to diagnose a ParparVM-specific regression. An unknown value fails the build instead of selecting a different compiler.
82.2. Troubleshooting build errors
If your JavaScript build fails, download the error log and inspect the first compiler error. The following error applies specifically to the fallback TeaVM builder:
"Method XXX wasn’t found"
TeaVM uses its own Java runtime library. It’s complete, but you may occasionally run into methods that haven’t been implemented. If you run into errors saying that certain classes or methods weren’t found, please post them to the Codename One issue tracker. You can also work around these by changing your own code to not use such functions. If this missing method doesn’t fall on a critical path on your app, you can also force the app to still build despite this error by adding the javascript.stopOnErrors=false build hint.
82.3. ZIP, WAR, or preview: What’s the difference
The default ParparVM builder produces a static browser ZIP and, unless proxy packaging is disabled or an external proxy is configured, a deployable proxy bundle. The deployable bundle is a Jakarta Servlet WAR by default. Use javascript.proxy.target to select another deployment platform as described in Section 82.4, “Setting up a proxy for network requests”.
The legacy TeaVM builder can result in up to three different bundles:
YourApp-1.0.war
YourApp-1.0.zip
YourApp-1.0-Preview.html
YourApp-1.0.war is the legacy TeaVM self-contained application bundle. It can be installed in a Java EE servlet container and includes the old javax.servlet proxy implementation. New ParparVM builds use the current proxy profiles below and default to Jakarta Servlet.
As an example, the PropertyCross.war file contains the following files:
$ jar tvf PropertyCross-1.0.war
0 Thu Apr 30 15:57:38 PDT 2015 META-INF/
132 Thu Apr 30 15:57:36 PDT 2015 META-INF/MANIFEST.MF
0 Thu Apr 30 15:57:36 PDT 2015 assets/
0 Thu Apr 30 15:57:36 PDT 2015 assets/META-INF/
0 Thu Apr 30 15:57:36 PDT 2015 js/
0 Thu Apr 30 15:57:36 PDT 2015 teavm/
0 Thu Apr 30 15:57:36 PDT 2015 WEB-INF/
0 Thu Apr 30 15:57:36 PDT 2015 WEB-INF/classes/
0 Thu Apr 30 15:57:36 PDT 2015 WEB-INF/classes/com/
0 Thu Apr 30 15:57:36 PDT 2015 WEB-INF/classes/com/codename1/
0 Thu Apr 30 15:57:36 PDT 2015 WEB-INF/classes/com/codename1/corsproxy/
0 Thu Apr 30 15:57:36 PDT 2015 WEB-INF/lib/
27568 Thu Apr 30 15:57:12 PDT 2015 assets/CN1Resource.res
306312 Thu Apr 30 15:57:12 PDT 2015 assets/iOS7Theme.res
427737 Thu Apr 30 15:57:12 PDT 2015 assets/iPhoneTheme.res
350 Thu Apr 30 15:57:12 PDT 2015 assets/META-INF/MANIFEST.MF
92671 Thu Apr 30 15:57:12 PDT 2015 assets/theme.res
23549 Thu Apr 30 15:57:14 PDT 2015 icon.png
2976 Thu Apr 30 15:57:14 PDT 2015 index.html
30695 Thu Apr 30 15:57:12 PDT 2015 js/fontmetrics.js
84319 Thu Apr 30 15:57:12 PDT 2015 js/jquery.min.js
13261 Thu Apr 30 15:57:12 PDT 2015 progress.gif
2816 Thu Apr 30 15:57:12 PDT 2015 style.css
1886163 Thu Apr 30 15:57:36 PDT 2015 teavm/classes.js
359150 Thu Apr 30 15:57:36 PDT 2015 teavm/classes.js.map
1147502 Thu Apr 30 15:57:36 PDT 2015 teavm/classes.js.teavmdbg
30325 Thu Apr 30 15:57:36 PDT 2015 teavm/runtime.js
1011 Thu Apr 30 15:57:18 PDT 2015 WEB-INF/classes/com/codename1/corsproxy/CORSProxy.class
232771 Wed Nov 05 17:35:12 PST 2014 WEB-INF/lib/commons-codec-1.6.jar
62050 Wed Apr 15 14:35:56 PDT 2015 WEB-INF/lib/commons-logging-1.1.3.jar
590004 Wed Apr 15 14:35:58 PDT 2015 WEB-INF/lib/httpclient-4.3.4.jar
282269 Wed Apr 15 14:35:56 PDT 2015 WEB-INF/lib/httpcore-4.3.2.jar
14527 Wed Apr 15 14:35:56 PDT 2015 WEB-INF/lib/smiley-http-proxy-servlet-1.6.jar
903 Thu Apr 30 15:57:12 PDT 2015 WEB-INF/web.xml
9458 Thu Apr 30 15:57:14 PDT 2015 META-INF/maven/com.propertycross/PropertyCross/pom.xml
113 Thu Apr 30 15:57:36 PDT 2015 META-INF/maven/com.propertycross/PropertyCross/pom.propertiesSome things to note in this file listing:
The index.html file is the entry point to the application.
CORSProxy.class is the proxy servlet for making network requests to other domains.
The assets directory contains all your application’s jar resources. All resource files in your app will end up in this directory.
The
teavmdirectory contains all the generated JavaScript for your application. Notice that there are some debugging files generated (classes.js.map and classes.js.teavmdbg). These aren’t loaded by the browser when your app is run, but they can be used by Chrome when you’re doing debugging.The jar files in the WEB-INF/lib directory are dependencies of the proxy servlet. They aren’t required for your app to run - unless you’re using the proxy.
YourApp-1.0.zip is appropriate for deploying the application on any web server. It contains all the same files as the .war file, excluding the WEB-INF directory (that is, it doesn’t include any servlets, class files, or Java libraries - it contains purely client-side JavaScript files and HTML).
As an example, this is a listing of the files in the zip distribution of the PropertyCross demo:
$ unzip -vl PropertyCross-1.0.zip
Archive: /path/to/PropertyCross-1.0.zip
Length Method Size Ratio Date Time CRC-32 Name
-------- ------ ------- ----- ---- ---- ------ ----
27568 Defl:N 26583 4% 04-30-15 15:57 9dc91739 assets/CN1Resource.res
306312 Defl:N 125797 59% 04-30-15 15:57 0b5c1c3a assets/iOS7Theme.res
427737 Defl:N 218975 49% 04-30-15 15:57 3de499c8 assets/iPhoneTheme.res
350 Defl:N 241 31% 04-30-15 15:57 7e7e3714 assets/META-INF/MANIFEST.MF
92671 Defl:N 91829 1% 04-30-15 15:57 004ad9d7 assets/theme.res
23549 Defl:N 23452 0% 04-30-15 15:57 acd79066 icon.png
2903 Defl:N 1149 60% 04-30-15 15:57 e5341de1 index.html
30695 Defl:N 7937 74% 04-30-15 15:57 2e008f6c js/fontmetrics.js
84319 Defl:N 29541 65% 04-30-15 15:57 15b91689 js/jquery.min.js
13261 Defl:N 11944 10% 04-30-15 15:57 51b895c7 progress.gif
2816 Defl:N 653 77% 04-30-15 15:57 a12159c7 style.css
1886163 Defl:N 315437 83% 04-30-15 15:57 2b34c50f teavm/classes.js
359150 Defl:N 92874 74% 04-30-15 15:57 30abdf13 teavm/classes.js.map
1147502 Defl:N 470472 59% 04-30-15 15:57 e5c456f7 teavm/classes.js.teavmdbg
30325 Defl:N 5859 81% 04-30-15 15:57 46651f06 teavm/runtime.js
-------- ------- --- -------
4435321 1422743 68% 15 filesYou’ll notice that it has many of the same files as the .war distribution. It’s missing the proxy servlet and dependencies.
YourApp-1.0-Preview.html is a single-page HTML file with all the application’s resources embedded into a single page. This is generated for convenience so that you can preview your application on the build server directly. While you could use this file in production, you’re probably better to use the ZIP or WAR distribution instead as some mobile devices have file size limitations that may cause problems for the "one large single file" approach. If you do decide to use this file for your production app (that is, copy the file to your own web server), you will need to change the proxy settings, as it’s configured to use the proxy on the Codename One build server - which won’t be available when the app is hosted on a different server.
82.4. Setting up a proxy for network requests
The Codename One API includes a network layer (the NetworkManager and ConnectionRequest classes) that allows you to make HTTP requests to arbitrary destinations. When an application is running inside a browser as a JavaScript app, it’s constrained by the same origin policy. You can make network requests to the same host that served the app originally.
For example, If your application is hosted at http://example.com/myapp/index.html, then your app will be able to perform network requests to retrieve other resources under the example.com domain, but it won’t be able to retrieve resources from example2.com, foo.net, etc.
The HTTP standard does support cross-origin requests in the browser via the Access-Control-Allow-Origin HTTP header. Some web services supply this header when serving resources, but not all. The way to be make network requests to arbitrary resources is to do it through a proxy. |
A ParparVM JavaScript build generates a same-origin proxy wrapper by default and configures the application to use /cn1-cors-proxy?_target=. Select its platform with the javascript.proxy.target build hint:
| Value | Generated deployment bundle |
|---|---|
| A Jakarta Servlet WAR for current containers such as Tomcat 10.1 or newer. This is the default. |
| A Servlet 4 WAR for older containers such as Tomcat 9. |
| A Node.js 20 application ZIP that serves both the static app and the proxy. |
| A PHP 8 application ZIP containing the static app, proxy endpoint, and Apache rewrite configuration. |
| An AWS SAM/Node.js 20 proxy ZIP. Static assets are included under |
| A Google Cloud Functions/Node.js 20 proxy ZIP. Static assets are included under |
| A Cloudflare Worker ZIP with a static-assets binding. |
| Don’t generate a proxy deployment bundle. |
Restrict a generated proxy before deploying it publicly. Set javascript.proxy.allowedTargets to a comma-separated list of allowed origins, host names, or wildcard subdomains. For example:
javascript.proxy.allowedTargets=https://api.example.com,*.services.example.org
If this hint is omitted, the generated proxy accepts any HTTP or HTTPS target and the build emits a warning.
Proxy hint precedence is explicit:
javascript.inject_proxy=falsedisables proxy generation and URL injection.javascript.proxy.urlconfigures an existing external proxy and suppresses generated proxy packaging unlessjavascript.proxy.targetis also set.javascript.proxy.target=nonedisables generated proxy packaging.Otherwise,
javascript.proxy.targetselects the bundle, defaulting tojakarta-servlet.
82.4.1. Step 1: Setting up a proxy
| You can skip this step when deploying one of the generated ParparVM wrappers. Use it when you host only the static ZIP or want to operate the proxy independently. |
For a ParparVM build, select the matching generated wrapper with javascript.proxy.target. The old cors-proxy project remains relevant only to legacy TeaVM WARs and older Java EE deployments.
If you don’t want to install the .war file, but would rather copy the proxy servlet into an existing web project, you can do that also. See the cors-proxy wiki for more information about this.
82.4.2. Step 2: Configuring your application to use the proxy
There are three ways to configure your application to use your proxy.
Using the javascript.proxy.url build hint.
E.g.:
javascript.proxy.url=http://example.com/myapp/cn1-cors-proxy?_target=
By modifying your app’s index.html file after the build.
E.g.:
<script type="text/javascript"> window.cn1CORSProxyURL='http://example.com/myapp/cn1-cors-proxy?_target='; </script>By setting the
javascript.proxy.urlproperty in your Java source. You would do this inside yourinit()method, but it has to be executed before you make a network request that requires the proxy.Display.getInstance().setProperty( "javascript.proxy.url", "http://example.com/myapp/cn1-cors-proxy?_target=" );
The method you choose will depend on the workflow that you prefer. Options #1 and #3 will almost always result in fewer changes than #2 because you’ve to set them up once, and the builds will retain the settings each time you build your project.
82.5. Using the CORS proxy for same origin requests
By default, the CORS proxy is used for HTTP requests to URLS at a different domain than the one that the app is running in. Some circumstances where you may want to even use the proxy for same domain requests. You can do this by setting the javascript.useProxyForSameDomain display property to true. For example:
Display.getInstance().setProperty("javascript.useProxyForSameDomain", "true");Why would you want to do this?
The browser shields some HTTP headers (for example, "Set-Cookie") from JavaScript so that your app can’t access them. Going through the proxy works around this limitation by copying and encoding such headers in a format that the browser will allow, and then decoding them client-side to make them available to your app seamlessly.
82.5.1. Using apache as a proxy
If you’re hosting your application on an Apache 2 web server with mod_proxy installed, and you need to make CORS requests to a single domain (or a limited set of domains), you can use Apache to serve as your proxy. One sample configuration (which you would place either in your VirtualHost definition or your .htaccess file is as follows:
SSLProxyEngine on ProxyPass /app https://www.myexternaldomain.com ProxyPassReverse /app https://www.myexternaldomain.com
This tells Apache to proxy all requests for '/app' to the domain https://www.myexternaldomain.com. You would then need to set your CORS proxy URL in your CN1 app to /app/.
The syntax is the same if you’ve multiple domains, but keep attention to the order of the lines to make the proxy working. For example:
SSLProxyEngine on ProxyPass /app https://www.myexternaldomain1.com ProxyPassReverse /app https://www.myexternaldomain1.com ProxyPass /storage https://www.myexternaldomain2.com ProxyPassReverse /storage https://www.myexternaldomain2.com
This tells Apache to proxy all requests for '/app' to the domain https://www.myexternaldomain1.com and all requests for '/storage' to the domain https://www.myexternaldomain2.com
82.6. Customizing the splash screen
Since your application may include many resource files, videos, etc., the build-server will generate a splash screen for your app to display while it’s loading. This basically shows a progress indicator with your app’s icon.
You can customize this splash screen by modifying the HTML source inside the cn1-splash div tag of your app’s index.html file:
<div id="cn1-splash">
<img class="icon" src="icon.png"/>
<img class="progress" src="progress.gif"/>
<p>...Loading...</p>
</div>82.7. Debugging
If you run into problems with your app that occur in the JavaScript version, you may need to do a little bit of debugging. Many debugging tools for JavaScript, but the preferred tool for debugging Codename One apps is Chrome’s debugger.
If your application crashes and you don’t have a clue where to begin, follow these steps:
Load your application in Chrome.
Open the Chrome debugger.
Enable the "Pause on Exceptions" feature, then click the "Refresh" button to reload your app.
Step through each exception until you reach the one you’re interested in. Chrome will then show you a stack trace that includes the name of the Java source file and line numbers.
Figure 366. Debugging using Chrome tools
82.8. Including Third-Party JavaScript libraries
Codename One allows you to interact directly with JavaScript using native interfaces. Native interfaces are placed inside your project’s native/JavaScript directory using a prescribed naming convention. If you want to, include third-party JavaScript libraries in your application you should also place these libraries inside the native/JavaScript directory but you must specify which files should be treated as "libraries" and which files are treated as "resources." You can do this by adding a file with extension .cn1mf.json file either the root of your native/JavaScript directory or the root level of the project’s src directory.
82.8.1. Libraries vs resources
A resource is a file whose contents can be loaded by your application at runtime using Display.getInstance().getResourceAsStream(). In a typical Java environment, resources would be stored on the application’s classpath (usually inside a Jar file). On iOS, resources are packaged inside the application bundle. In the JavaScript port, resources are stored inside the APP_ROOT/assets directory. Historically, JavaScript files have always been treated as resources in Codename One, and many apps include HTML and JavaScript files for use inside the BrowserComponent.
With the JavaScript port, it isn’t quite so clear whether a JavaScript file is meant to be a resource or a library that the application itself uses. Most of the time you probably want JavaScript files to be used as libraries, but you might also have JavaScript files in your app that are meant to be loaded at runtime and displayed inside a Web View - these would be considered resources.
82.8.2. The JavaScript manifest file
To differentiate libraries from resources, you should provide a cn1mf.json file inside your native/JavaScript directory that specifies any files or directories that should be treated as libraries. This file can be named anything you like, as long as its name ends with cn1mf.json. Any files or directories that you list in this manifest file will be packaged inside your app’s includes directory instead of the assets directory. It adds appropriate <script> tags to include your libraries as part of the index.html page of your app.
If you include the cn1mf.json file in your project’s src directory it could be used to add configuration parameters to platform’s other than JavaScript (although no other platforms use this feature). If you place it inside your native/JavaScript directory, then the JavaScript port will use the configuration contained therein. |
A simple manifest file might contain the following JSON:
{
"javascript" : {
"libs" : [
"mylib1.js"
]
}
}That is, It contains an object with key libs whose value is a list of files that should be treated as libraries. In the above example, you’re declaring that the file native/JavaScript/mylib1.js should be treated as a library. This will result in the following <script> tag being added to the index.html file:
<script src="includes/mylib1.js"></script>
This also caused the mylib1.js file to be packaged inside the includes directory instead of the assets directory. |
| A project may contain more than one manifest file. This allows you to include manifest files with your cn1libs also. You need to make sure that each manifest file has a different name. |
How to NOT generate the script tag
Sometimes you may want a JavaScript file to be treated as a library (that is, packaged in the includes directory) but not automatically included in the index.html page. Rather than specifying the name of the file in the libs list, you can provide a structure with multiple options about the file. For example,
{
"JavaScript" : {
"libs" : [
"mylib1.js",
{
"file" : "mylib2.js",
"include" : false
}
]
}
}In the above example, the mylib2.js file will be packaged inside the includes directory, but the build server won’t insert its <script> tag in the index.html page.
Library directories
You can also specify directories in the manifest file. In this case, the entire directory will be packaged inside the includes directory of your app.
If you’re including JavaScript files in your app that are contained inside a directory hierarchy, you should specify the root directory of the hierarchy in your manifest file and use the sub "includes" property of the directory entry to specify which files should be included with <script> tags. Specifying the file directly inside the "libs" list will result in the file being packed directly in the your app’s includes directory. This may or may not be what you want. |
For example,
{
"javascript" : {
"libs" : [
"mylib1.js",
{
"file" : "mylib2.js",
"include" : false
},
{
"file" : "mydir1",
"includes" : ["subfile1.js", "subfile2.js"]
}
]
}
}In this example the entire mydir1 directory would be packed inside the app’s includes directory, and the following script tags would be inserted into the index.html file:
<script src="includes/mydir1/subfile1.js"></script> <script src="includes/mydir1/subfile2.js"></script>
Libraries included from a directory hierarchy may not work with the single file preview that the build server generates. For that version, it will embed the contents of each included JavaScript file inside the index.html file, but the rest of the directory contents will be omitted. If your the library depends on the directory hierarchy and supporting files and you require the single-file preview to work, then you may consider hosting the library on a separate server, and including the library directly from there, rather than embedding it inside your project’s "native/JavaScript" directory. |
Including remote libraries
The examples so far have demonstrated the inclusion of libraries that are part of the app bundle. But, you can also include libraries over the network by specifying the URL to the library directly. This is handy for including common libraries that are hosted by a CDN.
For example, The Google Maps library requires the Google Maps API to be included. This is accomplished with the following manifest file contents:
{
"javascript" : {
"libs" : [
"//maps.googleapis.com/maps/api/js?v=3.exp"
]
}
}| This example uses the "//" prefix for the URL instead of specifying the protocol directly. This allow the library to work for both http and https hosting. You could but specify the protocol as well: |
+
{
"javascript" : {
"libs" : [
"https://maps.googleapis.com/maps/api/js?v=3.exp"
]
}
}Including CSS files
CSS files can be included using the same mechanism as is used for JavaScript files. If the file name ends with .css, then it will be treated as a CSS file (and included with a <link> tag instead of a <script> tag. For example,
{
"JavaScript" : {
"libs" : [
"mystyles.css"
]
}
}or
{
"JavaScript" : {
"libs" : [
"https://example.com/mystyles.css"
]
}
}Embedding variables in URLs
Sometimes the URL of a library may depend on the values of some build hints in the project. For example, in the Google Maps cn1lib, the API key must be appended to the URL of the API as a GET parameter. For example, https://maps.googleapis.com/maps/api/js?v=3.exp&key=SOME_API_KEY, but the developer of the library doesn’t want to put his own API key in the manifest file for the library. It would be better for the API key to be supplied by the developer of the actual app that uses the library and not the library itself.
The solution for this is to add a variable into the URL as follows:
{
"JavaScript" : {
"libs" : [
"//maps.googleapis.com/maps/api/js?v=3.exp&key={{javascript.googlemaps.key}}"
]
}
}The {{javascript.googlemaps.key}} variable will be replaced with the value of the javascript.googlemaps.key build hint by the build server, so the resulting include you see in the index.html page will be something like:
<script src="//maps.googleapis.com/maps/api/js?v=3.exp&key=XYZ"></script>82.9. Browser environment variables
Native interfaces allow you to interact with the JavaScript environment in unlimited ways, but Codename One provides a simpler method of obtaining some common environment information from the browser via the Display.getInstance().getProperty() method. The following environment variables are currently available:
| Name | Description |
|---|---|
| A String, representing the entire URL of the page, including the protocol (like http://) |
| A String, representing the querystring part of a URL, including the question mark (?) |
| A String, representing the domain name and port number, or the IP address of a URL |
| A String, representing the anchor part of the URL, including the hash sign (#) |
| A String, representing the protocol (including ://), the domain name (or IP address) and port number (including the colon sign (:) of the URL. For URLs using the "file:" protocol, the return value differs between browsers |
| A String, representing the pathname |
| A String, representing the protocol of the current URL, including the colon (:) |
| A String, representing the port number of a URL. + Note: If the port number isn’t specified or if it’s the scheme’s default port (like 80 or 443), an empty string is returned |
| A String, representing the domain name, or the IP address of a URL |
| The User-agent string identifying the browser, version etc. |
| The language code that the browser is currently set to. (for example, en-US) |
| the name of the browser as a string. |
| a string that must be an empty string or a string representing the platform on which the browser is executing.
+
For example: |
| the internal name of the browser |
| the version number of the browser |
| Specifies the deployment type of the app. This will be "file" for the single-file preview, "directory" for the zip distribution, and "war" for the war distribution. |
82.10. Changing the native theme
The JavaScript port selects a bundled native theme from the detected browser platform. You can override this behavior by setting the javascript.native.theme Display property to the path of a theme included with your app. Place additional JavaScript-only themes in the native/javascript directory so they aren’t bundled into other platforms.
82.11. Disabling the 'OnBeforeUnload' handler
By default, apps will display warning/confirm dialog when the user attempts to leave the page.

You can explicitly enable or disable this behaviour by setting the "platformHint.javascript.beforeUnloadMessage" display property. Setting the property to null will disable this behaviour, so that users won’t be harassed by this dialog when they navigate away from the app. Setting it to a string value, like "leaving so soon?," will re-enable this behaviour.
| Some browsers don’t allow you to specify the message that’s displayed in this dialog. In those browsers, this property can be viewed as boolean: A null value will result in no prompt being shown, and a non-null value will result in a prompt being shown. |
82.11.1. Example: Toggling the BeforeUnload prompt On/Off
Form f = new Form("Test Before Unload", BoxLayout.y());
CheckBox enableBeforeUnload = new CheckBox("Enable Before Unload");
enableBeforeUnload.setSelected(true);
enableBeforeUnload.addActionListener(e->{
if (enableBeforeUnload.isSelected()) {
CN.setProperty("platformHint.javascript.beforeUnloadMessage", "Are you sure you want to leave this page? It might be bad");
} else {
CN.setProperty("platformHint.javascript.beforeUnloadMessage", null);
}
});
f.add(enableBeforeUnload);
f.show();82.12. Deploying as a progressive web app
Out of the box, your app is ready to be deployed as a progressive web app (PWA). That means that users can access the app directly in their browser, but once the browser determines that the user is frequenting the app, it will prompt the user to install the app on their home screen. Once installed on the home screen, the app will behave like a native app. It will continue to work while offline, and if the user launches the app, it will open without the browser’s navigation bar. If you were to install the native and PWA versions of your app side by side, you would be hard-pressed to find the difference - especially on newer devices.
Below is a screenshot from Chrome for Android where the browser is prompting the user to add the app to their home screen.

If the app is available as a native app, in the Play store, you can indicate this using the javascript.manifest.related_applications and javascript.manifest.prefer_related_applications build hints. Then, instead of prompting the user to add the web app to their home screen, they’ll be prompted to install the native app from the Play store, as shown below.

The PWA standard requires that you host your app on over HTTPS. For testing purposes, it will also work when accessed at a localhost address. You can use the Lighthouse PWA analysis tool to ensure compliance. |
For more information about Progressive Web Apps see Google’s introduction to the subject.
82.12.1. Customizing the app manifest file
At the heart of a progressive web app is the web app manifest. It specifies things like the app’s name, icons, description, preferred orientation, display mode (for example, whether to display browser navigation or to open with the full screen like a native app), associated native apps, etc. The Codename One build server will automatically generate a manifest file for your app but you can (and should) customize this file via build hints.
Build hints of the form javascript.manifest.XXX will be injected into the app manifest. For example, To set the app’s description, you could add the build hint:
javascript.manifest.description=An app for doing cool stuff
You can find a full list of available manifest keys here. The build server will automatically generate all the icons so you don’t need to worry about those. The "name" and "short_name" properties will default to the app’s display name, but they can be overridden via the javascript.manifest.name and javascript.manifest.short_name build hints respectively.
The javascript.manifest.related_applications build hint expects a JSON formatted list, like in the raw manifest file. |
82.12.2. Related applications
One nice feature (discussed above) of progressive web apps, is the ability to specify related applications in the app manifest. Browsers that support the PWA standard use some heuristics to "offer" the user to install the associated native app when it’s clear that the user is using the app on a regular basis. Use the javascript.manifest.related_applications build hint to specify the location of the native version of your app. For example, javascript.manifest.related_applications=[{"platform":"play", "id":"my.app.id"}]
You can declare that the native app is the preferred way to use the app by setting the javascript.manifest.prefer_related_applications build hint to "true."
| According to the app manifest documentation, this should be used if the related native apps do offer something that the web application can’t do. |
82.12.3. Device/Browser support for PWAs
Chrome and Firefox both support PWAs on desktop and on Android. iOS doesn’t support the PWA standard, however, many aspects of it are supported. For example, On iOS you can add the app to your home screen, after which time it will appear and behave like a native app - and it will continue to work while offline. However, many other nice features of PWA like "Install this app on your home screen" banners, push notifications, and invitations to install the native version of the app, aren’t supported. It’s unclear when, or even, whether Apple will ever add full support; but most experts predict that they will join the rest of the civilized world and add PWA support in the near future.
On the desktop, Chrome provides an analogous feature to "add to your homescreen": Add to shelf. If it looks like the user is using the app on a regular basis, and it isn’t yet installed, it will show a banner at the top of the page asking the user if they want to add to their shelf.

Clicking the "Add button" prompts the user for the name they wish the app to appear as:

Upon submission, Chrome will generate a real application (on Mac, it will be a .app, on Windows, an "exe," etc.) which the user can double-click to open the app directly in the Chrome. And, importantly, the app will still work when the user is offline.
The app will also appear in their "Shelf" which you can always access at chrome://apps, or by opening the "Chrome App Launcher" app (on OS X this is located in "~/Applications/Chrome Apps/Application Launcher").

| The Chrome App Launcher lists apps installed both via the Chrome Web Store and via the "Add to Shelf" feature discussed here. The features described in this article are orthogonal to the Chrome Web Store and won’t be affected by its closure. |
82.13. Playing media and opening links
People don’t like it when the browser automatically starts playing sounds, or opening links without their permission. For this reason, modern browsers restrict your ability to programmatically do these things, unless they’re in response to a user action, like a mouse click.
If your app needs to play media (for example, Media.play()) without the user actually interacting physically (for example, key press or pointer press), then it will display a popup dialog confirming that the user actually wants to perform this action. Opening a link (for example, Display.execute("…")) used to do the same, but now defaults to navigating the current page instead of prompting — see Opening links below.
Sometimes this dialog may affect the utility of the app. For example, suppose you want to play a video in response to a voice command. Having to press an "OK" button after the command, may be annoying. For such cases, you can use the platformHint.javascript.backsideHooksInterval property to poll for media play requests on an authorized event.
For example:
CN.setProperty("platformHint.javascript.backsideHooksInterval", "1000");
// Now your app will process media.play() and Display.execute(null) calls
// once per second (1000ms). If play() or execute() has been called anytime
// in that second (since the last poll), it will seamlessly process the
// request.
// To disable polling, just set it to an interval 0 or lower.
// for example, CN.setProperty("platformHint.javascript.backsideHooksInterval", "0");| Don’t abuse this feature. You should enable this polling when necessary. For example, If your app enables the user to listen for voice commands, enable polling for the period of time that it’s listening. When the user wants to stop listening, you should also stop the polling by setting the interval to "0." |
82.13.1. Choosing where a link opens
Opening a link deserves its own note, because the restriction above bites almost every app that calls Display.execute(). Codename One dispatches events on its own EDT, so by the time your action listener runs, the browser no longer sees the tap as an ongoing user gesture and refuses to open a new window. Navigating the page the app already runs in has no such restriction: it always works, at the cost of unloading the app.
The port picks between those two with the javascript.execute.target property:
| Value | Behavior |
|---|---|
| The default. Opens a new tab while the page still has user activation, and navigates the current page when it doesn’t. No confirmation sheet is ever shown. |
| Only ever opens a new tab. When the browser blocks that, the port shows a confirmation sheet whose OK button supplies the gesture the browser wanted. This was the behavior before the property existed. |
| Always navigates the page the app runs in. |
// The default. Opens a new tab while the browser still considers a
// user gesture to be in progress, and navigates the page the app runs
// in when it doesn't. Never shows a confirmation sheet.
CN.setProperty("javascript.execute.target", "auto");
// Always navigate the page the app runs in. Never blocked and never
// prompts, but it unloads the app.
CN.setProperty("javascript.execute.target", "_self");
// Only ever open a new tab. When the browser blocks that, the port
// shows a confirmation sheet whose OK button supplies the gesture the
// browser wanted. This was the behavior before the property existed.
CN.setProperty("javascript.execute.target", "_blank");
CN.execute("https://www.codenameone.com/");Under auto and _self the app is unloaded whenever the current page navigates away, so persist anything you need before you call execute(). Pick _blank when keeping the app alive matters more than avoiding the sheet. |
The property applies to any URL the browser can hand off, which means anything carrying a URI scheme. Custom deep links such as imdb:///find?q=godfather count, and so do protocol-relative //host/path URLs. The exceptions keep their existing meaning: a javascript: URL still evaluates on the page, and a data: URL, a file: URL or a path into local storage still becomes a download.
82.14. BrowserComponent lifecycle
On the JavaScript port, BrowserComponent uses an iframe that’s added to the DOM when the component is initialized. Understanding the lifecycle is important when showing Dialog`s over forms that contain `BrowserComponent instances.
82.14.1. Dialogs and BrowserComponent
When a Dialog is shown, the parent Form is deinitialized. This causes any BrowserComponent instances on that form to also be deinitialized, which removes their iframes from the DOM. When the Dialog is dismissed and the parent form is re-shown, the BrowserComponent is reinitialized with a new iframe, losing all JavaScript state.
This affects:
Stateful embedded editors - content and cursor position lost
WebRTC connections - broken when removed from DOM
Interactive visualizations - charts, maps, diagrams with JavaScript state
Any JavaScript state - event listeners, variables, etc.
82.14.2. Preserving BrowserComponent state
To preserve the iframe and its JavaScript state across deinitialization cycles, set the HTML5Peer.removeOnDeinitialize client property to Boolean.FALSE:
BrowserComponent browser = new BrowserComponent();
browser.putClientProperty("HTML5Peer.removeOnDeinitialize", Boolean.FALSE);This keeps the iframe in the DOM even when the component is deinitialized, preserving all JavaScript state.
82.14.3. Lifecycle example
Without the property set:
Dialog.show()is calledParent
Form’s `deinitialize()is calledBrowserComponentis deinitialized, iframe removed from DOMDialog is dismissed
Parent
Form’s `initComponent()is calledBrowserComponentcreates a new iframe - JavaScript state is lost
With removeOnDeinitialize=false:
Dialog.show()is calledParent
Form’s `deinitialize()is calledBrowserComponentis deinitialized, but iframe stays in DOMDialog is dismissed
Parent
Form’s `initComponent()is calledBrowserComponentreconnects to the existing iframe - JavaScript state preserved
83. Working with macOS
83.1. macOS Desktop Build Options
Launch Codename One Settings from the Maven project root and open Hints to configure desktop.mac.* build hints such as entitlements and Info.plist entries:
mvn cn1:settings
Desktop signing values that aren’t build hints are top-level entries in common/codenameone_settings.properties: codename1.desktop.mac.certificate contains the .p12 path and codename1.desktop.mac.certificatePassword contains its password. The Maven desktop macOS build reads these properties together with the desktop.mac.* hints.
83.1.1. Bundle Types
Three bundle types dictate what the build server produces for you when you build your project as a Desktop macOS App.
DMG - Produces a
.DMGdisk image with your app. This is the preferred format for distributing your app outside of the Mac App Store. If you provide a Developer ID Application certificate (see "Understanding Certificates" below), the app will be signed so that users won’t receive warnings about "Unidentified developer" when they install your app.Sandboxed DMG - Same as DMG bundle type except that your app is set up to use the app sandbox. This is typically used to test an app that’s being distributed via the App Store, since App Store apps must use the sandbox. If you select this bundle type, you’re required to provide a Mac App Distribution Certificate, and you should also specify entitlements required for your app to function correctly. For more information about the app sandbox, see Apple’s documentation on the subject.
Mac App Store Upload (PKG) - Produces a
.PKGfile that you can upload to the Mac App Store. This requires that you provide both a Mac App Distribution certificate, and a Mac App Installer certificate (see "Understanding Certificates" below). Both of these certificates should be embedded into a single.p12file (See "Exporting Certificates as p12" below).
83.1.2. Understanding Mac Certificates
Currently (as of Jan. 5, 2020) the mac.desktop-vm build hint is ignored if you include a certificate with your app. This limitation should be fixed soon. |
For the purposes of Mac application distribution, there are 3 types of certificates that you will be interested in. The type(s) of certificate required will depend on the type of bundle you generate. The certificate types are:
Developer ID Application Certificate (Mac applications)
This type of certificate is used to sign an app to be distributed outside of the Mac App Store as a DMG image. This corresponds to the "DMG" bundle type. You can identify this kind of certificate because its identity will be of the form "Developer ID Application: YOUR COMPANY NAME (SOMECODE)." For example, Developer ID Application: Acme Widgets Corp. (XYSD5YF).
Mac App Distribution Certificate (Mac App Store)
This type of certificate is used to sign the.app bundle for an app that’s to be distributed in the Mac App Store. This certificate is required for both the "Sandboxed DMG," and "Mac App Store Upload (PKG)" bundle types. You can identify this kind of certificate because its identity will be of the form "3rd Party Mac Developer Application: YOUR COMPANY NAME (SOMECODE)." For example, 3rd Party Mac Developer Application: Acme Widgets Corp. (XYSD5YF).
Mac App Installer Certificate (Mac App Store)
This type of certificate is used to sign the.pkg installer for an app that’s being submitted to the Mac App Store. This certificate is required for the "Mac App Store Upload (PKG)" bundle type. You can identify this kind of certificate because its identity will be of the form "3rd Party Mac Developer Installer: YOUR COMPANY NAME (SOMECODE)." For example, 3rd Party Mac Developer Installer: Acme Widgets Corp. (XYXD5YF).
83.1.3. Obtaining Certificates
| Apple provides documentation on obtaining certificates on its website but the process described there involves Xcode. This section describes an alternate process that doesn’t require Xcode. |
If you have an Apple developer account, you can manage your certificates here.

The screenshot above shows an account that already has the three kinds of certificates you will require:
Developer ID Application - Used for the DMG bundle type.
Mac App Distribution - Used for the Sandboxed DMG and Mac App Store Upload (PKG) bundle types.
Mac App Installer - Used for the Mac App Store Upload (PKG) bundle type.
If your account doesn’t yet have a certificate of the required type, you should begin by pressing the "+" button in the upper right. This will bring you to a page asking "What type of Certificate do you need?" Two options on this page will interest you:

Production > Mac App Store - For both the Mac App Distribution and Mac App Installer certificates.
Production > Developer ID - For the Developer ID Application certificate.
Select the option corresponding to the certificate you wish to generate. In either case, you’ll be taken to a form to select whether you want an "Installer" certificate or an "Application" certificate. Select the appropriate type.
You will then be prompted to upload a Certificate Signing Request (CSR) file, and it will provide instructions on how to do this via the Keychain app.
| You can reuse the same CSR file for generating all 3 certificates. |
After generating the certificates, you should download them to your Mac, and import them into your keychain. You should be able to accomplish this by simply double-clicking the downloaded ".cer" file, and following the prompts.
83.1.4. Exporting Certificates as P12
| The following section requires access to a Mac, and assumes that you’ve already generated your 3 certificates |
Notice that Mac apps may require three different kinds of certificates, yet codename1.desktop.mac.certificate accepts a single P12 file. This isn’t a mistake. P12 files may contain more than one certificate, and you’re expected to include all the certificates that the build server may require inside a single P12. The build server automatically extracts the certificates it needs according to the bundle type.
When building the "DMG" bundle type, the build server will look for a "Developer ID Application Certificate" inside the P12. If one is found, it will be used to sign the app bundle.
The "Sandboxed DMG" target will look for a "Mac App Distribution Certificate" certificate in the P12.
The "Mac App Store Upload (PKG)" target will require both a "Mac App Distribution Certificate" and a "Mac App Installer Certificate" to be included in the P12.
The easiest way to produce a P12 that includes all 3 kinds of certificates is to export them from the Keychain Access app (Requires a Mac). Select all 3 certificates at once (using CMD-click), then right-click and select "Export 3 Items…"

You will then be prompted to select a location to save the .p12 file, as well as selecting a password for the file.
83.1.5. Entitlements
When distributing apps in the Mac App Store, or when using the "Sandboxed DMG" bundle type, your app is run inside a sandboxed environment, meaning that it doesn’t have access to the outside world. It’s provided its own "sandboxed" container for file system access, and it doesn’t get any network access. If your app requires access to the "outside world," request the required entitlements with desktop.mac.entitlement. entries in the *Hints view.
For more information about the app sandbox, and a full list of entitlements, see Apple’s documentation on the subject.
You can specify entitlements using the build hint desktop.mac.entitlement.XXXX where XXX is the entitlement you wish to set. For example, desktop.mac.entitlement.com.apple.security.network.client=true |
83.1.6. Custom Info.plist Entries
You can add custom entries to the Info.plist file using the following build hints:
- desktop.mac.plist.KEYNAME
Injects the entry with key
KEYNAMEinto the Info.plist file. For example,desktop.mac.plist.LSApplicationCategoryType=public.app-category.business
83.2. Mac Native Build (AOT-compiled macOS App)
The "macOS Desktop" section above covers the JavaSE bundled-JRE wrapper. Mac Native is a separate, AOT-compiled target: it routes through the same iOS pipeline (ParparVM bytecode-to-C, native UIKit) so the resulting macOS app shares its rendering code path, its memory profile, and its certificate story with your iPhone / iPad build. The output is a single signed .app bundle suitable for Mac App Store or Developer ID distribution.
This target is a good fit when:
Your app already builds against the iOS slice and you want a Mac version that looks and behaves the same.
You need native-speed startup and rendering on Mac, not a wrapped JVM.
You want a single AppKit-grade
.appbundle without bundling a JRE.
Java source is shared with the iOS target; no separate Mac-specific code is required.
83.2.1. Local Build
To generate an Xcode project locally that you can open and run on the Mac:
mvn -B -Dcodename1.platform=ios -Dcodename1.buildTarget=mac-source packageThe output is written to:
target/<finalName>-mac-source/<MainClass>.xcodeproj
Open the project in Xcode, select the Mac Catalyst destination, and press Run. The resulting .app is identical in shape to one produced by the cloud build server.
83.2.2. Cloud Build
To produce a release-ready signed Mac app on the Codename One build server:
mvn -B -Dcodename1.platform=ios -Dcodename1.buildTarget=mac-os-x-native packageMac distribution requires its own certificates and provisioning profile — Apple issues separate Mac App Distribution (3rd Party Mac Developer Application) and Developer ID Application certificates that aren’t interchangeable with the iPhone Distribution certificate used for iOS App Store builds. Configure them via the parallel codename1.mac.* hints:
| Hint | Purpose |
|---|---|
| Mac bundle identifier (the App Store Connect record is distinct from the iOS one). |
| Path to the |
| Password to unlock the P12. |
| Path to the Mac |
The Apple Developer Team ID itself can stay shared with the iOS slice (single Apple Developer account) — macNative.teamId falls back to ios.release.teamId when not set. The server returns a signed .app bundle.
83.2.3. IDE Shortcuts
The IntelliJ workspace template ships two Mac Native run configurations alongside the iOS ones:
Mac Native Project (Local Builds folder) — equivalent to running
mvn package -Dcodename1.buildTarget=mac-source. Use this to generate the Xcode project for hands-on debugging.Mac Native Build (Build Server folder) — equivalent to
mvn package -Dcodename1.buildTarget=mac-os-x-native. Use this for cloud builds.
83.2.4. Distribution
The Mac Native build supports both Mac App Store and Developer ID distribution. The generated Xcode project includes two ExportOptions-*-Mac.plist files in dist/:
ExportOptions-AppStore-Mac.plist— App Store distribution (sandboxed, hardened runtime off).ExportOptions-DeveloperID-Mac.plist— Developer ID distribution (hardened runtime on, sandbox off).
After archiving in Xcode, run:
xcodebuild -exportArchive \
-archivePath build/<MainClass>.xcarchive \
-exportOptionsPlist dist/ExportOptions-AppStore-Mac.plist \
-exportPath build/export83.2.5. Entitlements
The Mac Native build emits a <MainClass>.entitlements plist (or <MainClass>-AppStore.entitlements + <MainClass>-DeveloperID.entitlements when both channels are configured). The defaults are sensible: App Sandbox on for the App Store channel, hardened runtime on for the Developer ID channel, network client access enabled, user-selected file access enabled. The signing-certificate identity defaults to Apple Distribution for the App Store channel and Developer ID Application for the Developer ID channel.
83.2.6. Supported Distribution Channels
| Channel | Notes |
|---|---|
App Store | Sandboxed, hardened runtime off. Signed with Apple Distribution; uploaded via App Store Connect. |
Developer ID | Hardened runtime on, sandbox off. Signed with Developer ID Application; notarized before distribution. |
84. App Store Submission and Deployment
Once a build is signed you still have to get it in front of users: upload the binary, fill in the release notes, set the store listing, and send it for review — on every store where your users are. Codename One automates that last mile as a one-stop shop. From the build console you can submit a finished build to the App Store, the Mac App Store, Google Play, and Huawei AppGallery with one click, manage the store listing itself — title, description, keywords, what’s-new, screenshots — as code in your project, and produce per-store Android packages so you can reach the large Android audience that isn’t on Google Play.
Reaching those audiences doesn’t depend on, and can’t be restricted by, any single store. Google Play always receives the standard, unmodified Android App Bundle, so your Play listing follows Google’s rules exactly; the additional channels (AppGallery and other Android markets) are separate artifacts delivered to separate stores.
This chapter covers the end-to-end flow, credentials, the metadata-as-code workflow, and multi-store Android distribution. It builds on Signing: submission reuses the same App Store Connect API key the certificate wizard configures.
84.1. What it does, and what it doesn’t
Automated submission delivers the binary and applies your release metadata to an existing app on the store. It doesn’t create the app for you.
| You must create the app once, by hand, in App Store Connect and/or the Google Play Console before you can submit to it. Neither store’s API can register a brand-new app, set up pricing, in-app purchases, the privacy questionnaire, or the content-rating questionnaire — those remain one-time manual steps in the store consoles. After that, every release’s binary and listing can be shipped automatically. |
Three things are worth separating, because they happen at different times:
The app record — the listing shell in the store. Created once, manually, and exists before any build.
The binary — produced by your build, delivered when you submit.
The metadata — description, what’s-new, screenshots. Managed as code and applied when you submit. Metadata attaches to the app record and the new version, not to the binary, so there’s no chicken-and-egg problem: the app already exists on the store by the time you build.
84.2. Prerequisites
84.2.1. Store credentials
Apple. Submission uses the App Store Connect API key described under
the certificate wizard. If you have already run
mvn cn1:certificatewizard and stored the key, you are ready — the same key that
creates certificates and profiles also uploads builds and manages listings.
Google. Create a Google Play service account with the Android Publisher role in the Google Play Console (API access > Service accounts), download its JSON key, and add it to the build console’s submission credentials page. The console shows which stores are connected.
Huawei. In AppGallery Connect, create an API client under Users and permissions > API client and note its Client ID and Client Secret, then add them on the same submission credentials page. The app must already exist in AppGallery Connect (submission binds to the app resolved from your package name).
The Submissions page shows a connect card for each store you haven’t configured yet; fill one in and save to enable one-click submission to that store.

84.2.2. Beta vs production
When you submit you choose a destination. Beta means TestFlight (Apple) or the internal-testing track (Google). Production means App Store review (Apple) or the production track (Google).
84.3. Submitting a build from the console
On any successful build the console shows a Submit action for each store the build can go to:
Submit to App Store — when the build produced an iOS
.ipa.Submit to Mac App Store — when the build produced a native/Catalyst
.pkg(see the Working with macOS chapter). An iOS build that also produced a.pkgoffers both.Submit to Google Play — for an Android build.
Submit to AppGallery — for an Android build, to Huawei AppGallery. Production sends the build for review; the beta destination uploads it and leaves it as a draft for you to promote or open-test.
The submit dialog lets you pick the destination (Beta or Production) and add release notes for this submission, then delivers the binary. For an Apple production submission the console then tracks the App Store review state (processing → in review → approved/rejected) and can email you when the state changes. Google submissions and TestFlight deliveries complete as soon as the binary is delivered.
| Submitting to Production on Apple opens an App Store review submission automatically. Submitting to Beta delivers to TestFlight without opening a review. |
84.4. Metadata as code
Release metadata — the store listing text and screenshots — can live in your project as a folder of plain text and image files, versioned in git alongside your code, and pushed to the stores with a single command. This makes your listing reproducible and CI-drivable: generate release notes from your changelog, push, and the next submission applies it to both stores. It’s the alternative to typing the same fields into two different web consoles by hand for every release.
84.4.1. The metadata folder
By default the goal reads a cn1-metadata folder next to your
codenameone_settings.properties. It’s organized by store, then locale, with one
plain text file per listing field:
cn1-metadata/
apple/
primary_locale.txt (optional; defaults to the first locale)
primary_category.txt (optional; an App Store Connect category id)
secondary_category.txt (optional)
en-US/
name.txt (app name, max 30 chars)
subtitle.txt (max 30 chars)
description.txt (max 4000 chars)
keywords.txt (comma separated, max 100 chars)
promotional_text.txt (max 170 chars)
whats_new.txt (release notes for this version)
marketing_url.txt
support_url.txt
privacy_url.txt
screenshots/
APP_IPHONE_67/1.png 2.png ...
APP_IPAD_PRO_129/1.png ...
google/
en-US/
name.txt (listing title, max 30 chars)
subtitle.txt (short description, max 80 chars)
description.txt (full description, max 4000 chars)
whats_new.txt (release notes, max 500 chars)
support_url.txt
screenshots/
phoneScreenshots/1.png 2.png ...
tenInchScreenshots/1.png ...Every file is optional; a field you don’t include keeps whatever value the store
already has. The same neutral file names map to each store’s fields (for example
subtitle.txt becomes the App Store subtitle and the Google Play short
description). Fields a store doesn’t have (Apple keywords/promotional_text)
are simply ignored for the other store.
The screenshots/<dir> sub-folders are named with each store’s own type
identifiers: App Store screenshotDisplayType values (for example
APP_IPHONE_67) for Apple, and listing imageType values (for example
phoneScreenshots) for Google. Images are uploaded in filename order.
You don’t have to create the folder by hand. Run mvn cn1:metadata-init to
scaffold cn1-metadata with an empty template of the field files, a screenshots
folder, and a README, ready to fill in: |
+
mvn cn1:metadata-init # apple + google, en-US
mvn cn1:metadata-init -Dstore=apple -Dlocale=fr-FR+ It only creates what’s missing, so it’s safe to re-run (for example to add a new locale) — it never overwrites files you’ve already filled in.
84.4.2. Pushing the metadata
Run the goal from your project; it authenticates with the same Codename One
account your builds use (run mvn cn1:certificatewizard once to sign in, or pass
-Dtoken=):
# push both stores from cn1-metadata/
mvn cn1:metadata-push
# or a single store
mvn cn1:metadata-push -Dstore=apple
# override the folder or the package id if needed
mvn cn1:metadata-push -DmetadataDir=path/to/metadata -Dpackage=com.example.appThe package id defaults to codename1.packageName from
codenameone_settings.properties. The goal validates every field against the
store’s limits before storing it, so an over-long name or a malformed URL fails
fast with a clear message. Wire it into CI to keep the stored listing in sync with
your repo.
metadata-push uploads the descriptor and screenshots to Codename One; it
does not submit. The stored metadata is applied to the store the next time you
submit a build for that package. |
84.4.3. When and how it’s applied
At submission time the stored descriptor is applied to the store automatically:
Apple — applied to the production App Store version (App Store review), while the version is still editable. TestFlight has no store listing, so beta Apple submissions don’t apply listing metadata.
Google — applied to the listing on the edit that publishes the binary, on any track.
Applying metadata is best-effort: the binary is delivered first, so a rejected field (say a name that’s too long, or a locale the app hasn’t enabled) never blocks the submission — it’s recorded as a warning you can see in the console, and the rest of the listing still applies. You can always fix a field by hand in the store console afterward.
84.4.4. Screenshots aren’t stored long-term
Screenshots are a transient pass-through: metadata-push uploads them, the next
submission delivers them to the store, and they’re then deleted from Codename
One’s servers. Keep the canonical images in your repo (that’s the point of
managing them as code) and re-push when they change. Text descriptors are retained
until you delete them, your account is deleted, or they go unused for about a year.
Per-image limits: up to 10 MB, PNG or JPEG, and at most 10 screenshots per locale and display type (the stores' own limit).
84.5. Reaching Android users beyond Google Play
A large share of Android users — most of the market in China, and many devices elsewhere — can’t install from Google Play. Reaching them means shipping to other Android stores: Huawei AppGallery, and the many app markets run by device makers and carriers (Xiaomi, OPPO, VIVO, Tencent MyApp, Baidu, 360 and others). Codename One makes your app available on those stores without changing how you build or locking you to any of them.
Huawei AppGallery is a first-class submission target, exactly like the App Store or Google Play (see Submitting a build above). For the remaining Android markets, Codename One produces distribution-channel packages.
84.5.1. Distribution-channel packages
Most of these stores accept a plain, self-signed APK rather than an App Bundle, and they attribute each download and its revenue to the store it came from. A distribution-channel package is your signed release APK stamped with a store identifier — one APK per store, all built from the same release.
You choose the stores; the build produces one package per store, each carrying its
channel id. Your app reads that id at runtime with
Display.getInstance().getProperty("DistributionChannel", "") — an empty string
for a normal Google Play build — so you can report the install source (to your own
analytics or the store’s) without adding any third-party channel SDK. Codename One
writes the id and reads it back for you.
| Google Play is never a channel package. Play always receives the standard, unmodified Android App Bundle, so nothing about this feature affects your Play listing or its compliance — the channel packages are separate APKs for separate stores. |
Sensible defaults keep this simple: enable it and you get packages for the major Android markets out of the box, and you can narrow or extend the channel list to match the stores you actually publish to. Each package is signed with your app’s release key, so every store receives a signed, installable APK.
84.6. Benefits over editing the stores by hand
Managing submission and metadata through Codename One pays off most for teams, frequent releases, many locales, or many apps:
Automated release notes. Generate what’s-new from your changelog and ship it to both stores on every release — the one field that always changes.
One source, two stores. A single descriptor fans out to App Store Connect and Google Play, which have different fields and limits.
Reproducible and reviewable. The listing lives in git, versioned and code-reviewed like everything else. Console edits have no history.
Localization at scale. Localized listings are just files, and can be generated or translated in a pipeline.
Fewer console logins. Team members who ship releases don’t each need App Store Connect or Play Console access; they ship through the build pipeline instead.
For a single app with infrequent updates, editing the store console by hand is fine — the payoff scales with how often you release and how many listings you maintain.
85. Desktop Integration
Codename One is mobile-first, but the same app can run on the desktop: as a Java SE
“Run as desktop app” / executable jar, and as a native macOS app via the local
mac-source (Mac Catalyst) build target. By default a desktop build looks like a phone
app in a window - a mobile-style Toolbar at the top of every Form, fading touch
scrollbars, and commands tucked into a hamburger side menu.
The desktop integration features make a desktop build feel like a desktop app:
A native window title bar that shows the
Formtitle (instead of the in-appToolbar).A native menu bar populated from your
Commandobjects, with per-command placement hints (About, File, Edit, Quit, …).Interactive scrollbars - a draggable thumb that highlights on hover and while dragged, click-to-page on the track, a minimum thumb size so it stays easy to grab on long content, a reserved gutter so content isn’t drawn under the bar, and an always-visible (rather than fading) scrollbar.
Keyboard accelerators on the native menu items (a Save shortcut, a Quit shortcut).
Native desktop notifications driven by the standard
LocalNotificationAPI.
These behaviors are opt-in. They’re switched on by default for newly generated projects
(both the Maven archetype and the start.codenameone.com initializr) and stay completely
inert on phones/tablets - all the new behavior is gated on CN.isDesktop(), so a mobile
build of the same project is unaffected.
85.1. Title-bar modes
The window chrome is selected by the desktop.titleBar setting, which takes one of three values:
| Hide the CN1 |
| Undecorated window (no OS title bar) where the CN1 |
| Legacy behavior - the in-app CN1 |
The screenshots below show the same notes app, with File / Edit / View / Help commands, in each mode on macOS.

native mode: the Form title is in the OS window title bar, the commands populate the native menu bar, and there is no in-app Toolbar
custom mode: the window is undecorated and the CN1 Toolbar (title + hamburger side menu) is the window’s title bar; the commands are also in the native menu bar
toolbar mode: the legacy look - the in-app Toolbar sits below a generic OS title bar and the commands live in the hamburger side menu85.1.1. Enabling it on the Java SE desktop build
For the desktop (Java SE) target the mode is a build hint that the generated desktop launcher
applies for you. In codenameone_settings.properties:
codename1.arg.desktop.titleBar=native
codename1.arg.desktop.interactiveScrollbars=trueNewly generated projects already contain these lines. The generated <MainName>Stub reads them
at startup, so no code is required. Because the stub is the desktop entry point, the settings only
ever take effect on the desktop.
85.1.2. Enabling it on the macOS (Mac Catalyst) build
The local mac-source build runs through ParparVM and the iOS port, where the chrome is provided
by native UIWindowScene / UIMenuBuilder code. There it’s read as a runtime property and
defaults to toolbar, so existing Catalyst apps are unaffected. Opt in from your app before the
first Form is shown:
Display.getInstance().setProperty("desktop.titleBar", "native");
Display.getInstance().setProperty("desktop.interactiveScrollbars", "true");| The native title bar and native menu bar on macOS require iOS 13 / macOS 10.15 (Catalyst) or newer. On a phone/tablet iOS build these properties are ignored. |
85.2. Native menu bar and command placement hints
When the Toolbar is hidden (native or custom mode), the commands you add through the
Toolbar / Form command API are bridged to the platform’s native menu bar - a Swing JMenuBar
(which becomes the macOS screen menu) on the Java SE build, and a UIMenuBuilder menu on Catalyst.
Selecting a menu item runs the command’s actionPerformed on the Codename One EDT, exactly as a
button press would.
By default every command lands under a single Commands menu. To place commands into the
conventional desktop menus, tag them with a desktop-menu hint using Command.setDesktopMenu(String)
and the Command.DESKTOP_MENU_* constants:
Form hi = new Form("My App", BoxLayout.y());
Command about = new Command("About My App");
about.setDesktopMenu(Command.DESKTOP_MENU_ABOUT); // application menu
Command open = new Command("Open Filenull");
open.setDesktopMenu(Command.DESKTOP_MENU_FILE); // File menu
Command quit = new Command("Quit");
quit.setDesktopMenu(Command.DESKTOP_MENU_QUIT); // application menu
hi.addCommand(about);
hi.addCommand(open);
hi.addCommand(quit);
hi.show();The recognised values are (case-insensitive):
| Placed in the application menu (the macOS app menu / a leading menu). |
| Placed in the matching standard top-level menu. |
Any other string | Becomes a top-level menu with that literal title. |
Unset | Grouped under a default Commands menu. |
Each port maps the hint to its native structure: on Catalyst the command is inserted into the real
UIMenuApplication / UIMenuFile / UIMenuEdit / … menus; on the Java SE build a top-level
JMenu is created per hint group.
The hint is a plain client property (Command.DESKTOP_MENU), so it’s inert on platforms that
don’t have a native menu bar - it’s safe to set it unconditionally in shared code. |
85.2.1. Keyboard accelerators
Give a command a keyboard accelerator with Command.setDesktopShortcut(…). The shortcut is shown
next to the menu item and triggers the command from the keyboard:
Command save = new Command("Save");
save.setDesktopMenu(Command.DESKTOP_MENU_FILE);
save.setDesktopShortcut('S'); // Cmd+S on macOS, Ctrl+S on Windows/Linux
Command saveAs = new Command("Save Asnull");
saveAs.setDesktopMenu(Command.DESKTOP_MENU_FILE);
saveAs.setDesktopShortcut('S',
Command.DESKTOP_SHORTCUT_MODIFIER_PRIMARY | Command.DESKTOP_SHORTCUT_MODIFIER_SHIFT);The single-argument form uses the platform’s primary modifier - Command on macOS, Control on
Windows/Linux - which is the right default for most menu shortcuts. The
two-argument form takes a bit-mask of Command.DESKTOP_SHORTCUT_MODIFIER_PRIMARY,
Command.DESKTOP_SHORTCUT_MODIFIER_SHIFT and Command.DESKTOP_SHORTCUT_MODIFIER_ALT. On the
Java SE build the accelerator becomes a Swing KeyStroke; on Catalyst it becomes a UIKeyCommand.
Like the placement hint, the accelerator is inert on platforms without a native menu bar, so it’s
safe to set unconditionally.
85.3. Interactive scrollbars
Enabling desktop.interactiveScrollbars turns the scrollbar from a fading touch indicator into a
desktop-style control:
The thumb can be grabbed and dragged, and it highlights while the pointer hovers it and while it’s being dragged (the
DesktopScrollThumbselected / pressed styles).Clicking the track pages toward the pointer by about one viewport.
The thumb has a minimum size so it stays easy to grab even when the content is far taller than the viewport. The minimum (in pixels) is the
scrollThumbMinSizeInttheme constant; when unset it defaults to the equivalent of 4mm.A gutter is reserved for the scrollbar so content isn’t laid out underneath it. The gutter width comes from the
DesktopScroll/DesktopHorizontalScrollUIID padding (see below).The scrollbar stays visible rather than fading out.
This is a cross-platform core feature driven by the interactiveScrollBool theme constant, which
the desktop ports inject only when CN.isDesktop() is true. Mouse-wheel scrolling continues to work
as before.
85.4. Theme UIIDs
When interactive scrollbars are active, the desktop scrollbar is styled through dedicated UIIDs so the
mobile Scroll / ScrollThumb styling is never affected:
| The interactive desktop scrollbar track and thumb. The horizontal-/vertical-scroll UIID’s padding
sets the scrollbar gutter width. The thumb UIID’s |
The modern native themes ship platform-conventional defaults for these UIIDs (macOS-style in the iOS
theme, Material-style in the Android theme), including the .selected / .pressed thumb highlight
states; see Chapter 5, Native modern themes. Override them in your app’s theme.css like any other UIID.
The minimum thumb length is the scrollThumbMinSizeInt theme constant (pixels). In custom mode the
title bar is just the regular CN1 Toolbar, so it’s themed through the usual Toolbar / Title
UIIDs.
85.5. Desktop notifications
The standard com.codename1.notifications.LocalNotification API works on the desktop. On the
Java SE desktop build a scheduled notification surfaces as a native OS notification through the
system tray (Notification Center on macOS, the notification area on Windows/Linux); on the
macOS / Mac Catalyst build it goes through the same UNUserNotificationCenter path as iOS. Clicking
the notification delivers it to your app’s LocalNotificationCallback, exactly as on mobile, so the
same scheduling and handling code is shared across phone and desktop:
On the Java SE build desktop notifications require an OS with system-tray support
(java.awt.SystemTray); where it’s unavailable the notification is logged and skipped. |
86. Working with the native Windows port
The native Windows port compiles a Codename One app to a real, standalone Win32
executable — a single .exe with no JVM and no runtime dependencies. It’s the
Windows analog of the iOS port: the same ParparVM pipeline that turns your Java/
Kotlin bytecode into C and then into a native binary, here targeting Windows with
the LLVM toolchain and rendering through Direct2D / DirectWrite.
This is distinct from the long-standing Windows desktop build, which packages the app to run on a Java Virtual Machine (see Section 86.7, “Native Windows vs. the desktop (JVM) app vs. the jar” for a practical comparison). The native port needs no JVM on the target machine.

.exe (ParparVM + Direct2D/DirectWrite, no JVM)The native Windows port is a young port. It renders, runs and edits text,
but several platform services are still being filled in. Treat it as a foundation
to build on rather than a feature-complete replacement for the desktop build, and
consult the port’s status.md for the current gap list. |
86.1. How it works (the technology stack)
The port reuses Codename One’s portable architecture and swaps in a Win32 / Direct2D implementation layer:
ParparVM "clean" C target. The same VM that powers iOS translates your app
the Codename One core + the minimal Java runtime to C. A CMake project is generated and compiled with clang-cl (LLVM on the MSVC ABI) + Ninja into a native.exe. There is no bytecode interpreter and no JNI — your code is the native binary.Concurrent garbage collector. ParparVM’s non-blocking GC runs natively, the same collector used on iOS.
Direct2D + DirectWrite + WIC. All 2D graphics (primitives, gradients, clipping, affine and perspective transforms, images) go through Direct2D; glyph layout, measurement and rasterization use DirectWrite; image decode/encode uses Windows Imaging Component (WIC). Rendering is GPU-accelerated.
Media Foundation backs
Mediaplayback, and WebView2 backsBrowserComponent(when the WebView2 SDK is present at build time).WinHTTP backs networking; raw sockets and WebSockets use Winsock.
Single self-contained executable. There is no
.app-style bundle directory on Windows, so the app’s classpath resources — the theme.res, images, localization, the material icon font — are embedded directly into the executable’s PE resource section and read back at runtime throughgetResourceAsStream. The result is one file you can copy and run.
86.2. Building a native Windows app
A native Windows build runs through the codenameone-maven-plugin like every
other target; the project produced by the Codename One Initializr already knows
how to build it. The heavy lifting — translate to C, generate the CMake project,
configure and build with clang-cl/Ninja, collect the .exe — is handled by the
builder, so the configuration on your side is trivial.
The build can run two ways, and the builder picks automatically based on the host:
On a Windows host it uses clang-cl + CMake + Ninja inside a Visual Studio developer environment (the CRT and Windows SDK reach the compiler through
vcvarsall).On any other host — for example a Linux build server it cross-compiles with clang-cl + lld-link + llvm-rc against a Windows SDK laid out by
xwin. clang is a cross-compiler, so the PE it emits is identical to a Windows-host build. Point thewindows.sdkRootbuild hint (or theCN1_XWIN_SYSROOTenvironment variable) at thexwin splatdirectory. This is how the build cloud produces Windows binaries without a Windows machine.
Both x64 and arm64 are produced this way — clang-cl cross-compiles to either
architecture from either host; pick the target with the windows.arch build hint.
What you can’t do off Windows is run the result: Direct2D/DirectWrite need a real Windows GPU/display stack (emulation such as Wine is too incomplete to trust), so rendering can only be verified on Windows. A Windows 11 VM (Parallels, Hyper-V, …) or a real machine is therefore the place to test the app, even when the binary itself was built on Linux.
86.3. Cloud builds (the win32 target)
On the Codename One build cloud the native Windows build is the win32 target, and it builds on Linux (the Android/JavaScript build group) using the cross-compile above. Trigger it like any other cloud target:
mvn -pl common package -Dcodename1.platform=windows -Dcodename1.buildTarget=windows-deviceThe convenience goal mvn -pl common cn1:buildWin32 does the same thing. A regular
(release) build returns two binaries — x64 and arm64, both stripped release exes. Setting the
windows.debug build hint instead returns a single x64 exe with symbols, for
diagnosis. (To build locally on a Windows box, use
-Dcodename1.buildTarget=local-windows-device.)
86.4. Build hints
The native Windows port adds the build hints below. They use the windows.
prefix; don’t confuse them with the older win. hints, which configure the
JVM-based Windows desktop installer (win.installDirName, win.shortcutName,
…) and have no effect on the native port.
| Name | Description |
|---|---|
windows.arch | Target CPU architecture for the |
windows.debug |
|
The full cross-platform build-hints reference is in the Advanced topics chapter.
86.5. Optimized, with debug info in a separate file
The shipping build is optimized (/O2): the linker removes unused functions and
folds identical ones (/OPT:REF and /OPT:ICF), and the debug information isn’t
embedded in the executable — it’s written to a separate .pdb companion. The
.exe therefore stays as small as the translated code allows, while a faulting
address can still be turned back into a function name and source line with
llvm-symbolizer against the .pdb. As a concrete data point, the Codename One
Initializr sample builds to an ~8 MB .exe; the matching .pdb is several times
larger but ships beside the binary rather than inside it, and is only needed to
symbolize a crash. Setting windows.debug=true switches to an unoptimized debug
build with full symbols.
86.6. Code signing
Unlike iOS and Android, Windows does not require a signature to run a desktop exe — an unsigned win32 build launches fine. But an unsigned binary that a user downloads shows "Unknown publisher" in the UAC prompt and trips SmartScreen ("Windows protected your PC"), so anything you actually distribute should be Authenticode-signed. Signing is therefore optional in the port (the default is unsigned) but strongly recommended for release.
The port signs with osslsigncode, which
signs Windows PE files on any OS — so signing happens right in the Linux build
cloud, no Windows machine needed. Provide a code-signing certificate and the build
hints below, and each produced exe (x64 and arm64) is signed and timestamped.
86.6.1. Signing with a PKCS#12 certificate
Put your code-signing certificate and key in a PKCS#12 (.pfx/.p12) file and
point your project settings at it:
# codenameone_settings.properties
codename1.windows.signing.certificate=/secure/path/codesign.p12
codename1.windows.signing.password=your-pkcs12-password
# optional signature metadata + timestamping (shown with their defaults):
codename1.arg.windows.signing.name=Acme Corp
codename1.arg.windows.signing.url=https://acme.example
codename1.arg.windows.signing.timestampUrl=http://timestamp.digicert.com
codename1.arg.windows.signing.digest=sha256You configure the certificate once and it’s used for both local and cloud
builds — a cloud build automatically sends it with the build request (the same
way the iOS and Android signing certificates are uploaded), so there is nothing
extra to do for the build cloud. The signature is timestamped (RFC 3161) by
default, so it keeps verifying after the certificate expires; set
windows.signing.timestampUrl empty to turn that off. Set windows.signing=false
to force an unsigned build even when a certificate is configured.
86.6.2. Hardware-backed and cloud keys
Since June 2023 the CA/Browser Forum requires code-signing private keys to live in
a hardware module, so a brand-new OV/EV certificate is no longer a plain .pfx.
The usual answer is a managed signing service — Azure Trusted Signing, DigiCert
KeyLocker, eSigner from SSL.com — which exposes the key through PKCS#11. osslsigncode
speaks PKCS#11, so the build host points at the service’s provider per its docs; the
rest of the flow (digest, timestamp, the resulting signed exe) is identical. Plain
.pfx signing remains fine for internal/test certificates and for certs issued
before the cutoff.
osslsigncode must be on the build host’s PATH (or set CN1_OSSLSIGNCODE
to its location). If signing is requested but the certificate or tool is missing,
the build fails with a clear message rather than shipping an unsigned exe by surprise. |
86.7. Native Windows vs. the desktop (JVM) app vs. the jar
Codename One can produce three different Windows artifacts from the same project. They trade off self-containment, size, startup and maturity differently:
Native Windows .exe | Desktop app (JVM) | Executable jar | |
|---|---|---|---|
Summary | A real Win32 binary (ParparVM → C → native), Direct2D/DirectWrite rendering. | Your app running on a JVM with the Java SE port (Swing-hosted rendering), packaged as a Windows installer. | A runnable |
JVM required on the target? | No — fully self-contained. | No if the installer bundles a JRE; otherwise it relies on one. | Yes — a compatible JDK (11–25) must be installed on the machine. |
Artifact size | One | Largest: app + a bundled JRE (the JRE alone is ~40–70 MB). | Smallest: a few MB (just bytecode); the JVM lives outside it. |
Startup | Native process start — no VM warm-up. | JVM start-up cost. | JVM start-up cost. |
CPU architecture | Native x64 and arm64 binaries ( | Intel x64 only — it ships with a bundled Intel Java 8 JRE (no arm64 build; on an arm64 machine it runs through Windows' x64 emulation). | Whatever the installed JVM supports. |
Look & rendering | Direct2D/DirectWrite, GPU-accelerated; the material native theme. | Swing-hosted Codename One rendering (the simulator’s pipeline). | Same as the desktop app. |
Portability of the artifact | Windows-only, and per-architecture. | Windows-only installer. | Cross-platform — the same jar runs anywhere a supported JVM exists. |
Maturity | Young — a foundation, with gaps (see | Mature, battle-tested. | Mature, battle-tested. |
In practical terms: reach for the native .exe when you want to ship a single
self-contained, JVM-free, architecture-native Windows app that starts instantly;
reach for the desktop (JVM) app when you want the mature, fully featured desktop
experience and don’t mind shipping (or depending on) a JVM; and reach for the
jar when you want the smallest, most portable artifact for machines that already
have a JDK.
== Working with the native Linux port
The native Linux port compiles a Codename One app to a real, standalone Linux executable — a single ELF binary that runs with no JVM. It’s the Linux analog of the iOS and native Windows ports: the same ParparVM pipeline that turns your Java/Kotlin bytecode into C and then into a native binary, here targeting Linux and rendering through GTK3 / Cairo / Pango.
This is distinct from packaging the app as an executable jar that runs on a Java Virtual Machine on Linux (see Section 86.13, “Native Linux vs. the executable jar” for a practical comparison). The native port needs no JVM on the target machine.
86.8. How it works (the technology stack)
The port reuses Codename One’s portable architecture and swaps in a GTK3 / Cairo implementation layer:
ParparVM "clean" C target. The same VM that powers iOS and Windows translates your app + the Codename One core + the minimal Java runtime to C. A CMake project is generated and compiled with
cc/Clang + Ninja into a native ELF. There is no bytecode interpreter and no JNI — your code is the native binary.Cairo + Pango + GdkPixbuf. All 2D graphics (primitives, gradients, clipping, affine transforms, images) go through Cairo; glyph layout, measurement and rasterization use Pango (with FontConfig/FreeType, so bundled fonts — including the material icon font — register and render); image decode/encode uses GdkPixbuf. Windowing and native peers (text editing, browser, video) are GTK3 widgets layered over the Cairo drawing surface.
OpenGL ES (EGL) backs the portable 3D API (
com.codename1.gpu); GStreamer backsMediaplayback, audio recording and the camera; WebKitGTK backsBrowserComponent; libsecret backs secure storage; libnotify backs local notifications; GeoClue backs location; libcurl and POSIX sockets back networking.Single self-contained executable. There is no
.app-style bundle directory, so the app’s classpath resources — the theme.res, images, localization, the material icon font — are embedded directly into the ELF and read back at runtime throughgetResourceAsStream. The result is one file you copy and run.
86.9. Runs on essentially any Linux desktop
Two choices keep the binary portable, so in practice it just runs:
GTK3, dynamically linked. GTK3 has shipped on every Linux desktop since 2011, so its runtime is already present on virtually any machine with a graphical session, and the binary resolves
libgtk-3, Cairo and Pango from the system at startup. (GTK4 is newer and not yet universal, so a GTK4 build would be a separate future target.)An old glibc. The build compiles your app against an old glibc (via
zig cc), so the resulting ELF needs only an ancient, universally present glibc — in practice aroundGLIBC_2.17(2013) — and starts on essentially any glibc desktop from the last decade, no matter how new the build machine is.
The result is one small ELF that runs out of the box across mainstream distros.
Alpine, which uses musl instead of glibc, is an opt-in target — see the
linux.libc build hint below.
86.10. Building a native Linux app
A native Linux build runs through the codenameone-maven-plugin like every other
target. Build it with:
mvn -pl common package -Dcodename1.platform=linux -Dcodename1.buildTarget=local-linux-device cn1:buildThe builder translates the app to C with ParparVM’s linux app type, generates a
CMake project that links the GTK stack via pkg-config, builds it with CMake
Ninja, and produces the ELF.
86.10.1. Build-host dependencies
The native compile needs the GTK development stack and the capability libraries the port links. On Debian/Ubuntu:
sudo apt-get install -y \
cmake ninja-build pkg-config \
libgtk-3-dev libcairo2-dev libpango1.0-dev libgdk-pixbuf-2.0-dev libglib2.0-dev \
libfontconfig1-dev libfreetype-dev libcurl4-openssl-dev \
libgstreamer1.0-dev libgstreamer-plugins-base1.0-dev \
libwebkit2gtk-4.1-dev libsecret-1-dev libnotify-dev libgeoclue-2-dev \
libepoxy-dev libegl1-mesa-dev libgles2-mesa-devThe -dev packages are needed on the *build host. The machine that runs the
binary only needs the corresponding runtime libraries, which any standard desktop
already has.
86.10.2. Architecture and cross-compiling
Both x64 and arm64 are supported; pick the target with the linux.arch build
hint. The build is a native compile — it produces a binary for the host
architecture by default, so the straightforward way to get both is to build on a
machine of each.
You can also cross-compile — and you may well want to, for example producing an
arm64 binary from a build host that itself runs x64. The translated C is architecture-independent,
and the default toolchain (zig cc) is itself a cross-compiler, so it can emit a
binary for a different CPU from the one it runs on. Point linux.cc at a cross
zig cc wrapper for the target triple (or set linux.arch and let the builder
generate one) to cross-build.
86.11. Build hints
The native Linux port adds the build hints below (all use the linux. prefix).
| Name | Description |
|---|---|
linux.arch | Target CPU architecture for the ELF: |
linux.debug |
|
linux.libc |
|
linux.toolchain | Set to |
linux.cc | Override the C compiler CMake uses (for example a |
The full cross-platform build-hints reference is in the Advanced topics chapter.
86.12. Optimized and stripped by default
The shipping build is optimized and stripped: no debug information is embedded, so
the single self-contained executable stays as small as the translated code allows.
Setting linux.debug=true keeps the symbols so a faulting address can be
symbolized during development; the build stays optimized either way.
86.13. Native Linux vs. the executable jar
Before the native port, the way to run a Codename One app on Linux was to package it as an executable jar that runs on a JVM. The two differ in what ships and how it runs:
| Native Linux port | Executable jar | |
|---|---|---|
Needs a JVM on the target? | No — a native ELF | Yes (any installed JRE) |
What ships | One small ELF + the system GTK libraries | A single |
Rendering | GTK3 / Cairo / Pango (native) | Java2D on the JVM |
Startup / footprint | Native, small | JVM startup |
How it’s built | ParparVM → C → ELF (CMake/Ninja) |
|
The native port is the right choice when you want a true native Linux binary with no JVM dependency; the executable jar remains the convenient path for development and for environments where a JVM is acceptable.
86.14. Blocking native calls and the concurrent GC
ParparVM’s garbage collector is concurrent: before it can traverse a lightweight
(CN1-created) thread’s stack it sets that thread’s threadBlockedByGC flag and
spins until the thread parks itself (clears threadActive). A native that parks a
CN1 thread in a long blocking syscall — a socket read/write/connect, an
curl_easy_perform, a sleep — must drop threadActive across the call
(CN1_YIELD_THREAD / CN1_RESUME_THREAD), exactly as every other port does.
Forget it on even one path (for example the cn1ss screenshot reader parked in
read() waiting on the server) and a GC that happens to fire during that window
never completes, deadlocking every thread waiting on it. The Linux port wraps all
of its blocking I/O this way; keep that invariant when adding new native calls.
87. Wearables (Apple Watch and Wear OS)
Codename One builds a watch app from the same project as your phone app, on both Apple Watch and Wear OS. This chapter covers the whole picture: how one project produces two apps, how you run the pair while you develop, how the two apps exchange information, and how to put a complication on a watch face.
87.1. One Project, Two Apps
Declaring a watch lifecycle class next to your phone main class is the entire opt-in:
codename1.mainName=MyApp
codename1.watchMain=com.mycompany.myapp.MyWatchMainThere are no wearable build hints. The watch bundle identifier, deployment target, signing team and display name are all derived from settings your project already has, and one declaration builds the watch app on both platforms.
Note the asymmetry: codename1.mainName is a simple class name resolved against
codename1.packageName, while codename1.watchMain is fully qualified.
What the two apps share is the code base: your classes, your resources, your
theme and your CSS. What they don’t share is anything at runtime. They’re two
apps, on two devices, in two sandboxes, with separate lifecycles. In particular
Storage, Preferences and the SQLite database are per device: writing on
the phone doesn’t make the value appear on the watch. Moving information
between them is what [wearable-data] is for.
The two platforms get there by different routes, which is why their supported feature sets differ:
Wear OS is Android. A Wear OS app is an ordinary Android app that declares the watch hardware feature. The existing Codename One Android port renders the UI through exactly the same pipeline it uses on phones and tablets, so almost everything that works on Android works on the watch.
watchOS isn’t iOS. watchOS has no UIKit view hierarchy, no OpenGL ES and no Metal. The Codename One watchOS port therefore ships a dedicated Core Graphics rendering backend and a separate watch application target that hosts the Codename One runtime (the ParparVM-translated app) inside a SwiftUI shell. The graphics-heavy, GPU-bound and UIKit-peer APIs that have no watchOS equivalent are unavailable on the watch (see [watch-supported-apis]).
Without a watch main class the build is byte-for-byte what it was, so adding one never changes a phone build you already ship.
87.2. Companion or Standalone
By default the watch app is a companion: on Apple Watch it ships inside the phone app and the pair installs together. If the watch app is the product and there is no phone app to pair with, declare it standalone:
codename1.watchStandalone=trueWear OS has no companion form yet. An Android project that sets a watch main
class without codename1.watchStandalone builds the phone APK alone — the
build says so — so a Wear app has to be declared standalone today. Apple Watch
supports both.
On Android a standalone build turns the single APK into the Wear OS app, and that is what ships. On Apple the watch target is built standalone — detached from the phone app rather than embedded in it — but the archive step still targets the phone scheme, so submission needs one manual step in Xcode. See Section 87.8.1, “What the Watch App Runs Today” before you archive.
87.3. Running the Pair While You Develop
The simulator can run both halves. Choose a watch skin (Apple Watch 41mm or 45mm, Wear round or Wear square) to develop the watch UI on its own, or pick Watch → Launch Watch App to start the watch app beside the phone app.
The watch app runs in its own process rather than in another window of the same
one, because that’s what it becomes on a device — a second app with its own sandbox.
The two processes find each other, so sendMessage and putData genuinely
round-trip on your desktop and you can develop the conversation between the two
apps without deploying anything.
| Check your layout against the Wear round skin. A round face is where a design that assumes a rectangle falls apart, and its safe area is inset accordingly. |
87.4. Detecting the Watch Form Factor
Use CN.isWatch() (or Display.getInstance().isWatch()) to branch your UI for
the watch at runtime. This is the wearable analog of the existing isTablet()
and isDesktop() checks:
Form f = new Form(BoxLayout.y());
if (CN.isWatch()) {
// Compact, single-column layout suited to a small round/square screen
f.add(new Label("Hi Watch"));
f.getToolbar().setVisible(false);
} else {
// Full phone/tablet layout
f.add(new SpanLabel("Welcome to the full size application"));
}
f.show();On Android isWatch() is derived from PackageManager.FEATURE_WATCH
(android.hardware.type.watch); on iOS it’s reported natively by the watchOS
runtime. On every other platform it returns false.
isWatch() describes the device form factor, not the screen shape. A Wear
OS device can be round or square; query the display safe-area insets (see
[designing-for-the-watch]) rather than assuming a rectangle. |
87.5. Designing for the Watch
A watch screen is small and is frequently round. A few practical guidelines:
Prefer a single vertical column (
BoxLayout.y()inside aFormthat scrolls on the Y axis). The Digital Crown on Apple Watch and the rotary input on Wear OS scroll the focused scrollable container.Keep interactive targets large and few. There is little room for a
Toolbar, side menu or tabs — hide the title area when you don’t need it.On round screens, keep content away from the corners. Use the form’s safe-area insets so important content isn’t clipped by the rounded bezel.
Use the
"watch"theme/constant overrides if you want a distinct watch look without forking your code (the override layer activates on watch devices the same way platform overrides do elsewhere).
87.6. Sharing Data Between the Phone and the Watch
The two apps share no storage. Storage, Preferences and the SQLite database
are per device, and there’s no container that spans the pair, so a value written
on the phone is simply not on the watch. com.codename1.wearable is the channel
between them, and it’s the same API on Apple Watch and Wear OS.
The platforms offer three transports because they answer three different questions. Choosing the wrong one is the usual reason a watch app "never gets the update":
| You need | Use | Delivered |
|---|---|---|
An answer, now, while both apps are awake |
| Immediately, or it fails |
The peer to end up with the latest value, whenever it next looks |
| Eventually, survives sleep and relaunch |
To move a file or a large blob |
| In the background, possibly much later |
Data the watch needs with no phone involved at all | Ordinary | As usual |
Something rendered while your app isn’t running |
| By the system, from a published timeline |
A message is a phone call: it only connects if someone picks up. Replicated data is a noticeboard: you pin the current value at a path, and the peer reads it whenever it wakes. Reach for data by default and for messages only when you genuinely need an answer now.
87.6.1. Replicating State
Publish on one side:
// On the phone: publish the value the watch should show whenever it next wakes.
WearableConnection.putData(new WearableMessage("/steps")
.put("count", stepCount)
.put("goalReached", stepCount >= 10000));React on the other:
// On the watch: react to it. Register from init(), not from a form -- a value that
// arrived while the app was starting is replayed only to listeners that exist by then.
WearableConnection.addDataListener(new WearableDataListener() {
public void dataChanged(WearableMessage data) {
stepsLabel.setText("" + data.getInt("count", 0));
}
public void dataRemoved(String path) {
stepsLabel.setText("--");
}
});Each path holds one value, so this replicates state rather than queueing events: two rapid updates to the same path may reach the peer as one. That’s what makes it the right default — the peer always converges on the latest value, however long it was away.
Register listeners from your app’s init(). The platform starts an
app purely to hand it a payload, so what arrives may well be the thing that
launched you. Codename One queues those deliveries and replays them on the EDT,
but only to listeners that exist by the time it does. |
87.6.2. Asking a Question
When you need an answer rather than a value, send a message and handle the reply:
// Ask the phone something and use the answer. Only works while both apps are awake,
// so check first and fall back to what you already replicated.
if (WearableConnection.isReachable()) {
WearableConnection.sendMessage(new WearableMessage("/workout/start"),
new WearableReplyHandler() {
public void replyReceived(WearableMessage reply) {
showWorkout(reply.getString("id", null));
}
public void replyFailed(String message) {
Log.p("Could not start the workout: " + message);
}
});
}Then answer it on the other side:
// Answer the watch. Reply quickly and do slow work afterwards -- the sender is waiting.
WearableConnection.addMessageListener(new WearableMessageListener() {
public WearableMessage messageReceived(WearableMessage message, boolean expectsReply) {
if ("/workout/start".equals(message.getPath())) {
return new WearableMessage("/workout/start").put("id", beginWorkout());
}
return null;
}
});A reply is never guaranteed: the peer may be asleep, out of range, or running a
version of your app that doesn’t know the path. replyFailed is the normal
case, not the exceptional one.
87.6.3. Knowing What’s There
isSupported() asks whether the platform provides the link, not whether a watch
is there. It’s false on a desktop build and on any platform with no wearable
API, and every call is then a harmless no-op, so this API needs no platform
conditionals around it — but an iPhone with no paired watch still answers true,
because Apple’s API is present either way.
Ask the other three about the counterpart. isPaired(),
isCompanionAppInstalled() and isReachable() distinguish the cases worth
telling a user about: no watch, a watch without your watch app installed, and a
sleeping watch.
Don’t decide your UI from one call at startup. These answers come from state
queried asynchronously, so the first calls in a cold process can report false for
a device that’s paired — nothing is known until the first query lands. Register
a WearableStateListener and react when the answer changes.
One Android limit is worth knowing. The Data Layer exposes pairing only through
the nodes it knows about, so a paired watch that has never run your watch app
appears in no list and isPaired() reports false until it runs once. Treat
false as "no counterpart known" rather than proof there is none, and prefer
showing setup guidance to hiding it. Apple’s API answers pairing directly and
has no such gap. Gate a wearable feature on those rather than on isSupported(),
or you will offer it to someone holding a phone and nothing else. Add a
WearableStateListener rather than polling.
87.7. Complications and Tiles
A complication — the small live readout on a watch face — is the same idea as a
home-screen widget: content-driven, rendered while your app isn’t running, fed
by a timeline. Codename One models it as such, so a complication is a watch
family of com.codename1.surfaces rather than an API of its own:
// A complication is a widget in a watch family, published from the same timeline.
WidgetKind steps = new WidgetKind("steps")
.setDisplayName("Steps")
.addSupportedSize(WidgetSize.WATCH_CIRCULAR)
.addSupportedSize(WidgetSize.WATCH_RECTANGULAR);Everything you already know about surfaces applies: the same node catalog, the
same ${key} state interpolation, the same timeline that lets the OS advance
content on its own clock with no app wake-ups. SurfaceVector is especially at
home here, because most complications are a gauge, a dial or a ring.
| Family | Apple Watch | Wear OS |
|---|---|---|
|
| Ranged-value or monochromatic-image complication |
|
| Long-text complication, or a Tile for a richer layout |
|
| Short-text complication. Text only — anything else is dropped |
|
| Renders as circular; Wear OS has no corner slot |
Design for a glance. A complication is a few dozen pixels someone reads in under a second, so one number or one gauge beats any layout that has to be read.
WATCH_RECTANGULAR and LOCKSCREEN share a family on Apple. If you
publish both, each surface gets the layout you designed for it; if you publish
only one, it’s used for both. |
| The watch families and the descriptor pipeline behind them are in place, and declaring them is forward-compatible. The platform targets that render them on a watch face — the watchOS widget extension and the Wear OS complication data source and Tile service — aren’t generated yet, so a kind that declares only watch families produces no on-device surface today. Declaring a phone family alongside them keeps the widget working meanwhile. |
87.8. Apple Watch (watchOS)
The watchOS build adds a second Xcode target to the generated project. It
compiles the shared, translated application sources for the watch architecture
(arm64_32 on device), renders through the Core Graphics backend, and — in the
default companion distribution — embeds the watch app inside your iOS app so
the pair installs together. The watch app is rooted in a generated SwiftUI
@main shell that hosts the Codename One frames and forwards Digital Crown and
tap input into the runtime.

87.8.1. What the Watch App Runs Today
codename1.watchMain is the watch app’s entry point on both platforms. The
watchOS build writes a stub of its own for that class and runs a second
translation rooted there, so the watch binary starts your watch lifecycle class
and carries what that class reaches rather than everything the phone reaches. On
Wear OS the declared class is the watch launcher. Put the watch UI in the class
you declared.
One case differs by design: naming the phone’s own main class as
codename1.watchMain keeps a single translation, because both entry points
reach the same code and translating twice would produce the same binary twice.
There the watch starts the phone lifecycle, and CN.isWatch() is how you decide
what the watch shows. That check is still worth keeping in shared code, but it’s
no longer what selects the watch UI when the two entry points differ.
One rough edge is left at archive time. Under manual signing the embedded watch
target has no provisioning profile of its own, since the host app’s profile is
the one installed, so give the watch bundle id — <your.package>.watchkitapp — its own profile before you submit. That applies to codename1.watchStandalone
too, where the watch bundle is the only one being signed.
The watch app’s icon is generated for you, scaled from the project icon into the watch target’s own asset catalog, so there’s nothing to add by hand. Replace that set in the generated project if you want the watch to carry different artwork from the phone.
None of this affects building, running or testing on the simulator or a device.
87.8.2. Native Code and the Watch Slice
Your Objective-C is compiled for the watch as well as the phone. The translator
copies native sources through to every slice it produces, so a .m that imports
UIKit, or an iOS-only SDK, is a build error on watchOS even when no watch code
calls it.
Guard it the way the framework guards its own — there are several hundred such guards across the iOS port:
#if !TARGET_OS_WATCH #import <UIKit/UIKit.h> // ... the iOS-only implementation #endif
The same applies in reverse to a native interface only the watch uses. There is no build hint for this and no attempt to infer it: which of your native sources can compile for watchOS is a question about that source, and the preprocessor is where it’s answered.
87.8.3. Supported and Unsupported APIs on watchOS
Because watchOS lacks UIKit views, GPU rendering and several iOS frameworks, the APIs that depend on them aren’t available on the watch slice. They’re guarded so that the shared sources still link, and they degrade rather than crash:
Unavailable:
BrowserComponent/ web view, camera capture,MediaPlayervideo, inline native text editors (text input routes through the watch text input controller),MapComponentnative maps, and StoreKit in-app purchase.Available: the full Codename One UI and layout system, drawing and
Graphics(rendered via Core Graphics, including gradients, transforms, clipping and Gaussian blur via Accelerate/vImage),FontImage/material icons, images and mutable images, networking and storage, JSON/XML, and the property and binding frameworks.
| The watch slice runs the same garbage-collected ParparVM runtime as the iOS app. Memory and CPU budgets on the watch are far smaller than on the phone, so keep watch screens light. |
87.8.4. Building and Debugging
A companion build produces an iOS .ipa that carries the embedded watch app. A
standalone build generates the watch target, but the archive step still targets
the phone scheme, so the artifact handed back is the iOS app: open the generated
project and archive the watch scheme yourself to produce the watch application.
The build logs this. The generated project is a standard Xcode project, so you
can open it and debug or profile the watch target with the native Xcode tools as
usual. Cloud builds generate the watch target through the same iOS build — declare the watch main class and build for iOS — and the same applies there,
so a standalone cloud build returns the iOS archive.
87.9. Android (Wear OS)
A Wear OS app is a regular Android app. The Codename One Android port renders the
UI with the same pipeline it uses on phones, so no special rendering backend is
required. The same codename1.watchMain declaration drives both platforms.
What it produces differs, though, and that difference is worth stating precisely.
Set codename1.watchStandalone and the Android build is the watch app: one APK
that installs and runs on the watch. Leave it unset and the Android build stays a
phone build — a companion Wear APK alongside the phone APK isn’t generated yet,
so on Android the companion configuration currently gives you the phone app and
the wearable link, not a second artifact. The build logs this rather than leaving
you to discover it. On Apple the companion case does produce and embed the watch
app, which is why the two platforms have a section each.
A standalone Wear app declares the watch hardware feature in the manifest:
<uses-feature android:name="android.hardware.type.watch" android:required="true" />It also marks itself standalone, so it installs and runs directly on the watch without a paired phone app:
<meta-data android:name="com.google.android.wearable.standalone" android:value="true" />A standalone Wear build also raises the minimum SDK to API 23, the Wear OS 2.0 standalone baseline, if your project requests a lower level.
87.9.1. Wear OS Input and Screen Shape
Two things behave differently on a watch and are handled for you:
Rotary input. The rotating side button or bezel scrolls the focused scrollable container, exactly as the Digital Crown does on Apple Watch. It arrives on its own input source rather than the mouse-wheel axes, and is scaled by the device’s own scroll factor.
Round screens. A circular face reports no display cutout, so a layout drawn to the full rectangle would have its corners eaten by the bezel. The safe area is inset to the largest rectangle that fits inside the circle — about 15% a side — so honoring the form’s safe-area insets is enough.
Because a Wear OS app is an ordinary Android app, you can also declare any
additional manifest features and permissions with the generic
android.uses_feature.<name> and android.uses_permission.<name> hints. |
Referencing com.codename1.wearable adds the play-services-wearable
dependency and the listener service automatically. The
android.playService.wearable hint remains for apps that want to call the Data
Layer APIs directly. |
87.10. Summary
| Apple Watch (watchOS) | Wear OS (Android) | |
|---|---|---|
Enable |
|
|
Rendering | Dedicated Core Graphics backend + separate watch target | Standard Android rendering pipeline |
Distribution | Companion (embedded in the phone app) or standalone | Standalone only — companion doesn’t yet produce a Wear artifact |
Runtime detection |
|
|
Talking to the phone app |
|
|
Complications (no target generated yet) | WidgetKit accessory families, declarable only | Complication data source and Tiles, declarable only |
The complication row describes where each platform’s watch surfaces will come from, not something you can ship today. You can declare the watch families on a surface kind, and nothing builds a complication or tile from them yet — see [watch-complications] for what that means in practice.
The wearable build is additive on both platforms: without a watch main class, your phone builds are unchanged.
88. Television (Apple TV and Android TV)
Codename One can build and run your application UI on the living-room TV platforms: Apple TV (tvOS) and Android TV / Google TV. As with the phone and wearable targets, the same Java/Kotlin code base drives the TV app — you write Codename One UI as usual and the build pipeline produces the appropriate TV artifact for each platform.
The two platforms reach the TV through different mechanisms:
Android TV / Google TV is Android. An Android TV app is an ordinary Android app (the same APK) that adds a small amount of manifest metadata: a Leanback launcher category so the app appears on the TV home screen, the
android.software.leanbackfeature, and an optional banner. The existing Codename One Android port renders the UI through exactly the same pipeline it uses on phones and tablets.Apple TV runs tvOS. tvOS is a UIKit relative of iOS reached through the same ParparVM (Java bytecode → C → native) pipeline used for iPhone/iPad, built against the
appletvosSDK with a tvOS application target. tvOS has no touchscreen — navigation is driven by the Siri remote and the focus engine.
In both cases the build is additive: with the TV hints turned off your phone/tablet build is unchanged.
88.1. Detecting the TV Form Factor
Use CN.isTV() (or Display.getInstance().isTV()) to branch your UI for the
TV at runtime. This is the living-room analog of the existing isTablet(),
isDesktop() and isWatch() checks:
Form f = new Form(BoxLayout.y());
if (CN.isTV()) {
// 10-foot UI: larger fonts, generous spacing, focus-driven navigation
f.add(new Label("Hello TV"));
} else {
// Full phone/tablet layout
f.add(new Label("Hello"));
}
f.show();Codename One’s existing D-pad/arrow focus traversal (the same mechanism that
powers GAME_UP/GAME_DOWN/GAME_LEFT/GAME_RIGHT and component focus) drives
remote navigation on the TV, so focusable components such as Button are
navigable with the remote out of the box.
88.2. Adapting Styling with CSS Media Queries
The TV (and watch) form factors integrate with the CSS @media device-type
mechanism. Rules inside a device-tv (or device-watch) media block are
selected at runtime when Display.isTV() (respectively isWatch()) returns
true — exactly the way device-tablet / device-desktop already work:
Label {
color: black;
}
@media device-tv {
Label {
/* Larger type for the 10-foot UI */
font-size: 3mm;
color: white;
}
}88.3. Building for Android TV / Google TV
Enable the Android TV manifest metadata with a single build hint in
codenameone_settings.properties:
codename1.arg.android.tv=trueThis makes the build:
add
<category android:name="android.intent.category.LEANBACK_LAUNCHER"/>to the launcher activity so the app appears on the Android TV home screen;declare
<uses-feature android:name="android.software.leanback" android:required="false"/>and makeandroid.hardware.touchscreenoptional so the app installs on touchless TVs;generate a 320×180 launcher banner (
@drawable/tv_banner) from the app icon.
The resulting APK still installs and runs on phones and tablets.
88.3.1. Android TV Build Hints
| Build hint | Default | Description |
|---|---|---|
|
| Mark the build as an Android TV / Google TV app: adds the
|
88.4. Building for Apple TV (tvOS)
Enable the tvOS application target with the tvNative.* build hints (the Apple
Watch build is enabled by declaring a codename1.watchMain instead — see the
wearables chapter):
codename1.arg.tvNative.enabled=trueThe tvOS build produces a standalone Apple TV app. Because tvOS uses a separate App ID and provisioning profile from your iOS app, you supply tvOS signing material the same way you do for the other Apple targets.
codename1.tvMain (and tvNative.enabled) only add the tvOS target; the
iPhone/iPad build is unchanged. In particular enabling the tvOS target does
not switch the iOS app’s renderer — tvOS runs on Metal (it has no OpenGL ES),
but the iOS app continues to honor its own ios.metal setting. |
88.4.1. tvOS Build Hints
| Build hint | Default | Description |
|---|---|---|
|
| Force the tvOS target on even without a distinct |
| (none) | Fully-qualified tvOS lifecycle entry class. Setting it also turns on the tvOS
build. When omitted (with |
|
| Bundle identifier of the tvOS app. |
|
|
|
| (app display name) | The tvOS app name shown on Apple TV. |
| (falls back to the iOS team id) | Apple Developer Team ID used to sign the tvOS target. |
89. Working with Codename One sources
The Codename One SDK is published as a Maven multi-module project. Building the
aggregator in the /maven directory compiles every module, installs the
artifacts into your local Maven repository, and lets you depend on the exact
snapshot you cloned from GitHub.
89.1. Prerequisites
Codename One uses multiple JDKs and Maven profiles during the build. Make sure
your development machine includes the following tooling (see
BUILDING.md for platform-specific installation tips):
JDK 8 (required for the core build of the framework itself)
JDK 11 through 25 (required at runtime to launch the simulator or "Run as desktop app" target)
JDK 17 (required when compiling the Android port)
Apache Maven 3.6 or newer
macOS with Xcode (if you plan to build or test the iOS port)
89.2. Preparing the Maven workspace
Clone the repository and run the Maven aggregator from inside the maven
subdirectory. This installs the complete SDK (core runtime, simulator, and
ports) into your local Maven cache:
$ git clone https://github.com/codenameone/CodenameOne
$ cd CodenameOne/maven
$ mvn installThe default build runs every module and its unit tests. Append -DskipTests
if you want to skip the test phases to speed up local builds.
The version printed by Maven will end with -SNAPSHOT when you build
from the master branch. Release builds from Maven Central omit the suffix.
89.3. Installing the Maven archetypes
Codename One ships its project archetypes in a companion repository. Install
them once so that mvn archetype:generate (and the Codename One Initializr)
can reference your locally built SDK artifacts:
$ git clone https://github.com/shannah/cn1-maven-archetypes
$ cd cn1-maven-archetypes
$ mvn install89.4. Running tests selectively
The Maven aggregator exposes modules for the different automated test suites.
Run any of these from the CodenameOne/maven directory:
Core unit tests:
$ mvn -pl core-unittests testIntegration tests (simulator and build client):
$ mvn -pl tests -am verify
Refer to the READMEs in maven/core-unittests and maven/tests for more
configuration flags, platform requirements, and environment variables.
89.5. Using your local build in application projects
After running the mvn install commands above, the Codename One artifacts are
available in your local Maven repository. To consume that build in an
application generated from the Codename One Initializr (or any other Maven
project), adjust the pom.xml properties to reference your snapshot version:
<properties>
<!-- Replace with the snapshot printed during mvn install -->
<cn1.version>{cn1-snapshot-version}</cn1.version>
<cn1.plugin.version>{cn1-snapshot-version}</cn1.plugin.version>
</properties>Open the project in your IDE and build or run it. Maven will resolve the local snapshot instead of downloading the latest release from Maven Central.
89.6. Why build from source
Building the SDK yourself gives you:
Immediate access to fixes and features before they reach Maven Central.
The ability to inspect, debug, and change the framework when you need custom behavior.
A path to contribute improvements back to the Codename One core.
Once you’re comfortable with the baseline build, continue with the scripts in
scripts/ or the BUILDING.md guide to compile specific ports (Android or
iOS) or to automate CI workflows.
90. Skin Designer
The Skin Designer turns a device specification (resolution, PPI,
fonts, safe-area insets, cutouts) into a .skin file that the
JavaSE simulator can load. It runs in your browser at
https://www.codenameone.com/skindesigner — there is nothing to
install.
This chapter walks through the wizard and explains what each step
contributes to the generated .skin. If you only want a skin and
don’t care how it’s built: pick a device, accept the defaults, click
Finish, then Download skin. The file is ready to load via Add
in the simulator’s Skins menu.
The wizard is intentionally opinionated. It ships with a
curated device catalog, generates the device frame procedurally, and
writes a skin layout that matches the Themes/iPhoneTheme.res,
Themes/iOS7Theme.res, and Themes/android_holo_light.res themes
shipped with Codename One. For a custom skin from a hand-painted
device render, jump straight to the
"Upload an image" source. |
90.1. Stage 1 — pick a device

The first step shows a card per device from the bundled catalog. Use the search box to filter by name (it matches both the model and the brand) and the chips below to narrow by form factor: All / Phones / Tablets / Foldables. Tapping a card selects the device and enables the Continue button in the footer.
Picking a device pulls in its resolution, PPI, screen size, default safe-area insets, and the iOS / Android system font names from the device catalog, then seeds a sensible starting frame: notch, island, or hole presets are applied automatically based on the device’s hardware.
The catalog is large. The grid is capped to the most recent
matches by default; type into the search field to find older or
less-common devices. The Showing X of Y hint between the chips and
the grid tells you when you’re looking at a clamped subset. |
90.2. Stage 2 — pick a starting source

Three ways exist to seed the skin’s body image:
Pick a shape — generates the device frame procedurally from a small preset library (rounded rect, notch, dynamic island, punch-hole, corner hole, classic home-button). The frame is rendered as a dark gradient with the screen rect (and any cutouts) carved into it. Best when you want a generic-looking iPhone or Android frame and don’t care about exact hardware fidelity.
Upload an image — opens an image picker. The wizard scales the image into the device’s resolution, then carves the screen rect (and cutouts) on top. Use this when you have a marketing render of the specific device you’re targeting.
Blank rectangle — collapses the bezel and corner radius to almost nothing, drops every cutout, and turns the home indicator off. The screen fills the entire skin. Useful for desktop / web simulators where the device frame would just be visual noise.
Hover over a card on desktop to see the blue selection ring; click to advance to the editor.
90.3. Stage 3 — the editor

The editor is split into two panes: a live preview on the left that paints the device frame, screen tint, cutouts, and home indicator, and a sidebar on the right with three tabs.
90.3.1. Shape tab
When you started from Pick a shape, the Shape tab shows a preset grid (Rounded rect / Notch / Dynamic Island / Punch-hole / Corner hole / Classic home) and dimension fields:
Corner radius — the device’s outer corner radius in viewbox pixels (the design uses a 320 × 620 viewbox; the actual skin image is scaled to the device’s resolution).
Bezel — frame thickness in viewbox pixels. The screen rect is positioned at
(bezel, bezel)inside the skin image.Home indicator — toggles the lime pill drawn at the bottom edge. iPhones from X onward and most modern Androids should leave this on; classic devices with a hardware home button should turn it off.
When you started from Upload an image, the Shape tab swaps the preset grid for a Replace image button so you can swap the body image without restarting the wizard.
90.3.2. Cutouts tab

The Cutouts tab lists every cutout currently on the skin. Tap a row to expand its width / height / offset fields; the X button on the right removes it. The three add buttons at the bottom seed a sensible default of each type:
Notch (180 × 30 viewbox px) — physical hardware cutout. Notches are drawn in the device frame above the screen rect, with the bottom edge touching the screen top. Mirrors iPhone X / 11 / 12 / 13 hardware.
Island (120 × 35) — Dynamic Island. Software-reserved space rendered as an opaque pill inside the screen rect, floating on top of the iOS status bar.
Hole (28 × 28) — Android punch-hole camera. Rendered like the island: opaque circle inside the screen rect.
Offsets are relative to the top-center of the screen, in viewbox
pixels. For islands and holes, Offset Y is the gap between the
cutout’s top edge and the screen top. For notches, Offset Y is
ignored (the notch is anchored to the frame).
When the wizard generates the .skin file, it
automatically extends safePortraitTop to cover any in-screen
cutouts (islands, holes), so app content lands below the floating
shape. You don’t need to manually adjust safe area for the cutout
itself; only adjust it if you need extra padding above your title
bar. |
90.3.3. Info tab

The Info tab is mostly read-only and shows what’s about to be
written into skin.properties:
Name — the only editable field. Determines the saved file name (sanitised: spaces become hyphens, special characters dropped, appended with
.skin).Width / Height — display resolution from the device catalog.
PPI / Pixels per millimeter — the simulator uses
pixelMilliRatio = ppi / 25.4to derive font sizes when none are specified in the skin.Safe area Top / Bottom — the user-editable safe-area insets in viewbox pixels. The wizard converts these to display-relative pixels at save time.
90.4. Stage 4 — finish and download

Clicking Finish in the editor’s footer:
Renders the portrait skin image (
skin.png) at the device’s actual resolution + bezel, with rounded corners, transparent screen, opaque cutouts, and a home indicator if enabled.Synthesises the landscape skin (
skin_l.png) by 90° rotation.Writes
skin_map.png/skin_map_l.pngoverlays that mark the screen rectangle for the simulator’s screen-position detection.Bundles the appropriate native theme (
iOS7Theme.res,android_holo_light.res, orwinTheme.res) inside the skin zip.Writes
skin.propertieswithroundScreen=true,displayX/Y/Width/Height,safePortrait*/safeLandscape*, the platform name, override names, fonts, and PPI.
Clicking Download skin on the done page hands the file to the browser’s download dialog. The button is the only reliable trigger because the browser’s user-gesture window expires during the heavy image-generation step that Finish runs.
After the file is on disk, drop it into your simulator’s skins folder (or use the Add command in the simulator’s Skins menu) and your new device should appear in the picker.
90.5. File layout of a generated skin
A generated .skin is just a renamed zip. Unzip it to see the
layout:
Apple-iPhone-16-Pro.skin/
skin.png # portrait body (device frame + transparent screen + cutouts)
skin_l.png # 90° rotated portrait
skin_map.png # black rect = screen, white = frame, used for hit-testing
skin_map_l.png # rotated map
iOS7Theme.res # bundled native theme (or android_holo_light.res / winTheme.res)
skin.properties # platform metadata, safe-area, PPI, display rectThe skin.properties file is a normal Java .properties. The most
important keys the wizard writes:
touch=true
platformName=ios
tablet=false
ppi=460
pixelRatio=18.110236220472443
# roundScreen=true makes the simulator paint skin.png *over* the rendered
# UI rather than clipping the UI to non-frame pixels. That overlay step is
# what makes the Dynamic Island / punch-hole shapes appear "floating" on
# top of the iOS status bar instead of being carved out of the display.
roundScreen=true
displayX=89
displayY=89
displayWidth=1206
displayHeight=2622
# Safe area in display-relative coordinates (origin = screen top-left).
safePortraitX=0
safePortraitY=237
safePortraitWidth=1206
safePortraitHeight=2272
safeLandscapeX=237
safeLandscapeY=0
safeLandscapeWidth=2272
safeLandscapeHeight=1206
# These get composed by overrideNames(device) — they let users layer
# device-specific styling on top of the platform theme via
# UIManager.addThemeProps()-style theme inheritance.
overrideNames=phone,ios,iphone
systemFontFamily=SF Pro
proportionalFontFamily=SF Pro
monospaceFontFamily=SF MonoThe wizard intentionally does not write smallFontSize,
mediumFontSize, or largeFontSize. When those are absent the
simulator automatically derives them from pixelMilliRatio (med = round(2.6
* ppmm), sm = 2 * ppmm, la = 3.3 * ppmm), which is what you
want on high-PPI screens. Writing iOS-style point values (12 / 15 /
22) into the file used to make text render at sub-millimeter sizes
on a 460 PPI device. |
Appendix A: Project archetypes
A.1. Codename One application project archetype (cn1app-archetype)
The cn1app-archetype is the basis for all maven Codename One application projects. It provides a multimodule project with the following modules:
See Getting Started with the Bare-Bones Java App Template for details on using this archetype.
Also see Section 1.2.2.2.1, “Bare-bones Java project” for an example using this archetype from the command-line to create a bare-bones Java project.
A.2. Codename One library project archetype (cn1lib-archetype)
The cn1lib-archetype provides a project for building Codename One libraries. See Section 1.5, “Codename One libraries” for details on using this archetype.
Appendix B: Maven goals
B.1. Codename One build (build)
The build goal is used to send builds to the Codename One build server. It also supports a few local build targets, such as ios-source, which generates an Xcode project, and android-source which generates an Android Gradle project.
This goal is bound to the package phase of the Section A.1, “Codename One application project archetype (cn1app-archetype)”, so you don’t need to run this directly.
B.1.1. Example
mvn cn1:build -Dcodename1.platform=javase -Dcodename1.buildTarget=mac-os-x-desktopB.1.2. Properties
- codename1.platform
Specifies the platform to build for. Values include Java SE, android, ios, JavaScript, and win.
- codename1.buildTarget
The build target. Different platforms support different build sets of build targets.
Build Target Platform Description mac-os-x-desktop
Java SE
Sends a Mac desktop build to the Codename One build server.
windows-desktop
Java SE
Sends a Windows desktop build to the Codename One build server.
android-device
android
Sends an Android build to the Codename One build server.
android-source
android
Generates an Android Gradle project locally that can be opened and built in Android Studio.
ios-device
ios
Sends an iOS build to the Codename One build server.
ios-source
ios
Generates an iOS Xcode project locally that can be opened and built in Xcode.
JavaScript
JavaScript
Sends a JavaScript build to the Codename One build server.
- automated
Set to
trueto submit build as an automated build. When using this flag, the goal will wait for the build server to complete the build, then download it and save it in the target directory (of the associated module) using standard maven artifact file naming conventions. This allows you to set up automated CI workflows more.Default value is
false.Requires a Codename One enterprise subscription.
- open
If set to
true, this will automatically open the generated Gradle or Xcode project in Android studio or Xcode. Only applicable to theios-sourceandandroid-sourcebuildTargets.Default is
false
B.2. Generate legacy cn1lib (cn1lib)
This goal generates a legacy.cn1lib file. It’s bound to the package phase of cn1lib-archetype projects so you will never need to run this goal directly.
B.2.1. Output location
This will output the cn1lib file inside the common/target directory of the root multimodule maven project.
B.3. Compliance check (compliance-check)
Checks API usage in the project’s "common" module to ensure that it doesn’t use any classes or methods that aren’t supported by Codename One.
This goal is bound to the process-classes phase of both Section A.1, “Codename One application project archetype (cn1app-archetype)” projects and Section A.2, “Codename One library project archetype (cn1lib-archetype)” projects, so you shouldn’t ever need to run this goal directly.
B.4. Compile CSS (css)
Compiles the project’s CSS files, generating a theme.res file which is placed in the build/classes directory.
This goal is bound to the process-classes phase of Section A.1, “Codename One application project archetype (cn1app-archetype)” projects, so you shouldn’t need to run this goal directly.
B.5. Generate app project (generate-app-project)
Generates a Maven project using the Section A.1, “Codename One application project archetype (cn1app-archetype)” as a basis, and applying an optional project template. This goal can also be used to migrate legacy Codename One Ant-based Application projects into maven.
B.5.1. Usage example
This goal shouldn’t be run inside an existing Maven project directory. It will output a project into a directory named after the artifactId parameter.
Because there is no existing project, you will need to provide the full maven path to the goal:
mvn com.codenameone:codenameone-maven-plugin:$CN1VERSION:generate-app-project \
-DsourceProject=/path/to/my/ProjectTemplate \
-DgroupId=com.example \
-DartifactId=myapp \
-Dcn1Version=$CN1VERSIONSubstitute the latest Codename One plugin version for the $CN1VERSION in the above example. |
| This command is formatted for the bash prompt (for example, Linux or Mac). It will work on Windows also if you use bash. If you’re on Windows and are using PowerShell or the regular command prompt, then you’ll need to modify the command slightly. In particular, the entire command would need to be on a single line. (Remove the '\' at the end of each line, and merge lines together, with space between the command-line flags) |
In the above example, assuming all went well, it would output your project into a directory named myapp.
B.5.2. Parameters
- cn1Version
The Codename One version that you want to use for the project. This will be manifested as the
cn1.versionandcn1.plugin.versionproperties in the common/pom.xml file of the generated project. If omitted it will default to the cn1Version that’s hard-coded in the cn1app-archetype artifact.- sourceProject
The path to an optional project template to use. This may be either a legacy Ant project, or a Maven project that follows the structure of Section A.1, “Codename One application project archetype (cn1app-archetype)”.
- artifactId
The
artifactIdto use for the new project.- groupId
The
groupIdto use for the new project.- version
The
versionto use for the new project. Optional.Default value is "1.0-SNAPSHOT"
- packageName
The package name to use for the new project.
This is necessary if the
sourceProjectproperty is a Maven project. If thesourceProjectis a legacy Ant project, then this property is ignored.- mainName
The main class name to use for the new project.
This is necessary if the
sourceProjectproperty is a Maven project. If thesourceProjectis a legacy Ant project, then this property is ignored.
B.5.3. Migrating legacy Ant projects into Maven
When providing an Ant-based Codename One application project as the sourceProject parameter, this goal will generate an equivalent Maven project to the Ant project, with the same settings and sources.
See Section 1.2.3, “Migrating an existing project” for examples using this goal to migrate an existing project into Maven.
B.5.4. Project templates
When using a Section A.1, “Codename One application project archetype (cn1app-archetype)” maven project as the sourceProject parameter, the project will be treated project template, and perform some basic processing of the source files as necessary convert the template into a real project. This includes replacing all occurrences of ${mainName} and ${packageName} in project sources with the value of the mainName and packageName parameters provided on the command-line.
Any occurrences of mainName and packagePath in file or directory names will be swapped with the values of mainName and packagePath (which is automatically derived from packageName by substituting '.' with file separators).
The generate-app-project.rpf file
The (optional) secret sauce that differentiates a regular Maven project from a Maven project template is the existence of a generate-app-project.rpf file in the root project directory. This file is in rich property file format, and allows you to define a minimal amount of configuration details that the generate-app-project goal needs to convert the template into a real project.
This file may contain the following properties:
- template.mainName
The name of the main class that’s used in this project. This property isn’t required if the project is already using the
mainNameplaceholder in the file name that contains the main class, and the${mainName}placeholder in any source code referring to the main class.Often times it’s easier to specify this property here rather than injecting placeholders into the template source base, because that way the template itself can be used as a valid project.
- template.packageName
The package name for the app. This property isn’t required if the project is already using the
packagePathplaceholder in directories containing your main package files, and the${packageName}placeholder in any source code that refers to the main package.Often times it’s easier to specify this property here rather than injecting placeholders into the template source base, because that way the template itself can be used as a valid project.
- template.type
Either
mavenorant, depending on the project type.- dependencies
An XML snippet containing any more Maven dependencies that should be added to the project. This is handy of the project template relies on other cn1libs that are on Maven central.
Sample generate-app-project.rpf file
template.mainName=MyApp
template.packageName=com.example
template.type=maven
[dependencies]
====
<dependency>
<groupId>com.codenameone</groupId>
<artifactId>googlemaps-lib</artifactId>
<version>1.0.1</version>
<type>pom</type>
</dependency>
====B.5.5. Sample: The bare-bones Kotlin app project
As a fuller example of a project template, see the generate-app-project.rpf file in the bare-bones Kotlin app template.
This is the template that’s used in Codename One initializr for the Bare-bones Kotlin project.
B.6. Clone project (clone)
Clones the current project as a new project with a different groupId, artifactId, packageName, and mainName. Resulting project will be made available in the common/target/generated-sources/cn1-cloned-projects directory.
B.6.1. Usage example
mvn cn1:clone \
-DgroupId=com.example.newgroup \
-DartifactId=newapp \| This command is formatted for the bash prompt (for example, Linux or Mac). It will work on Windows also if you use bash. If you’re on Windows and are using PowerShell or the regular command prompt, then you’ll need to modify the command slightly. In particular, the entire command would need to be on a single line. (Remove the '\' at the end of each line, and merge lines together, with space between the command-line flags) |
In the above example, assuming all went well, it would output your project into a directory named myapp.
B.6.2. Parameters
- artifactId
The
artifactIdto use for the cloned project.- groupId
The
groupIdto use for the cloned project.
B.7. Create GUI Form (create-gui-form)
The create-gui-form goal will generate a GUI form that can be edited in the GUI builder.
Basic Usage Example
mvn cn1:create-gui-form -DclassName=com.example.MyFormThe above example will generate a GUIBuilder form with the provided class name. It effectively generates two files:
common/src/main/guibuilder/com/example/MyForm.guicommon/src/main/java/com/example/MyForm.java
| The paths above assume that this goal was run from the root multimodule maven project. If it were run inside the "common" submodule, then the files would be generated in the "src/main/…" directory of that module. (It would try to create yet another "common" submodule). See Project Structure. |
You can then open the GUI builder to edit this form using the cn1:guibuilder goal:
mvn cn1:guibuilder -DclassName=com.example.MyFormB.7.1. Parameters
- className
(Required) The class name of the form that you wish to generate. E.g
com.example.MyForm.- guiType
The kind of GUI component to generate. Supports
Form,Dialog, andContainer. Default value is "Form"- autoLayout
Whether to use autolayout. This is boolean (true/false), and the default value is
true.
B.8. Generate cn1lib project (generate-cn1lib-project)
Generates a Maven cn1lib project (using the cn1lib-archetype) given an ANT cn1lib project as a template.
This is to assist in migrating Ant projects to Maven projects. This won’t make any changes to the source Ant project. It generates a new project using the Section A.2, “Codename One library project archetype (cn1lib-archetype)” and copies all files and configuration from the source project, into the new project.
B.8.1. Usage example
| This goal isn’t run in an existing maven project directory, so you need to include the absolute Maven coordinates for the goal. |
Suppose you have an Ant Codename One library project at /path/to/MyLegacyAntLibraryProject and you want to convert it to a Maven project.
You can run the generate-cn1lib-project goal as follows:
mvn com.codenameone:codenameone-maven-plugin:$CN1VERSION:generate-cn1lib-project \
-DsourceProject=/path/to/MyLegacyAntLibraryProject \
-DgroupId=com.example \
-DartifactId=my-maven-lib \
-Dversion=1.0-SNAPSHOT \
-UMake sure you substitute the latest codenameone-maven-plugin version for the $CN1VERSION in this command. |
Some notes about this command as shown above:
This command is formatted for Unix/Mac on multiple lines, using the
\character to escape the new-lines. On Windows the command will need to be all one line, and you should omit those\escape characters.The
-Uflag tells Maven to update its catalogs to ensure that it can find the$CN1VERSIONthat you specify.
If all goes well, you should find a new maven project generated in the "your-maven-lib" directory (named after the artifactId that you specified).
To test that the project was generated successfully, try opening the resulting project in your IDE or run its "install" goal on the command-line.
For example:
cd my-maven-lib
mvn installAfter running the "install" command, you should be able to add your library as a dependency to a Section A.1, “Codename One application project archetype (cn1app-archetype)” project using the following dependency:
<dependency>
<groupId>com.example</groupId>
<artifactId>my-maven-lib-lib</artifactId>
<version>1.0-SNAPSHOT</version>
<type>pom</type>
</dependency>Notice that the artifactId has an extra "-lib" appended. That is, it’s <artifactId>my-maven-lib-lib</artifactId> and not <artifactId>my-maven-lib</artifactId>. This is because the artifactId that you specify in the generate-cn1lib-project goal is used for the "root" module of the multimodule maven project. The actual "lib" project that you can use as a Maven dependency is the "lib" submodule, which uses the specified artifactId with a "-lib" suffix. |
See Section 1.5, “Codename One libraries” for more information about the resulting maven library project.
B.8.2. Properties
- sourceProject
The path to the legacy Ant project that you want to convert to a Maven project.
- groupId
The maven
groupIdto use for the resulting project.- artifactId
The maven
artifactIdto use for the resulting project.- version
The maven
versionto use for the resulting project. Default "1.0-SNAPSHOT"
B.9. Generate desktop app wrapper (generate-desktop-app-wrapper)
Generates the bootstrapping wrapper class for the Java SE desktop app. This is used by the Java SE module of Section A.1, “Codename One application project archetype (cn1app-archetype)” projects.
You shouldn’t need to call this goal directly.
B.10. Generate GUI sources (generate-gui-sources)
Generates Java sources from the Codename One GUI builder files. This goal is bound to the process-sources phase of Section A.1, “Codename One application project archetype (cn1app-archetype)” projects, so you should never need to run this goal explicitly.
B.11. Generate native interfaces (generate-native-interfaces)
Generates stub implementations for all native interfaces defined in the project. This won’t overwrite any existing implementations that may exist.
You should run this goal explicitly after you create a native interface in your class.
See the Codename One Developer guide section on native interfaces for more information on creating native interfaces.
B.11.1. Usage example
Suppose you’ve created a native interface as the Java interface com.mycompany.myapp.MyNative, as described in the example in native interfaces.
After creating this (and possibly other) native interfaces in your project, run the generate-native-interfaces Maven goal as follows:
mvn cn1:generate-native-interfacesBy default this generates Java/Objective-C stubs. You can optionally include Swift and Kotlin stubs (both off by default):
mvn cn1:generate-native-interfaces \
-Dcn1.generateNativeInterfaces.swift=true \
-Dcn1.generateNativeInterfaces.kotlin=trueThis will generate the following files (if they don’t exist yet).
- Java SE
Java SE/src/main/java/com/mycompany/myapp/MyNativeImpl.java- ios
ios/src/main/objectivec/com_mycompany_myapp_MyNativeImpl.hios/src/main/objectivec/com_mycompany_myapp_MyNativeImpl.m
- android
android/src/main/java/com/mycompany/myapp/MyNativeImpl.java- android (optional Kotlin)
android/src/main/java/com/mycompany/myapp/MyNativeImpl.kt- JavaScript
JavaScript/src/main/JavaScript/com_mycompany_myapp_MyNativeImpl.js- ios (optional Swift)
ios/src/main/objectivec/com_mycompany_myapp_MyNativeImpl.swift
Open and edit these files to implement your native interface methods as desired.
B.12. Generate OpenAPI client (generate-openapi)
Generates a typed Codename One client from an OpenAPI 3.x JSON
specification. Writes one @Mapped record (Java 17+) or class (Java
8 target) per components.schemas entry and one
@RestClient-annotated interface per OpenAPI tag. The generated
files land in common/src/main/java so the project owns the
contract; the matching networking implementation is emitted into
common/target/generated-sources by the build-time annotation
processor so the project source stays clean.
The mojo is paired with the existing process-annotations pipeline:
identical schemas across operations collapse to one record/class, and
operationIds become interface methods that resolve at runtime via a
com.codename1.io.rest.RestClients registry populated by the generated
bootstrap class (the same splice pattern as @Mapped mappers).
B.12.1. Usage example
mvn -pl common cn1:generate-openapi \
-Dcn1.openapi.spec=petstore.json \
-Dcn1.openapi.basePackage=com.example.petstoreConfiguration:
| Property | Description |
|---|---|
| Local file path or URL of the OpenAPI 3.x JSON document, for example
|
| Java package the generated sources are written under. Records / classes
go under |
| Defaults to |
| Defaults to |
B.12.2. Generated output
For the Swagger Petstore reference spec the goal emits, under
common/src/main/java:
com/example/petstore/
PetApi.java // @RestClient interface, methods addPet, updatePet,
// findPetsByStatus, getPetById, deletePet, ...
StoreApi.java // @RestClient interface, methods getInventory,
// placeOrder, getOrderById, deleteOrder
UserApi.java // @RestClient interface
com/example/petstore/model/
Pet.java // @Mapped record (Java 17+) or class (Java 8)
Order.java
User.java
Category.java
Tag.javaEach @RestClient interface method is annotated with the HTTP verb
and path; parameters are annotated @Path / @Query / @Header /
@Body so the processor knows how to assemble the Rest call. The
emitted method shape:
@RestClient
public interface PetApi {
@GET("/pet/{petId}")
void getPetById(@Path("petId") Long petId,
@Header("Authorization") String bearerToken,
OnComplete<Response<com.example.petstore.model.Pet>> callback);
@POST("/pet")
void addPet(@Body com.example.petstore.model.Pet body,
@Header("Authorization") String bearerToken,
OnComplete<Response<com.example.petstore.model.Pet>> callback);
static PetApi of(String baseUrl) {
return RestClients.create(PetApi.class, baseUrl);
}
}The model type referenced by the generated API is emitted into the generated model package:
public class Pet implements PropertyBusinessObject {
public final Property<Long, Pet> id = new Property<Long, Pet>("id");
public final Property<String, Pet> name = new Property<String, Pet>("name");
private final PropertyIndex index = new PropertyIndex(this, "Pet", id, name);
@Override
public PropertyIndex getPropertyIndex() {
return index;
}
}Model types are emitted as fully qualified names (the API interface
lives in <basePackage> and models under <basePackage>.model) so
the generator never needs to track imports or worry about
collisions between an API class name and a same-named model.
Call sites use the static factory:
The <Tag>ApiImpl class that actually performs the HTTP call lives
in target/generated-sources — the project source never references
it directly. The build server probes the project zip for the
generated cn1app.RestClientBootstrap and splices the registry
wiring in, mirroring the existing cn1app.MapperBootstrap pattern.
B.12.3. Scope
HTTP verbs:
GET,POST,PUT,DELETE,PATCH.Parameter locations:
path,query,header,cookie. Multiplecookieparameters on the same operation are joined into a singleCookie: a=1; b=2request header.Request bodies:
application/json— serialized viaMappers.toJson(body)before being attached.Response schemas:
$refresolution, primitives (string/number/integer/boolean), arrays, object schemas.oneOf/anyOf/allOfcollapse toObject— callers cast.String
enumschemas are emitted as Java enums and bound by the JSON mapper through each constant’sname(), so a model property typed by an enum$refgets the generated enum type. This requires every enum value to be a valid (non-reserved) Java identifier; an enum whose values are not — for example"two-day"— degrades toStringrather than generating an enum that couldn’t round-trip. Integer/number enums keep their numeric type.Schema unification: two
components.schemasentries with identical property shapes collapse to a single record/class to avoid an explosion of duplicates.Authentication: bearer token is exposed as a
@Header("Authorization") String bearerTokenparameter on every operation. API-key auth declared in the spec is emitted as@Headeror@Querylike any other parameter; basic auth and OAuth bearer tokens travel through the samebearerTokenslot.
B.13. Generate gRPC client (generate-grpc)
Generates a typed Codename One gRPC-Web client from a proto3 .proto
specification. Writes one @ProtoMessage record (Java 17+) or class
(Java 8 target) per message, one @ProtoEnum enum per enum, and
one @GrpcClient-annotated interface per service. The generated
files land in common/src/main/java so the project owns the
contract; the matching protobuf codec and gRPC-Web call site are
emitted into common/target/generated-sources by the build-time
annotation processors so the project source stays clean.
The mojo is paired with the existing process-annotations
pipeline: @ProtoMessage triggers per-class binary protobuf codec
generation and a cn1app.ProtoBootstrap registration entry;
@GrpcClient triggers per-interface <Service>GrpcImpl generation
chained through com.codename1.io.grpc.GrpcWeb.invokeUnary(…)
and a cn1app.GrpcClientBootstrap that wires everything to the
com.codename1.io.grpc.GrpcClients registry (same splice pattern
as @Mapped mappers).
B.13.1. Usage example
mvn -pl common cn1:generate-grpc \
-Dcn1.grpc.proto=helloworld.proto \
-Dcn1.grpc.basePackage=com.example.helloConfiguration:
| Property | Description |
|---|---|
| Local path to the |
| Java package the generated sources are written under. Messages,
enums, and the |
| Defaults to |
| Defaults to |
B.13.2. Generated output
For a helloworld.proto declaring message HelloRequest,
message HelloReply, enum Mood, and service Greeter { rpc
SayHello(HelloRequest) returns (HelloReply); }, the goal emits
under common/src/main/java:
com/example/hello/ HelloRequest.java // @ProtoMessage record / class HelloReply.java Mood.java // @ProtoEnum enum with `number` accessor GreeterGrpc.java // @GrpcClient interface
Each @ProtoMessage carries one @ProtoField(tag = N) per field;
scalar fields use the default varint wire kind, sint32 / sint64
use wireType = ProtoField.WireKind.SINT, and fixed32 /
fixed64 / sfixed32 / sfixed64 use
wireType = ProtoField.WireKind.FIXED. Renamed fields (e.g.
snake_case → camelCase) carry the original proto name via the
optional name attribute so introspection tooling can recover it.
The @GrpcClient interface looks like:
Call sites use the static factory:
The <Service>GrpcImpl class that actually performs the gRPC-Web
POST lives in target/generated-sources — the project source
never references it directly. The build server probes the project
zip for cn1app.ProtoBootstrap and cn1app.GrpcClientBootstrap
and splices the registry wiring in, mirroring the existing
cn1app.MapperBootstrap pattern.
B.13.3. Wire protocol
The runtime speaks gRPC-Web binary
(application/grpc-web+proto) over HTTP/1.1, which is the standard
mobile / browser variant of gRPC supported by Envoy, the official
grpcweb Go proxy, and the gRPC-Web filter in modern gRPC server
implementations. Plain HTTP/2 gRPC requires trailers that
ConnectionRequest doesn’t expose; gRPC-Web carries grpc-status
in a synthetic trailer frame in the response body instead.
A successful call:
Encodes the request message via the build-time-generated
ProtoCodecfor the request type.Wraps the encoded bytes in a 5-byte frame header (
flag + length) and posts to<baseUrl>/<service-fqn>/<method>withContent-Type: application/grpc-web+protoandX-Grpc-Web: 1.Reads the response body, iterates frames, accumulates data payload, and parses the trailer frame for
grpc-status/grpc-message.Decodes the accumulated payload via the response codec and invokes the supplied
OnComplete<GrpcResponse<T>>.
B.13.4. Scope
Unary RPCs (single request, single response). Streaming RPCs (
streamkeyword on request or response) are rejected at generation time — gRPC-Web client streaming requires HTTP/2.proto3 syntax. proto2
requiredis rejected;optionalis accepted but treated as a nullable field.Scalar types:
int32,int64,uint32,uint64,sint32,sint64,fixed32,fixed64,sfixed32,sfixed64,float,double,bool,string,bytes.enumdeclarations (nested or top-level) emit@ProtoEnumenums with apublic final int numberfield and astatic T forNumber(int n)lookup.Nested
messagedeclarations are emitted as top-level siblings in the same package so the generated codec layout stays flat.repeatedfields land asjava.util.List<T>. Scalar lists are encoded packed on the wire (proto3 default); the reader accepts both packed and unpacked forms.oneofcollapses to a group of nullable fields on the parent message — the mutual-exclusion guarantee is lost but round-trips work. Use application code to enforce the invariant if needed.Not yet supported:
map<K, V>, well-known types (Timestamp, Empty, etc.), fileimport, streaming RPCs. These produce a clear error from the parser pointing at the offending line.Authentication: a bearer token is exposed uniformly as a
@Header("Authorization") String bearerTokenparameter on every RPC method, mirroring the OpenAPI bearer-token slot.
B.14. Generate GraphQL client (generate-graphql)
Generates a typed Codename One GraphQL client from a GraphQL SDL
schema, optionally driven by a set of operation documents. Writes one
@Mapped record (Java 17+) or class (Java 8 target) per response shape
and input type, a Java enum per GraphQL enum, and one
@GraphQLClient-annotated interface carrying one method per operation.
The generated files land in common/src/main/java so the project owns
the contract; the matching client implementation and JSON mappers are
emitted into common/target/generated-sources by the build-time
annotation processors so the project source stays clean.
The mojo is paired with the existing process-annotations pipeline:
the generated @Mapped types trigger per-class JSON mapper generation
and a cn1app.MapperBootstrap entry, while @GraphQLClient triggers
per-interface <Name>Impl generation chained through
com.codename1.io.graphql.GraphQL.execute(…) (queries and mutations)
or com.codename1.io.graphql.GraphQL.subscribe(…) (subscriptions),
plus a cn1app.GraphQLClientBootstrap that wires everything to the
com.codename1.io.graphql.GraphQLClients registry (same splice pattern
as @Mapped mappers and @GrpcClient clients).
B.14.1. Usage example
mvn -pl common cn1:generate-graphql \
-Dcn1.graphql.schema=schema.graphqls \
-Dcn1.graphql.operations=operations.graphql \
-Dcn1.graphql.basePackage=com.example.starwarsConfiguration:
| Property | Description |
|---|---|
| Local path to the GraphQL SDL schema ( |
| Java package the generated sources are written under. Models, enums,
input types, and the |
| Path to a |
| Simple name of the generated |
| Default endpoint URL recorded on the generated annotation. The
effective endpoint is always the argument passed to |
| Maximum selection-set depth used by the schema-only quick-start mode.
Defaults to |
| Defaults to |
| Defaults to |
B.14.2. Generation modes
Unlike OpenAPI paths or gRPC service methods, a GraphQL schema doesn’t enumerate the operations a client wants — the client chooses which fields to select. The goal therefore supports two modes:
Operations mode (recommended): supply
cn1.graphql.operations. For each namedquery/mutation/subscriptionthe generator emits one interface method plus a precise@Mappedresponse-type tree that mirrors exactly that operation’s selection set (nested selections become nested generated types). Referenced fragment definitions are merged into the request document automatically.Schema-only quick-start mode: omit
cn1.graphql.operations. For each field of the rootQuery/Mutation/Subscriptiontype the generator emits one method whose selection set is automatically expanded tocn1.graphql.maxDepthlevels, stopping at recursive types. This is a convenience for getting started; it may over- or under-fetch, so prefer operations mode for production code.
B.14.3. Generated output
For a Star Wars schema and an operations.graphql declaring
query HeroName, mutation AddReview, and
subscription OnReview, the goal emits under common/src/main/java:
com/example/starwars/ Episode.java // GraphQL enum -> Java enum ReviewInput.java // @Mapped input type HeroNameData.java // @Mapped query response root HeroNameData_Hero.java // nested selection type AddReviewData.java // @Mapped mutation response root OnReviewData.java // @Mapped subscription response root StarWarsApi.java // @GraphQLClient interface
GraphQL enums map to a generated Java enum in response types, input
types, and method variables alike — the JSON mapper binds enums by
their name(). Built-in scalars map to their boxed Java type
(Int → Integer, Float → Double, Boolean → Boolean,
String / ID → String); custom scalars fall back to String.
The @GraphQLClient interface looks like:
Call sites use the static factory. Queries and mutations report through
an OnComplete<GraphQLResponse<T>>:
A subscription returns a GraphQLSubscription handle whose cancel()
ends the stream:
The <Name>Impl class that performs the request lives in
target/generated-sources — the project source never references it
directly. The build server probes the project zip for
cn1app.GraphQLClientBootstrap and splices the registry wiring in,
mirroring the existing cn1app.MapperBootstrap pattern.
B.14.4. Wire protocol
Queries and mutations are sent as an HTTP POST to the endpoint with a
JSON body {"query":…,"operationName":…,"variables":{…}} and a
Content-Type: application/json header. The response envelope
({"data":…,"errors":[…]}) is parsed into a typed
GraphQLResponse<T>; because a GraphQL response can carry both data and
errors, GraphQLResponse exposes getData() and getErrors()
independently and isOk() reports whether the errors array was empty.
Subscriptions run over a WebSocket using the graphql-transport-ws
protocol (offered via the Sec-WebSocket-Protocol handshake header):
the client sends connection_init, waits for connection_ack, sends a
subscribe message carrying the operation, and maps each next
payload’s data to T before delivering it to the handler. The
WebSocket endpoint defaults to the query endpoint with its scheme
rewritten to ws / wss; pass a ws:// / wss:// URL to of(…) to
override it. All handler callbacks are dispatched on the EDT.
B.14.5. Scope
Queries, mutations, and subscriptions.
GraphQL enums map to generated Java enums in every position (response fields, input fields, and method variables); unknown enum names decode to
nullrather than throwing.Input object types map to generated
@Mappedclasses; variables of scalar, enum, input-object, and list types are supported.Named and inline fragments are resolved against the schema and merged into the generated response types and the request document.
Built-in scalars (
Int,Float,Boolean,String,ID) map to their boxed Java types. Custom scalars fall back toString.union/interfaceselections are emitted with their common fields in the quick-start mode; use explicit operation documents with inline fragments for full polymorphic typing.Authentication: a bearer token is exposed uniformly as a
@Header("Authorization") String bearerTokenparameter on every method, mirroring the OpenAPI and gRPC bearer-token slots.
B.15. GUIBuilder goal (guibuilder)
The guibuilder goal opens the Codename One GUI builder to edit a specified GUIBuilder form.
B.15.1. Usage
mvn cn1:guibuilder -DclassName=com.example.MyFormThis will open the GUI builder to edit the form whose class is com.example.MyForm.
B.15.2. Parameters
- className
The fully qualified name to the form class that you wish to edit. This must have been earlier generated using Section B.7, “Create GUI Form (
create-gui-form)”.
B.16. Generate archetype (generate-archetype)
| This goal isn’t used. It was originally developed to simplifying the maintenance of multiple application archetypes, but this approach was later abandoned in favor of application project templates. |
The generate-archetype mojo will generate a new archetype maven project based on an existing archetype project. It’s designed to ease the maintenance of several similar archetypes which differ in some dependencies or default project source code. It takes as input a template file which references the base archetype project and specifies what to customize.
Example Usage
mvn cn1:generate-archetype -Dtemplate=/path/to/mytemplate.java
B.16.1. Parameters
- template
Required. The path to a template file that should be used to generate the archetype project.
- outputDir
Optional. The output directory where the archetype project should be written to. The project will be created at
outputDir/artifactId, where theartifactIdis as specified in the[archetype]section of the template. By default this will be the current working directory.
This goal doesn’t require a project to run. You can run it directly using the full goal coordinates: mvn com.codenameone:codenameone-maven-plugin:7.0-SNAPSHOT:generate-archetype \ -Dtemplate=/path/to/mytemplate.java |
B.16.2. Template syntax
Here is a sample template file:
#set( $symbol_pound = '#' )
#set( $symbol_dollar = '$' )
#set( $symbol_escape = '\' )
package ${package};
/*
[archetype] (1)
----
extends=../cn1app-archetype (2)
groupId=com.codenameone.archetypes
artifactId=helloworld2-archetype
version=7.0-SNAPSHOT
----
[dependencies] (3)
----
<dependency>
<groupId>com.codenameone.libs</groupId>
<artifactId>filechooser-lib</artifactId>
<version>1.0-SNAPSHOT</version>
<type>pom</type>
</dependency>
----
*/
import static com.codename1.ui.CN.*;
import com.codename1.ui.*;
import com.codename1.ui.layouts.*;
import com.codename1.io.*;
import com.codename1.ui.plaf.*;
import com.codename1.ui.util.Resources;
/**
* This file was generated by <a href="https://www.codenameone.com/">Codename One</a> for the purpose
* of building native mobile applications using Java.
*/
public class ${mainName} {
private Form current;
private Resources theme;
public void init(Object context) {
// use two network threads instead of one
updateNetworkThreadCount(2);
theme = UIManager.initFirstTheme("/theme");
// Enable Toolbar on all Forms by default
Toolbar.setGlobalToolbar(true);
// Pro feature
Log.bindCrashProtection(true);
addNetworkErrorListener(err -> {
// prevent the event from propagating
err.consume();
if(err.getError()!= null) {
Log.e(err.getError());
}
Log.sendLogAsync();
Dialog.show("Connection Error", "There was a networking error in the connection to " + err.getConnectionRequest().getUrl(), "OK", null);
});
}
public void start() {
if(current!= null){
current.show();
return;
}
//WebSocket sock;
Form hi = new Form("Hi World", BoxLayout.y());
hi.add(new Label("Hello World"));
hi.show();
}
public void stop() {
current = getCurrentForm();
if(current instanceof Dialog) {
((Dialog)current).dispose();
current = getCurrentForm();
}
}
public void destroy() {
}
}| 1 | The [archetype] section specifies details about the archetype project to be generated. For example, the groupId, artifactId, etc. |
| 2 | The extends property in the [archetype] section is required, and points to the location of the archetype project that this template is based on. Path is relative to the location of the template file. |
| 3 | The [dependencies] section includes content that should be injected into the <dependencies> section of the pom.xml file. Note that this isn’t the pom file for the archetype project itself. It’s the pom.xml file for the project that the archetype project is to generate. |
Notice that the above template is velocity template for a Java file. It will be used as the source code for the main class in the resulting project. It’s a velocity template because maven’s archetype:generate goal will process it to replace properties such as package and the main class name.
Template sections
- archetype
This is a required section and specifies both the location of the base archetype project from which this project is to be derived, and the coordinates of the output archetype project, such as
groupId,archetypeId, andversion.Example
[archetype] ---- extends=../cn1app-archetype groupId=com.codenameone.archetypes artifactId=helloworld2-archetype version=7.0-SNAPSHOT ----Properties
- extends
Required. The path to the archetype project that this is based on. This should usually be the
cn1app-archetypeproject as it includes the placeholders that this generator relies on for injecting content into the pom.xml file and its project structure was used as a basis for developing this mojo.- groupId
The groupID of the resulting archetype project. You can or use the
idproperty to specifygroupId,artifactIdandversionin a single string.- artifactId
The artifactId of the resulting archetype project. You can or use the
idproperty to specifygroupId,artifactIdandversionin a single string.- version
The version of the resulting archetype project. You can or use the
idproperty to specifygroupId,artifactIdandversionin a single string.- id
A colon-separated string in the format
groupId:artifactId:versionthat can be used as an alternative togroupId,artifactId, andversion.- parentGroupId
If the output archetype project should be part of a multi-module project, then this will specify the parent
groupIdfor the<parent>tag in the pom.xml file.- parentArtifactId
If the output archetype project should be part of a multi-module project, then this will specify the parent
archetypeIdfor the<parent>tag in the pom.xml file.- parentVersion
If the output archetype project should be part of a multi-module project, then this will specify the parent
archetypeIdfor the<parent>tag in the pom.xml file.- parent
A colon-delimited string in the format
parentGroupId:parentArtifactId:parentVersionthat can be used as an alternative to theparentGroupId,parentArtifactId, andparentVersionproperties.
- dependencies
Specify more dependencies that should be injected into the
<dependencies>section of the pom.xml file for the common module of the maven project that the archetype will generate. The content of this section will be injected into thesrc/main/resources/archetype-resources/common/pom.xmlof the archetype project.Example
[dependencies] --- <dependency> <groupId>com.codenameone.libs</groupId> <artifactId>filechooser-lib</artifactId> <version>1.0-SNAPSHOT</version> <type>pom</type> </dependency> ---- css
CSS content that should be injected into the theme.css file of the project. This CSS will be injected into the
src/main/resources/archetype-resources/common/src/main/css/theme.cssfile of the archetype project.Example
[css] --- #Constants { includeNativeBool: true; } Button { color:green; border:1px solid green; border-radius: 2mm; margin: 5mm; } ---- properties
Properties that should be appended to the
codenameone_settings.propertiesfile. These will be added to thesrc/main/resources/archetype_resources/common/codenameone_settings.propertiesfile of the archetype project.Example
[properties] --- codename1.arg.win.desktop-vm=zuluFx8-32bit codename1.arg.win.desktopExtractDll=true codename1.arg.win.launchOnStart=true codename1.arg.win.runAfterInstall=true ---- files
Files contains a list of files that should be created in the archetype project. All file paths are relative to the "common" project root directory. Each path should have a corresponding section with the heading
[file:path/to/file].Example
[files] ---- src/main/guibuilder/__mainName__MainForm.gui src/main/java/__mainName__MainForm.java ---- [file:src/main/guibuilder/__mainName__MainForm.gui] ---- <?xml version="1.0" encoding="UTF-8"?> <component type="Form" layout="LayeredLayout" layeredLayoutPreferredWidthMM="0.0" layeredLayoutPreferredHeightMM="0.0" autolayout="true" title="${mainName}MainForm" scrollableY="true" name="${mainName}MainForm"> <component type="Button" text="Click Me" name="Button"> <layoutConstraint insets="auto auto auto auto" referenceComponents="-1 -1 -1 -1" referencePositions="0.0 0.0 0.0 0.0" /> </component> </component> ---- [file:src/main/java/__mainName__MainForm.java] ---- package ${package}; public class ${mainName}MainForm extends com.codename1.ui.Form { public ${mainName}MainForm() { this(com.codename1.ui.util.Resources.getGlobalResources()); } public ${mainName}MainForm(com.codename1.ui.util.Resources resourceObjectInstance) { initGuiBuilderComponents(resourceObjectInstance); } //-- DON'T EDIT BELOW THIS LINE!!! protected com.codename1.ui.Button gui_Button = new com.codename1.ui.Button(); // <editor-fold defaultstate="collapsed" desc="Generated Code"> private void initGuiBuilderComponents(com.codename1.ui.util.Resources resourceObjectInstance) { setLayout(new com.codename1.ui.layouts.LayeredLayout()); setInlineStylesTheme(resourceObjectInstance); setScrollableY(true); setInlineStylesTheme(resourceObjectInstance); setTitle("MyForm"); setName("MyForm"); gui_Button.setText("Click Me"); gui_Button.setInlineStylesTheme(resourceObjectInstance); gui_Button.setName("Button"); addComponent(gui_Button); ((com.codename1.ui.layouts.LayeredLayout)gui_Button.getParent().getLayout()).setInsets(gui_Button, "auto auto auto auto").setReferenceComponents(gui_Button, "-1 -1 -1 -1").setReferencePositions(gui_Button, "0.0 0.0 0.0 0.0"); }// </editor-fold> //-- DON'T EDIT ABOVE THIS LINE!!! } ----
B.17. Install Codename One (install-codenameone)
Installs/Updates Codename One into the user’s home directory. This goal is automatically run if a Maven build is attempted and it detects that Codename One isn’t yet installed (in the $HOME/.codenameone) directory.
B.18. Install legacy Cn1lib (install-cn1lib)
Installs a legacy cn1lib file as a dependency in this application project.
See Section 1.2.4, “Adding project dependencies” for fuller coverage of project dependencies.
| Using this goal explicitly is a last resort. The best solution for installing add-ons into your project is Section 1.2.4.5, “Managing add-ons in Codename One Settings”. |
B.18.1. Usage example
mvn cn1:install-cn1lib -Dfile=/path/to/MyLegacyLib.cn1libThis will generate a Maven pom project for this lib inside the "cn1libs" directory, and it will add a dependency inside the common/pom.xml file.
| The generated project isn’t a cn1lib-archetype project, and it isn’t meant to change. It’s merely a Maven wrapper around the cn1lib file that provides compatibility with Maven’s dependency mechanism. |
B.18.2. Removing the Cn1lib later
If you need to remove the cn1lib later (that is, revert an installation), you can remove the <dependency> tag that was added to the common/pom.xml file for the cn1lib.
You can also remove the directory that was created inside the cn1libs folder for this cn1lib - but this step isn’t necessary.
B.18.3. Parameters
- file
Path to the cn1lib file you want to install.
- groupId
The groupId to use for the generated pom project. Optional. If not specified, it will use the same groupId as the root project.
- artifactId
The artifactId to use for the generated pom project. Optional. If not provided, it will generate an artifactId derived from the project’s artifactId.
- version
The version to use for the generated pom project. Optional. If not provided, it will use the project version.
- updatePom
A boolean flag indicating whether it should automatically update the pom.xml file with the dependency.
Default is
true- overwrite
A boolean flag indicating whether it should overwrite an existing project of the same name. Default false.
Default is
false
B.19. Open Designer (designer)
Opens the legacy Codename One designer app to edit the project "theme.res" file.
| If your project is using CSS it may not have a theme.res file, thus this goal will fail in this case. |
B.19.1. Usage example
mvn cn1:designerThis will open the Codename One designer.
B.20. Prepare simulator classpath (prepare-simulator-classpath)
Sets up some properties and environment variables required for the Codename One simulator to run properly.
This goal is bound to the initialize phase of the Java SE module of the Section A.1, “Codename One application project archetype (cn1app-archetype)” and shouldn’t be executed directly.
B.21. Open settings (settings)
Downloads and opens the standalone Codename One Settings editor bound to the current Maven project. The editor manages basic project properties, build hints, and extensions.
mvn cn1:settingsB.22. Run tests (test)
Runs Codename One unit tests.
This goal is bound to the test phase of Section A.1, “Codename One application project archetype (cn1app-archetype)” projects, so that running it directly isn’t necessary. If you build a cn1app-archetype project using:
mvn installor
mvn packageThen this goal will be executed automatically.
Prevent tests from running using the skipTests flag. For example, mvn install -DskipTests |
B.23. Update Codename One (update)
Updates Codename One. This updates tools that live inside $HOME/.codenameone, such as the GUI builder, and tries to update the cn1.version and cn1.plugin.version properties in the project’s pom.xml. The standalone Settings editor is resolved from Maven using cn1.plugin.version when you run mvn cn1:settings.
B.23.1. Usage example
mvn cn1:updateParameters
- newVersion
(Optional) The version to update to. This should be a version number available on Maven central. Will accept a value of "LATEST" to cause it to resolve to the latest version available on Maven central.
If this parameter is omitted, then it will be implicitly set to
LATEST, but it won’t update thecn1.versionorcn1.plugin.versionproperties if they’re set to a SNAPSHOT version.
See Section 1.3, “Updating Codename One” for more information about updating Codename One.
Appendix C: API
| This section isn’t a comprehensive treatment of the Codename One API. For a more in-depth discussion of Codename One and it’s supported APIs, refer to the Developer Guide. |
Codename One apps support a subset of the Java SE 8 API as well as its own light-weight runtime and UI component library that includes support for everything that would expect in a mobile application platform.
See the JavaDocs for a full list of supported classes, and check out the source in the git repository.
| The Codename One source is open source. Released under GPLv2 with Classpath Exception. |
Codename One is much more than an API library. It provides a full tool-chain and eco-system for developing beautiful, performant native mobile apps with a single codebase in Java and Kotlin. Please see the introduction in the Developer guide for a proper overview of Codename One.
C.1. Limitations
- No reflection
Codename One apps don’t support reflection because reflection makes it impossible to keep app-size down.
C.2. Kotlin API support
Codename One apps support the Kotlin Standard Library. Kotlin support is still new, so are still discovering which libraries are compatible. APIs that rely on reflection won’t be supported, but most other libraries should work.
C.3. Add-on libraries
Add-on libraries can be added to your library in the common/pom.xml file, but, if you use APIs that aren’t supported by Codename One (for example, which use reflection), then your app will fail to build.
Codename One supports its own library format (cn1lib) which sort of "certifies" that it’s compatible with Codename One. Run mvn cn1:settings and open Extensions to browse the growing catalog of available cn1libs. See Codename One Settings.
For more information about cn1libs, see the cn1libs section of the developer guide.
Appendix D: Codename One Settings
Codename One Settings is a standalone editor for the current Maven project. Use it to edit the application’s basic properties, manage build hints, and browse, install, update, or uninstall extensions. Signing assets are managed by the separate Certificate Wizard, and cloud builds are monitored on the Codename One website.
D.1. Opening Codename One Settings
Run the following command from the root directory of a Codename One Maven project:
mvn cn1:settingsMaven downloads the Settings artifact that matches the Codename One Maven plugin version and opens it as a desktop application bound to the current project. The same command works in a terminal or an IDE’s Maven runner.
D.2. Basic settings
The Basic view edits the application title, description, version, vendor, package name, main class, icon, versioned-build selection, and include-source option. Changes are written to common/codenameone_settings.properties when you click Save.

D.3. Build hints
The Build Hints view searches the build-hint catalog from this guide. It provides a control appropriate to each known hint and also accepts arbitrary key/value hints. The editor adds and removes the codename1.arg. prefix when reading and writing codenameone_settings.properties.

D.4. Extensions
The Extensions view searches the Codename One library catalog. Depending on how an extension is distributed, installation either adds a Maven dependency to common/pom.xml or installs a legacy cn1lib. Click the action for an installed extension to uninstall it. Settings displays a compatibility warning before installing a catalog entry known to target an older Codename One release.

Appendix E: Rich properties file (rpf) format
The rich properties file (rpf) format is used to store configuration for the generate-app-project goal. The format is the same as a regular properties file except that it can accommodate properties whose values are "rich" and lengthy.
"Rich" properties use the following syntax:
[keyname] (1)
=== (2)
Key value (3)
=== (4)| 1 | The property key appears on a new line wrapped in square brackets. |
| 2 | A separator consisting of 3 or more equals signs on the next line. |
| 3 | The property value, which can be one or more lines of content. |
| 4 | The separator with the same number of equals signs on a line of its own. |
E.1. Example rich properties file
firstName=Bob
lastName=Smith
[bio]
====
Bob is a hard worker.
He attended Harvard and is looking for opportunities in the fast food industry.
====
age=23
# A comment that it is ignored
[xmldata]
========
<person>
<name>Bob Smith</name>
<age>23</age>
</person>
========
favoriteColor=BrownMany of the properties of this file are regular properties. Two rich properties exist: bio and xmldata.
Historical reference
91. Working with UWP
The Codename One UWP (Universal Windows Platform) target was discontinued in release 7.0.229. This chapter is retained to document historical context for legacy projects and older blog posts. New projects should target the supported Codename One platforms instead. |
If you’re maintaining an older codebase or reading archived material that mentions UWP, treat those instructions as historical. The current Maven build templates, initializr output, and IDE shortcuts no longer include a UWP target.